Loading...
HomeMy WebLinkAboutContract 51831-CO1 CITY SECRETARY CONTRACT NO. 51931- FORTWORTH• City of Fort Worth Change Order Request Project Name As halt Pavement Preservation 2019 City Sec# Client Project#(s)l 101712 Project Installation of HA5, A High Density Mineral Bond, For Asphalt Pavement Description 9 Y p Contractorl Andaie Construction Inc. Change order# 01 Date 04 City Project Mgr.1 City Inspector Dept.. TPW-Storm Contract Time Water Totals D Original Contract Amount Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date Go to ADD&DEL Tabs to Enter CO Backup Revised Contract Amount Original Funds Available for Change Orders KOO Remaining Funds Available for this CO Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) Please see attache_d�r Removed Streets a t�e�ets AtieMAW- Midy1 K er, ity Secretary It is understood and agreed that the acceptance of this Change Order by the contractor coil titii s�r Jcevr6nd satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The ProjecUProgram Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. And$le Cons ruction Inc etty.t M itar Pr idert y � ik y C M&C Number M&C Date Approved RECEIV APR 29 2019 I OFFICIAL RECORD ctN or VORTWORV CITY SECRETARY CVsic*TP'y FT. WORTH,TX City of Fort Worth Change Order#01 Request After further evaluation of the originally proposed street segments,three segments(Willomet,Lubbock and Yates)were removed as they were found to be unsuitable for the HAS application.To offset the reduction in planned work, three new segments from 3100 to 3599 Covert Ave,and segments from Martin Lyndon Ave( 2600-2699),Greene Ave(4700—4799)and Odessa Ave(4750-4799)were added to reestablish an equivalent total project quantity(District 9). Removed Streets Street name From Block From Street To Street Mapsco Council District Lane Mile Willomet Ave 3700-3899 Staples Ave W Spurgeon 89R District 9 0.42 St Yates St 2700-2999 Lubbock Ave Cockrell Ave 90P District 9 0.44 Lubbock Ave 4900-5099 Martin Lydon Leith Ave 90P District 9 0.71 Ave Added Streets Street name From Block From Street To Street Mapsco Council Lane District Mile Covert Ave 3200-3349 Odessa Ave Leith Ave 90N District 9 0.29 Covert Ave 3350-3599 Westcreek Dr Odessa Ave 90N District 9 0.38 Covert Ave 3100-3199 Leith Ave Rector Ave 90N District 9 0.22 Greene Ave 4700-4799 Binyon St Bilglade Rd 90K District 9 0.19 Martin Lydon 2600-2699 Lubbock Ave Merida Ave 90N District 9 0.16 Ave Odessa Ave 4750-4799 Binyon St W Fuller Ave 901 District 9 0.31 FOR WOR1-H City of Fort worth Change Order Additions Project Name City Sec# 0 Client Project# Project Description Contractor Change Order# Date City Project Mgr. City Inspector ADDITIONS Unit Unit Cost Total TPW-Storm Water $0.00 ub Total Ad itions Change Order Additions Page 1 of 1 FOx H City of Fort Worth Change Order Deletions Project Name City Sec# 0 Client Project# Project Description Contractor Change Order# Date City Project Mgr. City Inspector DELETIONS ITEM DESCRIPTION DEPT ty Unit Unit Cost I ota TPW-Storm Water $0.00 Sub Total Deletions o.00 Change Order Deletions Page 1 of 1 MIWBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO N/A Total $0.00 Previous Change Orders Co# DATE AMOUNT None Total $0.00 Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Shammi Rahman Project Manager ❑ This form is N/A as No City Funds are associated with this Contract Printed Name Signature OFFICIAL RECORD CITY SECRETARY FT. WORTH,TX