NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Dave Road A (Chaplin Drive)
City Project No.: 101355
Improvement Type(s): Water ® Sewer
Original Contract Price: $1,113,188.50
Amount of Approved Change Order(s): $18,144.00
Revised Contract Amount:
Total Cost of Work Complete: $1,131,332.50
limnly Hamblin(May 23,201g) May 23, 2019
Contractor Date
Conatser Construction Tx Lp
Title
Conatser Construction Tx Lp
Company Name
til heel V. mite May 23, 2019
Michael V.Flute(May 23,2019) _.
Project Inspector Date
May 24, 2019 _
Aaron Lone Min IT 2019)
Project Manager Date
May 24, 2019
J e Scarlett Morales(Mav 24 2019)
CC FA Manager Date
&(f"A i( - May 24, 2019
Susan Alanis(May 24,2019)
Asst. City Manager Date
OFFICIAL.RECORD
CITY SECRETARY
FT. WORTH,TX Page 1 of 2
Notice of Project Completion
Project Name: Dave Road A (Chaplin Drive)
City Project No.: 101355
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑x Yes ❑ N/A
Pipe Report: ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety I
Statement of Contract Time
Contract Time: 180 CD Days Charged: 180
Work Start Date: 4/16/2018 Work Complete Date: 12/17/2018
Page 2of2
FORTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name PROJECT DAVE,ROAD A(CHAPLIN DRIVE)
Contract Limits
Project Type WATER&SEWER
City Project Numbers 101355
DOE Number 1355
Estimate Number 1 Payment Number 1 For Period Ending 12/15/2018
CD
City Secretary Contract Number Contract Time 180;D
Contract Date 2/28/2018 Days Charged to Date 180
Project Manager NA Contract is 100.00 Complete
Contractor CONATSER CONSTRUCTION TXLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors MILLER,W / FLUTE
Wednesday,May 22,2019 Page 1 of 5
City Project Numbers 101355 DOE Number 1355
Contract Name PROJECT DAVE,ROAD A(CHAPLIN DRIVE) Estimate Number I
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 12/15/2018
Project Funding
UNIT I:WATER IMPROVEMENTS
Item Estimated Estimated Completed Completed
Description of Items Unit Unit Cost
No. Quanity Total Quanity Total
---------------------------------------
1 16"PRESSURE PLUG 1 EA $1,000.00 $1,000.00 1 $1,000.00
2 4"-12"PRSSURE PLUG 10 EA $800.00 $8,000.00 10 $8,000.00
3 TRENCH SAFETY 6060 LF $2.00 $12,120.00 6060 $12,120.00
4 CONCRETE ENCASEMENT FOR UTILITY PIPES 10 CY $200.00 $2,000.00 10 $2,000.00
5 DUCTILE IRON WATER FITTIGNS 7.5 TN $3,215.00 $24,112.50 7.5 $24,112.50
W/RESTRAINT
6 4"PVC WATER PIPE 31 LF $32.00 $992.00 31 $992.00
7 6"PVC WATER PIPE(CO#1) 204 LF $36.00 $7,344.00 204 $7,344,00
8 12"PVC WATER PIPE 231 LF $46.00 $10,626.00 231 $10,626.00
9 16"PVC C905 WATER PIPE 33 LF - $70.00 $2,310.00 33 $2,310.00
10 24"PVC C905 WATER PIPE 50 LF $120.00 $6,000.00 50 $6,000.00
11 CONNECTION TO EXISTING 24"WATER MAIN 1 EA $2,000.00_ $2,000.00 1 $2,000.00
12 3"COMBINATION AIR VALVE ASSEMBLY FOR 3 EA $9,500.00 $28,500.00 3 $28,500.00
WATER
13 3"WATER MAIN AND VAULT 2 EA $15,500.00 $31,000.00 2 $31,000.00
14 6"GATE VALVE(CO#1) 7 EA $950.00 $6,650.00 7 $6,650.00
15 12"GATE VALVE 5 EA $2,400.00 $12,000.00 5 $12,000.00
16 16"GATE VALVE W/VAULT 1 EA $12,500.00 $12,500.00 1 $12,500.00
17 20"GATE VALVE W/VAULT 6 EA $24,000.00 $144,000.00 6 $144,000.00
18 24"X 20"TAPPING SLEEVE&VALVE 1 EA $7,500.00 $7,500.00 1 $7,500.00
19 6"BLOW OFF VALVE 3 EA $7,200.00 $21,600.00 3 $21,600.00
20 20"PVC C905 WATER PIPE 5546 LF $90.00 $499,140.00 5546 $499,140.00
21 12"DOUBLE DETECTOR CHECK VAVLE WITH 2 EA $26,500.00 $53,000.00 2 $53,000.00
VAULT
22 FIRE HYDRANT(CO#1) 2 EA $3,800.00 $7,600.00 2 $7,600.00
23 2"WATER SERVICE(CO#1) 2 EA $2,500.00 $5,000.00 2 $5,000.00
24 2"WATER PIPE(CO#1) 30 EA $20.00 $600.00 30 $600.00
25 2"PRSSURE PLUG(CO#1) 2 EA $250.00 $500.00 2 $500.00
26 2"DOUBLE CHECK VALVE ASSEMBLY(CO#1) 2 EA $1,200.00 $2,400.00 2 $2,400.00
--------------------------------------
Sub-Total of Previous Unit $908,494.50 $908,494.50
--------------------------------------
Wednesday,May 22,2019 Page 2 of 5
City Project Numbers 101355 DOE Number 1355
Contract Name PROJECT DAVE,ROAD A(CHAPLIN DRIVE) Estimate Number I
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 12/15/2018
Project Funding
UNIT II:SANITARY SEWER IMPROVEMENTS
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 8"SEWER ABANDONMENT PLUG 6 EA $800.00 $4,800.00 6 $4,800.00
2 12"SEWER ABANDONMENT PLUG 1 EA $1,000.00 $1,000.00 1 $1,000.00
3 POST-CCTV INSPECTION 2195 LF $2.00 $4,390.00 2195 $4,390.00
4 MANHOLE VACUUM TESTING 11 EA $150.00 $1,650.00 11 $1,650.00
5 TRENCH SAFETY 2195 LF $2.00 $4,390.00 2195 $4,390.00
6 CONCETE COLLAR 1 EA $500.00 $500.00 1 $500.00
7 CONCRETE ENCASEMENT FOR UTILITY PIPES 32 CY $200.00 $6,400.00 32 $6,400.00
8 8"SEWER PIPE 210 LF $46.00 $9,660.00 210 $9,660.00
9 12"SEWER PIPE 1985 LF $60.00 $119,100.00 1985 $119,100.00
10 T MANHOLE 8 EA $5,000.00 $40,000.00 8 $40,000.00
11 T DROP MANHOLE 3 EA $6,000.00 $18,000.00 3 $18,000.00
12 T EXTRA DEPTH MANHOLE 66.4 VF $195.00 $12,948.00 66.4 $12,948.00
Sub-Total of Previous Unit $222,838.00 $222,838.00
--------------------------------------
Wednesday,May 22,2019 Page 3 of 5
City Project Numbers 101355 DOE Number 1355
Contract Name PROJECT DAVE,ROAD A(CHAPLIN DRIVE) Estimate Number I
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 12/15/2018
Project Funding
Contract Information Summary
Original Contract Amount $1,113,188.50
Change Orders
Change Order Number I $18,144.00
Total Contract Price $1,131,332.50
Total Cost of Work Completed $1,131,332.50
Less %Retained $0.00
Net Earned $1,131,332.50
Earned This Period $1,131,332.50
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $1,131,332.50
Wednesday,May 22,2019 Page 4 of 5
City Project Numbers 101355 DOE Number 1355
Contract Name PROJECT DAVE,ROAD A(CHAPLIN DRIVE) Estimate Number I
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 12/15/2018
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors MILLER,W / FLUTE Contract Date 2/28/2018
Contractor CONATSER CONSTRUCTION TxLP Contract Time 180 CD
5327 WICHITA ST Days Charged to Date 180 CD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $1,131,332.50
Less %Retained $0.00
Net Earned $1,131,332.50
Earned This Period $1,131,332.50
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $1,131,332.50
Wednesday,May 22,2019 Page 5 of 5
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR: 1 /�
PROJECT NAME: _�_ t.-- ,�, {)!Ly r�G7 '�Gi[/G •{�_a /`t
PROJECT NUMBER ` /d/.3�5
DOE NUMBER:
WATER
PIPE LAID SIZE TYPE OF PIPE LF
fM eatite 214'' Dr-iLv 14 `90 5'L►c ;7�,"'.-J -50
_l to`�/Z'l'1- C^f o o 3 3
vD 1.2 '" j)2 1q 1 T 5 f
ba
FIRE HYDRANTS: �2- VALVES(16" OR LARGER)
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES:
NEW SERVICES: 0 1 4 41 00 At I
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
43 2,ta (-%fgvy TM Ie i.'` • -'v4- 194/5
Od /� G S(i r r (y-5 00 5 L�p J`..• 5:U 7-10
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES:
NEW SERVICES:
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth• 1000 Throckmorton Street•Fort Worth,TX 76012-6311
a
(817)392-7941 •Fax: (817)392-7845
a°
am
zo
0
U
8@ a o 6 a
a
8 � aaags
a' $$
3 $ $ Y a P
u
t4 �
.R4 4 oM I
N�S
u o a a N u
r `
d 9 $ a $ $ V U 1
a a a a iS
b N m
D
C W
m
o
�n � ZI n - '
W
83
a v W Y
q
w Q
O n. ..6 a
a ;�_ vv zaagaa �
a
W E Ut'-
n
- 4fl fl G t anaa e3 ��
p Ct [1 G\
0m
� o o aaasa F
zi
7 °
Q a 7 o g 2 4 N
d nz za w hl N
Y
a u
'S o
4 rr
F ww Z �a
2
U a ¢ � a
W �W., n a R w w w w z '� C 2 w i 8
Z g W a Z J N ri, o 5
a UU U U O 7i �GUl1JI u. �d D � U u 2 a >
pon his oath deposed anci saict :
is., firms, associations , corporations or other or;
e been paid in full ';
scale established by the City Council in the C:
rio claims pending for personal injury and/or prod
;scribed as :
PROJECT DAVE, ROAD A (Chaplin Drive)
SANITARY SEWER, PAVING, DPAINAGI
AND STREET LIGHT IMPROVEMENTS
DOE# .0 N/A
CFA PRJ0# N /A
CITY PROJCT # o. 101355
CITY OF FORT WORTH
STATE OF TEXAS
HIH GQ N I hAtmo i rvn
Water,
hDrainage
Sewers
o (Ch �
OH 43062 � CONTRACT DATE :
TRUCTION TX , L. P .
the Contract between the Owner and the Contractor as 1'.
06830
Contractor)
76119-6035
to the Contractor, and agrees that final payment to ti
rations to (here insert name and address of Owner)
;USA) AND THE CITY OF FORT WORTH
43082
F's bond .,