HomeMy WebLinkAboutContract 50567-CO3 RY FORT WORTH® City of Fort worth CONTRACT CITY SECRETARY SoSb 7-0O3 � Change Order Request Breakdown Project Name HMAC 2017-5 Street Rehabiliation at Various Locations City Sec# 1 50567 Client Project#(s)l101265 Contractorl JLB Contracting,LLC PM Kristian Sugrim Inspedorl Martina Salinas Change Order Submittal# 0 Date 511312019 Dept. TIPW Contract Time Totals (CD) Original Contract Amount $1,945,950.00 $1,945,950.00 210 Extras to Date $83,827.90 $83,827.90 84 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $2,029,777.90 $2,029,777.90 294 Go to ADD&DEL Tabs to Enter CO Backup $0.00 28 Revised Contract Amount 2,029,777.90 $2,029,777.90 322 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 4.31% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,432,437.50 An additional 28 days are required for the additional project Marshall Avenue that was added to the contract. No additional funds are requested. o� so. oFF�G�PQ�t OFFICIAL RECORD CITY SECRETARY FT. WORTH,TX City of Fort worth unange uraerAaamons Project Name HMAC 2017-5 Street Rehabiliation at Various Locations City Sec# Client Project# 101265 Contractor JLB Contracting,LLC PM Kristian Sugrim Inspector Martina Salinas Change Order Submittal# 0 Date 5/13/2019 ADDITIONS ty Unit Unit Cost Total T/PW $0.00 Sub Total Additions Change Order Additions Page 1 of 1 FORI'WORTH City of Fort Worth V- - cnange Uroer metions Project Name HMAC 2017-5 Street Rehabiliation at Various Locations City Sec# Client Project# 101265 Contractor JLB Contracting,LLC PM Kristian Sugrim Inspector Martina Salinas Change Order Submittal# 3 Date 5/13/2019 DELETIONS ITEM DESCRIPTION DEPI ty Unit Unit Cost I ota T/P W $0.00 Sub Total Deletions $0.00 Change Order Deletions Page 1 of 1 MISBE Breakdown for this Change Order MISBE Sub I ype of Service Amount tdr this CO None Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 BIM 360 Document Management Page-1 of 2 El AUTODESK`BIM 360' fortworthgov > 101265-HMAC 2017-5 Street Rehabilitation- A KS •:: Document Management FOLDERS REVIEWS TRANSMITTALS ISSUES Reviews > Review detail CLOSED #10 Change Order Approval Workflow Name^ Version Markup PROGRESS change order 3-marshal(-hardcopy routing versi... V1 0 Initiator Initial Review n Q j Change Order Breakdown-co3-marshall days.xls... V1 0 KS Kristian Sugrim May 21,4:46 PM <kristian.sug rim@fortworthtexas.gov> Submitted to Reviewer 1 Reviewer 1 Initial Review 1 0 LP Lauren Prieur May 29,11:26 AM Y ® <tau ren.prieur@fortworthtexas.gov> • Submitted to Reviewer 2 i� 1 No comments Mary J. K r,biji 96=tary Reviewer 2 Initial Review 2 SC steve cookes May 29,3:55 PM MQ_^ _a q(O 0 07/1G1 <stephen.cooke@fortworthtexas.gov> Submitted to Reviewer 3 1295: aoig-y-tasoa Reviewer 3 Initial Review 3 DB Douglas Black May 30,6:13 PM <doug.black@fortworthtexas.gov> Submitted to Approver Ok to go Approver Final Review SA Susan Alanis May 31,5:37 PM <s u sa n.a l a ni s @ fo rtwo rt h texas.g ov> Review ended Review closed OFFICIAL.RECORD CITY SECRETARY < > FT. WORTH,TX https:Hdocs.b360.autodesk.com/projects/a874fca9-d47a-4766-962d-57c936269c55/reviews/141 b97... 6/5/2019 Official site of the City of Fort Worth,Texas CITY COUNCIL AGENDA FORT711 REFERENCE ** 20HMAC 2017-5 STREET DATE: 5/7/2019 NO.: C-29104 LOG NAME: REHABILITATION C.O. 3 CODE: C TYPE: CONSENT PUBLIC NO HEARING: SUBJECT: Authorize Execution of Change Order No. 3 to City Secretary Contract No. 50567 with Texas Materials, Inc. f/k/a JLB Contracting, LLC, for the Rehabilitation of Marshall Avenue and the Addition of 28 Calendar Days for the Completion of the Contract, with No Increase to the Contract Amount (COUNCIL DISTRICT 9) RECOMMENDATION: It is recommended that the City Council authorize the execution of Change Order No. 3 to City Secretary Contract No. 50567 with Texas Materials, Inc. f/k/a JLB Contracting, LLC, to rehabilitate the additional street segment of Marshall Avenue within the limits of N. Sylvania Avenue and Grace Avenue at no increase in contract cost and add an extension of 28 calendar days for completion of the contract (City Project No. 101265). DISCUSSION: On March 6, 2018, Mayor and Council Communication (M&C C-28614), the City Council authorized the execution of a contract with JLB Contracting, LLC n/k/a Texas Materials, Inc., in the amount of $1,945,950.00 for Hot Mix Asphaltic Concrete (2017-5) Street Rehabilitation at multiple locations within the City (CPN 101265) (CSC No. 50567). Staff desires to add an additional street segment, Marshall Avenue within the limits of N. Sylvania Avenue and Grace Avenue, to the contract. This change of contract scope will not increase the existing contract amount. TPW staff has reviewed and verified the quantities for the additional work under this Change Order No. 3. To complete this additional work, the contract time will be extended by 28 calendar days. This contract amendment will have no impact to future operating budgets for the TPW Department. On April 3, 2019, the City acknowledged the January 2019 assignment of several contracts from JLB Contracting LLC, to Texas Materials, Inc., including the subject contract. The added project is located in COUNCIL DISTRICT 9. FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that funds are available in the current capital budget, as appropriated of the General Capital Projects Fund. TO n7!1-� epartment Account Project Program Activity Budget Reference# Amount ID ID Year Chartfield 2 FROM Fund Department Account Project Program Activity Budget Reference# Amount ID ID Year (Chartfield 2) Submitted for City Manager's Office by: Susan Alanis (8180) Originating Department Head: Steve Cooke (5134) Additional Information Contact: Kristian Sugrim (8902) ATTACHMENTS 2017-5-change order 3- 1295 texas materials group 2019-472502 Redacted.pdf Map HMAC 2017-5 C O 3.pdf MAYOR AND COUNCIL COMMUNICATION MAP H2O17-05 STREET REHABILITATION MAP-PAGE-1 VIRGINIA CT EMBREY PL MURPHY ST w z } MC LEMORE AVE z MC LEMORE AVE MC LEMORE AVI F- z 0 z g m RACE ST RACE ST w w PLUMWOOD ST U 9 AKERS AVE DISTRICT: 9 MARSHALL AVE MARSH LL AVE MARSHALLAVE z ¢ GILLIS ST NOBLE AVE 63U Z z c �QS o ¢ l 1 m w m 2 n O Q 'p o PITTSBURG L iyripht2l1t1 City of Fort Worth.Unautharizizedreproduction is a violation otapplicable laws. __ __ /'+IT\/ P►' n.Ir/'�T*- .1012F Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. i Kristian Sugrim Name of Employee/Signature Project Manager Title L This form is N/A as No City Funds are associated with this Contract Kristian Sugrim / Printed Name Signature OFFICIAL RECUR® CITY SECRETARY FT WORTH,TX