c CONTRACTNO. 5to35-A�i
FORT WORTH. City of Fort worth
Construction Allowance Request
Construction FDA#I�J Date 5/14/2019 City Sec# 1 51035
Client Project#(s)l CPN#101386
FAC#(s)l 30100-0200431-5740010-101386-002480-9999
Project Name HMAC 2018-5 Street Rehabilitation
Description
Conlractorl Advance Paying City Inspector Jesse Gu fin
Funding TPW Select Day
Allocation Account Totals Type
Original Contract Amount $945,691.15 $945,691.15 180
Extras to Date $28,710.33 $28,710.33 20
Credits to Date
Current Contract Amount $974,401.48 $974,401.48 200
Amount of Proposed Allocation $12 006.67 $12,006.67
Original Allowance Available for Allocation $90,000.00 $90,000.00
Allowance Funds Previously Allocated $0.00
Remaining Funds Available for this Allocation $90,000.00 $90,000.00
JUSTLFjICATION SUMMARY
IN ACCORDANCE WITH THIS CONSTRUCTION ALLOWANCE REQUEST,THE CONTRACTOR SHALL:Furnish all labor and
material as per attached proposed Construction Allowance Request(with attachments)to the Construction Allowance Requesi:This
Construction Allowance Request is needed to cover the additional cost of adjusting the irrigation system at Berkeley PL.Also the
Contractor has been asked to do additional works at Forxfire Way and Coffey St.This construction allowance is need to pay a
remobilization costs to the contractor.Also to pay the contractor the extra cost to replace one mailbox at Coffey St.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and satisfaction
and represents payment in full for all costs arising out of,or incidental to,the above Construction Allowance Request.Contract The will be
adjusted on the bass of the lime shown on this Constriction Allowance Request by a later Change Order,if necessary.
Contmetoeq Ra tesentafNe Date loinspector Date
Q-4A 105/30/19
ArohltestlCTeai t>_ Ineer D to Pto eetu n ate.
o� 3► i'
'Pro Bart►Mon et' _ Date topital P e 'Uffioef/Asot<Et3ir
al l
. �
last
!3 uGk
U _ OFFICIAL RECORD
' *r CITY SECRETARY
M Jlkdys , City Secretary FT. WORTH,TX
FORT WORTH, City of Fort Worth
Construction Allowance Request
Construction FOA# Date 5/14/2019 City Sec# 1 51035
Client Project#(s)l CPN#101386
FAC#(s)l 30100-0200431-5740010-101386-002480-9999
Project Name HMAC 2018-5 Street Rehabilitation
Description
Contractorl Advance Paving City inspector Jesse Guptin
MaiMEMATION FOR CONSTRUCT
IN ACCORDANCE WITH THIS CONSTRUCTION ALLOWANCE REQUEST,THE CONTRACTOR SHALL:Furnish all labor and material
as per attached proposed Construction Allowance Request(with attachments)to the Construction Allowance Request:This Construction
Allowance Request is needed to cover the additional cost of adjusting the irrigation system at Berkeley PL.Also the Contractor has been asked
to do additional works at Forxfire Way and Cottey St.This construction allowance is need to pay a remobilization costs to the contractor.Also to
pay the contractor the extra cost to replace one mailbox at Cottey St..
FORT WORTH., City of Fort Worth
Construction Allowance Request
Construction FOA# 0 Date 5/14/2019 City Sec# 51035
Client Project#(s) CPN#101386
FAC 9(s)1 30100-0200431-5740010-101386-002480-9999
Project Name HMAC 2018-5 Street Rehabilitation
Description
Contractorl Advance Paving City Inspector Jesse Guptin
ADDITIONS
ITEM DLbGRIF I ION ep nit Unit Cost Total
Miscellaneous Utility Adjustment(irrigation)
39 0170,0101 Specified Remobilization TPW 1.00 LS 7.
40 Additional cost for replacing the Mailbox TPW 1.00 LS $732.50
TPW $12,006.67
Sub Total Additions 1 ,006.67
Change Order Additions Page 1 of 1
FORT WORTH.. City of Fort Worth
� — Construction Allowance Request
Construction FOA# l 1 Date 5/1412019 City Sec# 51035
Client Project#(s) CPN#101386
FAC#(s)1 30100-0200431-5740010-101386-002480-9999
Project Name HMAC 2018-5 Street Rehabilitation
Description
Contractorl Advance Paving City Inspector Jesse Guptin
CONSTRUCTION ALLOWANCE ITEMS TO BE REDUCED
HEM JEKKIP I ION Dept/FAG y Unit UnitCost o a
TPW $0.00
Sub I otal Deletions
Change Order Deletions Page 4 of 5
MIWBE Breakdown for this Construction Allowance Request
MWBE Sub Type of Service Amount for this FOA
Total $0.00
Previous Construction Allowance Requests
CO# DATE AMOUNT
Total $0.00
Contract Compliance Manager:
By signing, I acknowledge that I am
the person responsible for the
monitoring and administration of this
contract, including ensuring all
performance and reporting
requir menu.
Maged Zaki
Project Manager