HomeMy WebLinkAboutContract 35625 (2) City Secretary Contract No
AMENDMENT NO. 2 TO ENGINEERING CONTRACT
FOR WEST SIDE IV PUMP STATION, AND GREENWAY AND CASTLE
CIRCLE LIFT STATIONS CONSTRUCTION MANAGEMENT
STATE OF TEXAS §
COUNTY OFTARRANT §
WHEREAS, on March 25, 2003, the City of Fort Worth, the "City", and Chiang, Patel & Yerby,
Inc., the "Engineer", made and entered into City Secretary Contract No. 28559, which was duly
authorized by the City Council by M&C C-19523 on March 25, 2003, and
WHEREAS, the Contract involves the engineering services for the construction management for
the West Side IV Pump Station;
WHEREAS, the "City"and "Engineer"desire to amend City Secretary Contract No. 28559.
NOW, THEREFORE, That the City of Fort Worth, a municipal corporation situated in Tarrant
County, Texas, acting herein by and through its duly authorized City Manager, hereinafter called
"City", and Chiang, Patel & Yerby, Inc., acting and herein by and through its duly authorized
President, hereinafter called "Engineer", hereby make and enter into the following agreement
which amends the Contract:
1.
Article 1, Section 1 of the Contract is amended to include the additional engineering services
specified in Exhibit A which is incorporated herein. The cost for the additional services to be
performed by the Engineer is $150,000.00.
2.
Article III of the Contract is amended to provide for an increase in the maximum fee to be paid
to the Engineer for all work and services performed under the Contract as specified in Exhibit A
of which is hereto and incorporated herein, so that the total fee paid by the City for all work
and services shall not exceed the sum of $348,946.00.
3.
The Engineer acknowledges its commitment to obtain an additional 10% Minority/Women
Owned Business Enterprise (M/WBE) Participation for this amendment. The Engineer's
commitment for the original contract remains unchanged.
0. RX I
Amendment 2 Page- 1 Ju y1007
Contract No. 28559 ORIGINAL
4.
All other provisions of the Contract, which are not expressly amended herein, shall remain in
force and effect.
AUTHORIZATION
EXECUTED in the City of Fort Worth this day of A.D., 2007.
ATTEST: CITY OF FORT WORTH
BY
City S retary arc ista City Man er
APPROVED: CHIANG, PATEL &YERBY, INC.
aael
By Byrank rumb, P.E. AGraves, P.E.
Director, Water Department
APPROVEDJAFORM EGA ATTEST:
Amy Ramsey
Assistant City Attorney
D—aao Secretary
Contract uthor i zatioa
I— Contract Authorization
Date
Date
V�IIAIL WOOD
Amendment 2 Page-2 Lj SEI-'R fQA o�� July 27,2007
Contract No. 28559 uaSLni
Try. ORTMIOIL �
EXHIBIT A
AMENDMENT NO. 2 TO ENGINEERING CONTRACT
FOR WEST SIDE IV PUMP STATION, AND GREENWAY AND CASTLE
CIRCLE LIFT STATIONS CONSTRUCTION MANAGEMENT
1 SCOPE OF SERVICES
1.1 Additional Construction Phase Services for Westside IV Pump Station
1.1.1 General Description of Work
Additional engineering services for the West Side IV Pump Station included additional services
for: 1) additional site trips during construction, 2) additional requests for information, 3)
additional construction management services due to extending the original 11 month project
duration for West Side IV to 19 months, and 4) services related to replacement of electric motor
on Pump No. 2.
1.1.2 Project Tasks
As part of the additional professional services required for this project, Chiang, Patel and Yerby
Inc. performed the following tasks:
Task 1 Engineer provided services for 26 additional site trips to observe construction
during the project through June 1, 2004.
Task 2 Engineer provided additional office services related to more than 55
unanticipated requests for information during the project.
Task 3 Engineer -provided additional construction management services for the time
period extending from the original 11-month project duration to 19 months. The
19-month time period was from the construction contractor's Notice to Proceed
dated January 6, 2003, until August 10, 2004.
Task 4 Engineer provided additional construction management services after August 10,
2004, relating to the replacement of the electric motor on Pump No. 2. Services
include witnessing the pump and motor alignment procedures, witnessing
vibration tests, and conducting periodic review of the unit during its initial test
period.
Amendment 2 Page-3 July 27,2007
Contract No. 28559
1.2 Construction Phase Services for Greenway and Castle Circle Lift
Stations
1.2.1 General Description of Work
Chiang, Patel and Yerby, Inc. performed Construction Inspection services for the Greenway and
Castle Circle Lift Stations that included part-time on-site construction observations and testing
services
1.2.2 Project Tasks
As part of the professional services required for these projects, Chiang, Patel and Yerby Inc.
performed the following tasks:
Task 1 General Project Inspection Activities
General project inspection activities included the following:
1. Pre-Construction Meetings — Chiang, Patel and Yerby, Inc. attended the project pre-
construction meeting for each facility.
2. Monthly Invoices — Chiang, Patel and Yerby, Inc. prepared and submitted six (6)
monthly invoices for construction inspection activities.
3. Monthly Project Meetings — Chiang, Patel and Yerby, Inc. attended six (6) monthly
progress meetings with representatives from the City and Contractor.
4. Review Contractor Pay Requests — Chiang, Patel and Yerby, Inc. reviewed six (6)
Contractor Pay Requests to verify percent of construction activities completed.
5. Shop Drawings — Chiang, Patel and Yerby, Inc. received and kept on file one (1)
copy of all contractor submittals. Engineer field verified equipment and materials
were as submitted.
6. Other Items — Chiang, Patel and Yerby, Inc. review interpretations and clarifications
of Contract Documents from the Design Engineer. Chiang, Patel and Yerby, Inc.
made recommendations to the Owner as to acceptability of the work.
Task 2 Construction Observations and Testing
Construction testing services were furnished by a sub consultant to Chiang, Patel and Yerby,
Inc. These construction testing services were provided to assist the Owner in determining that
construction was proceeding in accordance with the Contract Documents.
Construction observation was on a part-time basis involving an average of three (3) site trips
per week over a 26-week period. Observations occurred during specific construction phases, or
after specific portions of the work were complete. Construction observations included the
following activities:
Amendment 2 Page-4 July 27,2007
Contract No.28559
1. Conducted observations of Contractor's work in progress and performed field checks
of materials and equipment.
2. Conducted observations of testing services that were provided by sub consultant.
3. Reported to Owner whenever Chiang, Patel and Yerby, Inc. believed that part of
Contractor's work in progress would not produce a completed project that generally
conformed to the Contract Documents; or prejudiced the integrity of the design
concept of the completed project as a functioning whole as indicated in the Contract
Documents; or was damaged, or did not meet the requirements of inspection, tests,
or approval required to be made; and advised Owner of that part of the work in
progress that we believed should be corrected or uncovered for observation, or
required special testing, inspection, or approval.
4. Witnessed pipe pressure and leakage tests performed by the Contractor.
5. Attended walk-through of the completed project and assisted in preparation of a list
of observed items requiring completion or correction. Observed whether items had
been completed or corrected, and made recommendations to Owner concerning
acceptance.
6. Reviewed Contractor's as-built drawings and provided comments to Owner to aid in
completion of record drawings by others.
1.3 Project Schedule
Chiang, Patel and Yerby, Inc. completed the tasks described in the Scope of Work within the six
(6) month period designated for construction of the facilities from the Contractor's mobilization
to final completion.
2 Compensation
For construction management services under Amendment No. 2, the ""City" shall pay the
"Engineer"a lump sum fee of $150,000. A breakdown of the fees is shown in Table 1.
Table 1 Fee Breakdown for Engineering Services
Team Member Total Fee Percentage
Participation
Westside IV Pump Station
Chiang, Patel &Yerby, Inc. $81,000.00 90%
Gupta Associates, Inc. (MWBE firm) $9,000.00 10%
Subtotal $90,000.00 100%
Amendment 2 Page-5 July 27,2007
Contract No. 28559
Greenway and Castle Circle Lift Stations
Chiang, Patel &Yerby, Inc. $54,000.00 90%
Mas-Tech Engineering Associates Inc. $6,000.00 10%
(MWBE firm)
Subtotal $60,000.00 100%
TOTAL $150,000.00
Amendment 2 Page-6 July 27,2007
Contract No. 28559
M&C Request Review Page 1 of 2
CuLy of Fort forth Employee Intranet
f •� 1♦ 1 ♦ ei,. L I
Print M&
COUNCIL ACTION: Approved on 7/24/2007
DATE: 7/24/2007 REFERENCE NO.: **C-22267 LOG NAME: 60WESTSIDE IV
CODE: C TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT: Authorize Amendment No. 2 to City Secretary Contract No. 28559 with Chiang, Patel and Yerby,
Inc., for Construction Management of the West Side IV Pump Station and the North Side III High
Service Pump Station
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Amendment No. 2 to City
Secretary Contract No. 28559 with Chiang, Patel and Yerby, Inc., for Construction Management of the West
Side IV Pump Station and the North Side III High Service Pump Station, in the amount of$150,00 , thereby
increasing the contract from $198,949 to $348,949.
DISCUSSION:
On March 25, 2003, (M&C C-19523) the City Council authorized the execution of an engineering agreement
with Chiang, Patel and Yerby, Inc., for construction administration services and inspection services for the
West Side IV Pump Station project and the Eagle Mountain Water Treatment Plant (EMWTP) Northside III
High Service Pump Station project. The new West Side IV Pump Station expands the West Side IV water
service area and the water service delivery capability in far west Fort Worth including Walsh Ranch. The
EMWTP North Side III High Service Pump Station Improvements provide additional pumps to serve the
growing North Side III pressure plane in far north Fort Worth.
The completion time for the West Side IV Pump Station and the EMWTP Northside III High Service Pump
Station construction contracts was extended by change orders requiring additional construction management
services and part-time inspection work from the Engineer.
The contractor for the West Side IV Pump Station project was unable to complete the work; however, the
bonding company intervened using a take-over agreement to complete the project. Chiang, Patel and Yerby,
Inc., provided inspection and construction management services during the take-over period.
In addition, the Engineer will provide specialized electrical inspection and construction services support for
small lift stations. The City is responsible for construction services for Castle Circle and Greenway Lift
Stations. Specialized electrical and mechanical inspectors from the City were not available at certain times
and Chiang, Patel and Yerby, Inc., was requested to provide support and inspection as necessary. In additioi
to the amendment, $12,000 is required for project management by Water Department staff.
Chiang Patel and Yerby, Inc., is in compliance with the City's MWBE Ordinance by committing to 10 percent
MWBE participation on this Amendment No. 2. The City's goal on this Amendment is 10 percent.
This project is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION/CERTIFICATION:
http://www.cfwnet.org/council_packet/mc review.asp?refnum=C-22267 7/30/2007
NJI&C Request Review Page 2 of 2
The Finance Director certifies that funds are available in the current capital budget, as appropriated, of the
Commercial Paper Water Fund.
TO FundlAccount/Centers FROM Fund/Account/Centers
PW77 539120 060770160210 $150,000.00
Submitted for City Manager's Office by: Marc Ott (8476)
Originating Department Head: S. Frank Crumb (8207)
Additional Information Contact: S. Frank Crumb (8207)
ATTACHMENTS
http://www.cfwnet.org/council_packet/mc review.asp?refnum=C-22267 7/30/2007