HomeMy WebLinkAboutContract 36551AMENDMENT NO. 7
STATE OF TEXAS § CITY SECRETARY CONTRACT NO. 1
COUNTY OF TARRANT §
WHEREAS, the City of Fort Worth (City) and TranSystems Corporation
Consultants (Engineer) made and entered into City Secretary Contract No. 26807 (the
Contract) which was authorized by the City Council by M&C C-18571 on the 24th day of
April, 2001; and
WHEREAS, the Contract involves engineering services for the following project:
Engineering Contract for Sanitary Sewer Main 244A Relief Study and
Design
WHEREAS, it has become necessary to execute Amendment No. 7 to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
Contract:
1.
Article I of the Contract is amended to include the additional engineering services
specified in a proposal letter dated August Z. 2007, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional services to be performed by
Engineer total $23,470.00.
2.
Article II of the Contract is amended to provide for an increase in the maximum
fee to be paid to Engineer for all work and services performed under the Contract, as
amended, so that the total fee paid by the City for all work and services shall not exceed
the sum of $1,158,759.06.
All other provisions of the contract, which are not expressly amended herein, shall
remain in full force and effect.
01-29-08 P03�05 I�!
'' 1�1N , VG As
EXECUTED on this the 1 day of -U , 200S,
Fort Worth, Tarrant County, Texas.
APPROVAL RECOMMENDED:
A, I ! ���fFl
1,IFil Yj
Do . ad_
Director, Department
TranSystems Corporation Consultants
ENGINEER
By:
Name: Raul Pena III. P.E.
Regional Vice -President
Assistant City Manager
ATTEST:
Marty Hendrix,
t
8-2-2001
Gopal Sahu, P.E.
Department of Engineering
City of Fort Worth
1000 Throckmorton
Fort Worth, Texas
76102
Reference to: Summary and Scope of Services
Sanitary Sewer Main 244-A Village Creek Parallel Collector
Amendment No. 7
Dear Mr. Sahu,
TranSystems
500 West Seventh Street
Suite 1100
Fort Worth, TX 76102
Tel 817-339-8950
Fax 817-336-2247
www.transystems.com
We have prepared this amendment request to cover additional services not provided for in the original
contract or subsequent amendments. In summary this request is as follows:
1. Construction Management Meetings with the Contractor Lump Sum 9,770.00
The Water Dept. requested that TranSystems set-up construction schedule meetings for the Contractors (2)
that were awarded the 4 construction phases. The goal of the meeting is to record progress and discuss
project concerns. This is for services from April through December 2007 (16 meetings). This includes
minutes/agendas and coordination.
Project Manager 36hrs x 150.00 = $ 5,400.00
Sr. Project Manager 15hrs x 170.00 = $ 2,500.00
Principal 7hrs x 260.00= $ 1,820.00
2. M- 503 Relief Line Lump Sum 13,700.00
The City directed TSC to redesign the Town of Pantego sewer into a force main under the Union Pacific
Railroad. The proposed design would avoid the cost and time to relocate some existing utilities and elevate
the Pantego Sewer above the crown of M-503. The design includes reviewing existing utilities elevation
with franchise utilities, coordination with Town of Pantego and their consultant, site visits, design of
improvements, and coordination with the Union Pacific Railroad to obtain an amended permit. This does not
include construction services.
Coordination and design
Engineer III 40 his x 150.00 = $ 6,000.00
'ADD Technician IV 24 hrs x 100.00 = $ 2,400.00
Additional UPRR Permit
Engineer III 20 hrs x 150.00 = $ 3,000.00
CADD Technician IV 8 hrs x 100.00 = $ 800.00
Subtotal $23,470.00
In an effort of good faith we have already been performing work outside our contract by attending meetings
with Contractor, and working with the Town of Pantego on the redesign of the sewer.
1
Summary of the Contract and Amendments
Original Contract $ 727,760.00
Amendment 1.
Amendment 3
Amendment 4
Amendment 5.
$ 179,141.48 Increase Pipe Size, Far East Fort Worth HOA Study
and Design/Survey Phase 1
$ 18,897.00 Geotechnical Services
$ 72,556.00 Pipe Reduction, Odor Control, Diversion Structure,
Far East Fort Worth HOA Study and Design/Survey
Phase 2
$ 19,546.52 36" Sewer and Structures, Environmental Information
Document for SRF Funding, Break Plans into
Additional Phases.
$ 83,855.00
Amendment 6. $ 33, 533.06
Sub Total 1,135,289.06
Renewal of permits and Engineering Assistance
during construction (council authorized amount)
Hydraulic Modeling, M-503 plans relating to
Pantego and construction assistance (revised)
Amendment 7. $ 23,470.00 Revised Pantego Sewer design
Total 1,158,759.06
Please feel free to contact me or Kent Lunski P.E., if you should have any questions.
MMM
Raul Pena III, P-�---
Regional Vice -President
TranSystems
2