HomeMy WebLinkAboutContract 34073-A2 AMENDMENT NO. 2
STATE OF TEXAS § CITY SECRETARY CONTRACT NO.-3A013-A:�,
(No M&C Needed)
COUNTY OF TARRANT §
WHEREAS, the City of Fort Worth (City) and Multatech Engineering , Inc.,
(Engineer) made and entered into City Secretary Contract No. 34073 (the Contract)
which was authorized by the City Council by M&C C-21720 on the 26th day of
September,2006; and
WHEREAS,the Contract involves engineering services for the following project:
Engineering Contract for Pavement Reconstruction and Water and Sanitary
Sewer Main Replacement on NE 29TH Street, North Hampton Street and North
Terry Street.
WHEREAS, it has become necessary to execute Amendment No. 2 to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
Contract:
1.
Article I of the Contract is amended to include the additional engineering services
specified in a proposal letter dated December 18, 2008, a copy of which is attached
hereto and incorporated herein. The cost to City for the additional services to be
performed by Engineer total $8,000.00
2.
Article II of the Contract is amended to provide for an increase in the maximum
fee to be paid to Engineer for all work and services performed under the Contract, as
amended, so that the total fee paid by the City for all work and services shall not exceed
the sum of$155,526.00
3.
All other provisions of the contract,which are not expressly amended herein, shall
remain in full force and effect.
OFFICIAL RECORD
CCU°!IsECK—TARP
< !T
FT'. .0
=-- ORIGINAL
01 -20-09 A11 :41 IN
EXECUTED on this the Sk day of t' C , 2009_, in
Fort Worth, Tarrant County, Texas.
APPROVAL RECOMMENDED: APPROVED:
Fernando Costa
William A. Verkest/,/PE. Assistant City Manager
Director, Transportation and
Public Works Department
Multatech Engineering, IInc.
ENGINEER
ATTEST:
r"*\
Marty Hendri City Secretary
By: —
Name: Alfred Saenz
President --
1407 Texas Street, Suite 200 NO M&C REQUIRED
Fort Worth, Texas 76102
APPROV S TO FO LEGALITY:
Assistant Cit Attorney
OFFrIAL RECORD
C17-'f•�',,---CRETARY
FT �.''O ii,Tx
December 18, 2008
,f .. Mr. Gopal Sahu, P.E.
MULTATECH Project Manager,
City of Fort Worth TPW Department
1000 Throckmorton
Fort Worth, Texas 76102
RE: Revisions for Capital Improvement Project 00442 DOE # 5397
Mr. Sahu:
Due to existing elevation differences, the design for the street
rehabilitation required use of a non-standard street section for North
Terry Street to produce acceptable slopes for residential driveways
and to minimize the effects of the rehabilitation on existing retaining
walls and other permanent structures.
Since this was not approved until after the 60% submittal, the paving
plan and profiles and the cross sections for the CIP Project 42 to
accommodate the non-standard section with 12" grade separation
required extensive changes in the plan/profiles and cross sections for
North Terry Street.
These changes resulted in additional revisions, reviews and an
additional utility clearance submittal.
As a result of this extra effort, we are asking that the fee for the
project be amended to include these additional changes.
We are requesting an additional $ 8,000.00 to cover these costs and
the expenses incurred by completing these changes. See attached
sheet for breakdown of hours and fees.
This amount is for work done under Work Phase 33 — Final Design
for the Paving/Drainage part of the project. The following tables are
included to show original and revised contract amounts including this
and a previous addendum for Geotechnical Services included in
Work Phase 31 — Concept Design.
1407 Texas Street,Suite 200,Fort Worth,Texas 76102-3428 • Phone:817-877-5571 • Fax:817-877-4245 • www.multatech.com
Work
Phase PAVING OR DRAINAGE
Amendment Revised Amt.
Orig. Amount Amount incl. Amendment
51 Design survey Fee $ 11,185.00 $ 11,185.00
31 Concept Design $ 21,666.79 $ 13,200.00 1 $ 34,866.79
32 Preliminary Design $ 43,333.58 $ 43,333.58
33 Final Design $ 7,222.63 $ 8,000.00 2 $ 15,222.63
CONTRACT AMT. $ 83,408.00 $ 104,608.00
(1) Amendment 1 - Contract No. 34884
(2) Amendment 2 -
Work
Phase TOTALS (including Amendments
WATER Sanitary Sewer Paving/Drainage
51 Design survey Fee $ 10,952.00 $ 1,183.00 $ 11,185.00
31 Concept Design $ 10,501.20 $ 1,133.70 $ 34,866.79
32 Preliminary Design $ 21,002.40 $ 2,267.40 $ 43,333.58
33 Final Design $ 3,500.40 $ 377.90 $ 15,222.63
$ 45,956.00 $ 4,962.00 $ 104,608.00
PROJECT TOTAL
Incl. Amendments $ 155,526.00
If you have questions, please contact me at (817) 877-5571 x 107.
Sincerely,
Multatech Engineering, Inc.
Bruce Nelson, P.E.
Sr. Civil Engineer
Accepted:
City of Fort Worth TPW
N e/Title IM Date
1407 Texas Street,Suite 200, Fort Worth,Texas 76102-3428 Phone:817-877-5571 Fax:817-877-4245 www.multatech.com
City of Fort Worth
2004 Capial Improvement Program Contract 42
PAVEMENT RECONSTRUCTION, WATER AND SEWER REPLACEMENT
NE 29T" STREET (WEBER ST. TO SCHWARTZ AVE.)
N. HAMPTON STREET (NE 32ND ST. TO E. LONG AVE.)
N. TERRY STREET (NE 30T" ST. TO NE 35T" ST.)
MANHOURS TOTAL
TASK& DESCRIPTION 0
UNITS d L J L J 0 V H HRS/TASK
a) Paving Design 84.0
1 Field Visits & meetings Hr 12.0 8.0 20.0
2 Revise plan and profiles Hr 4.0 24.0 4.0 32.0
3 Revise Cross Sections Hr 4.0 24.0 4.0 32.0
TOTAL HOURS 20.0 56.0 8.0
HR FEE with OH $110.00 $95.00 $60.00
$2,200.00 $5,320.00 $480.00 $8,000.00