� 2019 Change Order Request
Pr �*1%1 Northside IV 24-Inch Water Transmission Main City Sec No.: 1 49527
ov �R5
P?#Ao'.(s): 56011-0600430-5740010-100277 DOE No. I N/A CityProj.No.:l 100277
Project Description: 24-Inch Water Main from Eagle Mountain Water Treatment Plant to Baily Boswell
Contractor: Condie Construction Company, Inc. Change Order# ® Date: 6/1912019
City Project Mgr.J John Kasavich City Inspector: I Judy Die
Phone Number:1 817-392-8480 Phone Number: 817-392-8452
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $4,859,595.00 $4,859,595.00 320
Extras to Date $310,538.33 $310,538.33 0122
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $5,170,133.33 $5,170,133.33 442
Amount of Proposed Change Order $245,518,85 $245,518.85 170
Revised Contract Amount $5,415,652.18 $5,415,652.18 612
Original Funds Available for Change Orders $243,000.00 $243,000.00
Remaining Funds Available for this CO
Additional Funding(if necessary) $245,518.85 $245,518.85
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 11.44%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+2591o) $6,074,493.75
.iUSTiFfCATiON R!A4ONS ,FOR CHANCE ORI R
Change Order No.4 will provide for the importation of select concrete low strength backfill material to replace
additional areas with unsuitable material that were encountered during trenching operations.The change order
will also provide increased pay item quantities of temporary asphalt pavement repair, 24-inch ductile iron pipe
and fittings, 8-inch flanged outlet to the hydro pneumatic tank, installation of drain for transfer station sump
pump and chlorine analyzer into the sanitary sewer system and traffic control that are necessary on the project.
Staff concurs with the addition of 170 additional calendar,days to the project for this change order.
of FoRr�
Attes d by: ,`� :p
M L kY)4e-rUy Secretary
It is understood and agreed that the acceptance of this Change Order by actor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
on rac
Condie Construction Company, Inc. Ken Condie
Inspector Date Pro'ect Plana er
—
Directo (Wa r Dept) Date C 4ruction Su ervlsor Water Dept) Date
T s.
AsslApnL2Wo= Dat Assistant City Manager .
JR®
Council Action if Required CRY
M&C Number C-29153 , i(Gf _`T! Y� M&C Date Approved T WORTH TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Northside IV 24-Inch Water Transmission Main City Sec No.: 49527
Project No.(s): 56011-0600430-5740010-100277 1 DOE No.E� City Proj. No.: 100277
Project 24-Inch Water Main from Eagle Mountain Water Treatment Plant to Baily Boswell
Description
Contractor Condie Construction Company, Inc. Change Order:® Date: 1/30/2019
City Project Mgr. John Kasavich City Inspector Judy Die
ADDITIONS
ITEM DESCRIPTION DEPT Q Unit Unit Cost Total
1a 24"Ductile Iron Wate Pipe(Pressure Class 250) Installed in Trench Water 83.00 LF $176.00 $14,608.00
3a Ductile Iron Water Fittings w/Restraint Water 0.10 LS $170,000.00 $17,000.00
7 2"Combination Air Valve Assembly for Water Water 1.00 EA $9,550.00 $9,550.00
13 Manhole/Vault Concrete Collar Water 4.00 EA $700.00 $2,800.00
14 Valve Box Concrete Collar Water 1.00 EA $500.00 $500.00
16 7'Wide Permanent Asphalt Pvmt. Repair, Residential Water 13.00 LF $44.00 $572.00
17 Asphalt Pvmt Repair Beyond Trench Width Water 67.00 SY $56.00 $3,752.00
18 Temporary Asphalt Pvmt Repair(2"HMAC on 6"CTB) Water 2,009.00 LF $14.00 $28,126.00
23 Trench Safety Water 92.00 LF $1.00 $92.00
30 Imported Embedment/Backfill CLSM Water 470.00 CY $142.00 $66,740.00
33 Imported Embedment/Backfill Select fill Water 1850.00 CY $36.00 $66,600.00
35 Remove 12"Storm Line-Seth Barwise St Water 8.00 LF $3.00 $24.00
37 Remove 18"Storm Line-Seth Barwise St Water 87.00 LF $5.00 $435.00
39 12"RCP, Class III-Seth Barwise St Water 8.00 LF $39.00 $312.00
41 18"RCP Class III-Seth Barwise St Water 87.00 LF $46.00 $4,002.00
45 Construction Staking Water 0.20 LS $15,200.00 $3,040.00
47 Traffic Control Water 0.20 LS $68,000.00 $13,600.00
48 Cost to add 8"flanged outlet to Hydropneumatic tank Water 1.000 LS $24,000.00 $24,000.00
49 Install drain for both transfer station sump and CL2 analyzer into sewer Water 1.00 LS $14,877.85 $14,877.85
50 Install geotextile fabric and 3-inch layer of crushed rock inside transf.station Water 1.00 LS $6,000.60 $6,000.00
Water $276,630.85
Sewer
Page 2 of 4 Additions Sub Total $276,630.85
FC3RT Wc3RTH City of Fort worth
! Change Order Deletions
Project Name Northside IV 24-Inch Water Transmission Main City Sec No.: 49527
Project No.(s): 56011-0600430-5740010-100277 DOE No. N/A City Proj.No.: 100277
Project Description 24-Inch Water Main from Eagle Mountain Water Treatment Plant to Bally Boswell
Contractor Condie Construction Company, Inc. Change Order: ® Date
City Project Mgr. John Kasavich City Inspector: Judy Die
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
2a 24"Ductile Iron Water Water 83.00 LF $214.00 $17,762.00
29 Imported Embedment/Backfill CSS Water 50.00 CY $91.00 $4,550.00
31 Imported Embedment/Backfill Crushed Rock Water 100.00 CY $52.00 $5,200.00
32 Imported Embedment?Backfill,Acceptable Backfill Water 100.00 CY $36.00 $3,600.00
Water $31,112.00
Sewer
Page 3 of 4 Deletions Sub Total $31,112.00
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Page 4 of 4
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
Signature
Name of Employee
/Q cc E►,
Title
M&C Review Page 1 of 2
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA FORT
COUNCIL ACTION: Approved on 6/18/2019 �
REFERENCE ** 60NSIV24INWMC04-
DATE: 6/18/2019 NO.: C-29153 LOG NAME: CONDIE
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Change Order No. 4 in the Amount of$245,518.85 and the
Addition of 170 days to City Secretary Contract No. 49527 with Condie Construction
Company, Inc. for a Revised Contract Amount of$5,415,652.18 for Northside IV 24-Inch
Water Transmission Main Along Bowman Roberts Road from Santa Gertrudis Street to
Bailey Boswell Road (COUNCIL DISTRICT 7)
RECOMMENDATION:
It is recommended that the City Council authorize the execution of Change Order No. 4 to City
Secretary Contract No. 49527 with Condie Construction Company, Inc., in the amount of$245,518.85
and the addition of 170 calendar days for Northside IV 24-Inch Water Transmission Main along
Bowman Roberts Road from Santa Gertrudis Street to Bailey Boswell Road. (City Project No.
100277)
DISCUSSION:
On August 1, 2017, Mayor and Council Communication (M&C C-28316) the City Council authorized
a contract with Condie Construction Company, Inc., in the amount of$4,859,595.00 for Northside IV
24-Inch water transmission main along Bowman Roberts Road from Santa Gertrudis Street to Bailey
Boswell Road. The contract was subsequently revised by Change Order No. 1 in the amount of
$19,277.70 administratively authorized on February 1, 2018, Change Order 2 in the amount of
$205,786.00 authorized on June 12, 2018 (M&C C-28727) and Change Order No. 3 in the amount of
$85,474.63 administratively authorized on October 30, 2018.
Change Order No. 4 will provide for the importation of select concrete low strength backfill material
to replace additional areas with unsuitable material that were encountered during trenching
operations. The change order will also provide increased pay item quantities of temporary asphalt
pavement repair, 24-inch ductile iron pipe and fittings, 8-inch flanged outlet to the hydro pneumatic
tank, installation of drain for transfer station sump pump and chlorine analyzer into the sanitary
sewer system and traffic control that are necessary on the project.
MWWBE OFFICE—Condie Construction Company, Inc. agrees to maintain its initial MWBE
commitment of nine percent that it made on the original contract and extend and maintain that same
MWBE commitment of nine percent to all prior change orders up to and inclusive of this Change
Order No. 4. Therefore Condie Construction Company, Inc. remains in compliance with the City's
MWBE Ordinance and attests to its commitment by its signature on the Acceptance of Previous
MWBE Commitment form executed by an authorized representative of it company.
This project is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budgets, as
appropriated, of the Water/Sewer Bond 2017A Fund. The Major Mains Programmable Project
P00002 includes an appropriation of$9,954,000.00 for the Water main capital projects. After the
funding of this M&C, the amount of$9,212,635.00 of the appropriation will be available to fund future
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=27129&councildate=6/18/2019 6/28/2019
M&C Review Page 2 of 2
individual projects.
Appropriations for Northside IV 24-Inch Water Transmission Mair Along Bowman Roberts Road from
Santa Gertrudis Street to Bailey Boswell Road Project by Fund will consist of the following:
FUND Existing Additional ProjE�ct Total"
Appropriations Appropriations
W&S Community
Facilities Agmt - $868,322.70 $0.00 $86:3,322.70
Fund 56008
Water& Sewer
Bond 2017A- Fund $5,574,655.00 $0.00 $5,5; 4,655.00
56011
Project Total 11 $6,442,977.70 $0.00 $6,442,977.70
*Numbers rounded for presentation purposes.
TO
ru—nTDepartment Account Project Program Activity Budget Reference# Amount
ID I ID I Year (Chartfleld 2)
FROM
Fund Department Account Project Program Activity_.Budget Reference# Amount
ID ID Year (Chartfield 2)
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Chris Harder (5020)
Additional Information Contact: John Kasavich (8480)
ATTACHMENTS
60NSIV24INWMC04-CONDIE MAP.PDF
http://apps.cfwnet.org/council_packet/mc review.asp?ID=27129&councildate=6/18/2019 6/28/2019