Change Order Request
Project Name:1 2004 Capital Improvements Program-Year 1 Contract 6 City Sec No.: 1 35764
Project No.(s): C200-204400075583&P264-604170075583 I DOE No. 5644 City Proj.No.:1 00755
Project Description: The replacement of water,sanitary sewer mains and Concrete pavement on Mesquite Road from cul-de-sac to Fossil
Drive.
Contractor:I McClendon Construction Co.Inc. Change Order# L Date: 1 5/10/2012
City Project Mgr.J Roberto C.Sauceda I City Inspector. I Wade Johnson
Phone Number. 817-392-2387�---1 Phone Number. 817-991-8133
Dept. TPW Water Sewer Totals
Contract Time
(Calender days)
Original Contract Amount $262,236.50 $73,856.50 $81,157.50 $417,250.50 90
Extras to Date $12,856.25 $12,856.25 01
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $275,092.75 $73,856.50 $81,157.50 $430,106.75 91
Amount of Proposed Change Order $9,850.50 9,850.55 04
Revised Contract Amount $284,943.25 $73,856.50 $81,157.50 $439,957.25 95
Original Funds Available for Change Orders $13,112.00 $6,000.00 $6,000.00 $25,112.00
Remaining Funds Available for this CO $255.75 $6,000.00 $6,000.00 $12,255.75
Additional Funding(if necessary) $9,594.75 $9,594.75
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.44%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) 1$521,563.13
JUSTIFICATION(REASONS)FOR CHANGE ORDER
The change order will provide for the following.
• Additional pay item quantity for hand pouring of cement on cul-de-sac due to petroleum line
relocation.
• Additional pay item quantity for additional excavation and subgrade stabilization due to petroleum
line relocation during construction.
Op Qattjl
Staff concurs with the contractor's req AA cl�® jkpa,,l calendar days be provided on the project.
pV Oo°0000poo Y
!y�oo *0
AwsW by. �o o��¢ OFFICIAL RECORD
o U°�� CITY SECRETARY
jV-arly . Ka 1 a o°°itb FT.WORTH, TX
°°0000°° -O'
It is understood and agreed that the acceptance of this Chan r er by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Or
Contractor's Company Name Contractor Name CortrAor,% Date,
McClendon Construction Co. Inc. B.j. Blair 2
IN
In t ate Project Mana er Date
Assi a ept Date struction Supervisor JPW Dept Date
�,t.,, i e Date Assistant City Manager Date
VIC-
Council Action If Required)
M&C Number M&C Date Approved
FORT WOO RT H City of Fort Worth City Secretary C161;;. I
1W Now— Change Order Request
Project Name:1 2004 Capital Improvements Program-Year 1 Contract 6 City Sec No.: 35764
Project No.(s): C200-204400075583&P26"04170075583 I DOE No. 5644 City Proj.No.: 00755
Project Description:
The replacement of water,sanitary sewer mains and Concrete pavement on Mesquite Road from cul-de-sac to Fossil
Drive.
Contractor: McClendon Construction Co.Inc. Change Order# Date: 5I1012012
City Project Mgr.1 Roberto C.Sauceda City Inspector: I Wade Johnson
Phone Number. 817-392-2387 Phone Number: 817-991-8133
Dept. TPW Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $262,236.50 $73,856.50 $81,157.50 $417,250.50 90
Extras to Date $12,856.25 $12,856.25 01
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $275,092.75 $73,856.50 $81,157.50 $430,106.75 91
Amount of Proposed Change Order $9,850.50 $9,850.50 04
Revised Contract Amount $284,943.25 73,856.50 $81,157.50 $439,957.25 95
Original Funds Available for Change Orders $13,112.00 $6,000.00 $6,000.00 $25,112.00
Remaining Funds Available for this CO $255.75 $6,000.00 $6,000.00 $12,255.75
Additional Funding(if necessary) $9,594.75 $9,594.75
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.44%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25916) 1$521,563.13
JUSTIFICATION(REASONS)FOR CHANGE ORDER
The change order will provide for the following.
• Additional pay item quantity for hand pouring of cement on cul-de-sac due to petroleum line
relocation.
• Additional pay item quantity for additional excavation and subgrade stabilization due to petroleum
line relocation during construction.
Staff concurs with the contractor's request for 04 additional calendar days be provided on the project.
Ifi
IPA II 111
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change 01�eF�
Contractor's Company Name Contractor Name Co r Date
McClendon Construction Co. Inc. B.j.Blair
tn+ectcA A ate Project Manager Date
/I„'-
Assists ° ate ft t Date Co struction Supervisor(TPW Dept) Date
i e Date Assistant City Manager Date
Council Action if R uired
M&C Number M&C Date Approved
- • �FOITt'`7VC�I 'I"H City of Fort Worth City Secretary Copy-
Change Order Request
Project Name:1 2004 Capital Improvements Program-Year 1 Contract 6 City Sec No.: 35764
Project No.(s): C200-204400075583&P264-604170075583 I DOE No. 5644 City Proj.No.: 00755
The replacement of water,sanitary sewer mains and Concrete pavement on Mesquite Road from cul-de-sac to Fossil
Project Description: Drive.
Contiractorl McClendon Construction Co.Inc. Change Order# 0 Date: 5/10/2012
City Project Mgr.1 Roberto C.Sauceda City Inspector; I Wade Johnson
Phone Number:1 817-392-2387 Phone Number. 817-991-8133
Dept. TPW Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $262,236.50 $73,856.50 $81,157.50 $417,250.50 90
Extras to Date $12,856.25 $12,856.25 01
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $275,092.75 $73,856.50 $81,157.50 $430,106.75 91
Amount of Proposed Change Order 9,850.50 9,850.50 04
Revised Contract Amount $284,943.25 $73,856.50 $81,157.50 $439,557.25 95
Original Funds Available for Change Orders $13,112.00 $6,000.00 $6,000.00 $25,112.00
Remaining Funds Available for this CO $255.75 $6,000.00 $6,000.00 $12,255.75
Additional Funding(if necessary) $9,594.75 $9,594.75
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.44%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) 1$521,563.13
JUSTIFICATION(REASONS)FOR CHANGE ORDER
The change order will provide for the following.
• Additional pay item quantity for hand pouring of cement on cul-de-sac due to petroleum line
relocation.
• Additional pay item quantity for additional excavation and subgrade stabilization due to petroleum
line relocation during construction.
Staff concurs with the contractor's request for 04 additional calendar days be provided on the project.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.,
Contractor's Company Name Contractor Name Cor#rqct9r Date
McClendon Construction Co. Inc. B.j.Blair f:'
InspectqF Date Project Manager Date
r
Assistant Dir Water Dept) Date Coiptruction Supervisor JPW Dept Date
sta Att a Date Assistant City Manager Date
Council Action if Required
M&C Number M&C Date Approved
FO RTQ�IYO RT H City of Fort Worth City Secretary Copy 4
Change Order Request
Project Name:1 2004 Capital Improvements Program-Year 1 Contract 6 City Sec No.: 35764
Project No.(s): C200-204400075583&P264-604170075583 I DOE No. F-5-64-4--7 City Proj.No.: 00755
The replacement of water,sanitary sewer mains and Concrete pavement on Mesquite Road from cul-de-sac to Fossil
Project Description:
Drive.
Contractor: McClendon Construction Co. Inc. Change Order# Date: 1 5/10/2012
City Project Mgr.1 Roberto C.Sauceda City Inspector. I Wade Johnson
Phone Number:1 817-392-2387 Phone Number.1 817-991-8133
Dept. TPW Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $262,236.50 $73,856.50 $81,157.50 $417,250.50 90
Extras to Date $12,856.25 $12,856.25 01
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $275,092.75 $73,856.50 $81,157.50 $430,106.75 91
Amount of Proposed Change Order 9,850. 0 _ 9,850.50 04
Revised Contract Amount $284,943.25 $73,856.50 $81,157.50 $439,957.25 95
Original Funds Available for Change Orders $13,112.00 $6,000.00 $6,000.00 $25,112.00
Remaining Funds Available for this CO $255.75 $6,000.00 $6,000.00 $12,255.75
Additional Funding(if necessary) $9,594.75 1 $9,594.75
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 1 5.44%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) 1$521,563.13
JUSTIFICATION(REASONS)FOR CHANGE ORDER
The change order will provide for the following.
• Additional pay item quantity for hand pouring of cement on cul-de-sac due to petroleum line
relocation.
• Additional pay item quantity for additional excavation and subgrade stabilization due to petroleum
line relocation during construction.
Staff concurs with the contractor's request for 04 additional calendar days be provided on the project.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractors Company Name Contractor Name Contractor Date
McClendon Construction Co. Inc. B.j.Blair
Inspector Date Project Manager Date
Assistant Director Water Dept) Date Construction Supervisor TPW Dept) Date
Assistant City Attorney Date Assistant City Manager Date
Council Action If Required)
M&C Number M&C Date Approved
FORT WORTH City of Fort Worth
—� Change Order Additions
Project Name 2004 Capital Improvements Program-Year 1 Contract 6 City Sec No.: 35764
Project No.(s): C200-204406075583&P264-604170075583 DOE No. 5644 City Proj.No.: 00755
Project The replacement of woter,sanitary sewer mains and Concrete pavement on Mesquite Road from cul-de-sac to Fossil
Description Drive.
Contractor McClendon Construction Co.Inc. Change Order: L__J Date: 5I1012012
City Project Mgr. Roberto C.Sauceda City Inspector Wade Johnson
ADDITIONS
ITEM DEMIRIPTION ---D-97 Oty Unit Unit Cost Total
18 Pavement-Concrete-Hand Pour TPW 1.00 LS $4,961.00 $4,961.00
19 Walk-ADA Wheelchair Ramp—Install TPW 1.00 LS $4,889.50 $4,889.50
TPW $9,850.50
Water
Sewer
Page 1 of 1 Additions Sub Total $9,850.50
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name 2004 Capital Improvements Program-Year 1 Contract 6 City Sec No.: 35764
Project No.(s): C200-204400075583&P264-604170075583 DOE No. L5644 City Proj.No.: 1 00755
Project Description The replacement of water,sanitary sewer mains and Concrete pavement on Mesquite Road from cul-de-sac to Fossil
Drive.
Contractor McClendon Construction Co.Inc. Change Order: a] Date 5/10/2012
City Project Mgr. Roberto C.Sauceda City Inspector. Wade Johnson
DELETIONS
ITEM DESCRIPTION DEPT City Unit Unit Cost Total
TPW
Water
Sewer
Page 1 of 1 Deletions Sub Total
MMBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
Co# DATE AMOUNT
Total $0.00
Page 1 of 1