HomeMy WebLinkAboutContract 35873 AMENDMENT NO. 5
STATE OF TEXAS S CITY SECRETARY CONTRACT NO.53Z3
(M&C Required)
COUNTY OF TARRANT S
WHEREAS, the City of Fort Worth (City) and TranSystems
Corporation d/d/a TranSystems Corporation Consultants, (Engineer)
made and entered into City Secretary Contract No. 27574 , (the
Contract) which was authorized by the City Council by M&C C-18999 on
the 19th day of March, 2002 and subsequently revised by four previous
amendments; and
WHEREAS, the Contract involves engineering services for the
following project:
Trinity Boulevard Water Main Extension from Greenbelt Road to
State Highway 360.
WHEREAS, it has become necessary to execute Amendment No. 5 to
said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly authorized representatives, enter into the following
agreement which amends the Contract:
1.
Article I, of the Contract is amended to include the additional
engineering services specified in M&C C-22372, adopted by the City
Council on the 9th day of September, 2007, and further amplified in a
proposal letter dated June 19, 2007 copies of which are both attached
hereto and incorporated herein. The cost to City for the additional
services to be performed by Engineer total $35,200.00.
2.
Article II, of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the total
fee paid by the City for all work and services shall not exceed the
sum of $730,324 .00.
:; Rom ORIGINAL
3.
All other provisions of the Contract which are not expressly
amended herein shall remain in full force and effect.
EXECUTED on this the _ day of6\-AV1AdJ4V-VY-1(_') , 2007, in Fort
Worth, Tarrant County, Texas.
ATTEST:
c,n`r t uthorization
Marty Hendri.
City Secretary
APPROV RECOMb,ENDED: / PR
A. Douglas Rademaker, P.E . Mar A. -Ot -
Director, Department of Assistant City Manager
Engineering
TRANSYSTEMS CORPORATION d/d/a
TRANSYSTEMS CORPORATION CONSULTANTS
Engineer
By:
Name:Joseph C. Masterson P.E .
Vice President
500 W. 7 St. STE 600
Fort Worth, TX 76102 - 4773
APPRt TO RM LE ITY:
k
Assist it Attorne
-2-
rage i of .
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 9/11/2007
DATE: Tuesday, September 11, 2007
LOG NAME: 30TRINITYWA5 REFERENCE NO.: **C-22372
SUBJECT:
Authorize Execution of Amendment No. 5 to City Secretary Contract No. 27574 with TranSystems
Corporation d/b/a TranSystems Corporation Consultants for Trinity Boulevard Water Main Extension
from Greenbelt Road to State Highway 360 (City Project No. 00352)
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Amendment No. 5 to City
Secretary Contract No. 27574 with TranSystems Corporation d/b/a TranSystems Corporation Consultants
in the amount of$35,200.00 to provide for additional engineering services, thereby increasing the contract
amount to $730,344.00,
DISCUSSION:
On March 19, 2002, (M&C C-18999) the City Council authorized the City Manager to execute an agreement
with TranSystems Corporation d/b/a TranSystems Corporation Consultants, in the amount of $379,195.00
for Trinity Boulevard Water Main Extension from Greenbelt Road to State Highway 360. The agreement
provided for the design of a 36-inch water main to ultimately provide additional water supply to the
Centerport Area and surrounding areas. The agreement was subsequently revised by four previous
amendments totaling $315,949.00 as follows:
• Amendment No. 1 (M&C C-19500, March 4, 2003) in the amount of$51,600.00, provided for
alternate alignment studies because the originally selected alignment was determined to be in
direct conflict with several utilities whose existence were unknown until after design of the project
was underway.
• Amendment No. 2 (administratively approved by the City Manager on November 17, 2005) in
the amount of$24,820.00, provided for additional design survey on the project and the preparation
of a permanent easement.
• Amendment No. 3 (M&C C-21414, April 15, 2006) in the amount of$145,324.00, provided
for the design of additional water lines to be connected to the 36-inch main.
• Amendment No. 4 (M&C C-21994, March 6, 2007) in the amount of$94,205.00, provided
for the design of a 16-inch water main on Tarrant Main Street to an existing water main and the
project 36-inch water main.
Amendment No. 5 will provide the necessary engineering, geotechnical and survey services for the
realignment of the project water main across the DFW Regional Airport Board property located at the
southwest quadrant of SH360 and Trinity Boulevard. Subsequent to approving the original alignment, the
property owner requested that the water main be located elsewhere on the site in order to accommodate
http://www.cfwnet.org/council_pa.cket/Reports/mc_print.asp 9/12/200
Page 2 of
the latest development plans for the property. The amendment will also allow for the design of a new
metering station to measure the water supply to the City of Grand Prairie.
TranSystems Corporation d/b/a TranSystems Corporation Consultants proposes to provide the necessary
additional engineering services for a lump sum fee of$35,200.00. Staff considers this amount to be fair and
reasonable.
In addition to the amendment amount, $19,161 is required by the Department of Engineering for project
management, design survey and real property negotiations.
The project is located in COUNCIL DISTRICT 5, Mapsco 54W, Z, 55S, T, U, V, W, 56N, P, S, T and 68 A,
E.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current capital budgets, as appropriated, of the
Water Capital Projects Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
P264 531200 60514003523 $22,792.00
P264 531200 605140035233 $9,768.00
P264 531200 605140035251 $2,640.00
Submitted for City Manager's Office by: Marc A. Ott (8476)
Originating Department Head: A. Douglas Rademaker (6157)
Additional Information Contact: Rakesh Chaubey (6051)
http://www.cfwnet.org/council_packet/Reports/mc_print.asp 9/12/200
TranSystems
® Sysre���s Bank of America Building
500 West 7 Street
Suite 1100
Fort Worth,TX 76102
Tel 917 339 8950
Fax 817 336 2247
www.transystems.com
AMENDMENT NO. 5
SUMMARY OF DESIGN FEE
June 19,2007
Rakesh Chaubey, P.E.
Department of Engineering
City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102-6311
RE: Amendment No. 5
Trinity Boulevard Water Main Extension
Contract 1 DOE 3600 and 5191
Original Wailer Project No. PI61-060161141050
Unit 4 DOE No.5509
Dear Mr. Chaubey,
We appreciate the opportunity to present this proposal for your consideration. Per the request of the Water
Department,this amendment revises the previously approved 36"water main design plans and contract
documents. Specifically,this amendment includes the provision of a geotechnical investigation along the
east side of the existing Southern Office Supply(SOS) property to determine acceptable trench and
earthwork grading operations in the proximity of the existing retaining wall that runs along the property limit.
This work is to be performed in support of the re-alignment of the proposed water line across the DFW
Regional Airport Board property that is situated at the southwest quadrant of the intersection of SH 360 and
Trinity Boulevard. The realignment has been required by the Airport Board to minimize interference with
future development of the property. In addition to the geotechnical study,additional survey and engineering
time is required for the design of the revised alignment.
Additionally,with regard to the proposed Grand Prairie metering station,we propose to contract directly with
McCreary&Associates, Inc.for the provision of electrical engineering services associated with the electrical
components and controls. These services will include the provision of a signal path study and strength test
in accordance with City of Fort Worth requirements.
The additional costs for the surveying,geotechnical study,electrical and control design,and water main
plan/profile re-design are summarized as follows:
Systems
Topographic Survey(East side of SOS property and south of Trinity Blvd.) $ 2,640.00
Geotechnical Investigation(CMJ Engineering) $ 5,900.00
Metering Station Electrical and Control Design(McCreary&Associates) $ 14,500.00
Plan and Profile Design Revision(ANA) $ 9,200.00
Sub-consultant Management(10%) 2,960.00
Total Additional Costs: $ 35,200.00
LUMP SUM TOTAL
Original Contract Fee: $379,195.00
Amendment No. 1: $ 51,600.00
Amendment No. 2: $ 24,800.00
Amendment No.3: $145,324.00
Amendment No.4: $ 94,205.00
Amendment No.5: 35 200.00
TOTAL CONTRACT $730,324.00
The above work effort will be accomplished for the total lump sum fee of$35,200.00. This amount includes
26%being provided to our DBE sub consultant. Please contact me should you require any additional
information.
Sincerely,
TranSystems Corporation Consultants
raig P.Schellbach,P.E.
Project Manager
Attachments