HomeMy WebLinkAboutContract 50172-AR1 CFW Construction Allowance Request Approval CAAppr-01 Page 2 of 3
RECEIVED CITY SECRETARY
JUL � � 2019 conTRAcr No. 501 7 �I
C CRART WORTH„ Cityof Fort Worth
C'IYSECRETARY Construction Allowance Request Approval _
(Construction Allowance Breakdown Available in Links)
For Construction Allowance Submittal No.: 1
Construction Allowance Request Approval No.:ECAAppr-01
Date Started: 2� 018-10-22 Date Due: i, 018-12-11
City Sec. No.: ,50172
Project Name: 2014 CIP Year 3 - Contract 7
:c02965 'DOE Numbers:
Project Numbers:
Project !This- is a combined paving, water/sanitary sewer main,
Description: stormwater and box culvert improvements project in Eastern
Hills and Lakewood addition neighborhoods.
Project/Contract
Compliance Mary Hanna City Inspector: Christopher Bell
Manager: __.. __ __-_. --
Contractor: tCircle C Construction Company
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
TPW $ 63,612.00 `34014-0200431-5740010-c02695-ct 0
_ Stormwater ;$ 31,165.00 :52002-0200431-5740010-c02695-cQ 0
Total Cost:',$ 94,L7�.00 Total Requested Days:
Approval Status:
M
AL RECORDSECRETARYORTH,TX
https://projectpoint.buzzsaw.com/ bz web/Forms/ForinPrint.aspx?SiteId=51500&ProcessI... 11/7/2018
CFW Construction Allowance Request Approval CAAppr-01 Page 3 of 3
,Approved: Yes
Comments:
User: Lane Zarate
Date: 2018-10-23 7:19 PM
Approved: Yes
`.Comments:
User: Ricardo Matute
Date: 2018-10-23 2:25 PM
Approved: Yes
Comments:
User: Signing for TPW Director Role Approvals
Date: 2018-10-23 3:47 PM
Approved: Yes
Comments:
User: Doug Black
Date: 2018-10-25 5:19 PM
Approved: Yes
Comments:
User: Susan Alanis
Date: 2018-10-27 8:16 AM
Action Required: Please review and approve _J
OFFICIAL RECORD
CITY SECRETARY
ET WORTH,Tat
https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?SiteId=515OO&ProcessI... 11/7/2018
FORT WORTH, City of Fort Worth
-- 111 - Construction Allowance Request Breakdown
Construction CA# Date 10/11/2018 City Sec# 1 50172 —�
Client Project#(s)l c02695
FAC#(s) 59601/59607/34014/52002-0600430/0700430/0200431-5740010-c02695-c01783/c02483
Project Name 2014 CIP Year 3 Contract 7- This is a combined paving,water/sanitary sewer main,stormwater and box culvert
Description improvements project in Eastern Hills and Lakewood addition neighborhoods.
Contractor Circle C Construction CompanyI City Inspector I Christopher Bell
Funding TPW Stormwater Water&Sewer Contract Time
Allocation Account Totals CD
Original Contract Amount $1,713,542.00 $1,057,636.00 $2,700,863.50 $5,472,041.50 450
Extras to Date $301,946.00 $79,045.50 $380,991.50 120
Credits to Date
Current Contract Amount $2,015,488.00 $1,136,681.50 $2,700,863.50 $5,853,033.00 570
Amount of Proposed Allocation $63,612.00 $31,165.00 $0.00 $94,777.00 0
Original Allowance Available for Allocation $100,000.00 $80,000.00 $200,000.00 $380,000.00
Allowance Funds Previously Allocated
Remaining Funds Available for this Allocation $100,000.00 $80,000.00 $200,000.00 $380,000.00
IN ACCORDANCE WITH THIS CONSTRUCTION ALLOWANCE REQUEST,THE CONTRACTOR SHALL:Furnish all labor and material
as per attached proposed Construction Allowance Request(with attachments)to the Construction Allowance Request:This construction
allowance add Metal Beam Gurd Fence end treatments to the guardrail in front of the culverts in Meadowbrook Drive.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and satisfaction and
represents payment in full for all costs arising out of,or incidental to,the above Construction Allowance Request.Contract Time will be adjusted on the
basis of the time shown on this Construction Allowance Request by a later Change Order,if necessary.
FORT WORTH,a City of Fort Worth
Construction Allowance Request Breakdown
Construction FOA# Date 10/11/2018 City Sec# 50172
Client Project#(s)l c02695
FAC#(s)1 59601/59607/34014/52002-0600430/0700430/0200431-5740010-c02695-001783/c02483
Project Namel 2014 CIP Year 3 Contract 7- This is a combined paving,water/sanitary sewer main,stormwater and box culvert improvements project in
Desciptionl Eastern Hills and Lakewood addition neighborhoods.
Contractorl Circle C Construction Company City Inspector Christopher Bell
ADDITIONS
ITEM DESGKIII[ION ep y Unit ni s I o a
rot 7 3217.2103 REFL Raised Marker TY II-A- PW A
rotSingle Guardail TerminalM w teelPost) W A 5, 5.
Unit T-47 Metal Beam Guard Fence ownstraem Anchor Terminal DATwtwoodPost) 5 .
Unit - Concrete Sidewalk Stormwater
rid - Concrete curb and gutter tormwater
rot - emove sidewalk tormwater
nit - op soil Tto-nwater Y 5.
nitConcrete Pavement Repair tormwater Y 5.
rot Unclassified Excavation tormwater 5. Y 5.
Unit - 5 Borrow(FlexibleBase) tormwater 40.00 CY
TPW 63,612.00
Stormwater $31,165.00
Water&Sewer $0.00
ub otal Additions $94,///.UU
FORT WORTH- City of Fort Worth
Construction Allowance Request Breakdown
Construction FOA# 1 Date 10/11/2018 City Sec# 50172
Client Project#(s) c02695
FAC#(s) 59601159607134014/52002-06004301070043010200431-5740010-c02695-cOl7831c02483
Project Namel 2014 CIP Year 3 Contract 7- This is a combined paving,water/sanitary sewer main,stormwater and box culvert improvements project in
Descdpdonj Eastern Hills and Lakewood addition neighborhoods,
Contractorl Circle C Construction Company City Inspector Christopher Bell
GUNSTRUCTIUN ALLOWANCE ITEMS TU BE REDUCED
ep y unit UnitCost Total
-77777 Construction Allowance(Paving) W L
nit Construction Allowance tormwater) tormwater L
TPW $63,612.00
Stormwater $31,165.00
Water&Sewer $0.00
Sub Total Deletions
M/WBE Breakdown for this Construction Allowance Request
MWBE Sub Type of Service Amount for this FOA
Total $0.00
Previous Construction Allowance Requests
CO# DATE AMOUNT
Total $0.00