HomeMy WebLinkAboutContract 50172-AR2 CFW Construction Allowance Request Approval CAAppr-02 Page 2 of 3
CITY SECRETARY
Vf, CONTRACT NO. 5 o 17d-A lZa
WORTHcity of Fort Worth
crn-o�Fa 201 QRT Construction Allowance Request Approval
crTySF�q Ry q PP
Fr TH (Construction Allowance Breakdown Available in Links)
For Construction Allowance Submittal No.: 12 1
Construction Allowance Request Approval No.: ICAAppr-02
Date Started: 111/7/2018 Date Due: 12/27/2018
City Sec. No.: 50172
Project Name:12014 CIP Year 3 — Contract 7
Project Numbers:1c02695 DOE Numbers:
Project 'This is a combined paving, water/sanitary sewer main, stormwater and
Description: box culvert improvements project in Eastern Hills and Lakewood addition
I neighborhoods.
Project/Contract
Compliance Manager: ., !a _Han_n_a City Inspector: lChristopher Bell
Contractor:JCircle C Construction Company
COST AND DAYS SUMMARY:
Department: Cost($) Fund Account Center: Requested Days:
IStormwater � $ 81$ 064.00 i52002-0200431-5740010-c02& 0
F- _ — ---
F--
Total:I$ 18,064.000 Total Requested Days:10-.
Approval Status:
a
RUAL RECORD
UTY SECRETARY
LT. WORTH,TX
https://projectpoint.buzzsaw.com/ bz web/Forms/FomiPrint.aspx?Siteld=51500&Proces... 11/27/2018
CFW Construction Allowance Request Approval CAAppr-02 Page 3 of 3
Approved: Yes
Comments:
User: Lane Zarate
Date: 2018-11-07 10:39 PM
Approved: Yes
Comments:
User: Ricardo Matute
Date: 2018-11-07 5:08 PM
Approved: Yes
Comments:
User: Signing for TPW Director Role Approvals
Date: 2018-11-08 9:02 AM
Approved: Yes
Comments:
User: Doug Black
Date: 2018-11-08 9:14 PM
Approved: Yes
Comments:
User: Susan Alanis
Date: 2018-11-11 9:25 PM
Action Required: Please review and approve
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH,TX
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Site1d=51500&Proces... 11/27/2018
FORT WORTH City of Fort Worth
Construction Allowance Request Breakdown
Construction CA# 0 Date 11/7/2018 City Sec# 1 50172
Client Project#(s)l c02695
FAC#(s) 59601/59607/34014/52002-0600430/0700430/0200431-5740010-c02695-c01783/c02483/c02883
Project Name 2014 CIP Year 3 Contract 7- This is a combined paving,water/sanitary sewer main,stormwater and box culvert
Description improvements project in Eastern Hills and Lakewood addition neighborhoods.
ContractorF Circle C Construction CompanyI City Inspector I Christopher Bell
Funding TPW Stormwater Water&Sewer Contract Time
Allocation Account Totals CD
Original Contract Amount $1,713,542.00 $1,057,636.00 $2,700,863.50 $5,472,041.50 450
Extras to Date $301,946.00 $79,045.50 $380,991.50 120
Credits to Date
Current Contract Amount $2,015,488.00 $1,136,681.50 $2,700,863.50 $5,853,033.00 570
Amount of Proposed Allocation $0.00 $18,064.00 $0.00 $18,064.00 0
Original Allowance Available for Allocation $100,000.00 $80,000.00 $200,000.00 $380,000.00
Allowance Funds Previously Allocated $63,612.00 $31,165.00 $94,777.00 _
Remaining Funds Available for this Allocation $36,388.00 $48,835.00 $200,000.00 $285,223.00
IN ACCORDANCE WITH THIS CONSTRUCTION ALLOWANCE REQUEST,THE CONTRACTOR SHALL:Furnish all labor and material
as per attached proposed Construction Allowance Request(with attachments)to the Construction Allowance Request:This construction
allowance for some additional concrete work on Jacqueline Rd as pasrt of Stormwater Eastern Hills Phase 3.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and satisfaction and
represents payment in full for all costs arising out of,or incidental to,the above Construction Allowance Request.Contract Time will be adjusted on the
basis of the time shown on this Construction Allowance Request by a later Change Order,if necessary.
FORT WORTH City of Fort Worth
Construction Allowance Request Breakdown
Construction FOA# = I Date 11/7/2018 City Sec# 50172
Client Project#(s) c02695
FAC#(s) 59601/59607/34014/52002-0600430/0700430/0200431-5740010-c02695-c01783/c02483/c02883
Project Namel 2014 CIP Year 3 Contract 7-This is a combined paving,water/sanitary sewer main,stormwater and box culvert improvements project in
Descdptionl Eastern Hills and Lakewood addition neighborhoods.
Contractorl Circle C Construction Company City Inspector r Christopher Bell
ADDITION5
Dept/FAG y Unit Units o a
m - Concrete Sidewalk 7 ormwa er
mt - Remove sidewalk tormwater
7n1t - Concrete Pavement Repair tormwater 75. 5.
Nit - 01— assi ied Excavation tormwater 7. 5.
nd - Borrow(FlexibleBase) tormwater
UnitConcrete Driveway Stormwater
Unit 3-37 Remove Concrete Driveway Stormwater
TPW 0.00
Stormwater $18,064.00
Water&Sewer $0.00
Sub Total Additions
Change Order Additions Page 2 of 4
FORT WORTH- City of Fort Worth
Construction Allowance Request Breakdown
Construction FOA# 2 Date 11(712018 City Sec# 50172
Client Project#(s) c02695
FAC#(s) 59601/59607134014/52002-06004301070043010200431-5740010-c02695-c017831c024831c02883
Project Namel 2014 CIP Year 3 Contract 7- This is a combined paving,waterlsanitary sewer main,stormwater and box culvert improvements project in
Descriptionj Eastern Hills and Lakewood addition neighborhoods,
Contractor Circle C Construction Company City Inspector Christopher Bell
CONSTRUCTION ALLOWANCE ITEMS TO BE REDUCED
ep yUnit Unit Cost o a
n -- Construction owance ormwa er ormwa er
TPW $0.00
Stormwater $18,064.00
Water&Sewer $0.00
Sub TotalDeletions
Change Order Deletions Page 3 of 4
MWWBE Breakdown for this Construction Allowance Request
MWBE Sub Type of Service Amount for this FOA
Total $0.00
Previous Construction Allowance Requests
co# DATE AMOUNT
Total $0.00