HomeMy WebLinkAboutOrdinance 23582-03-2019 ORDINANCE NO. 23582-03-2019
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER AND SEWER CAPITAL PROJECTS FUND, FROM AVAILABLE FUNDS IN THE
AMOUNT OF $437,985.00, FOR THE PURPOSE OF FUNDING THE BIG FOSSIL CREEK
PARALLEL RELIEF SANITARY SEWER M-402A, PHASE 1 AND HALTOM CITY METER
STATION AND SEWER OUTFALL, PHASE 3 PROJECT; PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND
PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2018-2019 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of$437,985.00, from available funds, for the Big Fossil Creek
Parallel Relief Sanitary Sewer M-402A, Phase 1 and Haltom City Meter Station and Sewer Outfall, Phase 3
Project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 23392-09-2018 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
Douglas W Black Mary J. Kay
Sr.Assistant City Attorney City Secre
OpIr
ADOPTED AND EFFECTIVE: March 5, 2019 �j 2
�XPAS
MAYOR AND COUNCIL COMMUNICATION MAP
60BFOSSILPlANDP3CO2 - RENDA
0 _ "`%� ♦� ���'�ff i'l ' R � � {
PHASE 3
# F -
ry:
T 1-
PHASla 7
E 1
co
F
ELLIOTT REEDER RD
vilk14
AK
FORTWORTH
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 315/2019 -Ordinance No. 23582-03-2019
DATE: Tuesday, March 5, 2019 REFERENCE NO.: **C-29050
LOG NAME: 60BFOSSILP1ANDP3CO2-RENDA
SUBJECT:
Authorize Execution of Change Order No. 2 in the Amount of$437,985.00, and the Addition of 325
Calendar Days to City Secretary Contract No. 48098 with Oscar Renda Contracting, Inc., for a Revised
Contract Amount of$8,483,807.45, for Big Fossil Creek Parallel Relief Sanitary Sewer M-402A, Phase 1
and Haltom City Meter Station and Sewer Outfall, Phase 3 and Adopt Appropriation Ordinance (COUNCIL
DISTRICT 4)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water and Sewer Capital Projects Fund in the amount of$437,985.00 from available funds; and
2. Authorize execution of a Change Order No. 2 to City Secretary Contract No. 48098 with Oscar
Renda Contracting, Inc., in the amount of$437,985.00 and the addition of 325 calendar days for Big
Fossil Creek Parallel Relief Sanitary Sewer M-402A, Phase 1 and Haltom City Meter Station and
Sewer Outfall, Phase 3. (City Project No. CO1303)
DISCUSSION:
On June 28, 2016, Mayor and Council Communication (M&C C-27823), the City Council authorized a
contract with Oscar Renda Contracting, Inc., (City Secretary Contract No. 48098) in the amount of
$7,973,721.00 for construction of Big Fossil Creek Parallel Relief Sanitary Sewer M-402A, Phase 1 and
Haltom City Meter Station and Sewer Outfall Phase 3. The contract was subsequently revised by Change
Order No. 1 in the amount of$72,101.45 authorized administratively on December 10, 2018.
Change Order No. 2 will provide for the construction of a larger sewer junction structure to provide for the
connection of incoming large diameter sewer main to the outgoing sewer main and also allow for future
maintenance.
Construction is expected to be completed by May 2019.
M/WBE OFFICE — Oscar Renda Contracting, Inc., is in compliance with the City's BDE Ordinance by
committing to an additional two percent MBE participation on this change order.
The project is located in COUNCIL DISTRICT 4.
FISCAL INFORMATION/ CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendation and adoption of the
attached appropriation ordinance, funds will be available in the current capital budget, as appropriated, of
Logname: 60BF0SSILPIANDP3CO2-RENDA Paize I of 2
the Water and Sewer Capital Projects Fund. The Fiscal Year 2019 Water Operating Budget includes
appropriations of$35,856,873.00 for the purpose of providing Pay-As-You-Go funding for Sewer Capital
Projects. After this transfer for Fiscal Year 2019, the balance will be $25,161,727.00.
Appropriations as depicted below for the Big Fossil Creek Parallel Relief Sanitary Sewer Main 402A:
FUND FAppropriations
gdditional Project Total*
Appropriations e_t Total*
Water State Revolving Loan - �$8,950,000.00 $0.00 $8,950,000.00
Fund 56006 _
Clean Water SRF - Fund F$963,644.00 $0.00 $963,644.00
59602
Sewer Capital Legacy - Fund '$3,306,254.00 $0.00 $3,306,254.00
59607 k
Water Capital Projects - Fund
56002
$0.00 $437,985.00 $437,985.00
Project Total �$13,219,898.00 437,985.00 _._____-$ 31 657,883.001
* Numbers rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO _
Fun yJ Budget I Reference # moun
ID ID Year (Chartfield 2)
FROM
J-D—e, ccoun Project Program ctivity Budget Reference # moun
ID ____I ID Year (Chartfield 2
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Chris Harder (5020)
Additional Information Contact: Walter Norwood (5026)
Logname: 60BFOSSILPIANDP3CO2-RENDA Paize 2 of 2