WHEREAS, the City of Fort Worth (City) and Stream Water Group, Inc. ,
(Engineer) made and entered into City Secretary Contract No. 34090, (the
Contract) which was authorized by the City Council by M&C C-21721 on the 26th
day of September 2006; and
WHEREAS, the Contract involves engineering services for the following
project:
Engineering Design Services: Street Reconstruction, Water and Sewer Replacement
on NE 37th Street (Grover Ave to Deen Rd) , Decatur Avenue (Terminal Rd to
Altamont Dr and Altamont Dr to Elaine P1) , Hardy Street (Elaine P1 to Mineola
Ave) and Selene Street (Decatur Ave to Weber St) , 2004 CIP Contract Year 4 & 5,
Contract 41, Project No. 00441; DOE No. 5396
WHEREAS, it has become necessary to execute Amendment No. 3 to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their duly
authorized representatives, enter into the following agreement which amends the
Contract:
1.
Article I of the Contract is amended to include the additional engineering
services specified in a proposal letter dated September 18, 2007, a copy of
which is attached hereto and incorporated herein. The cost to City for the
additional design services to be performed by Engineer total $7,105.00.
2.
Article II of the Contract is amended to provide for an increase in the
maximum fee to be paid to Engineer for all work and services performed upde _ the
Contract, as amended, so that the total fee paid by the City .for all work- and
services shall not exceed the sum of $222,384. 61.
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the day of 2007, in Fort Worth,
Tarrant County, Texas.
ATTEST:
)EL NO M&C REQUIRED
Marty Hendri
City Secretary
APPROVAL RECOMMENDED: APPROVED:
A. Douglas Rademaker, P.E. Marc A. Ott
Director, Department of ' Assistant City Manager
Engineering
Stream Water GrouA, Inc.
ENGINEER
By:
Name: Shamsul Arefin, P.E.
President
6737 Brentwood Stair Rd, Suite 230
Fort Worth, Texas 76112
APPROVED7AST, FORM AND LEGALITY:
Assistant'
ssistan Ci A orney
0 0
September 18,2007
Mr.Gopal Sahu,P.E.
Project Manager
Department of Engineering
1000 Throckmorton St.;Fort Worth
TX 76102
Phone:(817)392-7949
RE: Contract Amendment No.3
Engineering Design Services: Street reconstruction,Water and Sanitary Sewer Replacement on Selene St
(Decatur Rd to Weber St),N.E. 37th St(Grover St to Den Rd),Hardy St(Elaine PI to Mineola Ave),and
Decatur Ave(Terminal Rd to Elaine P1).2004 CIP Neighborhood Street Projects Year 4&5,Contract 41,
Project No.00441
Dear Mr.Sahu:
The following is a summary of additional work requested for Amendment No. 3 to the above referenced project,per
design meetings with City of Fort Worth officials.
The proposed amendment includes Model update for Decatur Rd Box Culvert location,additional survey,and
preparation of easement document project limit as shown in Exhibit 1.
Easement Document Preparation(9 ea)(by Subconsultant) $4,000.00
Additional Survey along Creek S 600.00
Model update and coordination for Decatur Rd Box Culvert S2,705.00
10%A WBE $ 400.00
Total Additional Services S7,705.00
Amendment No.3 TOTAL LUMP SUM $7,705.00
The current status of the contract between Stream Water Group,Inc and City of Fort Worth for the Street
Reconstruction,Water and Sewer Replacement,2004 CIP Contract Year 4&5,Contract 41 is as follows:
Original Contract Amount= $ 164,947.00
Amendment No. 1 Amount= $ 14,201.00
Amendment No.2 Amount= $ 35,531.61
Amendment No.3 Amount= $ 7,105.00
Total Contract Amount including Amendments= $222,384.61
Please process Amendment No. 3,to the Street Reconstruction,Water and Sewer Replacement,2004 CIP Contract
Year 4&5,Contract 41 in the amount of$7,705.00.
If you require any additional information or have any questions regarding this matter,please give me a call at 817-446-
4171.We appreciate the opportunity to provide Engineering design services for the City of Fort Worth.
Sincerely,
Stream Water roue,Inc.
Shamsul Are m,P.E.
President
Copy:File,Dena Johnson,P.E.(City of Fort Worth)
b? Rrentmood SUIH Rd • Suite 230 1�ort !X -AI i2 Phouc_ R 1 4 r; ;i 1 • Pcis: ( 4.13;
4iGtU'. S1Crct tl]li`ftL�lL rUlf h.i:641�
r v
9 I
"4J,
50 =� �"�- 1 �? 15R 14R 113R ;12R110 �U �Lo
28 16R 4;7
,/��
27 ��, i" 2R I j.� /9 / 12 `fl4g
10
�' � � T
2 6 1. i .� ! tC
27 ��� � ;1 3
;
.lF 5 8 8R I ! L-
25R \�� �� - jam / 6 �� `^�/� 14R
I j 5
/ 23 -. / 15R -- --- i
/ r �� 6R I
1 ;{
/ 22
T o' sr /' 5
13 / 2 0 / Cb
�T� / 14 ^ ` O,.Q .�` / % PROPOSED -
O 19 3-1 OW BOX CULVERT
47 22
21 r19
17
1
0 ! 19
%� .\ 18 16!' -jam.• �� ~ v� / /j /' / s��� !
44
17 / 16 \ ,/ \ 2 / 3 \•/, /1513
41
13
14
\. PROPOSED GABION /
! O 15 60 20/' '�%;� \ ' CHANNEL IMPROVEMENTS
•� ,
19
18
l 3 4 \ 'V`15 '14
3 I Imo / 5 ! !{ 12 /
18R /� .� ' 6 / 7
_ � _ ! N 8 ;
2A _ I 17 ! i 9 1 10 � !
I' 19R 16 /` .` 1 i
cue I 20R �,I / 15 ------
14B -
-e-
N FORT WORTH CITY OF FORT WORTH, TEXAS Exhibit I
MYNA. 20U4 CIP NEIGHBORHOOD STREET PROJECTS
aw&41e IS0 YEAR 4&5,CITY PROJECT NO.00441 l STREAM WATER GROUP,INC.
` STREET RECONSTRUCTION,WATERAND J M'R'�RS'RWAYoRs
SANITARYSEWERREPLACEMENT,CONTRACT41 ( E-M "���
n.. .wen