HomeMy WebLinkAboutContract 37043COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS § City Secretary
a
COUNTY OF TARRANT § Contract No.10
WHEREAS, Hillwood Alliance Services, LLC., hereinafter called "Developer",
desires to make certain improvements to Horizon Drive, an addition to the City of Fort
Worth, Texas; and
WHEREAS, the said Developer has requested the City of Fort Worth, a municipal
corporation of Tarrant, Denton and Wise Counties, Texas, hereinafter called "City", to do
certain work in connection with said improvements.
NOW, THEREFORE, KNOW ALL BY THESE PRESENTS:
For and in consideration of the covenants and conditions contained herein, the City and
the Developer do hereby agree as follows:
I. General Requirements
Horizon Dr.
2008011
02/13/2008
A. The Policy for the Installation of Community Facilities ("Policy")
dated March 2001, approved by the City Council of the City of Fort
Worth and subsequently amended, is hereby incorporated into this
Community Facilities Agreement as if copied herein verbatim.
Developer agrees to comply with all provisions of said Policy in the
performance of its duties and obligations hereunder.
B. The requirements of the Policy shall govern this Community Facilities
Agreement, provided, however, that any conflict between the terms of
this Community Facilities Agreement and the Policy shall be resolved
in favor of this Agreement.
C. Developer shall provide financial security in conformance with
paragraph 6, Section II, of the Policy.
D. Developer acknowledges that there shall be no reduction in the amount
of financial security prior to project completion and acceptance by the
City.
E. The Developer shall award all contracts for the construction of
community facilities in accordance with Section II, paragraph 7
Policy.
1
M;W'1;,c L
F. The contracts for the construction of the public infrastructure shall be
administered in conformance with paragraph 8, Section II, of the
Policy.
G. The Developer further covenants and agrees to, and by these presents
does hereby, fully indemnify, hold harmless and defend the City, its
officers, agents and employees from all suits, actions or claims of any
character, whether real or asserted, brought for or on account of any
injuries or damages sustained by any persons (including death) or to
any property, resulting from or in connection with the construction,
design, performance or completion of any work to be performed by
said Developer, his contractors, subcontractors, officers, agents or
employees, or in consequence of any failure to properly safeguard the
work, or on account of any act, intentional or otherwise, neglect or
misconduct of said DEVELOPER, his contractors, sub -contractors,
officers, agents or employees, whether or not such injuries, death or
damages are caused, in whole or in part, by the alleged nea _, ence of
the City of Fort Worth, its officers, servants, or employees.
H. Developer shall install or adjust all of the required utilities to serve the
development or to construct the improvements required herein.
I. In the event that City participation exceeds $25,000, Developer agrees
that no street construction or storm drainage will begin prior to City
Council approval of this Community Facilities Agreement. (Article
104,100, Ordinance 7234).
J. Developer agrees that no lot shall be occupied under a certificate of
occupancy until the improvements required herein have been
constructed (Article 1 U49100, Ordinance 7234).
K. Developer hereby releases and agrees to indemnify and hold the City
harmless for any inadequacies in the preliminary plans, speccations
and cost estimates supplied by the Developer for this contract.
L. Developer agrees to provide, at its expense, all necessary rights of way
and easements across property owned by Developer required to
Horizon Dr.
2008011
02/13/2008
3
construct current and future improvements provided for in this
agreement.
M. Developer agrees to construct proposed improvements as shown on the
exhibits attached hereto. The following exhibits are made a pant
hereof: Water (A)None; Sewer (A4) None; Paving (B) None Storm
Drain (B-1) Attached; Street Lights and Signs (C) None..
N. City shall not be responsible for any costs that may be incurred by
Developer in the relocation of any utilities that are or may be in
conflict with any of the community facilities to be installed hereunder.
II. Street and Storm Drain Facilities
A. The Developers) agree to install or to cause to have installed, the street,
storm drainage, street lighting, street name sign and other community
facilities improvements shown as "current improvements" on the attached
Exhibit B l .
B. As shown below in the "Summary of Cost for Street and Storm Drain
Facilities", the Developer shall fund its share of "current improvements"
and shall pay to the City for its share of the cost of street, storm drainage,
street lighting, street name signs as shown on the attached Exhibit B 1. The
estimated total cost of current improvements and related support services
specified in this agreement, including design, construction and inspection
is estimated to $ 5,198.24
Horizon Dr. 3
2008011
02/13/2008
SUMMARY OF
COST
Horizon Drive
Item
Developer
Cost
City Cost
Total Cost
A. Construction
$ -
1. Streets
$ -
2. Storm Drainage
$4,904.00
47904000
3. Street Lights
$ -
4. Street Name Signs
$
B. Engineering Design
$ -
C. Construction Engineering
and Management by DOE
4%
$
196.16
$
196.16
D. Materials Testing by DOE
2%
$
98.08 1
1
$
98.08
TOTALS
5,198.24
$ -
51198024
Notes:
l .All Preliminary Plats filed after July 2000 will require sidewalks on all streets.
2. Developer's column for Item C represents four percent (4%) cost for construction
inspection fees. The City will pay additional inspection fee over 4%.
3. City not preparing plans and specifications.
4. Developer's column for Item D represents two percent (2%) of paving and storm drain
costs for materials testing.
Horizon Dr. 4
2008011
02/13/2008
IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be
executed in triplicate in its name and on its behalf by its Assistant City Manager, attested by
its City Secretary, with the corporate seal of the City affixed, and said Developer has
executed this instrument in triplicate, at Fort Worth, Texas this the day of l
2008.
Approval Recommended:
ATTEST:
�1 Mart Hendrix
City Secretary
ATTEST:
Corporate Secretary
Horizon Dr.
2008011
OZ/13/2008
Transportation and Public Works
Cit of Fort Worth
Atw
Fernando Costa
Assistant City Manager
DEVELOPER
HILLWOOD ALLIANCE SERVICES, LLC.,
a Texas limited liability company
By: Hillwood Development Company, LLC,
a Texas limited liability company,
its managing member
STATE OF TEXAS §
COUNTY OF TARRANT §
This instrument was acknowledged before me on �P�uCtx� aa, 200E, by
L .f ssetL Lc ,,,+< Q In , S U .y � e_ V�res C�. of Hillwood Development
Company, LL , a Texas limited liability company, on behalf of said limited liability
company, in its capacity as managing member of Hillwood Alliance Services, LLC, a
Texas limited liability company, on behalf of said limited liability company.
Notary Public, State of Texas
o,�pPY PU�o K R KILLMAN
aOl� Notary Public
* y State of Texas
N�grEOFtti�Q MY Comm Expires 04 2. &2�011
Horizon Dr.
2008011
02/13/2008
SH 114
4
^^
� Jy
y h�
AIRW Y
EAGLE HENRIETTA
CREEK
INTERMODAL
R F incyf SN l�o IL
WESTPORT �c WESTPORT — KNOX
y W Ex
W
O C7
PROJECT a o
LOCATION ay Mr G►LEAD
09
Lo
2F,
a
FM 1709
Gay,
Gs,
28,
NOT TO SCALE
LOCATION MAP
HORIZON DRIVE
DGN=q�\Job\ 015000020\EST\CFA\ HC2CFA.DGN
darter �� Burgess
CAmRT�R �6�9URGE55, INC.
F � W 71f 76102
PROJECT NO* 015000* 020. 001* 0630
PAGE 1 OF 2
Lot,
SCALEF t" = 40'
30`
R C P
W ; ADL DEVELOPMENT, L . P. , FORMERLY KNOWN AS
I I I HILLWOOD12470, LTD., FORMERLY KNOWN AS
i
ALLIANCE AIRPORT, LTD.
VOL.9378,PG.2033
Q
C,
,
1
1
I
f 1 � • Q �
1' Ion (� Q
N I
2401DR.
-
RCP-6sR
_ �_u
srCP
cfw
SD
7211RC5R�
•HERITAGE C MOV II. L
rsc634
1,t11 WOL • F 284p C �4 0ICAT/LiV - _
e•G
- _ _ . T •
_ - - -
_y- _-
oil
-1, ---- Ft 'X '
_
;D LET
1
1
I
I
I
1 �
HERITAGE COMMON I• LTD. 1 _ —
VOL.13013•PG.342
C.R.T.C.T.
1 -
,
1 ,
1
1 _1-
1
STORM DRAIN
LEGEND EXHIBIT 'G-'
06
PROP• STORM DRAIN LINE ,1.
HORIZON DRIVE
PROP. INLET
PROP. MANHOLE -f-
PROP. HEADWALL -�
Carter Burgess
EXIST. STORM DRAIN LINE _____``_____ MMSMEEr s,INC.
FORT N'ORfH, TX 76g7
LIMITS OF PROJECT ----- 017)77seoUo
PROJECT NO. 015000. 020. 001a 0630
PAGE 2 OF 2
DGN=qI\JoD\ 015000020\EST\CFA\ NC2CFA.DGN
CFA Estimate for:
Horizon Drive
DECEMBER 27, 2007
CONSTRUCTION COST SUMMARY
FEE COST SUMMARY
STORM DRAIN SYSTEM
ITEM#
DESCRIPTION
QTY
UNIT
PRICE
AMOUNT
1
27" RCP
34
L.F.
55.00
$15870*00
2
8' Modified Drop Inlet
1
EA.
3,000.00
$31000.00
3
Trench Safety
34
L.F.
1400
$34600
SUB -TOTAL STORM DRAIN SYSTEM $45904.00
G:\JOB\015000020\EST\CFA\20071227 Horizon Drive CFA