Loading...
HomeMy WebLinkAboutContract 50906-CO2 CITY SECRETARY FORT WORTH. City of Fort Worth CONTRACT NO. 5q O O-( OOL — �- Change Order Request Breakdown ProjectNamel Wilbarger St&Miller Ave Intersection Improvements City Sec# 1 50906 Client Project#(s)j 02552 Contractorl Bean Electrical,Inc. PM Wilma Smith Inspectorl Neal Kime Change Order Submittal# U Date 51612019 Contract Time Dept. TPW Totals WD Original Contract Amount 1,135,497.95 1,1 55,497.95 128 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1,135,497.95 $1,135,497.95 128 Amount of Proposed Change Order $28,41320 $28,413.20 45 Revised Contract Amount 1,163,9 1.15 17163,911.15 173 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0,00 Additional Funding(if necessary) 1 $28,413.20 1 $28,413.20 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 2.50% MAXALLOWASLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,419,372.44 Integral sidewalk retaining wall was added along the sidewalk on the southwest corner.Topsoil and sodding was added.Fabrication plant for monotube signal structure shall be changed to a TxDOT approved fabrication facility.Time added for delay of monotube signal structure approval.Additional traffic control added to install four-way stop during signal installation. RECEIVED JUL 2 2019 CITY OF FORT WORTH CITY SECRETARY OFFICIAL RLCUkD CITY SECRETARY FT. WORTH,TX City of Fort Worth Change Order Additions Project Name Wilbarger St&Miller Ave Intersection Improvements City Sec# 50906 Client Project# 02552 Contractor Bean Electrical,Inc. PM Wilma Smith Inspector. Neal Kime Change Order Submittal# = Date 5/6/2019 AUDI I IONS unit unit Cost Total L K CODINGY L FBR IVILCH M)( RBAN)( LA ) TPW goomoococio 5-RETAINING WALL(SPECIAL) Fabrication Plant Change L BARR,SIGNSAND TRAFFIC HANDLING ADD ALT (STOP SIGNS) 7 FW- TPW $28,413.20 Sub Total Additions 413.20 Change Order Additions Page 2 of 4 Fo r��Vo Tlj city of Fort Worth T Change Order Deletions Project Name Wilbarger St&Miller Ave Intersection Improvements City Sec# 50906 Client Project# 02552 Contractor Bean Electrical,Inc. PM Wilma Smith Inspector F Neal Kim. Change Order Submittal# 0 Date 5/6I2019 DELET IDNS ty Unit Unit Cost Total TPW $0.00 Sub Total Deletions $0.00 Change Order Deletions Page 3 of 4 M/SBE Breakdown for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders Co# DATE AMOUNT 1 12/11/2018 $0.00 Total $0.00 Page 1 o: u CONSTRUCTION CONTRACT CHANGE ORDER NUMBER: $ itt�l dl 1.CONTRACTolt Been EI(Mrical,hm C+CSJ: 017206092 2:Ounpe Order Work LJnrtks:SM 1 �fo Stp 20+00 project CM 1 WM63) 3.Type of Ownp(on bder+d-vid no maarrwt tarojma* Minor (MeOdMha) H111111"Mr. 287 t Dowrilsa llte donpe and tlta neon tar dta change adw Wlta necouary,include cou"Ir. Tarrant exceptions to d*agreement FTW District A snvW retaining war was added long sidewalk in soul twiest comer.Sod and topsail was added.Fa6ricatlon pant for ntaatotube signal etnxan*0 be dunged..Time added for delay of awrn ignet a s structure aWmAd.Time will be � 50906 w Wanded on the p-gett to alknv for(abricatlon of the rnwWajbe sigrtal structure which a 4spectad to take 26-28 weeks. 5 New or tawhed pan**x* )are attad>ed eard rtU berecb 4 S.29.41.51 Ead►sigrtitory 1te�►war'rarrts tttet eeeh tree the atrraoett)r m ttsreart+a tltls tdtertpa tlydar. sy low"ttrb mesa orb.the cm mow swe"to*on&100 0 The tONWA*q'Otmoslim.rarer be provided dAm ra v0tJ0nai campWWtbn due to RM and as odnx eapartyas .a®tterrr dam,rat arm.ovwhaW and preAt or lond carp wits Time Ext.# Days added an 0*C.O.• 16 n a resort or"Orange£ oaurapa awes dux fats aw""We b made on actor rrc a and the C4N&Kt Exa0am atmuM be rwtad ar tr,. abom Amt added by rtle toga order: S►413.M Prot TxDQT use only, THE T Date Shl 1 04"p"CONOW Dl+ ArtaaurttildpatltW TypedlPrinted Name E.Bart ....,... WPM T"vdIftnied TaaPresident Namelfitle FtECOMMENDED FOR EXECUTX) : // ttivt�/Zcuvt to+U,„q A b 7 2-3 /4 tltetTl Dat � Ci ou�xr a�tow�. . =- 7 (+lam iris m.__ Date fTi jA PR f7 [ REQUEST APPROVAL elTitiMe e Date APM OVED ❑REgIrrST APPRDVAL David SO*WPubk Worsts Turn Leader -5/7 )" .0 t r c n, rt�fT��tebate Nam l Etginae�s Seat . CI n. ED i ° o � e L ®RD ARY TX ps://docs.b360.autodesk.com/projects/ae85894e-Oa4f-4b99-a167-ed3e0428a7f9/reviews/a2b 175a9-6567-4a79-... 7/12/20 O O O O O O N O O 0 N O O p w O O O m O V M z CD M ',I- M CD CD Q z = V O M N o ` O ❑X D = N N N N O cn N J OZ LLJ T O ❑ O V O O O O O O CD >j O O O N O O C O O O M O V H Cl) V) CDV V M CD O N 'a U Q) (D N N O D7 LO M d 0 (D F- 0 N o z CD CD CD 0 0 0 0 0 0 0 0 0 0 0 0 o v CD CD 0 O D D7 0 F- z Q Z cr w N g a O O O o 0 0 0 oCD 0 0 0 0 o Q W o 0 0 0 0 CDO m N N O WLU M LU J w O O O O O O G= Q } 00 00 0 0 0 0 p z F V W N o Z D a Q U a 2 Y O O V 0 0 V w O (D CO O O w N O N r O O V _U V J d C F- z = O z ca � O O N � O N a a E5 U- 0)z 0 oL < � co z w v cm z Cn Jo z = c m a a p N o J w v~i ON Z C� .0 m 0 O Y m z n ° af a U u O OJ w w Q O ca V r N f� N (p Q O N O O v V c (D (D (D CO (D (D N 0 U E LL uj Q m H m m ~ N V M N D7 0 LL (D CO co �N O x N N M M Z Z v v W W p > Z O � N N f N N N v v O O'i O'i N U n n m O W c.0 F o N - r O Z N U H Z Q CJ N CD CD ai o 0 W H o 0 �mj N o 0 N U M M z W uj d'N LU a- +W J O W O z C7 Q U W U � Q a � Z Y z O O 3 U a Z � O z o- U = � Q m o r 0 N Z E O Z a a m 0 0 o 5 w s E � ~ � E m � J V A co L � C N U E m � O J LU ~ m O Q 0 f X F- BIM 360 Document Management Page 1 of 2 BAUTODESK'BIM 360- fortworthgov > CO2552-Miller-Wiltbarger Intersection Improvements- a WS .:: Document M a.n a g e m e n t FOLDERS REVIEWS TRANSMITTALS ISSUES Reviews > Review detail CLOSED #24 Change Order Submittal Workflow No.2 Name^ Description PROGRESS CO2552_Change Order 2 Breakdown(002).pdf -- Initiator Initial Review � CO2552_Change Order#2 Revised Sheets.pdf -- WS Wilma Smith Jul 10,12:07 PM CO2552 <wilma.smith@fortworthtexas.gov> _TxDOT_CO#2 Form-Signed(002).pdf -- Submitted to Reviewer 1 Reviewer 1 Initial Review 1 n LP Lauren Prieur Jul 10,1:13 PM ✓(� `�/� <tauren.prieur@fortworthtexas.gov> 0"' Submitted to Reviewer 2 �Fn9T!?i 9 No comments 9<`Tq�ORTi� Reviewer 2 Initial Review 2 n v �OR SC steve cookes Jul 11,5:00 PM <stephen.cooke@fortworthtexas.gov> Submitted to Reviewer 3 Atte ) �, r Reviewer 3 Initial Review 3 xP\1 M 7e ayser, ity taay �J,� SC Steve cookes Jut 12,10:55 AM IQ1 <stephen.cooke@fortworthtexas.gov> Submitted to Approver Approver Final Review n ;Sc Steve cookes Jul 12,10:56 AM <stephen.cooke@fortworthtexas.gov> Review ended 60MAVRECORD CITY SECRETARY FT WORTH,TX https:Hdoes.b360.autodesk.com/projects/ae85894e-Oa4f-4b99-a167-ed3eO428a7f9/reviews/a2b 175a9-656... 7/12/2019