�� S� RErARY NOTICE OF PROJECT COMPLETION
f
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Wellington Area 1 South Phase 2
City Project No.: 101467
Improvement Type(s): Water ® Sewer
Original Contract Price: $233,992.75
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $233,992.75
—:::k Aug 27,2019
Contractor Date
Project Manager
Title
Conatser Construction Tx Lp
Company Name
I,1ark McFadw(A,g 27,2J19� Aug 27,2019
Project Inspector Date
gYon Lon �_ Aug 27,2019
Project Manager Date
e SuarIett Morales(Aug 3J 2019) Aug 30,2019
CFA Manager Date
�m& lye
Dana Burpddf(Aug 31,2J1 Aug 31,2019
Asst. City Manager Date
LFT.
IAL RECORD
SECRETARY Page 1 of 2
�i� r: 0 / T'X
Notice of Project Completion
Project Name:Wellington Area 1 South Phase 2
City Project No.: 101467
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Pipe Report: x❑ Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 180 CD Days Charged: 179
Work Start Date: 2/25/2019 Work Complete Date: 8/22/2019
Page 2of2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name WELLINGTON AREA 1 SOUTH PHASE 2
Contract Limits
Project Type WATER&SEWER
City Project Numbers 101467
DOE Number 4670
Estimate Number 1 Payment Number 1 For Period Ending 8/20/2019
CD
City Secretary Contract Number Contract Time 18(ED
Contract Date 1/11/2019 Days Charged to Date 179
Project Manager NA Contract is 100.00 Complete
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors CORDOVA / MCFADIN
Monday,August 26,2019 Page I of 4
C'�
i
I
City Project Numbers 101467 DOE Number 4670
Contract Name WELLINGTON AREA 1 SOUTH PHASE 2 Estimate Number 1
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 8/20/2019
Project Funding
II
UNIT I-WATER IMPROVEMENTS
Item Description of Items Unit Unit Cost
Estimated Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 8"WATER PIPE 2294 LF $32.00 $73,408.00 2294 $73,408.00
2 8"GATE VALVE 4 EA $1,250.00 $5,000.00 4 $5,000.00
3 FIRE HYDRANT 1 EA $3,200.00 $3,200.00 1 $3,200.00
4 DUTICLE IRON WATER FITTINGS 0.96 TN $4,000.00 $3,840.00 0.96 $3,840.00
W/RESTRAINT
5 1"WATER SERVICE 58 EA $900.00 $52,200.00 58 $52,200.00
6 CONNECTION TO EXISTING 4"-12"WATER 6 EA $500.00 $3,000.00 6 $3,000.00
MAIN PARTIAL SHUTDOWN
7 ADJUST EXISTING SERVICE FOR METER 36 EA $250.00 $9,000.00 36 $9,000.00
8 TRENCH SAFETY 2294 LF $0.25 $573.50 2294 $573.50
9 SWPPP 1 ACRE 1 LS $2,500.00 $2,500.00 1 $2,500.00
--------------------------------------
Sub-Total of Previous Unit $152,721.50 $152,721.50
UNIT 11-SEWER IMPROVEMENTS
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 8"SEWER PIPE SDR-26 ASTM D3034 721 LF $36.00 $25,956.00 721 $25,956.00
2 4"SEWER SERVICE 24 EA $650.00 $15,600.00 24 $15,600.00
3 ADJUST 4"EXISTING SERVICE 70 EA $250.00 $17,500.00 70 $17,500.00
4 4'MANHOLE 4 EA $3,200.00 $12,800.00 4 $12,800.00
5 4'EXTRA DEPTH MANHOLE 20.87 VF $175.00 $3,652.25 20.87 $3,652.25
7 CONNECT TO EXISTING SEWER LINE 2 EA $1,000.00 $2,000.00 2 $2,000.00
8 POST-CCTV INSPECTION 721 LF $2.00 $1,442.00 721 $1,442.00
9 MANHOLE VACUJM TESTING 4 EA $150.00 $600.00 4 $600.00
10 TRENCH SAFETY 721 LF $1.00 $721.00 721 $721.00
11 SWPPP 1 ACRE I LS $1,000.00 $1,000.00 1 $1,000.00
-------------------- - ------------------
Sub-Total of Previous Unit $81,271.25 $81,271.25
--------------------------------------
Monday,August 26,2019 Page 2 of 4
City Project Numbers 101467 DOE Number 4670
Contract Name WELLINGTON AREA 1 SOUTH PHASE 2 Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 8/20/2019
Project Funding
Contract Information Summary
Original Contract Amount $238,992.75
Chance Orders
Total Contract Price $233,992.75
Total Cost of Work Completed $233,992.75
Less %Retained $0.00
Net Earned $233,992.75
Earned This Period $233,992.75
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $233,992.75
i
i
i
Monday,August 26,2019 Page 3 of 4
City Project Numbers 101467 DOE Number 4670
Contract Name WELLINGTON AREA 1 SOUTH PHASE 2 Estimate Number I
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 8/20/2019
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors CORDOVA / MCFADIN Contract Date 1/11/2019
Contractor CONATSER CONSTRUCTION TxLP Contract Time 180 CD
5327 WICHITA ST Days Charged to Date 179 CD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $233,992.75
Less %Retained $0.00
Net Earned $233,992.75
Earned This Period $233,992.75
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $233,992.75
Monday,August 26,2019 Page 4 of 4
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Wellington Area 1 South Phase 2
PROJECT NUMBER: Water: 56008-0600430-101467-001580 Sewer:56008-0700430-101467-001380
DOE NUMBER: 101467
WATER
PIPE LAID SIZE TYPE OF PIPE LF
8"PVC 8 PVC 2294
FIRE HYDRANTS: 1 VALVES(16" OR LARGER)
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES: yes Passed
NEW SERVICES: 1"-58 Services Copper
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
8" SDR-26 8 PVC 721
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES:
NEW SERVICES: 4"-24 Serivices PVC
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth•1000 Throckmorton Street•Fort Worth,TX 76012-6311
FORTWORTH rev 03/05/07
TRANSPORTATION & PUBLIC WORKS
FINAL STATEMENT OF CONTRACT TIME
FINAL STATEMENT NO.: 1
NAME OF PROJECT: Wellinton Area 1 South Phase 2
PROJECT NO.: water:56008-0600430-101467-001580 CONTRACTOR: Conatser Construction
Sewer: 56008-0700430-101467-001380 DOE NO.: 101467
PERIOD FROM:Feb 25 2019 TO: 08/22/19 FINAL INSPECTION DATE: 22-Aug-19
WORK ORDER EFFECTIVE:2/25/2019 CONTRACT TIME: o WD ® CD
DAY OF DAYS REASON FOR DAYS DAY OF DAYS REASON FOR DAYS
MONTH CHARGED CREDITED MONTH CHARGED CREDITED
DURING DURING
1. 16.
2. 17.
3. 18.
4. 19.
5. 20.
6. 21.
7. 22.
8. 23.
9. 24.
10. 25.
11. 26.
12. 27.
13. 28.
14. 29.
15. 30.
31.
SAT, SUN, RAIN,TOO WET, UTILITIES DAYS TOTAL
&HOLIDAYS &TOO COLD RELOCATIONS OTHERS * CHARGED DAYS
THIS 0 0 0 0 179 179
PERIOD
PREVIOUS 0 0 0 0 0 0
PERIOD
TOTALS 0 0 0 0 179 179
TO DATE
*REMARKS:
P U
CONTRACTOR DATE INSPECTOR DATE
_ ENGINEERING DEPARTMENT
ti The City of Fort Worth• 1000 Throckmorton Street•Fort Worth,TX 76012-6311
(817) 392-7941 •Fax: (817) 392-7845
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a Notary Public in the state and county aforesaid,
on this day personally appeared Brock Huggins, President of Conatser Management Group, Inc.,
general partner of Conatser Construction TX LP, known to me to be a credible person, who
being by me duly sworn, upon his oath deposed and said:
That all persons, firms, associations, corporations or other organizations furnishing
labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fort Worth, has
been paid in full; and
That there are no claims pending for personal injury and/or property damages;
On Contract described as:
WELLINGTON AREA 1 SOUTH PH 2
WATER, SANITARY SEWER, STORM DR,
PAVING AND LIGHTING IMPROVEMENTS
DOE#: N/A
CFA PRJ #: 2018-058
CITY PROJCT #: N/A
CITY OF FORT WORTH
STATE OF TEXAS
CONATSER CONSTRUCTION TX, LP
IN
__�.. BERTHA GIAN1siot�o�Texos
Noiafy Publie.mission Expires
a,=�: •�: My Corn bey �, 2019 Brock Huggins
g ptem
! rr r•, • },w
E r,Il'rIf 1lsi+
Subscribed and sworn to before me this 26rh day of June
Notary Pu4hc in Tarrant County, Texas
CONSENT OF OWNER ❑
SURETY COMPANY ARCHITECT ❑
TO FINAL PAYMENT CONTRACTOR El
SURETY ❑
Conforms with the American Institute of OTHER
Architects, AIA Document G707
Bond No 0219502
PROJECT:
4name, address}Wellington Area 1 South Phase 2
Fort Worth, TX
TO `Owner)
HPC WELLINGTON SOUTH DEVELOPMENT ARCHITECT'S PROJECT NO: CFA#2018-058
CORPORATION AND THE CITY OF FORT WORTH
CONTRACT FOR,
3001 Knox St., Suite 207 Water, Sewer, Stone, Paving, & Street Light Improvements for
Wellington Area 1 South Phase 2
Dallas TX 75205 CONTRACT DATE:
CONTRACTOR: CONATSER CONSTRUCTION TX, L.P.
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
(here insert name and address of Surety Company)
BERKLEY INSURANCE COMPANY
475 Steamboat Road
Greenwich CT 06830 , SURETY COMPANY
on bond of there insert name and address of Contractor)
CONATSER CONSTRUCTION TX, L.P.
5327 Wichita St.
Fort Worth TX 76119-6035 , CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to there insert name and address of Owner)
HPC WELLtNGTON SOUTH DEVELOPMENT CORPORATION AND THE CITY OF FORT WORTH
3001 Knox St_, Suite 207
Dallas TX 75205 , OWNER,
as set forth in the said Surety Company's bond.
IN WITNESS, WHEREOF,
the Surety Company has hereunto set its hand this 21 st day of ,June, 2019
BERKLEY INSURANCE COMPANY
Sur CompanyCompany
Attest: ��L.4 2 �� "awe
{Seal): Signature of Authorized Representative
Robbi Morales _ Attorney-in-Fact
Title
NOTE: This form is to be used as a companion document to AIA DOCUMENT G706, CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS,