NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: THE BRIDGES PHASE 4A
City Project No.: 101458
Improvement Type(s): Water ® Sewer
Original Contract Price: $454,666.30
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $454,666.30
Albert Grantges(Oct 4,20M Oct 4,2019
Contractor Date
Contract Manager
Title
Burnsco Construction, Inc
Company Name
Q`"4it4A�'P"dd-k Oct 8,2019
Cristobal Fuentes(Oct 8,2019)
Project Inspector Date
Patrick Buckley(Oct 8.2019) Oct 8,2019
Proje
�ct
Manager Date p (�
Jennifer Ezerrn ck on behalf of Janie Morale,(Oct 8,2019) Oct 8,2019
CFA Managerfj/�/ Date
Dana Burghdoff(O 10,20191 Oct 10,2019
Asst. City Manager Date
LoFFICIALRECORDRETARY Page 1 of 2
TH,TX
Notice of Project Completion
Project Name: THE BRIDGES PHASE 4A
City Project No.: 101458
City's Attachments
Final Pay Estimate 0
Change Order(s): ❑ Yes 0 N/A
Pipe Report: 0 Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 70 CD Days Charged: 70
Work Start Date: 12/31/2018 Work Complete Date: 9/11/2019
Page 2 of 2
FORTWORT
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name THE BRIDGES PHASE 4A
Contract Limits
Project Type WATER&SEWER
City Project Numbers 101458
DOE Number 1458
Estimate Number I Payment Number I For Period Ending 10/4/2019
CD
City Secretary Contract Number Contract Time 7(FD
Contract Date Days Charged to Date 70
Project Manager NA Contract is 100.00 Complete
Contractor BURNSCO CONSTRUCTION,INC.
6331 SOUTHWEST BLVD
FORT WORTH, TX 76132
Inspectors DICKINSON / FUENTES
Friday,October 4,2019 Page I of 4
City Project Numbers 101458 DOE Number 1458
Contract Name THE BRIDGES PHASE 4A Estimate Number I
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 10/4/2019
Project Funding
WATER
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
I TRENCH SAFETY 3650 LF $0.10 $365.00 3650 $365.00
2 DUCTILE IRON WATER FITTINGS 3 TN $3,300.00 $9,900.00 3 $9,900.00
W/RESTRAINT
3 8"WATER PIPE 3650 LF $23.10 $84,315.00 3650 $84,315.00
4 FIRE HYDRANT 5 EA $3,500.00 $17,500.00 5 $17,500.00
5 1"WATER SERVICE 96 EA $800.00 $76,800.00 96 $76,800.00
6 8"GATE VALVE I EA $1,300.00 $14,300.00 11 $14,300.00
7 CONNECTION TO EXISTING 4"-12"WATER 4 EA $800.00 $3,200.00 4 $3,200.00
MAIN
--
Sub-Total of Previous Unit $206,380.00 $206,380.00
SEWER
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
1 POST-CCTV INSPECTION 3793 LF $1.50 $5,689.50 3793 $5,689.50
2 MANHOLE VACUUM TESTING 18 EA $110.00 $1,980.00 18 $1,980.00
3 TRENCH SAFETY 3793 LF $1.00 $3,793.00 3793 $3,793.00
4 4"SEWER SERVICE 96 EA $590.00 $56,640.00 96 $56,640.00
5 8"PVC SEWER PIPE 3183 LF $28.60 $91,033.80 3183 $91,033.80
6 8"SEWER PIPE,CSS BACKFILL 100 LF $40.00 $4,000.00 100 $4,000.00
7 15"PVC SEWER PIPE 490 LF $64.00 $31,360.00 490 $31,360.00
8 15"PVC SEWER PIPE,CSS BACKFILL 20 LF $72.00 $1,440.00 20 $1,440.00
9 T MANHOLE 18 EA $2,450.00 $44,100.00 18 $44,100.00
10 4'EXTRA DEPTH MANHOLE 55 VF $150.00 $8,250.00 55 $8,250.00
--------------------------------------
Sub-Total of Previous Unit $248,286.30 $248,286.30
--------------------------------------
Friday,October 4,2019 Page 2 of 4
City Project Numbers 101458 DOE Number 1458
Contract Name THE BRIDGES PHASE 4A Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 10/4/2019
Project Funding
Contract Information Summaiy
Original Contract Amount $454,666.30
Chance Orders
Total Contract Price $454,666.30
Total Cost of Work Completed $454,666.30
Less %Retained $0.00
Net Earned $454,666.30
Earned This Period $454,666.30
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $454,666.30
Friday,October 4,2019 Page 3 of 4
City Project Numbers 101458 DOE Number 1458
Contract Name THE BRIDGES PHASE 4A Estimate Number 1
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 10/4/2019
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors DICKINSON / FUENTES Contract Date
Contractor BURNSCO CONSTRUCTION,INC. Contract Time 70 CD
6331 SOUTHWEST BLVD Days Charged to Date 70 CD
FORT WORTH, TX 76132 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $454,666.30
Less %Retained $0.00
Net Earned $454,666.30
Earned This Period $454,666.30
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $454,666.30
Friday,October 4,2019 Page 4 of 4
FORT WORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME:
PROJECT NUMBER:
DOE NUMBER:
WATER
PIPE LAID SIZE TYPE OF PIPE LF
8"PVC 8" C900 PVC 3650LF
FIRE HYDRANTS: 5 VALVES(16" OR LARGER)
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES: yes
NEW SERVICES: 1" P copper 96EA
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
8"PVC 8" PVC Sewer 3183LF
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES: Yes
NEW SERVICES: 4" PVC Sewer 96 EA
TRANSPORTATION AND PUBLIC WORDS