HomeMy WebLinkAboutContract 37049-A2 (2) t
CITY SECRETAW
CONTRACT NO..
JAN 13 2016 AMENDMENT No.2
crrcra��oar
'YOFFORT W ORrH TO CITY SECRETARY CONTRACT No. 37049
WHEREAS, the City of Fort Worth (CITY) and HNTB Corporation,
(ENGINEER) made and entered into City Secretary Contract No. 37049, (the
CONTRACT) which was authorized by M&C C-22780 on the 22nd day of April,
2008 in the amount of $ 967, 435 . 00; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment No. 1
in the amount of $50, 579 . 00 which was authorized by M&C C-27370 on the
7tn day of July, 2 015; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
North Central Texas Council of Governments Railroad Projects (Live
Oak Connector) ; and
WHEREAS, it has become necessary to execute Amendment No. 2 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the additional
engineering services specified in a proposal dated October 16, 2015, a
copy of which is attached hereto and incorporated herein. The cost to
City for the additional design services to be performed by Engineer
totals $36, 521. 00. (See Attached Funding Breakdown Sheet, Page -3-)
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $1, 054, 535. 00.
3 .
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
City of Fort Worth
Professional Services Agreement Amendment Template OFFICIAL RECORD
PMO Official Release 6/1/2012
Page 1 of 3 [' {71C CITY SECRETARY(
r JJ � FT.WORTH, TX
EXECUTED and EFFECTIVE as of the date subscribed by the City' s
designated city manager.
APPROVED:
City of Fort Worth ENGINEER
HNTB Corporation
Jay Chapa Carlos A Lop z, .E.
Assistant/ City Manager Vice President
DATE: 1-I� -& DATE:
APPROVAL RE/COMMENDED:
(,,,
Dougla Wiersig, P.E.
Director, Transportation and Public Works Department
APPROVED AS TO FORM AND LEGALITY: M&C: IV/At
gz��— Date:
Douglas W. Black
Senior Assistant City Attorney
ATTEST: of?
` q
ry J. 9 e r
City Sec eTy '
City of Fort worth OFFICIAL RECORD
Professional Services Agreement Amendment Template CITY SECRETARY
PMO Official Release 8/1/2012
Page 2 of 3 FT.WORTH,TX
FUNDING BREAKDOWN SHEET
City Secretary No. 37049
Amendment No. 2
Department Fund Identifier Amount
TPW 30106-0200431-5330500—000593-007530-2016- $36, 521 . 00
Total : $36, 521 . 00
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012
Page 3 of 3
HNTB Corporation Austin Centre Telephone(512)447-5590
Engineers Architects Planners 701 Brazos.Suite 450 Facsimile(512)447-5329
Austin,TX 78701 www.hntb.com
October 16,2015 HNTB
Roy Teal,Jr.,P.E.
City of Fort Worth
1000 Throckmorton Street
Fort Worth,TX 76102
Re: Proposal for Amendment 2
Dear Mr.Teal,
HNTB Corporation is pleased to submit this proposal to provide additional design services as part of the
Fort Worth Quiet Zones projects. The additional services include adjustments to the plans,specifications,
and estimate(PS&E)package to account for the shift in TEX Rail alignment on Task Order 1 (Peach
Street Improvements/Live Oak Connector).
Our scope of services and fee schedule are attached for the work tasks associated with the above-
mentioned items for Amendment 2. We propose to complete the attached additional services for a cost-
plus-fixed fee amount of$36,521,as shown in the attached fee schedule. This will increase the total cost-
plus-fixed fee amount of the task order from$122,699 to$159,220. The fixed fee associated with HNTB
labor is increased by from$5,709 to$9,757,an increase of$4,048.
We appreciate the opportunity for continued work with the City of Fort Worth. Please do not hesitate to
call with any questions.
Best regards,
C� Q. c"OP �, P
Carlos A.Lopez,P.E.
Vice President
HNTB Corporation
SERVICES TO BE PROVIDED BY THE ENGINEER
Amendment 2 to Task Order 1—Peach Street Area
CSJ:0902-48-688
CSJ:0902-48-689
Amendment Objective:
To provide changes to plans,specifications,and estimates(PS&E)to shift the Live Oak Connector
alignment approximately 20 feet to the west near 15i Street based on changes requested by the TEX Rail
project. The changes impact the alignment from Belknap Street to 2"d Street.
Below is the scope of services for Amendment 2:
• Project management/project administration—Provide additional project management and
project administration services for completion of changes due to TEX Rail realignment.
• Schematic design changes—Prepare changes to the Live Oak Connector schematic drawing to
identify differences in plan, profile, and right-of-way(ROW) requirements to the current design.
This shall include the following tasks:
o Horizontal and vertical geometry design of Live Oak Connector and side streets
o Preliminary cross sections to identify potential design challenges
o Identification of ROW changes in plan
o Preparation of schematic drawing to show changes from current design and proposed
alignment shift
The schematic drawing shall be submitted to the City via PDF for review and comment.
Submissions to TxDOT and TEX Rail shall be sent by the City to those agencies.
PS&E design changes—Prepare changes to the current PS&E package based on the revised
schematic drawing. Submissions shall be made at the 90% and 100%design level and shall be
submitted to the City of Fort Worth with the City submitting to TxDOT and TEX Rail for review;
once comments are received from all parties,comments shall be handled after each submission
with responses in Excel spreadsheet format. Submissions of the 90%and 100% PS&E packages
shall be in PDF format and submitted to the City. Submissions to TxDOT and TEX Rail shall be
sent by the City to those agencies. This shall include the following PS&E changes:
o Plans
■ Typical sections
• Quantity sheet
■ Horizontal alignment data
■ Roadway plan/profile
■ Removal plan
■ ROW plan
■ Traffic control sequencing and plan (including changes for water/wastewater
line adjustments)
■ Signing/pavement markings plan
■ Drainage area map
■ Drainage calculations
■ Storm sewer plan/profile
■ Stormwater pollution prevention plan (SWPPP) plan
■ Roadway cross sections
o Specifications as required by plan changes
o Construction cost estimate/quantity changes
o Utility verification and identification of potential adjustments
This scope of services does not cover additional changes in alignment/plan once schematic
design is approved.
• Waterline PS&E—Adjust waterline design to under the proposed Live Oak Connector per TEX
Rail project request. The waterline adjustment shall be from approximate Live Oak Connector
STA 17+50 to STA 22+00 and shall include connections to existing waterlines east and west along
1st Street(including a new fire hydrant).This shall include the following tasks:
o Waterline plan & profile sheets for the new waterline location and all connections as
described above
o Additional waterline details as needed for the design
o Quantities and estimated construction costs for the changes to the waterline design
o Specifications as needed based on the new design
50 feet of 24"steel casing shall be installed under the proposed TEX Rail crossing location along
1st Street east of the proposed Live Oak Connector.
• Changes to PS&E based on TEX Rail sanitary sewer realignment—Adjust the Live Oak Connector
PS&E to account for the realignment of the sanitary sewer design by others under the proposed
Live Oak Connector pavement as part of the TEX Rail project.This shall include the following
tasks:
o Potential storm sewer changes, including storm sewer profile adjustments, adjustments
to the stormwater modeling, and associated plan sheet changes
o Quantities and estimated construction costs for the associated changes
• ROW documents—Adjust the ROW documents per the changes in the Live Oak Connector
alignment. This shall include updates to parcel maps and metes/bounds surveys and submission
of those documents to the City for review and comment. It is assumed that parcels between
Belknap Street and 2"d Street would require adjustments based on alignment changes.
Services not included in the scope of services include:
• Sanitary sewer design as part of the Live Oak Connector project
• Adjustment of Live Oak Connector project items except as defined in this scope of services
• Other services not defined as part of this scope of services
FEE SCHEDULE
HNTB
Salary Classification Sala Range Rate Used Hours Direct Labor
Min Max-FY 2015 For Calculations FC 110 FC 164 FC 390 FC 110 FC 164 FC 390 Total
Project Principal $40 $ 118.44 $95.00 0 0 0 $0 $0 $0 $0
Project Director $35 $ 105.27 $81.00 0 0 0 $0 $0 $0 $0
Project Manager $30 $ 92.12 $68.00 61 0 0 $4,148 $0 $0 $4,148
Project Business Manager $25 $ 72.37 $54.00 4 0 0 $216 $0 $0 $216
Project Admnistrator $20 $ 46.05 $39.00 8 0 0 $312 $0 $0 $312
Clerical $10 $ 26.32 $18.00 0 0 0 $0 $0 $0 $0
Senior Design Engineer $30 $ 80.27 $58.00 0 0 0 $0 $0 $0 $0
Engineer V $25 $ 72.37 $51.00 0 0 0 $0 $0 $0 $0
Engineer IV $25 $ 59.22 $50.00 130 0 0 $6,500 $0 $0 $6,500
Engineer III $20 $ 46.05 $40.00 0 0 0 $0 $0 $0 $0
Engineer II $20 $ 36.85 $26.00 0 0 0 $0 $0 $0 $0
Engineer 1 $15 $ 32.90 $29.00 0 0 0 $0 $0 $0 $0
Senior Urban Designer $20 $ 72.37 $50.00 0 0 0 $0 $0 $0 $0
Urban Designer II $15 $ 46.05 $33.00 0 0 0 $0 $0 $0 $0
Senior Landscape Architect $20 $ 59.22 $43.00 0 0 0 $0 $0 $0 $0
Landscape Architect II $15 $ 46.05 $32.00 0 0 0 $0 $0 $0 $0
Public Involvement Director $25 $ 65.79 $45.00 0 0 0 $0 $0 $0 $0
Public Involvement Mana er $20 $ 52.63 $30.00 0 0 0 $0 $0 $0 $0
Public Involvement Coordinat $10 $ 46.05 $25.00 0 0 0 $0 $0 $0 $0
Technologies-Director $30 $ 92.12 $65.00 0 0 0 $0 $0 $0 $0
Technologies-Manager $30 $ 78.96 $57.00 0 0 0 $0 $0 $0 $0
Technologies-Graphic Artist $20 $ 59.22 $41.00 0 0 0 $0 $0 $0 $0
Technologies-3D modeler $20 $ 46.05 $32.00 01 0 0 $0 $0 $0 $0
Technol ies-ITS Specialist $25 $ 65.79 $48.00 0 1 0 0 $0 $0 $0 $0
Totals 203 0 0 $11,176 $0 $0 $11,176
Overhead @ 141.45% $15,808 $0 $0 $15,808
Subtotals $26,984 $0 $0 $26,984
Fixed Fee @ 15.00% $4,048 $0 $0 $4,048
Direct Ex enses see attached $125 $125
Totals $31,157 $0 $0 $31,157
Subconsultant DBE HUB FC 110 FC 164 FC 390 Total
Campbell Technologies Corporation $0 $0 $0 $0
Gorrondona x x $5,364 $0 $0 $5,364
STL x x $0 $0 $0 $0
Subtotal-Subcontracted Expenses $5,364 $0 I $0 $5,364
'DBE/HUB Firms
FC 110 FC 164 FC 390 Total
TOTALS- $36,521 $0 $0 $36,521
Maximum Fee for Work Authorization $36,521
Total Fixed Fee for Work Authorization $4,048
FEE SCHEDULE
HNTB
MANHOUR ESTIMATE-STAFF
Func. Project Project Project Engineer
Code Task Manager Business Admnist IV Totals
Manager rator
$68.00 $54.00 $39.00 $50.00
110 Live Oak Connector TEX Rail Realignment Chan es
Project Management/Project Adminstration 12 4 8 24
Schematic Design Changes
Horizontal/vertical geometry 4 8 12
Preliminary cross sections 2 2 4
Identification of ROW changes 2 2
Schematic drawing preparation 2 6 8
PS&E Design Changes
Typical sections 1 2 3
Quantity sheet 4 8 12
Horizontal alignment data 2 2
Roadway plan/profile 4 8 12
Removal plan 1 4 5
ROW plan 2 2
Traffic control sequencing and plan 2 6 8
Signing/pavement markings plan 1 4 5
Drainage area map 1 4 5
Drainage calculations 4 4 8
Storm sewer plan/profile 4 12 16
SWPPP plan 1 4 5
Cross sections 4 4 8
Specifications 4 4
Construction cost estimate 1 2 3
Utility verification/identification of potential adjustments 4 4 8
Waterline PS&E
Waterline plan&profile sheets 20 20
Waterline details 6 6
Traffic control changes 4 4
Quantites/estimated construction costs 2 2
Specifications changes 4 4
Changes to PS&E based on sanitary sewer design
Storm sewer changes 2 4 6
Quantites/estimated construction costs 1 2 3
ROW Documents 2 1 2
TOTAL 1 611 41 81 13OF 203
Page 2 of 5
FEE SCHEDULE
Direct Expenses-HNTB
Item Quantity Units Rate Total
Office Expenses
Printing
Digital Plotter SF $2.00 = $0.00
11"x17"Mylar Sheet $2.00 = $0.00
8 1/2"x 11"B/W Paper copies Sheet $0.10 = $0.00
11"x17"B/W Paper Copies 500 Sheet $0.25 = $125.00
8 1/2"x 11"Color paper copies Sheet $0.75 = $0.00
11"x17Color Copies Sheet $1.10 = $0.00
Miscellaneous Office Expenses
Postage
Standard Postage @ cost $0.39 = $0.00
Express mail @ cost $10.00 = $0.00
Overnight Mail-Letter Size @ cost $20.00 = $0.00
Overnight Mail-Oversized Box @ cost $50.00 = $0.00
Travel Expenses
Mileage(TxDOT allowable mileage rate) miles $0.560 = $0.00
Airfare($750 max) RT $750.00 = $0.00
Airfare RT $500.00 = $0.00
Airfare RT $250.00 = $0.00
Garage Parking($15 daily maximum) days @ $15.00 = $0.00
Lodging($85 daily maximum excluding tax) days @ $85.00 = $0.00
Meals($36 daily maximum) days @ $36.00 = $0.00
Car Rental($60 daily maximum without fuel) days @ $60.00 = $0.00
Miscellaneous Expenses
Website development @cost $5,000.00 = $0.00
Website maintenance month $40.00 = $0.00
Court reporter @cost $500.00 = $0.00
Public meeting brocures @cost $1,000.00 = $0.00
Techical use of computer hourly $17.00 = $0.00
SUBTOTAL-FUNCTION CODE 110 = $125.00
Page 3 of 5
FEE SCHEDULE
Gorrondona
Salary Classification Salary Range Rate Used Hours Direct Labor
Min Max For Calculations FC 130 FC 150 FC 390 FC 130 FC 150 FC 390 Total
Project Mana er/RPLS $25 $ 43.53 $ 43.53 6 0 0 $261 $0 $0 $261
Tech/RPLS $20 $ 34.55 $ 34.55 1 0 0 $35 $0 $0 $35
2-Man Field Part $25 $ 45.60 $ 45.60 10 0 0 $456 $0 $0 $456
3-Man Field Part $20 $ 58.74 $ 58.74 0 0 0 $0 $0 $0 $0
CADD Tech $10 $ 26.96 $ 26.96 35 0 0 $944 $0 $0 $944
Admin/Clerical $10 $ 19.35 $ 19.35 3 0 0 $58 $0 $0 $58
Totals 55 0 0 $1,753 1 $0 $0 $1,753
Overhead 166.00% $2,911 $0 $0 $2,911
Subtotals $4,664 $0 $0 $4,664
Fixed Fee 15.00% $700 $0 $0 $700
Direct Expenses see attached $0 $0
Totals $5,364 $0 $0 $5,364
FC 110 FC 164 FC 390 Total
TOTALS- $5,364 $0 $0 $5,364
Maximum Fee for Work Authorization $5,364
Total Fixed Fee for Work Authorization $700
FEE SCHEDULE
Gorrondona
MANHOUR ESTIMATE-STAFF
Project 2-Man
Func. Tech/RP 3-Man CADD Admin/C
Code Task Manager/ LS Field Field Party Tech lerical Totals
RPLS Part
$ 43.53 $ 34.55 $45.60 $58.74 $26.96 $19.35
130 Live Oak Connector TEX Rail Realignment Changes
Project Management/Project Adminstration 0
Schematic Design Changes
Horizontal/vertical geometry 0
Preliminary cross sections 0
Identification of ROW changes 0
Schematic drawing preparation 0
PS&E Design Changes
Typical sections 0
Quantity sheet 0
Horizontal alignment data 0
Roadway plan/profile 0
Removal plan 0
ROW plan 0
Traffic control sequencing and plan 0
Sign i n / avement markings plan 0
Drainage area map 0
Drainage calculations 0
Storm sewer plan/profile 0
SWPPP plan 0
Cross sections 0
Specifications 0
Construction cost estimate 0
Utility verification/identification of potential adjustments 0
Waterline PS&E
Waterline plan&profile sheets 0
Waterline details 0
Traffic control changes 0
Quantites/estimated construction costs 0
Specifications changes 0
Changes to PS&E based on sanitary sewer design
Storm sewer changes 0
Quantites/estimated construction costs 0
ROW Documents 61 1 101 01 351 31 55
TOTAL 1 61 11 101 01 351 31 55
Page 5 of 5