HomeMy WebLinkAboutOrdinance 6497 ORDINANCE NO.
ORDINANCE ACCEPTING IMPROVEMENTS ON A PORTION OF ERATH STREET
AND PORTIONS OF SUNDRY OTHER STREETS, AVENUES AND PUBLIC PLACES
IN THE CITY OF FORT WORTH, TEXAS; DECLARING THE CONTRACT WITH
AUSTIN ROAD COMPANY FOR THE CONSTRUCTION CF SAID
IMPROVEMENTS FULLY COMPLETED AND PERFORMED; DIRECTING THE ISSUANCE,
EXECUTION AND DELIVERY OF CERTIFICATES IN EVIDENCE OF SPECIAL ASSESS-
MENTS LEVIED AFTER GIVING EFFECT TO SUNDRY CREDITS HEREIN AUTHORIZED
AND ALLOWED AGAINST SOME OF SAID ASSESSMENTS; DIRECTING THE CITY
SECRETARY TO ENGROSS AND ENROLL THIS ORDINANCE BY COPYING THE CAP-
TION OF SAME IN THE MINUTE BOOK OF THE CITY COUNCIL OF FORT WORTH,
TEXAS, AND BY FILING THE COMPLETE ORDINANCE IN APPROPRIATE ORDINANCE
RECORDS OF SAID CITY; AND PROVIDING AN EFFECTIVE DATE.
WHEREAS, the City of Fort Worth, Texas, has heretofore entered into a contract
with AUSTIN ROAD COMPANY for the making and construction of certain
street improvements on the hereinafter described portions of streets, avenues and public
places in said City, to-wit:
UNIT 1: ERATH STREET From Vaughn Boulevard to Highway 287,
known and designated as Unit 1,
Project No. 104-24000-205.
UNIT 2: ERATH STREET From Highway 287 to Reed Street,
known and designated as Unit 2,
Project No. 104-24000-205.
UNIT 3: SHACKLEFORD STREET From Martin Street to Knox Street,
known and designated as Unit 3,
Project No. 104-24000-205.
UNIT 4: SHACKLEFORD STREET From Knox Street to Howard Street,
known and designated as Unit 4,
Project No. 104-24000-205.
UNIT 5: KELROY STREET From Trentman Street to Miller Avenue,
known and designated as Unit 5,
Project No. 104-24000-205.
WHEREAS, by sundry proceedings heretofore passed by the City Council of the
City of Fort Worth, Texas, including Ordinance No. 6347, a portion of the cost of
said improvements was levied and assessed against the respective properties abutting
on each of the above described portions of streets, avenues and public places and against
the real and true owners thereof; and,
WHEREAS, the City Council of the City of Fort Worth, Texas, has, upon review,
found and determined that, in some instances, in order to effect substantial justice
and equality, it is desirable and necessary to grant and issue certain credits against
some one or more of the assessments levied by Ordinance No. 6347 , and
WHEREAS, the street improvements hereinabove mentioned have been completed
upon each of the portions of streets, avenues and public places hereinabove described,
and have been inspected and found to be in complete accordance with the contract therefor;
NOW, THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS9 THAT:
I.
The improvements on each of the portions of streets, avenues and public
places hereinabove described be, and they are hereby, accepted; .and the contract with
reference thereto be, and it is hereby, found and declared fully completed and performed.
II.
The Mayor, be, and he is hereby, directed to issue and execute in the name
cf the City, certificates in evidence of the special assessments levied against abutting
property and the owner thereof for such improvements, and the City Secretary is directed
to attest same and impress thereon the corporate seal of the City, all in accordance with
the proceedings relating to such improvements and assessments. The certificates shall_ be
numbered, shall describe the property against which the assessment has been levied, shall,
where known, state the name or names of the true owners of the respective parcels of pro-
perty assessed and shall be issued in an amount equal to the difference between the
principal amount of the assessment and the amounts of any credit issued thereon. The
numbers of the certificates, with the property descriptions to be shown on the respective
certificates, together with the names of the owners of said property, the principal amount
of the assessment, the respective credits, if any which are hereby authorized, granted and
allowed against the principal amount of some one or more of the assessments heretofore
levied, and the principal amount for which each certificate is to be issued after giving
effect to such credit, if any, are hereby enumerated and itemized as follows.
aaa.
When each of the certifiactes has been duly executed as hereinabove provided,
same shall be delivered to the Tax Assessor-Collector as part payment of the contract
price.
IV.
The City Secretary is hereby directed to engross and enroll this ordinance by
copying_ the caption of same in the Minute Book of the City Council of Fort Worth, Texas,
and by filing the complete ordinance in the appropriate Ordinance Records of said City.
V.
This ordinance shall take effect and be in full force and effect from and after
the date of its passage.
PASSED APED APPROVED THIS day of a 19
APPROVED AS TO FORM AND LEGALITY:
r /
City Attorney
PROJECT NO. 104-24000-205, UNIT 1: ERATH STREET FROM VAUGHN BOULEVARD TO HIGHWAY 287, to
be improved with six-inch thick hot-mix asphaltic concrete pavement on a six-inch thick
cement stabilized subgrade with seven-inch high concrete curb and eighteen-inch wide
concrete gutter, so that the finished roadway will be thirty-six feet wide and by con-
structing six-inch thick concrete driveways where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
BEGINNING AT NORTHWEST CORNER OF ERATH STREET AND VAUGHN BOULEVARD
WEST SIDE OF STREET MASONIC HILL ADDITION
Gulf Coast Inv. Corp. 29 224' Converging Lot adjusted to
P.O. Box 1660 Res. 200' Pavement $2.82 $564.00
Houston, Texas 200' Curb & Gutter 2.58 516.00
77001 $1,080.00
M. A. Nelon 28 & 180' Pavement $2.82 $507.60
3808 Erath Street 27 Res. 180' Curb & Gutter 2.58 464.40
76119 104 Sq. Ft. Drive .81 84.24
$1,056.24
W. S. Taylor 26 90' Frontage
3762 Erath Street Res. 65' Pavement $2.82 $183.30
65' Curb & Gutter 2.58 167.70
52 Sq. Ft. Drive .81 42.12
$ 393.12
W. S. Taylor 25 37.52' Existing Facilities
3762 Erath Street Res. No Assessment
SOUTH SERVICE ROAD TO HIGHWAY 287 INTERSECTS
EAST SIDE OF STREET
James E. Swofford 4 90' Shallow lot adjusted to
4505 Erath Street Res. 57' Pavement $2.82 $160.74
57' Curb & Gutter 2.58 147.06
$ 307.80
James E. Swofford 3 90' Pavement $2.82 $253.80
4505 Erath Street Less Res. 90' Curb & Gutter 2.58 232.20
R.O.W. 52 Sq. Ft. Drive .81 42.12
$ 528.12
PROJECT NO. 104-24000-205, UNIT 1: ERATH STREET FROM VAUGHN BOULEVARD TO HIGHWAY 287,
CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
EAST SIDE OF STREET MASONIC HILL ADDITION
W. S. Middleton 2-A 75' Pavement $2.82 $211.50
3809 Erath Street Less Res. 75' Curb & Gutter 2.58 193.50
R.O.W. 67 Sq. Ft. Drive .81 54.27
$ 459.27
Wilburn F. Hand 1-B 75' Pavement $2.82 $211.50
3737 Bluebell Drive Res. $ 2ll. 50
Everman, Texas
Henry Brauer W. 163' Side Lot Credit
3915 Vaughn Blvd. 232.8' Res. 100' Pavement $2.82 $282.00
of 1-A 100' Curb & Gutter 2.58 258.00
52 Sq. Ft. Drive .81 42. 12
$ 582.12
COST TO PROPERTY OWNERS . . . . . . . . . . $ 4,618.17
COST TO CITY OF FORT WORTH . . . . . . . . . . . . 9,199.54
TOTAL ESTIMATED CONSTRUCTION COST, UNIT 1 . , . . . $13,817.71
PROJECT NO. 104-24000-205, UNIT 2: ERATH STREET FROM HIGHWAY 287 TO REED STREET, to be
improved with six-inch thick asphaltic concrete pavement on a six-inch thick cement
stabilized subgrade with seven-inch high concrete curb and eighteen-inch wide concrete
gutter, so that the finished roadway will be thirty-six feet wide and by constructing
six-inch thick concrete driveways where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
BEGINNING AT NORTHWEST CORNER OF HIGHWAY 287 NORTH SERVICE ROAD AND ERATH STREET
WEST SIDE OF STREET MASONIC HILL ADDITION
H. 0. Weldon 20 90' Shallow Lot adjusted to
2072 Lotus Street less Res. 86' Pavement $2.82 $242.52
76111 R.O.W. 86' Curb & Gutter 2.58 221.88
$ 464.40
H. 0. Weldon 19 180' Pavement $2.82 $507.60
2072 Lotus Street & 18 Res. 180' Curb & Gutter 2.58 464.40
$ 972.00
John B. Shea 17 90' Pavement $2.82 $253.80
1729 Sheffield Place Res. 72' Curb & Gutter 2.58 185.76
76112 $ 439.56
John M. Cantrell 16 90' Pavement $2.82 $253.80
3608 Erath Street Res. 79' Curb & Gutter 2.58 203.82
76119 $ 457.62
Richard A. Layne 15 100' Pavement $2.82 $282.00
3600 Erath Street Res. 100' Curb & Gutter 2.58 258.00
76119 $ 540.00
REED STREET INTERSECTS
EAST SIDE OF STREET MASONIC HILL ADDITION
Saleeta D. Brink 14 100' Pavement $2.82 $282.00
121 Avenue A Res. 100' Curb & Gutter 2.58 258.00
Hereford, Texas $ 540.00
PROJECT NO. 104-24000-205, UNIT 2: ERATH STREET FROM HIGHWAY 287 TO REED STREET, CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
EAST SIDE OF STREET MASONIC HILL ADDITION
Saleeta D. Brink 13 90' Pavement $2.82 $253.80
121 Avenue A Res. 72' Curb & Gutter 2.58 185.76
Hereford, Texas $ 439.56
J. D. Hill 12, 360' Pavement $2.82 $1,015.20
Rt. 3 11, Res. 360' Curb & Gutter 2.58 928.80
Honeygrove, Texas 10 and $1,944.00
9
A. H. Stephenson 8 90' Adjusted to
3643 Erath Street Res. 35' Pavement $2.82 $ 98.70
$ 98.70
J. D. Hill 7 3.7' Existing Facilities
Rt. 3 Res. No Assessment
Honeygrove, Texas
COST TO PROPERTY OWNERS - ASSESSMENTS . . . . . . . $ 5,895.84
COST TO CITY OF FORT WORTH . . . . . . . . . . . . 9,735.45
TOTAL ESTIMATED CONSTRUCTION COST, UNIT 2 . . . . . $15,631.29
PROJECT NO. 104-24000-205, UNIT 3: SHACKLEFORD STREET FROM MARTIN STREET TO KNOX STREET,
to be improved with six-inch thick hot-mix asphaltic concrete pavement on a six-inch thick
cement stabilized subgrade with seven-inch high concrete curb and eighteen-inch wide concrete
gutter, so that the finished roadway will be thirty feet wide and by constructing six-inch
thick concrete driveways where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
BEGINNING AT NORTHWEST CORNER OF SHACKLEFORD STREET AND MARTIN STREET
WEST SIDE OF STREET COBB'S ORCHARD ADDITION
Charles F. Corder M-R-A 16 110.10' Pavement $2.82 $310.48
Rt. 2, Box 362 �& Res. 53.85' Curb & Gutter 2.58 138.93
Burleson, Texas N-R $ 449.41
76028
Trentman Co. 0 16 56.25' Pavement $2.82 $158.63
1310 Trans-American Res. 56.25' Curb & Gutter 2.58 145.13
Life Building 85 Sq. Ft. Drive .81 68.85
$ 372.61
Roy C. Brymer P 16 56.25' Pavement $2.82 $158.63
3500 Hardeman Res. 56.25' Curb & Gutter 2.58 145.13
76119 85 Sq. Ft. Drive .81 68.85
$ 372.61
James A. Baugh Q 16 56.25' Pavement $2.82 $158.63
4728 Shackleford Street Res. 56.25' Curb & Gutter 2.58 145.13
76119 85 Sq. Ft. Drive .81 68.85
$ 372.61
WEST SIDE OF STREET
Roy L. Speck R 16 56.25' Pavement $2.82 $158.63
841 Lilac Dr. Res. 56.25' Curb & Gutter 2.58 145.13
Garland, Texas 85 Sq. Ft. Drive .81 68.85
$ 372.61
B. W. Johns S 16 56.25' Pavement $2.82 $158.63
2313 Oneal Res. 56.25' Curb & Gutter 2.58 145.13
Greenville, Texas 85 Sq. Ft. Drive .81 68.85
$ 372.61
PROJECT NO. 104-24000-205, UNIT 3: SHACKLEFORD STREET FROM MARTIN STREET TO KNOX STREET,
CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
WEST SIDE OF STREET COBB'S ORCHARD ADDITION
Jennie May Murrell T 16 56.25' Pavement $2.82 $158.63
4716 Shackleford St. Res. 56.25' Curb & Gutter 2.58 145.13
76119 85 Sq. Ft. Drive .81 68.85
$ 372.61
Cora A. Braunt U 16 56.25' Pavement $2.82 $158.63
4833 Erath St. Res. 56.25' Curb & Gutter 2.58 145.13
76119 85 Sq. Ft. Drive .81 68.85
$ 372.61
J. C. Beck V 16 56.25' Pavement $2.82 $158.63
2720 Mansfield Hwv. Res. 56.25' Curb & Gutter 2.58 145.13
76119 85 Sq. Ft. Drive .81 68.85
$ 372.61
Joseph P. Lance W 16 56.25' Pavement $2.82 $158.63
4704 Shackleford St. Res. 56.25' Curb & Gutter 2.58 145.13
76119 85 Sq. Ft. Drive .81 68.85
$ 372.61
Western Savings X 16 56.25' Adjusted to
and Loan Association Res. 50' Pavement $2.82 $141.00
315 W. Seventh St. 50' Curb & Gutter 2.58 129.00
$ 270.00
KNOX STREET INTERSECTS
EAST SIDE OF STREET W. S. KELLER ADDITION, 2ND FILING
E. J. Hukill 1-R 6 79.8' Slant Lot Adjusted to
4701 Shackleford St. Res. 70' Pavement $2.82 $197.40
76119 70' Curb & Gutter 2.58 180.60
$ 378.00
PROJECT NO. 104-24000-205, UNIT 3: SHACKLEFORD STREET FROM MARTIN STREET TO KNOX STREET,
CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
EAST SIDE OF STREET W. S. KELLER ADDITION, 2ND FILING
Charlie Hillard, Inc. 2 6 60' Pavement $2.82 $169.20
1400 S. University Drive Res. 60' Curb & Gutter 2.58 154.80
76107 $ 324.00
Ivan J. Davis 3 6 60' Pavement $2.82 $169.20
4709 Shackleford St. Res. 60' Curb & Gutter 2.58 154.80
76119 85 Sq. Ft. Drive .81 68.85
$ 392.85
C. T. HILLIARD SURVEY
Earl Region Tract 8-K 269.99' Pavement $2.82 $761.37
7200 Evergreen Road Res. 269.99' Curb & Gutter 2.58 696.57
76118 $1,457 .94
Southside Baptist Church Tract 8-0 202.2' Pavement $2.82 $570.20
4101 Frazier Res. 202.2' Curb & Gutter 2.58 521.68
76115 155 Sq. Ft. Drive .81 125.55
$1,217 .43
COST TO PROPERTY OWNERS - ASSESSMENTS . . . . . . . $ 7,843.12
COST TO CITY OF FORT WORTH . . . . . . . . . . . . . 7,621.37
TOTAL ESTIMATED CONSTRUCTION COST - UNIT 3 $15,464.49
PROJECT NO. 104-24000-205, UNIT 4: SHACKLEFORD STREET FROM KNOX STREET TO HOWARD STREET,
to be improved with six-inch thick hot-mix asphaltic concrete pavement on a six-inch thick
cement stabilized subgrade with seven-inch high concrete curb and eighteen-inch wide concrete
gutter, so that the finished roadway will be thirty feet wide and by constructing six-inch
thick concrete driveways where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
BEGINNING AT NORTHWEST CORNER OF SHACKLEFORD STREET AND KNOX STREET
WEST SIDE OF STREET COBB'S ORCHARD ADDITION
Knox Street M, N, 15 168.75' Adjusted to
Baptist Church 0 Res. 163.75' Pavement $2.82 $461.78
4644 Shackleford St. 163.75' Curb & Gtr. 2.58 422.48
76119 116 Sq. Ft. Drive .81 93.96
$ 978.22
Rudolph J. Duty P 15 56.25' Pavement $2.82 $158.63
4632 Shackleford St. Res. 56.25' Curb & Gtr. 2.58 145.13
76119 170 Sq. Ft. Drive .81 137.70
$ 441.46
Pearl Briggs 0 15 56.25' Pavement $2.82 $158.63
4628 Shackleford St. Res. 56.25' Curb & Gtr. 2.58 145.13
76119 85 Sq. Ft. Drive .81 68.85
$ 372.61
F. H. Stalcup R & 15 112.50' Pavement $2.82 $317.25
4626 Shackleford St. S Res. 112.50' Curb & Gtr. 2.58 290.25
76119 171 Sq. Ft. Drive .81 138.51
$ 746.01
Ethel Puckett T 15 56.25' Pavement $2.82 $158.63
4616 Shackleford Res. 56.25' Curb & Gtr. 2.58 145.13
76119 85 Sq. Ft. Drive .81 68.85
$ 372.61
Arthur L. Sealy U 15 56.25' Pavement $2.82 $158.63
4612 Shackleford St. Res. 56.25' Curb & Gtr. 2.58 145.13
76119 43 Sq. Ft. Drive .81 34.83
$ 338.59
PROJECT NO; 104-24000-205, UNIT 4: SHACKLEFORD STREET FROM KNOX STREET TO HOWARD STREET,
CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
WEST SIDE OF STREET COBB'S ORCHARD ADDITION
W. D. Dollarhide V 15 56.25' Pavement $2.82 $158.63
3520 Howard Street Res. 56.25' Curb & Gtr. 2.58 145.13
$ 303.76
Mrs. Iris Dollarhide W & 15 112.50' Pavement $2.82 $317.25
3520 Howard St. X Res. 109,50' Curb & Gtr. 2.58 282.51
76119 $ 599.76
HOWARD STREET INTERSECTS
EAST SIDE OF STREET KAYWOOD HEIGHTS ADDITION
Alfred H. Herring 1 3 97' Pavement $2.82 $273.54
6416 Regal Road Res. 97' Curb & Gtr. 2.58 250.26
76119 $ 523.80
C. T. HILLIARD SURVEY
0. S. Jones, Jr. Tract 6 416.6' Pavement $2.82 $1,174.81
4615 Shackleford St. Res. 416.6' Curb & Gtr. 2.58 1,074.83
76119 85 Sq. Ft. Drive .81 68.85
$2,318.49
W. S. KELLER ADDITION, 2ND FILING
W. S. Keller 1-R 1 159.37 ' Side Lot Credit
3601 Knox St. Res. 100' Pavement $2.82 $282.00
76119 100' Curb & Gtr. 2.58 258.00
85 Sq. Ft. Drive .81 68.85
$ 608.85
COST TO PROPERTY OWNERS - ASSESSMENTS . . . . . . . . $ 7 ,604.16
COST TO CITY OF FORT WORTH . . . . . . . . . . . . . 8,779.91
TOTAL ESTIMATED CONSTRUCTION COST, UNIT 4 . . . . . . $16,384.07
PROJECT NO. 104-24000-205, UNIT 5: KELROY STREET FROM TRENTMAN STREET TO MILLER AVENUE,
to be improved with a five-inch thick reinforced concrete pavement on a two-inch thick
sand cushion on a five-inch thick cement stabilized subgrade with seven-inch high concrete
curb and eighteen-inch wide concrete gutter, so that the finished roadway will be thirty
feet wide and by constructing four-foot wide concrete sidewalks and six-inch thick
concrete driveways where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
BEGINNING AT NORTHEAST CORNER OF KELROY STREET AND TRENTMAN STREET
NORTH SIDE OF STREET TRENTMAN CITY ADDITION
Trentman Avenue W. 145' 14 145' Converging Lot Adjusted to
Baptist Church of Res. 128' Pavement $2.32 $296.96
5401 Trentman St. 8-A 128' Curb & Gutter 3.08 394.24
76119 88' Sidewalk 2.76 242.88
310 Sq. Ft. Drive .81 251.10
$1,185.18
J. D. Adams 8 14 199.9' Pavement $2.32 $463.77
3907 Kelroy St. Res. 199.9' Curb & Gutter 3.08 615.69
76119 85 Sq. Ft. Drive .81 68.85
$1,148.31
Seller:
J. T. Couch 9 14 100' Pavement $2.32 $232.00
5083 Nell St. Res. 100' Curb & Gutter 3.08 308.00
76119 $ 540.00
Buyer:
Curtis W. Murr, Jr.
412 Haynes
Shuford B. Tunnell 10 14 100' Pavement $2.32 $232.00
4005 Kelroy St. Res. 100' Curb & Gutter 3.08 308.00
76119 85 Sq. Ft. Drive .81 68.85
$ 608.85
K. C. Bernard 11 14 100' Pavement $2.32 $232.00
6409 Crawford Lane Res. 100' Curb & Gutter 3.08 308.00
76119 140 Sq. Ft. Drive .81 113.40
$ 653.40
PROJECT NO. 104-24000-205, UNIT 5: KELROY STREET FROM TRENTMAN STREET TO MILLER AVENUE,
CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
NORTH SIDE OF STREET TRENTMAN CITY ADDITION
Roy C. Hollenback 12 14 100' Pavement $2.32 $232.00
4015 Kelroy Street Res. 100' Curb & Gutter 3.08 308.00
76119 85 Sq. Ft. Drive .81 68.85
$ 608.85
T. E. Howard 13 14 100' Pavement $2.32 $232.00
c/o Roger L. Howard Res. 100' Curb & Gutter 3.08 308.00
4101 Kelroy 85 Sq. Ft. Drive .81 68.85
$ 608.85
Wardell M. Larson 14 14 100' Pavement $2.32 $232.00
4105 Kelroy Res. 100' Curb & Gutter 3.08 308.00
76119 85 Sq. Ft. Drive .81 68.85
$ 608.85
Myrtle Ellis 15 & 14 164.3' Pavement $2.32 $381.18
4113 Kelroy St. 16 Res. 143.3' Curb & Gtr. 3.08 441.36
76119 171 Sq. Ft. Drive .81 138.51
$ 961.05
MILLER AVENUE INTERSECTS
SOUTH SIDE OF STREET
E. E. Allen 14 16 85.6' Pavement $2.32 $198.59
201 Chateau Res. 64.6' Curb & Gtr. 3.08 198.97
76134 85 Sq. Ft. Drive .81 68.85
$ 466.41
Martin Pyle 13 16 80' Pavement $2.32 $185.60
c/o Ernest R. Res. 80' Curb & Gutter 3.08 246.40
Hawkins, Executor 85 Sq. Ft. Drive .81 68.85
937 E. Berry Street $ 500.85
76110
t ► `
PROJECT NO. 104-24000-205, UNIT 5: KELROY STREET FROM TRENTMAN STREET TO MILLER AVENUE,
CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
SOUTH SIDE OF STREET TRENTMAN CITY ADDITION
C. D. Caldwell 12 16 100' Pavement $2.32 $232.00
4104 Kelroy Street Res. 100' Curb & Gutter 3.08 308.00
76119 85 Sq. Ft. Drive .81 68.85
$ 608.85
W. W. Sellers 11 16 100' Pavement $2.32 $232.00
c/o C. W. Hutchison Res. 100' Curb & Gutter 3.08 308.00
801 N. P. Anderson Bldg. 194 Sq. Ft. Drive .81 157.14
76102 $ 697.14
Robert L. Smith 10 16 100' Pavement $2.32 $232.00
4012 Kelroy Street Res. 100' Curb & Gutter 3.08 308.00
76119 85 Sq. Ft. Drive .81 68.85
$ 608.85
H. A. Eason 9 16 100' Pavement $2.32 $232.00
4008 Kelroy Street Res. 100' Curb & Gutter 3.08 308.00
76119 279 Sq. Ft. Drive .81 225.99
$ 765.99
A. C. Isaacs 8 16 200' Pavement $2.32 $464.00
4000 Kelroy St. & Res. 200' Curb & Gutter 3.08 616.00
76119 7 341 Sq. Ft. Drive .81 276.21
$1,356.21
Clarence Taylor 6 16 100' Pavement $2.32 $232.00
3908 Kelroy Street Res. 100' Curb & Gutter 3.08 308.00
76119 170 Sq. Ft. Drive .81 137.70
$ 677.70
PROJECT NO. 104-24000-205, UNIT 5: KELROY STREET FROM TRENTMAN STREET TO MILLER AVENUE,
CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
SOUTH SIDE OF STREET TRENTMAN CITY ADDITION
E. H. Carter E. 16 50' Pavement $2.32 $116.00
3906 Kelroy St. of 5 Res. 50' Curb & Gutter 3.08 154.00
76119 85 Sq. Ft. Drive .81 68.85
$ 338.85
Trentman Avenue 1 & 16 212.4' Pavement $2.32 $492.77
Baptist Church W. ' Res. 212.4' Curb & Gtr. 3.08 654.19
5401 Trentman St. of 5 192.4' Sidewalk 2.76 531.02
76119 155 Sq. Ft. Drive .81 125.55
$1,803.53
COST TO PROPERTY OWNERS - ASSESSMENTS . . . . . . . . $14,747.72
COST TO CITY OF FORT WORTH . . . . . . . . . . . . .. 23,794.61
TOTAL ESTIMATED CONSTRUCTION COST, UNIT 5 . . . . . . $38,542.33
- y - City of Fort `worth, 'rexas
UNK
MORMIS Mayor and Council Communication
TDSES
DATE REFERENCE SUBJECT: Final Payment - Assessment Pav- PAGE
GRAHAM NUMBER ing at Five Locations on the Southeast �
6/7/71 or T
FP-806 Side
Final Council action on the project described below is requested.
Project Description
Name: Assessment Paving at Five Locations on the Southeast Side,
Project No. 104-24000-205
Contractor: Austin Road Company
Contract Awarded: July 20, 1970 (M&C C-1789)
Work Order Issued: November 20, 1970
Work Order Effective: December. 1, 1970
Date of Final Inspec-
tion and Approval: March 30, 1971
Working Time Bid: 85 Working Days
Working Time Used: 48 Working Days
Project Cost and Financing
Original Bid Price: $93,193.00
Final Construction Cost: $90,763.54
Less Deficient Paving Penalty
on Unit I, Erath Street: $ 98.56
Final Contract Cost: $90,664.98
Partial Payments Previously Made: 4, Amount: $81,389.06
Final Payment Due: $ 9 ,275.92
Payment is to be made from Project Account No. 104-24000-205. Sufficient funds
are available.
Deviation from Bid Price: The final cost of this project is $2,429.46 less
than the original bid price. This under-run is attributable to minor varia-
tions between quantities estimated in the contract documents and quantities
actually measured and used at the job site.
Compliance with Specifications
During testing on this project 32 corings were made with the following results:
Units 1 through 4 (22 corings)
Exceeds Even with -Below Specs but Below
Specs Specs within Tolerance Tolerance
Paving 19 0 2 1
Sub-grade 6 16 0 0
On Units 1 through 4 the average thickness of the BMAC paving is 6.56 inches as
compared to the 6.00 inches specified, and the average thickness of the cement
stabilized sub-grade is 6.05 inches as compared to the 6.00 inches specified.
DATE REFERENCE SUBJECT: Final Payment - Assessment Pav- PAGE
NUMBER ing at Five Locations on the Southeast 2 2
6/7/71 FP-806 Side of
Unit 5 (Kelroy Street) (10 corings)
Exceeds Even with Below Specs but Below
Specs Specs within Tolerance Tolerance
Paving 8 0 2 0
Sub-grade 3 7 0 0
On Unit 5 the average thickness of the reinforced concrete paving is 5.45 inches
as compared to the 5.00 inches specified, and the average thickness of the
cement stabilized sub-grade is 5.06 inches as compared to the 5.00 inches
specified. The contractor is paying a $98.56 penalty for paving in the area
that had the core shown as "Below Tolerance". Tests made during construction
show that materials used were in compliance with contract specifications.
Recommendations
It is recommended that the project described above be accepted by the adoption
of an ordinance and that final payment of $9,275.92 be authorized to
Austin Road Company.
RNL/je
SUBMITTED BY: DISPOSITION OUNCfL: PROCESSED BY
-PROVED Q_OT;HER (DESCRIBE)
CITY SECRETARY
DATE
CITY MANAGER