HomeMy WebLinkAboutContract 50411-CO4 COY SECREfAF'c'r
FORT WORTH® City of Fort Worth CONTRACT NO. Soy 11--C04
Change Order Request Breakdown
Project Namel Six Points Urban Village Streetscape Improvements City Sec# 1 50411
Client Project#(s)l 00705
Contractorl The Fain Group,Inc. PM I Wilma Smith Inspectorl Habte A.Taezaz
Change Order Submittal# ® Date 7/1612019
Contract Time
Dept. TPW Totals D
Original Contract Amount $2,357,709.60 $2,357,709.60 214
Extras to Date $99,273.17 $99,273.17 30
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $2,456,982.77 $2,456,982.77 244
Amount of Proposed Change Order $200152.66 $200,152.66 35
Revised Contract Amount $2,657,135.43 $2,657,135.43 279
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0,00
Additional Funding(if necessary) $200,152.66 $200,152.66
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS Y.OF ORIGINAL CONTRACT 12.70 a
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+2591.) $2,947,137.00
The bid documents included a bid item for the contractor to install 4"PVC Conduit along the roadway. The 4"PVC Conduit is to be used by AT&T after the contractor
completes the roadway project. AT&T will relocate their overhead communication lines to underground using the 4"PVC Conduit. The project requires additional 4"PVC
conduit to provide the necessary conduit for AT&T to relocate their overhead lines to underground.It was decided to have the roadway contractor install the 4"conduit to
avoid incurring the cost of requiring AT&T to install temporary pavement.
The owner would like to revise the location of the irrigation controller. This revision requires additional conduit(bored)and conductor to accommodate this change paid for as
electrical power for irrigation controller by this change order. The landscaping and irrigation design has been revised as directed by the City Parks and Recreation
Department. Minor drainage improvements are added by this change order to accomodate roof drain outfalls by an adjacent developement. Concrete staining has been
added along a step to increase contrast between the sidewalk,step,and curb to create a safer pedestrian environment. One decorative Berry Style light pole was added to
the quantities. The original bid quantities for the decorative light poles where one light pole short.
u
OFF10AL RECORD
C11Y SECRETARY
FT WORTH,TX
City of Fort Worth
Change Order Additions
Project Name Six Points Urban Village Streetscape Improvements City Sec# 50411
Client Project# 00705
Contracto The Fain Group,Inc. PM Wilma Smith Inspector Habte A.Taezaz
Change Order Submittal# Date 7I16/2019
AUUI I IONS
DI
ty nit nit ost ole
Conduit c
Remove Existing Water Meter
Electrical Power for Irrigation Controller
Stain Concrete(Surlace Application)
Plant Material(45 Gal)(Tree)
ver oc ggregate
Black Basalt Rock Aggregate
rigation System Revisions
Black tee ging x
Remove Existing Tree and Dispose
12 Mobilization
Drainage System at Hoof Drain ou a slocations)
Remove and Replace a ree
15 umis nstaBe"Polean ummaire
on
TPW $206,548.66
Sub TotalAdditions
Change Order Additions Page 2 of 4
FORTWORTH City of Fort Worth
�v--- Change Order Deletions
Project Name Six Points Urban Village Streetscape Improvements City Sec# 50411
Client Project# 00705
Contractor The Fain Group,Inc. PM Wilma Smith Inspector Fable A.Taezaz
Change Order Submittal# ® Date 711612019
ULLEI IONS
ty Unit Unit Cost Total
Plant Material(3 Gal)(Shrub)
ant Material(I Gal)(Shrub)
TPW $6.396.00
Sub TotalDeletions
Change Order Deletions Page 3 of 4
MISBE Breakdown for this Change Order
MISBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
g AUTOOESK'BIM 380' fortworthgov>C00705-1-Urban Villages Central Cluster-Six Points 0 CA
Document Management FOLDERS REVIEWS TRANSMITTALS ISSUES
Reviews > Review detail
CLOSED # Change Order Approval Workflow
Gppt Ryon This review is closed
Na_ Descriptl_ varsl_ Mark_ PROGRESS
® DOC-000705-CO No 4 Six Points Urban Village Streetsci_ -- V1 0
Initiator Instal Review n
CA Chad Allen Oct 28,IL-02 AM
<chad.allen0fortworthtexai.gov.
submitted to Reviewer
Reviewer I Initial Review I
V:OR
A` r ® NS Noel Sanchez Oct29,BA2 AM
<nsanchez®faingp.com>
^; •''� �.q�,`F. Submitted to Reviewer
IL
A b •Sr f Reviewer 2 Initial Review 2
e .2 ly r LA Lissette Acevedo Oct 29,432 PM
<liasetteacevedo®f0rtworthtM2.g0vr
ary J. se City Secretary
_ t,,},„: Submitted toReviewer 3
� �"� approved
R
Reviewer 3 Initial Review 3
M&C a ►°I•o ab 3 I o p/19 LP Lauren Prieur Oct 29,4,"PM
.Iauren.prfeurefortworthtexas.gov>
1 /��a..e � Submitted to Reviewer 4
L 5 �� Nocomments.
Reviewer 4 Initial Review 4 n
W3 Wiliam Johns_ Oct 30,442 PM
<wiiDam.lohnson @rortworthtwm&gov-
Submitted to Reviewer S
No further comments
Revlewsr5 Initial RwAaw5 n
DB Douglas Bla_ Nov 6,259 PM
<doug.blackefurtworthtems.gov.
L� � CjCQ`,�! SubmittXoroverisamresnMiC.therearrovpagesanth.
.documeproved by tagal.
Approver Final Review n
DE) Dana Burghdoff Nov Iz 334 PM
<dana.burghdofTlfortworthtexas.gov-
Review ended
Review closed
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH,TX
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA FORT
REFERENCE **M&C 19- 20SIX POINTS URBAN
DATE: 10/22/2019 NO.: 0263 LOG NAME: VILLAGES STREETSCAPE
CHANGE ORDER NO. 4
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Change Order No. 4 to City Secretary No. 50411 with The Fain Group, Inc., in
the Amount of$200,152.66 for the Urban Villages Central Cluster Project in The Six
Points Urban Village on Race Street between Grace Avenue to Holden Street for a Total
Contract Amount of$2,657,135.43 (COUNCIL DISTRICT 9)
RECOMMENDATION:
It is recommended that the City Council authorize Change Order No. 4 to City Secretary No. 50411
with The Fain Group, Inc., in the amount of$200,152.66 for the Six Points Urban Village Project, plus
35 days, thereby increasing the total contract amount to $2,657,135.43 (City Project No. 00705)
DISCUSSION:
On January 23, 2018, (M&C C-28544), the City Council awarded a construction contract with The Fain
Group, Inc., in the amount of$2,357,709.60, for the construction of improvements through the Urban
Villages Central Cluster Project in the Six Points Urban Village between Grace Avenue and Holden
Street.
Construction began on the project on April 23, 2018. As shown in the table below, there have been
three change orders approved to date totaling under$100,000 for various items. The purpose of this
M&C is to authorize Change Order No. 4 to add the following items identified during construction.
Additional conduit was required along Race Street to accommodate AT&T utility relocation. The
original amount in the bid proposal was insufficient to accommodate the relocation of AT&T overhead
lines to buried underground lines due to pedestrian requirements. The conduit runs from the service
pedestal located on the north side of Race Street approximately 500 feet east of N. Blandin Street to
the irrigation controller which is located on the south side of Race Street nearly adjacent to the service
pedestal.
As a result of the utility relocation work delay, additional quantities for temporary paving were needed
and installed in four areas. The contractor could not complete all the concrete work where utility poles
were located, hence the installation of temporary paving. The delays resulted in:
The city not receiving the estimated cost for the relocation from AT&T in a timely manner
The execution of the discretionary service agreement, and
Issuing payment to AT&T in order for them to proceed with the design and the relocation work
In addition to the changes for the utility work, refinements were made to the landscaping plan that
would revise the plant spacing to avoid over growth, as well as to the plant species to meet Park and
Recreation Department requirements since they will assume responsibility of the maintenance after
the two year establishing period.
The installation of two roof drains by an adjacent development were installed too low which resulted in
water flowing and damaging the planting beds. The City corrected this issue by installing an area
drain directly in front of the outfall, preventing the water from flowing directly into the planting beds.
There are various areas along the north side of Race Street that require a step one foot behind the
curb to accommodate drainage and ADA compliant grades. The area between the step and the back
of the curb was stained red to provide an increase in pedestrian awareness of the change in grade.
The following is a summary of all the Change Orders to date:
I- JAmount IlDays JIM&C No. IlApproved IlDescription
OriginalOriginal
g $2,357,709.60 214 C-28544 1/23/2018 C a
Contract
Change Add
Order#1 $141714.44 0 Administrative 7/6/2018 Construction
Staking
Add new water
meters and
boxes,
Change add ROW prep,
Order#2 $66,466.79 0 Administrative 10/4/2018 provide
temporary
access to
businesses in
the area.
Remove a
quantity of the
Change flex base, add
g $18,091.94 30 Administrative 4/4/2019 Handrails, trench
Order#3 drain, relocate
Metal fence
and gate.
Add conduit
required for utility
relocation,
irrigation
controllers, install
temporary
pavement
required by AT&T
Change
$200,152.66 35 - Pending delay,
revised the
landscaping
plans,
accommodate
roof drains by
developer, and
add safety
measures.
Total1$2,657,135,43]1 279
The TPW staff has reviewed and verified the quantities for the additional work under this Change
Order No. 4. Additionally, to complete this work, staff recommends that the contract time be extended
by a total of 35 calendar days.
M/WBE OFFICE: THE FAIN GROUP, INC, is in compliance with the City's DBE Program by
committing to an additional 7\% DBE participation on change order no. 4. The TxDOT DBE goal on the
entire project is 7\%.
These projects are included in the 2014 Bond Program. Available resources within the General Fund
will be used to provide interim financing until debt is issued. Once debt associated with the project is
sold, bond proceeds will reimburse the General Fund, in accordance with the statement expressing
Official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election
(Ordinance No. 21241-05-2014) and subsequent actions taken by the Mayor and City Council.
This project is located in COUNCIL DISTRICT 9.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendation, funds are
available in the current capital budget, as appropriated, in the 2014 Bond Program Fund. Prior to any
expenditure being incurred, the Transportation & Public Works Department has the responsibility to
validate the availability of funds.
TO
Fund Department Account Project Program Activity Budget Reference# Amount
I I ID Year Chartfield 2
FROM
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year Chartfield 2
Submitted for City Manager's Office by: Dana Burghdoff(8018)
Originating Department Head: William M. Johnson (7801)
Additional Information Contact: Lissette Acevedo (2722)
ATTACHMENTS
C00705 SIX POINTS IMPROVEMENTS MAP.pdf