HomeMy WebLinkAboutContract 51701-CO1 CITY SECRETARY
FORTWoRTH, City of Fort Worth
CONTRACT NO. 5 17 01-GO I
Change Order Request
Project Namel FY 16 CD9 Street Repair and Reconstruction City Sec# 1 51701
Client Project#(s)l CO2387&CO2445
Project Description FY 16 CD9 Street Repair and Reconstruction Program and Near Southside Medical District Water and Sanitary Sewer
Main Improvements
Contractor Jackson Construction Ltd Change Order# Date 10/23/2019
City Project Mgr.J Mary Hanna City Inspector Martina Salinas
Dept. Water Unit 1 Sewer Unit 2 TIPW Unit 3 Contract Time
Totals WD
Original ContractAmount $3,130,449.75 $422,758.00 $2,618,148.25 $6,171,356.00 430
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $3,130 449.75 $422,758.00 $2,618148.25 $6,171,356.00 430
Amount of Proposed Change Order $38,811.90 $0.00 $0.00 $38,811.90 30
Revised Contract Amount $3,169,261.65 $422,758.00 $2,618,148.25 $6,210,167.90 460
Original Funds Available for Change Orders $156,522.00 $21,138.00 $130,907.00 $308,567.00
Remaining Funds Available for this CO $156,522.00 $21,138.00 $130,907.00 1 $308,567.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.63%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) 7,714,195.00
While placing the box tunnel for the new 30"water line in Vickery Blvd,the Contractor encountered existing fiber optic lines that were in conflict
with the tunnel alignment for an approximate distance of 70 LF.The Contrac r these fiber lines and moved them to the top of the
tunnel. OR
x ,
Atte
airy J. . r City Secretarry
7 �
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below
acknowledges that helshe is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
Gonlractors;Gom an ,Namme. Corit�actot Name . ContradlIsl r,t 61)/"
Jackson Construction Ltd
-`I 's` ectorflns "ctronSu`ervi`sot .Date; �Pr cttVt' a edPro�am'Mana er:' i: �, Date:. .,
Assistant�Dir�tor be t` Date: a o�;,C ra' t" De"artmetit De t Date:,;,;
Ass ' Date Assistant (t Mari r:.:, Da
Council Action if re uired
M&C Number NIA M&C Date Approved
F6Rr_-�)RrN City of Fort worth
Change Order Additions
Project Name FY 16 CD9 Street Repair and Reconstruction City Sec# 51701
Client Project# CO2387&CO2445
Project Description FY 16 CD9 Street Repair and Reconstruction Program and Near Southside Medical District Water and Sanitary Sewer Main
Improvements
Contractor Jackson Construction Ltd Change Order# 0 Date 1072372619
City Project Mgr. Mary Hanna City Inspector Martina Salinas
ADDITIONS
y unit Units o a
1- Existing Utility Adjustment Fn-7 tunnel Water Unit L
Water Unit 1 38,811.90
Sewer Unit 2 $0.00
TIPW Unit 3 $0.00
otal Additions
Change Order Additions Page 2 of 4
eOR._ Tz H City of Fort Worth
Change Order Deletions
Project Name FY 16 CD9 Street Repair and Reconstruction City Sec# 51701
Client Project# CO2387&CO2445
Project Description FY 16 CD9 Street Repair and Reconstruction Program and Near Southside Medical District Water and Sanitary Sewer Main
Improvements
Contractor Jackson Construction Ltd Change Order# 0 Date 1 012 3/2 01 9
City Project Mgr. Mary Hanna City Inspector Martina Salinas
DELETIONS
y Unit Units o a
Water Unit 1 0.00
Sewer Unit 2 $0.00
T/PW Unit 3 $0.00
Sub 1 otal Deletions
Change Order Deletions Page 3 of 4
MWWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
NIA
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
None
Total $0.00
Circle H Contractors, LP
CIRCLE P.O.Box 220/1550 W FM 875
CONTRACTORS L.P.
Midlothian,TX 76065
972-723-0802
BORING B UTILITIES www.circlehcontractors.com
Near Southside Medical District
Water & Sewer Main Improvement
Explanation of conflicting fiber optic duct run.
While placing the wood box tunnel for the 30 inch water line Circle H crew
encountered an inner duct package that encroached the alignment. The tunnel started
at station 5+53 going west to station 2+29. At approx. station 4+45 the inner duct
started to appear in the face on the right side at our 2:00 o'clock. The package had
eight, one inch and quarter pipes that were bundled together in a horizontal
directional boring hole. As Circle H continued to progress forward, the package
started to move across the middle of the tunnel making it very difficult to work
around. At this point, Circle H was directed to ring cut the pipes being very careful
not to damage the 3 fibers. With having the pipes cut, Circle H went to the hand
holes on either end of the inner ducts and gained slack on the fibers. With having
slack on the 3 fibers and the empty inner ducts, we moved them to the top of the
tunnel as we continued to progress forward. At approx. station 3+75 the package had
moved all the way across the tunnel and were no longer in the crews' way. The
seventy feet that the package was in conflict, our production went to half of what it
was prior.
Blake Norwood
blake@circleheontractors.com
214-202-5478
Jackson Construction, Ltd. County: Tarrant
City: Fort Worth
Change Order Request Project: FY19-CD9
Date: 27-Jul-19
Revised: 16-Sep-19
Item M Description Quantity I UM Bid Price Amount
'Lost of production in 4V tunnei due to
,communication cable conflict. 1.000I LS i $ 38,812.50 $ 38,812.50
1 $
10ur subcontracftors products T was reduced from
116 U Wday to 7 U per day when the communication
Icable was exposed within the alignment of the tunnel.
-fOur subcontractor was able to"interduct the lines
rthat had fiber present in order to gain slack and cut 'I
I away the empty ones. ; $
I
Half daoon were the w ---1 $
June 1 Oth-June 15th un
J -
J;17th-June 19th - I
1 $
PLEASE SEE ATTACHED EXPLANATION
$
Additional Days Requested:Seven(T), $
$
$
$
$
$
$
$
$
Total $ 38,812.50
Pige 1 of 1 9/16/2019 7:11 AM
JACKSON CONSTRUCTION LTD.
Force Account Daily Time and Material
County Tarrant City Fort Worth Phase Project FY16-CD9,South0%Medical District
Description of Work: Ste Suntrnay Page&eviarldonaf COW&
Date: 27-Jul-19
EQUIPMENT Labor
Description Hrs Rate Amount Reg.HoursO.T. Reg.
i!�O�.T
Amount
KOMATSU PC450 EXCAVATOR 45.00 $ 176.82 $ 7,956.90 1 SUPERINTENDENT 45.001 $ 46.00 $ - $ 2,070.00
DEERE 444K LOADER 45.00 $ 73.23 $ 3.295.35 (1)FOREMAN 45.001 $ 32.00 $ $ 1,440.00
MULTI GENERATOR 65KW 45.00 $ 51.79 $ 2,330.55 1 LOADER OPERATOR 45.001 $ 20.00 $ - $ 900.00
BIG BOSS BLOWER 45.00,$ 26.69 $ 1,201.05 1 BACKHOE OPERATOR 45.00 $ 21.00 $ - $ 945.00
SULLAIR 375 HD COMPRESSOR 45.00 $ 29.25 $ 1,316.25 2 HAMMER OPERATOR 90.00 $ 19.50 $ - $ 1,755.00
POWER UNIT 45.00 $ 47.00 $ 2,115.00 2 SKILLED LABORER 90.00 $ 18.00 $ - $ 1,620.00
2 TRENCH BOXES 45.00 $ 31.00 $ 1,395.00 $ - $ -
4 STEEL PLATES 45.00 $ 20.00 $ 900.00 $ - $ -
$ - $ - $ -
$ - $ - $ -
I $ - $ - $ -
$ - $ - $ -
$ - $ - $
$ - $ - $ -
$ - $ - $
Sub-Total $ 20,510.10 Sub-Total $ 8,730.00
15% $ 3,076.52 55% $ 4,801.50
Total Equipment: $ 23,586.62 15% $ 1.309.50
Total Labor: $ 14,841.00
Material Subcontract
Description Quantity UOM Rate Amount Quantity UOM Rate Amount
$ - $ -
Sub-Total $ - Sub-Total $ -
15% $ - 5% $ -
Total Material: $ - Total Subcontract: $ -
Summary
Approved: Date 07/27/19 Labor $ 14,841.00
JACKSON CONSTRUCTION LTD. Equipment $ 23,586.62
Date Material $ -
Subcontract $ -
Bond 1% $ 384.28
JACKSON CONSTRUCTION JOB t 3222 Total This Sheet $ 38,811.90
9/16/2019 7:12 AM
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Ct✓ /
Name f Employee/Signature
Sr.
Title
❑ This form is N/A as No City Funds are associated with this Contract
Printed Name Signature
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH,TX