Change Order Request
Project Namel HAMMOND STREET DRAINAGE IMPROVEMENTS City Sec# 1 51290
Client Project#(s)l 000488
Project Description DRAINAGE IMRPOVEMENTS ON HAMMOND STREET AND TIMOTHY DRIVE.
Contractorl WOODY CONTRACTORS,INC. Change Order# 0 Date 11/12/2019
City Project Mgr.J MICHAEL WELLBAUM City Inspector r7WOMAS MILLER
Dept. TPW Water Sewer Contract Time
Totals WD
Original Contract Amount $1,678,034.62 $651,771.83 $488,050.00 $2,817,856.45 330
Extras to Date $736,600.84 $178,865.77 $150,659.97 $1,066,126.58 150
Credits to Date $399,316.00 $80,000.00 $60,000.DO $539,316.00
Pending Change Orders(in M&C Process)
Contract Cost to Date $2,015,319.46 $750,637.60 $578,709.97 $3,344,667.03 480
Amount of Proposed Change Order $58,343.00 $0.00 $0.00 $58,343.00 0
Revised Contract Amount $2,073,662.46 $750,637.60 $578,709.97 $3,403,010.03 480
Original Funds Available for Change Orders $83,901.00 $32,589.00 $24,403.00 $140,893.00
Remaining Funds Available for this CO 1 $0.00 1 $0.00 1 $0.00
Additional Funding(if necessary) 1 $58,343.00 1 1 1 $58,343.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 20.77%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $3,522,320.56
This change order is needed for the following: 1)to provide for an unforseen water line lowering to avoid a conflict with the new storm drain line;
2)to provide for the installation of grout in an abandoned storm drain line as a condition precedent to obtaining a drainage easement;and,3)to
provide for an alternative paving option for a parking lot with no net cost increase.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The ProjectlProgram Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
_pqry"ct Signature Da e
WOODY CONTRACTORS,INC. 1 7r4 n/0 vJ I
Ins ct6rAn ction%pervisor _ Date ``c f�i'p'a ra Man. er_ - _Daio
Ass[stanll Director(Dept). Data r Contra De artment Drot)
DatQ_ _
Milo AssistantCi Manager Data.
` Council Action if required)
-- -
M&C Number M&C Date Approved CORD
FTYWORTH,TX
cu . . . . . . . _
o °
m
# , m
/
CD
� m
o /
k
n \ C) C=> =�'. . C� C� C=! C� C�
CD CD C) CN CD CD
# _
$
6
k \ k /
h 6 / C14
o \ a
L.o � §
� 7 k / 4-
<04) L /
B
LL e ƒ « �5
0D \ 2
& LU k \
� 0 \ to
M 2
U i ƒ
f
\ / \
J w %
e 3 / u
L o o < §
/ - LL
e k R $LU
o cu
\ \ \ / ° � \ ( S S
k \ \ 2 / § § / � cu
0)
_ ~ # a § = 2 F 2 =
¥ o f - h E » � # LL
§ E q ® & e E 2 \ g o a 2
� 8 # k � \ o (1) ca b a t
3 ° _ « b Q 7 »
E / e . 0) t@ C— o
w = — / o r 2 - / % 5 = 0 , 0=
§ & C e E � o G o e c
co to co co cn cc co
rrr
0 0 0
Loo0
m E» vs
Ict
06
M
C
O
� 3
0
0
m
v
w
ra
a
c
0
=a
v
Q
v
v
O
01
ao
c
ra
s
U
m � �
o °
m
Li
\
m • -
f - -
A )
G °
3
i -
/
n \
f \ C:)
C)
. .
*
6 �
LO
Li
c ° �
/ c C %
� / � �
■ » °
tio
� .0 / 2
o �
0 J §
� p 9 ¥ \
w
0 � � LLJ
/
2 in cu
C) \LL \
O
�_ & w k G
M 0 \
U i ƒ
f cj
\ /
3
w
E 0 C) <
\ k z w
k $ E _ § Co
\ / / / ƒ G r
7 / § 2 k ffi >
# r_
} Li Li
2
/ °r n
: \ / /
_ 5
2 C) 4 G
Lo
0 0 0
GV O O 14
� Eft Vy
O
co 30
C
O
d
a co
U) m
0
Lj
O
V1
v
to
co
a
C
O
N
N
N
O
v
on
c
ca
t
U
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
LIONS GATE TRUCKING $1,500.00
Total $1,500.00
Previous Change Orders
Co# DATE AMOUNT
None
Total $0.00
"- `" City of Fort Worth
ACCEPTANCE OF PREVIOUS MBE COMMITMENT FORM
(for use with CHANGE ORDERS or AMENDMENTS greater than$50,000)
To be Completed by City Project Manager
Change Order(for Construction Contract)
Project Name: City Project Number
C00488
Hammond Street Drainage Improvements
City Project
Manager
Contractor: Michael Wellbaum
Woody Contractors, Inc. City's MBE Project Goal: 25
Original Amount of Contract: $2,817,856.45 Accepted MBE Commitment: 8 %
Total of Previous Change Order: $526,810.58 Date of Last MBE Report: 10/31/2019
Amount for this Change Order: $58,343.00 Change Order#: 3
Revised Amount of Contract: $3,403,010.03 Date: 11/14/2019
Language to be inserted in the M&C for this Contract
Woody Contractors, Inc. agrees to maintain its initial MBE commitment of 8% that it made on the
original contract and extend and maintain that same MBE commitment of 8%to all prior change
orders up to and inclusive of this Change Order No. 3. Therefore Woody Contractors, Inc.
remains in compliance with the City's BDE Ordinance and attests to its commitment by its
signature on the Acceptance of Previous MBE Commitment form executed by an authorized
representative of its company.
To be Completed by the Representative of the C7nv //
Troy Woody President -/ -1 9
Printed Signature Title Authorize 'gna e
Woody Contractors, Inc.
Company Name Contact Name(if different)
650 Tower Drive twoody202O@aol.com
Address E-mail address
Kennedale,TX 76060 817-483-4787 817-483-2048
City/State/Zip Phone number Fax Number
142% as of 10/31/2019
MBE% Paid to Date Date
City Project Manager has reviewed the work associated with this Change Order,
considers it the same or similar to work in the on inal Contract, and recommends that the
Contractor have the option to retain f' m ' ex' t' MBE commitment.
Michael Wellbaum 11/15/2019
City Project Manager City P ject Manager Signature Date
Attach Compiete Change Order Documentation
To be . • - • by . •
Tasha Kilgore 600539 25%
M/WBE Compliance Staff ID# MBE Current% Level via Last Report Rec'd
Tasha L. Kilgore Digitally signed by Tasha L.Kilgore
Date:2019.11.19 11:05:54-06'00' 11/19/19
M/WBE Signature Date
12/9/2019 BIM 360 Document Management
7 AUTODESIC DIM 360 fortworthgov>00488-Hammond Street Drainage Improvement- o MW
•�� Document Management FOLDERS REVIEWS TRANSMITTALS ISSUES
Reviews > Review detail
CLOSED #21 Allowance and Change Order Request
Export Report - This review is closed.
Name A Description Version Markup Om PROGRESS
p 2019.11.12-00488 CO3-FINAI-xIsm -- VI 0 No c
Initiator Initial Review n
2019.11.12-00488 CO3-FINAL Pdf.Pdf -- VI 0 NO c TW Troy Woody Nov 20,1:11 PM
191119_Woody APCFff3_20191118_1020- -- VI 0 No c <twoody202O@aol.com-
Submitted to Reviewer 1
Reviewer 1 Initial Review 1(6/6 submitted)n
MW Michael Welibaum Nov 20,3:22 PM
-mwellbaum @westraconsultants.com-
Submitted
I recommend approval of this Co
p3
TM thomas miller Nov 22,2:39 PM
<thomas.miller@fortworth texas.gov>
Submitted
good
MW Michael Wellba-. Nov 25,10:00 AM
<mwelibaum@westraconsultants.com.,
Submitted
Additional Inspector reviews not
required.
MW Michael Wellba-. Nov 25,10:01 AM
<mwellbau m @westraconsultants.com=
Submitted
Additional Inspector reviews not
required.
MW Michael Wellba-. Nov 25,10:02 AM
<mwellbau m @westraconsultants.com
Submitted
Additional PM reviews not
required.
LY Linda Young Nov 27,3:58 PM
<li nda.you ng@ fo rtworthtexas.gov>
Submitted to Reviewer 2
approve
Reviewer2 Initial Review 2 n
MW Michael Welibaum Dec2,9:01AM
<mwel lba u m @ westraconsu Ita nts.com,
Submitted to Reviewer 3
This position/role is vacant and
OFFICIAL RECORD therefore no review is required.
� Michael Show more
CITY l/ YlN SECRETAR'f
rc Reviewer 3 Initial Review 3 n
FT,
i
"- LP Lauren Prieur Dec 2,10:03 AM
<lau ren,prieu r @fortworth texa s.gov,
Submitted to Reviewer 4
No Comments
https://docs.b360.autodesk.com/projects/4ae74e8a-8be5-4383-84eO-2beb3d33e873/reviews/4b99835d-1 d77-4275-96ae-dOcdaf72484b 1/1
12/9/2019 BIM 360 Document Management
y AUTODESK BIM 360 t rtworthgov>00488-Hammond Street Drainage improvement- A MW
Document Management FOLDERS REVIEWS TRANSMITTALS ISSUES
Reviews > Review detail
CLOSED #21 Allowance and Change Order Request
Export Report , This review is closed.
NameA Description Version Markup Om PROGRESS
MW Michael Wellba— Nov 25,10:01 AM -
p 2019.11.12-00488 CO3-FINALxIsm -- VI 0 Noc
<mwelibaum@westraconsuitants.com.
0 2019.11.12-.00488 CO3-FINAL pdf.pdf -- V1 0 Noc Submitted
Additional Inspector reviews not
required.
191119_Woody APCFM3 20191118_1020_ -- VI 0 Noc
MW Michael Wellba-. Nov 25,10:02 AM
<mwellbau m @ westraconsulta nts.com;
-+...� Submitted
G Additional PM reviews not
�O3 FOR' required.
LY Linda Young Nov 27,3:58 PM
V t• <linda.young@fortworthtexas.gov>
S Submitted to Reviewer 2
approve
atte4 by: 'j� .r
�• Reviewer Initial Review n
J ' As
/ i ... MW Michael Wellbaum Dec 2,9:01 AM
�(
fi r q <mwellbaum@westraconsultants.com=
T
Mary d• K a, 1 Y�� Submitted to Reviewer 3
This position/role is vacant and
therefore no review is required.
Michael Show more
Reviewer 3 Initial Review 3 n
LP Lauren Prieur Dec 2,10:03 AM
<lau ren.prieu r@fortworth texas.gov
Submitted to Reviewer 4
No Comments
Reviewer4 Initial Review4 n
W3 William 3ohnson Dec 2,1225 PM
<wllliam.joh nson@fortworthtexas.gov:
Submitted to Reviewer 5
Reviewers Initial Review 5 n
DB Douglas Black Dec 5,4:03 PM
<doug.blac k@fortworthtexa s.gov>
Submitted to Approver
Rejected because no signatures are
on the change order.Minimum Is
contractor,inspector and project
manager. ,
Approver Final Review n
® DB Dana Burghdoff Dec 6,6:02 PM
<da na.bu rg h doff@ fortwo rthtexas.gov>
Review ended
Review closed
https://docs.b360.autodesk.com/projects/4ae74e8a-8be5-4383-84e0-2beb3d33e873/reviews/4b99835d-1 d77-4275-96ae-dOcdaf72484b 1/�
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
10
Name of Employee Signature
Project Manager
Title
❑ This form is N/A as No City Funds are associated with this Contract
Printed Name Signature
'�FNUAL RECORD
CITY SECRETARY
ET WORTH, TX
Soto, Vania Elizabeth
From: Black, Doug
Sent: Thursday, December 12, 2019 12:29 PM
To: Soto, Vania Elizabeth
Cc: Wellbaum, Michael
Subject: RE: Question about Change Order No. 3 to CSC No. 51290
Dana's signature overrides any omissions. It should be good to go.
Thanks,
Doug
From:Soto,Vania Elizabeth
Sent:Thursday, December 12, 2019 11:42
To: Black, Doug<Douglas.Black@fortworthtexas.gov>
Subject: Question about Change Order No. 3 to CSC No. 51290
Importance: High
When you approved this change order your comment(page 9) states that you Rejected because no signatures are on the
change order. Minimum is Contractor, Inspector, and Project Manager. Per Page 1 the Inspector is not on there. But since
it went to Dana for approval as well I am just trying to make sure it is good to go or if it needs to go back to the
department to get the Inspector signature?