HomeMy WebLinkAboutContract 51375-CO1 S'( 37S T S.
17-
City of Fort Worth CITY SECRETARY
Change Order Request (�ON'1P,�G NO.
roject Nanne:1 Lake Worth Dam Improvements Project City Sec No.: —4Br19`7� 1 S
Project No.(S):l FTw16591 DOE No. City Proj.No.: 100543
Project Description: Conduct slope restoration as required by TCEQ,clear the spillway underdrain piping system,provide a riew manhole drain
improvements and weir box for measurement purposes,rehabilitate concrete spall,and crack repairs to the spillway
Contractor; Welch Excavation and Utility Company Change Order# Date: 6/29/2019
City Project Mgr.1 John Lopez City Inspector; I Ron Rackley
Phone Number: 817-392-6818 Phone Number: 817-392-6950
Dept, Facility Totals Contract-Thine
(Calender days)
Original Contract Amount $363,960.00 $363,960.00 180
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date . $363,960.00 $363,960,00 180
Amount of Proposed Change Order 157
Revised Contract Amount $363,960.00 $363,960.00 337
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding(If necessary) II
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $454,950.00
JUSTIFICATION(REASONS)FOR CHANGE ORDER
The additional days needed are due to water flowing over the spillway that prevented work to be performed as directed by the City of Fort
Worth Water Department. Staff also concures with contractors request for the addition of 157 Calendar Days be added to the project.
6 .Atte
� yy
tM J. a•, City secrotaxy
I
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes ccord a d-sa faction and represents payment
in full(both time and money)for all costs arising out of,or Incidental to,the above Change Orde
Contractor's Company Name Contractor Name Q4pffctor Si t e Pate
Welch Excavation and Utility Company Jeffery Pool
;i
Ins ec r Date Project Manager Date
7
DVoctor(WatelDepp — Date C nsiruction Supervisor—(Water Dept) Date
T S
Aol tant C't ttorne Date Assistant Ci nag r Dale
-
Council Action(If Required
M&C Number N/A M&C Date Approved NIA
RY
VVba—FI-]i City of Pori Worth
Change Order Additions
Project Name Lake Worth Dam Improvements Project City Sec No.: 48477
Project No.(s): FTW16591 DOE No. City Proj.No.: 100543
Project
Description drain improvements and weir box for measurement purposes,rehabilitate concrete spall,and crack repairs to the
Contractor Welch Excavation and Utility Company Change Order:0 Dale: 6/29/2019
City Project Mgr. John Lopez City Inspector Ron Rackley
ADDITIONS
- rw ES—C 2R]P1TO DEPT Ctry Unit I ffnit Cost Total
7 8"Sewer Pipe Sewer 2,963.00 LF $4200 $124,446.00
A 4'Manhole Seaver 21.00 EA $3,200.00 $67,200.00
21 Remove 4'Sewer Manhole Sewer 48.00 EA $800.00 $38,400.00
30 4"Sewer Service,2-Way Cleanout Sewer 100.00 EA $600.00 $60,000.00
33 4".Sewer Service,Private Relocation Sewer 295.00 LF $60.00 $17,700.00
47 Temporary Asphalt Pavin Repair Sewer 2,337.00 LF 1$16.00 $37,392.00
49 7"Conc Curb and Gutter Sewer 2,585.00 LF $25.00 $64,625.00
82 Warren Coating Sewer 242.00 VF $325.00 $78,650.00
51 11"Pavement Pulverization Paving 8,188.00 SY $5.00 $40,940.00
52 3"Asphalt Pvmt Type D Paving 6299.00 SY $19.50 $122,830,50
65 Cement Modification Paving 118.00 TN $150.00 $17,700.00 I
71 6"Conc Curb and Gutter Paving 170.00 LF $25.00 $4,250.00 fI
II _
I
i
i
i
it
i
Facility
Page 2 of 4 Additions Sub Total
I-`<�>_I T "TV(CD -FI-1 City of Fort Woi`ih
Change Order Deletions
Project Name F Lake Worth Dam Improvements Project City Sec No.: 48477
Project No.(s): FTW16591 DOE No. City Proj.No.: 100543
Project Description Conduct slope restoration as required by TCEQ,clear the spillway underdrain piping system,provide a new
manhole drain improvements and weir box for measurement purposes,rehabilitate concrete spall,and crack
Contractor Welch Excavation and Utility Company Change Order: F—, ] Date 6/29/2019
City Project Mgr. John Lopez City Inspector: Ron Rackley
DELETIONS
ITEM IDESCRIPTION DEPT I Qty Unit I Unit Cost —]Total
19 Epoxy Manhole Liner Sewer I 85.00 VF $185.00 1$15,725.00
39 Construction Allowance(Sewer) Sewer 1.00 LS $100,000.00$100,000.00
81 Construction allowance(Paving) Sewer 1.00 LS $27,788.70 $27,788.70
76 Construction allowance Paving 1.00 LS $72,211.30 $72,211.30
i'
li
I�
I
i
N
N
it
I)
I
Facility i
Page 3 of 4 Deletions Sub Total
MIUVBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co It DATE AMOUNT
Total $0.00
Page 4 of 4
Contract Compliance Manager
By signing I achowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
Signature
Name of Employee
Pr�ct /y1ti.,a J•rr
Title
i
i
i
Fr- UAL RECORD �I
t-U W SEMETARY
FT: WORTH,YX
i
Il�l�t+tgJitvet�lli.l�nrolir•r:�
r FREESE
L'Ia:1liotallaa:ulii:. —MIMICHOLS lol�fl:k_hNll�l{�1:In
4055 International Plaza,Suite 200 Fort worth,Texas 76109 • 817-735-7300 • fax 817-735-7491 w,vw.(reese.Luni
June 28,2019
Mr.John Lopez
City of Fort Worth
Water Department
200 Texas Street
Fort Worth,TX 76102
Re: Lake Worth Dam
Change Order 1
Dear Mr. Lopez:
Enclosed is a copy of Change Order 1 for a time extension from Welch Excavation and Utility Company for
the Lake Worth Dam Improvements project. As you are aware the Lake Worth spillway has been spilling
a significant portion of the first six months of the year. They are requesting a time extension to the end
of September. We have reviewed the subject request and recommend approval.
Please let me know if you have questions.
Sincerely,
�',Janis Murphy,P,E.
Enclosure
IFfWI65911 T;\4.0 CONSTRUCTION\4.10 Correspondence and Memos\4.11 Letters\Cliange Order 1 Recommendation rev.docx
And Utility '_ Company
—Inc.
,slhnalfll,l:••I'+1•Irhoxravalion.n.•I
June 27,2019
Janis Murphy
Freese and Nichols
2711 N Haskell Ave.Suite 300
Dallas,TX 75204
RE: Request for Extension of Lake Worth Dam Improvements Project: 100543 Contract Time
Janis,
Welch Excavation and Utility Company, Inc. is requesting an extension of the contract time to
September,30,2019 for the Cake Worth Dam Improvements Project: 100543.Due to the release of
water over the spillway,since October 29,2018,the date of the notice to proceed,water has been
flowing over the spillway for 127 days,as of the date of this request. Because of the release of water,we
have been unable to work on the spillway or underdrains at all. Please reference the USGS water surface
elevation graphs for each month of the project that show the amount of time the water elevation has
been over the crest elevation of 594.Welch understands that this project is very important to the City.
We plan to begin work as soon as the water stops flowing over the spillway and are committed to using
the necessary resources to get the project completed as soon as possible.
„. - _ __-1 ' f,'
Most I)ISIU)I Mv.1,40 I Troth.11 U;GS(IN).111tm,nh.Lrl)Y.-.It Uf93f))I58IUY1.L1;;IIV?m1Ix
s
ic, t`.. .4� /"'•..� fig
Yh. ldl X.
ml., ♦.L..,1-nun.•m s-,❑v - n.L. nax...... l,.•nn,la, — :RI;;;:. ,......... r.......... -
UScsCINI NLYlcrt Itvl)Y(alh It USLSLIMIIILLYln116,IMIA Is US4S IM$11)LLVun IV,IIT14%f9 _ -
:�..
wlr u,v wlm tluO,.wn.,•p Im _ •:,.,..uL•I:i',Up.:.Lpn— !n ,....—
.I,•�1�„ a ............ .....1... . . ,In..l,.,....•,A 1..
e •n Y••'.I,MI r n+,..,..r••111 rwl a
17190 1-20 fast,Winona,TX 75792
Phone 903-877-3528 Fix 903-877-3092
w\w\\,.wcichcxcavarion.nct
branclou(�I)wcictiexcavatiou.net
CHANGE ORDER (4.43)
NICHOLS
PROJECT: Lake Worth Dam Improvements
OWNER: City of Fort Worth OWNER PROJ It 100543
CONTRACTOR: Welch Excavation and Utility Company CONTRACTOR It
ENGINEER: Freese&Nichols, Inc. ENG,PROD.N F FW16591
CHANGE ORDER NO. 1 CHANGE ORDER DATE: 28-Jun-19
Make following additions/deletions or modifications to work described in the Contract Documents:
Extend the contract completion date to September 30,2019,in accordance with the attached request.
File compensation agreed to upon In this change order Is full,complete and final payment for all costs the Contractor may Incur as a result of or
related to tlds change Whether said costs are(mown,unlenown,foreseen or unforeseen at this time,Including without llmltatlon,any cost for delay,
extendedoverhead,ripple or Impact cost,or any other affect on changed or unchanged wade as result of this Change order.
Contract Cost and/or Time Impacts:
Original Contract Amount $363,960.00
Previously Approved Change Order Amount $0.00
Adjusted Contract Amount $363,960.00
Proposed Change Order Amount(this change order) $0.00
Revised Contract Amount $363,960.00
Previous Contract Time 180
Previous Substantial Completion Date 26-Apr-19
Previous Final Completion Date 26-Apr-19
Net Change in Contract Time 157
Revised Contract Time 337
Revised Substantial Completion Date 30-Sep-19
Revised Final Completion Date 30-Sep-19
Recommended by:
FREESE AND NI HOLS, INC
By ��.-+s ��' 1G Z7 �
Date
Approved by:
WE �, `eOAU !/D1T _ITY COMPANY
Y
a
Approved by:
CITY OF FORT WORTH
GVA EXCAVpr/off
And Utility Company
—Inc.
1z, �
n,11n+a11nq..w.ddu+xravatlnn.nel
—
0109(W0101UW,A.)vrlwflkIx Yi0111#1ISO M.•AA,F1Ww,%t1 YWiNMN1YllN..n.1./tWM.18
i.
.., ri. ai. A .. . ..., - .,,.....a.r�.a1,............. .... ,.,.
Sincerely!
^2� G�v�l
Russell Welch
Vice President
17190 I-20 Last,Winona,TX 75792
Phone 903-877-3528 Fax 903-877-3092 If
www.welchexcavation.net
brandon 1l)%�,cichcxcavation.tut I
Soto, Vania Elizabeth
From: Black, Doug
Sent: Monday, December 16, 2019 1:26 PM
To: Soto, Vania Elizabeth; Kayser, Mary
Cc: Sholola, Tony
Subject: FW: City Secretary Contract No. 51375
Attachments: 20191216124109961.pdf, 20191216124039874.pdf
Importance: High
Vania—please see the attached corrected documents for corrections of the record.
Please let me know if there are any questions.
Thanks,
Doug
From: Sholola,Tony
Sent: Monday, December 16, 2019 12:21
To: Black, Doug<Douglas.Black@fortworthtexas.gov>
Cc: Lopez,John (Water) <John.Lopez1 @fortworthtexas.gov>; Howe, Cheryl <Cheryl.Howe @fortworthtexas.gov>; Oakes,
Heather<Heather.Oakes@fortworthtexas.gov>; Rackley, Ronald <Ronald.Rackley@fortworthtexas.gov>
Subject: City Secretary Contract No. 51375
Doug:
The City Secretary Contract No. was inadvertently listed as 48477 instead of 51375 on the attached change orders for
the Lake Worth Dam Improvement Project. Please okay the City Secretary's office swapping out the two existing change
orders for the project with the attached change orders and advise them of such.
Thanks