AMENDMENT 1 TO FIRST RENEWAL OF AGREEMENT
WHEREAS, the City of Fort Worth, ("City"), and William J. Schultz, Inc. dba
Circle C Construction Company, authorized to do business in Texas, ("Contractor"), entered
into that certain ORIGINAL AGREEMENT (City Secretary #47793, M&C C-27702) for
the PROJECT generally described as: Sanitary Sewer Pipe Enlargement Contract 2015A,
City Project No. 2737; and
WHEREAS, the ORIGINAL AGREEMENT may be renewed up to three times as
provided by M&C C-27702; and
WHEREAS, The City and Contractor, anticipating the need to do so, renewed the
ORIGINAL AGREEMENT on January 9,2018,- and
WHEREAS, The City has not had the need to engage Contractor under the First
Renewal as demand for the services to be provided have slowed and funding under the
ORIGINAL AGREEMENT remains; and
WHEREAS, The City and Contractor desire to amend this First Renewal to provide
for an extended term, thus allowing an immediate transition from the ORIGINAL
AGREEMENT to this First Renewal.
NOW, THEREFORE, it is agreed by the City and Contractor as follows:
Article I
The Term of the First Renewal shall be effective as of the effective date as stated
thereon and be for a duration commensurate with the expenditure of the funding, but in no
event shall the agreement last Ionger than five years from the effective date.
EXECUTED by each party's duly authorized representative and EFFECTIVE as of
the date subscribed by the City's designated City Manager.
SIGNATURE PAGE TO FOLLOW
FT. WORK TX
First Amendment.to First Renewal of Agreement -- — '�d�e'4"4'ff'2-;
Sanitary Sewer Pipe Enlargement MSSPE2015A
Contract 2015A City Project No.2737
City of Fort Worth William I Schultz Inc. dba Circle C
Construction Company
�m �s4r-
Dana Burghdoff Teresa S. Skelly,
Assistant City Manager Vice President
DATE: DATE: IZ - 9 - /,9
APPROVAL RECOMMENDED:
Chris Harder,P.E.
Director, Water Department
APPROVED AS TO FORM:
M&C: C-27702
Date: 05/03/2016
Douglas W. Black
Sr. Assistant City Attorney OR 7'
ATTEST: _ • '•
Mary J. se �xo
City Secretary
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
w�
"Alg ature
-Lawrence Hamilton
Narne of Employee OFF90AL ECORii)
UUTV SECRETARY
Senior Professional Engineer �� �o���d".��
__-
.-
First Amendment to First Renewal of Agreement Page 2 of 2
Sanitary Sewer Pipe Enlargement MSSPE2015A
Contract 2015A City Project No.2737
+° ��
x ��« Fort Wo« ««xv Texas
N&� =P Council
Communication
u��
N��N�������Np �� ��R} 0�,�~�N0���m0N ����.N��|0�rAUU�� W�°�� ������
����� �� n�'m �nuux�� ~~ n�'��mm��m. �� m*�mm �mmu��mmm���m�mn�"mm
�
COUNCIL ACTION: Approved o05/3/201G - Ordinance No. 22187-05-2016
DATE: Tuesday, May 3. 201O REFERENCE NO.: °"C-27702
LOG NAME: 8O8EVVERENLARGE- C|RCLEC
SUBJECT:
Authorize Execution of a Contract with William J. Schultz Inc. d1b/a Circle C Construction Company, in the
Amount of$1,000,000.00 for the Sewer Pipe Enlargement Contract 2015A Throughout the City and Adopt
Appropriation Ordinance (ALL COUNCIL DISTRICTS)
|tio recommended that the City Council:
1. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Sewer Capital Projects Fund |nthearnountof$1.210.0OO.00; mnd
2. Authorize the City Manager to execute o contract with William J. Schultz Inc. d/b/a Circle C
Construction Company, in the amount of$1,000,000.00 for the Sewer Pipe Enlargement Contract 2015A,
including the option to renew for upto two additional terms.
DISCUSSION:
The work to be performed under this contract consists of replacing sewer mains, services and other
pertinent construction by tnanch|ase methods to provide sewer service to individual uuatunneno or
developers.
The bid documents included a stipulation that the total quantities listed may not reflect actual quantities
and that the amount budgeted for the project in$1.O0O.00O.DD. Final payments will bo made based nnthe
unit prices established by the bid and actual measured quantities installed. The bid documents also
included o stipulation giving the City the option to renew (subject to appropriated funding) this contract two
times under the same terms, conditions and unit prices.
The projectvveoadvert|oednnNnvannbor5. 2O15andNovember12. 2015inthe
Fort Worth Star-
Tele.gram. On December 1O. 2O15 the following bids were received:
11 BIDDER TIME
ItNilliam J. Schultz Inc.d/bla Circle C Construction Compa:n:����
|n addition to the contract amount, $21O.00O.00ie required for project mmonegement. con:truutionatoking.
material testing and inspection. This contract will have no impact on the Water Department's operating
budget when complete.
Appropriations for the Sewer Pipe Enlargement Contract 2015A Project will consist of the following:
Existing Additional Future Project
Description FAppropriations Appropriations A ro riations Total*
Construction 11 $0.00 11 $1 000 000.00 $0.00 $1 000 000.00
Project Management,
Construction Staking,
Material Testing, Inspection $0.00 $ 210,000.00 $0.00 $ 210,000.00
and Contingencies
Project Total $0.00 $1,210,000.00 $0.00 $7 210,000.00
*Numbers rounded for presentation purposes.
Appropriations for the Sewer Pipe Enlargement Contract 2015A Project by fund will consist of the
following:
FUND JAppropriations*
ewer Capital Pro ects Fund 59607 $1,210,000.00
Project Total $1 210,000.00
*Numbers rounded for presentation purposes.
MIWBE OFFICE -William J. Schultz, Inc. d/b/a Circle C Construction Company, is in compliance with the
City's BDE Ordinance by committing to zero percent MBE participation and documenting good faith
effort. William J. Shultz, Inc. d/b/a Circle C Construction Company, identified several subcontracting and
supplier opportunities. However, the MBE's contacted in the areas identified did not submit the lowest
bids. The City's MBE goal on this project is 11 percent.
This project is located in ALL COUNCIL DISTRICTS.
FISCAL INFORMATION 1 CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in the current capital budget, as appropriated, of
the Sewer Capital Projects Fund. The Fiscal Year 2016 Sewer Operating Budget includes appropriations
of$26,300,046.00 for the purpose of providing pay-as-you-go funding for Sewer Capital Projects. After
this transfer for Fiscal Year 2016, the balance will be $16,561,660.00.
Existing Additional Future Revised
FUND ir Appropriations Appro riations I Ap ro riations Appropriations
Sewer Capital Projects Fund
59607 IF $0.00 F $1,21D,000.OD $0.00 IL
$1,210,000.00
Project Total $0.00 $1,210 000.00 $0.00 $1 210 000.00
* Numbers rounded for presentation purposes.
FUND IDENTIFIERS FIDs :
TO
Fund Department Accoun Project JProgram ctivit Budget Reference # Amount
ID ID Year Chartfield2) _
1 59607 0700430 4956001 CO2737 C017ZZ 2016 1 210 000.00
1 59607 0700430 5110101 CO2737 _ C01730 _ 2016 $101,500.00
1 59607 0700430 5710010 CO2737 C01741 2016 $2,000.00
1 59607 0700430 5310350 CO2737 C01742 2010 _ $2,000-00
1)59607 0700430 5310350 CO2737 C01751 2016 $2,000.00
1)596071 0700430 5330500 CO2737 C01751 2016 $10,000.00
1)59607 0700430 5310350 CO2737 C01752 2016 $1,000.00
1)59607 0700430__ 5330500 CO2737 C01752 2016 $15,000.00
1)59607 0700430 5330500 CO2737 C01753 2016 $1,000.00
1 59607 0700430 5330500 CO2737 C01781 2016 $300.00
1),59607 0700430 5540101 CO2737 C01781 2016 $200.00
1 596071 0700430 5310350 1 CO2737 C01784 2016 $5,000,00
1 59607 0700430 5330500 CO2737 C01784 2016 $_20_,000.00
1)59607 07 00430 5740010 CO2737 C01783 2016 _ 1,000,000.00
1)59607 0700430 5110101 CO2737 C01785 2016 $50,000.00
FROM
Fund Department Accoun Project Program ctiyit Budget Reference # Amount
ID ID Year Ghartfield 2
)59607 070043D 574DD10 CO2737 C01783 T 2016 1,000,D00.00
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: John Carman (8246)
Additional Information Contact: Adolpho Lopez (7829)
ATTACHMENTS
1. 60SEWERENLARCE CIRCLEC MWBE. df (CFW Internal)
2. 60SEWERENLARGE -CIRCLEC sewer AO.doex (Public)
3. 60WSR2015A Circlec 1295 Form.pdf (Public)
4. Fund 56001.docx (CFW Internal)
5. SAM for Circle C Construction.pdf (CFW internal)