Change Order Request CONTRACT No.�q ga-tea
Project Name:1 Northside 1148-Inch Water Main Phase 11, Part II City Sec No.: 47982
Project No.(s): 56005-0600430-CO2304 I DOE No. F N\A City Proj.No.: CO2304
Project Description: 48-Inch Water Main installation from Wagley Robertson Rd.to Parkview Lane
Contractor: S.J. Louis Construction of Texas, Ltd. Change Order# �2 Date: 1/14/2020
�J��� �QCtty Project Mgr. John Kasavich City Inspector: Raymond Brice
� -Phone Number: 817 392 8480 Phone Number: 817-392-8452
Dept. Water Paving and Totals Contract Time
Drainage (Calender days)
Original Contract Amount $11,391,347.00 $2,829,076.00 $14,220,423.00 540
Extras to Date 039
Credits to Date $0.96 $0.96
Pending Change Orders(in M&C Process)
Contract Cost to Date $11,391,346.04 $2,829,076.00 $14,220,422.04 579
$0.00 $0.00 $0.00 $0.00 168
Revised Contract Amount $11,391,346.04 $2,829,076.00 $14,220,422.04 747
Original Funds Available for Change Orders $429,700.00 $429,700.00
Remaining Funds Available for this CO $429,700.96 $429,700.96
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $17,775,528.75
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change order No. 2 will provide for an additional 168 days time on the project for the time it took to acquire
easements and railroad permits that had not been acquired at the time the project was advertised for bid.The
contractor was not able to work in the applicable areas until the easements and permits were acquired.
i
�� •.,• E icy
Attested by: `�
• �`fir .',• ,,"' '�., •,�'`�;
Allison Tidwell,A34104fit to tho City Secretary
i
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name I kfintracIpAignature Date.
S.J. Louis Construction of Texas, Ltd. Adam Lunsford 1 G
I r Date Project Manager Date
Assistant " ector( ater Dept) Date Cori uction Supervisor(Water Dept) Date
A i to ne Da t Assistant City Manager Date
Council Action If Required)
M&C Number N/A M&C Date Approved N
Fc�RT V4�OR r H City of Fort Worth
Change Order Additions
Project Name Northside II 48-Inch Water Main Phase II, Part II City Sec No.: 47982
Project No.(s): 56005-0600430-CO2304 DOE No. N\A City Proj. No.: CO2304
Project 48-Inch Water Maininstallation from Wagley Robertson Rd. to Parkview Lane
Description
Contractor S. J. Louis Construction of Texas, Ltd. Change Order:�2 Date: 1/14/2020
City Project Mgr. John Kasavich City Inspector F Raymond Brice
ADDITIONS
DESCRIPTION DEPT Qty Unit Unit Copt Total
Water
Paving and Drainage
Page 2 of 4 Additions Sub Total
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Northside II 48-Inch Water Main Phase II, Part II City Sec No.: 47982
Project No.(s): 56005-0600430-CO2304 DOE No. EEEI City Proj. No.: CO2304
Project Description 48-Inch Water Main installation from Wagley Robertson Rd. to Parkview Lane
Contractor S.J. Louis Construction of Texas, Ltd. Change Order: ETI Date 1/14/2020
City Project Mgr. John Kasavich City Inspector: FRaymond Brice
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
Water
Paving and Drainage
Page 3 of 4 Deletions Sub Total
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 4 of 4
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
A
,Signature
Name of Employee
Al
G�
Title
COT sp(C:kamy