HomeMy WebLinkAboutContract 35501CITY SECRETARY "
0 .0.E. FILE
...
C ONTRACTOR 'S BONDING CO. SPECIFICATIONS ' .,·r C °7r-'""'::T, RY~,
f ,... .. ~
C ONSTRUCTl O N1S COPY AND
CONTRACT DOCUMENTS
,C1 _ I , , •'-' ,-NO·--
C LIEf'(f 0F.DART\11 EN1 FOR
/
THE CONSTRUCTION OF
SH 121T Southwest Parkway Water & Sanitary Sewer
Main Relocations,
Part 1: 24-inch Water & 36-inch Sanitary Sewer Main at
Bellaire Drive, DOE No. 5502
Part 5: 24-inch Water & Sanitary Sewer Main at IH 20,
DOE No. 5503
Part 7A: 21-inch Sanitary Sewer Main at Overton Ridge
Blvd., DOE No. 5504
Water Project No. P264-603170020483
Sewer Project No . P274-703170020483
City Project No . 00204
Mike Moncrief
Mayor
Charles Boswell
City Manager
A. Douglas Rademaker, P.E.
Director, Department of Engineering
S . Frank Crumb, P.E.
Director, Water Department
Robert Goode, P.E.
Director, Department of Transportation & Public Works
Prepared for
The City of Fort Worth
Department of Engineering
November 2006
.......-i _.,... Kimley-Horn
111111....J-~ and Associates, Inc.
KHA No. 061018028
[)ORIGINAL
C "f F . \A l . 'h E .. •. l I ·. fORTWORTH .. ·· 1 .. · .. o .. ort vv ort1· mp oyee ntrane WW';f'.c.fN et.org ... ~
IIMullli·M,Bif#JMd•UHN·Hl#•)iMMdt4i@ffii•M&i4¥9t#ii@INP&J•l•fflildil•i+£iU,1H,iNliMHii
Print M&C
COUNCIL ACTION: Approved on 6/19/2007 -Ord. #17627-06-2007
DATE: 6/19/2007
C
REFERENCE NO.: C-22211 LOG NAME: 30121T-CONASTER
CODE: TYPE: NON-CONSENT PUBLIC HEARING: NO
SUBJECT: Authorize Execution of Contract with Conatser Construction Texas , LP , for Water and Sanitary
Sewer Relocations for SH-121T (Southwest Parkway), Parts 1, 5 and 7A and Adopt
Appropriation Ordinance (City Project No . 00204)
RECOMMENDATION:
It is recommended that the City Council :
1. Authorize the transfer of $3,409,486 .00 from the Water and Sewer Operating Fund to the Water Capital
Project Fund in the amount of $1,405 ,326 .00 and Sewer Capital project Fund in the amount of
$2 ,004 ,160 .00 ;
2 . Adopt the attached appropriation ordinance increasing the estimated receipts and appropriations in the
Water Capital Project Fund in the amount of $1 ,405 ,326 .00 and the Sewer Capital Project Fund in the
amount of $2 ,004 ,160.00; from available funds ; and
3. Authorize the City Manager to execute a contract with Conatser Construction , Texas , LP , in the amount of
$3 ,184 ,938.00 for Water and Sanitary Sewer Relocations for SH-121T (Southwest Parkway), Parts 1, 5 and
7A.
DISCUSSION:
On April 5, 2005 , (M&C C-20632) the City Council authorized an engineering agreement with Kimley Horn &
Associates , Inc ., for Water and Sanitary Sewer Relocations for SH-121T (Southwest Parkway), from Hulen
Street to Alta Mesa Boulevard .
This project cons ists of water and sanitary sewer main improvements at Bellaire Drive (Part 1) and I.H . 20
(Part 5) and sewer improvements at Overton Ridge Boulevard (Part 7 A).
This project was advertised for bid on November 16 and 22 , 2006 . On December 21 , 2006, the following
bids were rece ived :
Bidder
Conatser Construction Texas , L.P .
William J . Schultz , Inc. dba
Circle "C" Construction Company
S .J . Louis Construction , Ltd.
Oscar Renda Contractors
AUi Contractors , L.P .
Amount
$3,184 ,938 .00
$3,190 ,769 .00
$3,308 ,313.42
$4 ,287 ,522.00
$4 ,952 ,187.40
The project is located in COUNCIL DISTRICT 3 , Mapsco 89E .
Time of Completion
200 Calendar Days
Conatser Construction Texas , LP , is in compliance with the City 's M/WBE Ordinance by committing to 5
percent M/WBE participat ion and documenting good faith effort. Conats'er Con struction Texas, LP , identified
several subcontracti ng and supplier opportunities . However, the M/WBE-certified firms contacted in the
areas identified did not submit the lowest bids . The City 's goal on this project is 16 percent.
In addition to the contract cost , $129 ,000 (water: $5 1,000 sewer: $78 ,000) is required for i nspection , project
management and survey ; and $95 ,548 (wate r $39,446 ; sewer $56 ,102) is provided for project
contingencies .
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that upon approval of the above recommendations and the adoption of the
attached appropriat ion ordinance , funds will be ava ilable in the current capital budgets , as appropriated , of
the Water Capital Proj ects Fund and the Sewer Capital Projects Fund .
TO Fund/Account/Centers FROM Fund/Account/Centers
1)PE45 538070 0604020 1 405 326 .00
1)PE45 538070 0703020 $2,004 ,160 .00
~P264 541200 603170020487 1314880.00
1&2 $2 ,004 ,160 .00 P274 472045 7031700204ZZ
1&2 $1,405 326 .00 P264 472045 603 1700204ZZ
i)P264 531350 603170020452 lli,000 .00 ~P274 541200 703170020487 $1,870 ,058 .00
2 P264 531350 603170020484 i§.,000.00
2 P264 531350 603170020485 $30 ,000 .00
~P264 541200 603170020487 $1,354 ,326 .00
~P2 74 531350 703170020452 $20 ,000.00
~P2 74 531350 703170020484 $.Ll.,000 .00
~P274 531350 703170020485 $45 ,000 .00
2)P274 541200 703 170020487 $1 ,926 ,160 .00
Submitted for Cit Manager's Office by_;_
Originating Department Head:
Marc A. Ott (8476 )
A. Douglas Rademake r (6157 )
Liam Conlon (6824 ) Additional Information Contact:
ATTACHMENTS
30 12 1 T-Conatser.doc
-
. ,
ADDENDUM NO. 1
CITY OF FORT WORTH
DEPARTMENT OF ENGINEERING
SH 121 T Southwest Parkway Water & Sanitary Sewer Main Relocation s,
Part I : 24-inch Water & 36-inch Sanitary Sewer Main at Bellaire Drive, DOE No . 5502
Part 5 : 24-inch Water & Sanitary Sewer Main at IH 20 , DOE No . 5503
Part 7 A: 21-inch Sanitary Sewer Main at Overton Ridge Blvd., DOE No. 5504
Water Project No. P264-603 l 70020483
Sewer Project No . P274-703 I 70020483
City Project No. 00204
Addendum No. I. Issue Date: December 12, 2006
Bid Receipt Date (revised): December 21, 2006
This addendum forms part of the contract documents referenced above and modifies the original Contract
Documents. Acknowledge receipt of this addendum by signing and attaching it to the Contract Documents
(inside). Note receipt of the Addendum in the Bid Proposal and on the outer envelope of your bid.
PART A -NOTICE TO BIDDERS
• The bid opening date is hereby changed from December 14 , 2006 to December 21, 2006.
-PART A-COMPREHENSIVE NOTICE TO BIDDERS
• The bid opening date is hereby changed from December 14, 2006 to December 21, 2006.
PART DA -ADDITIONAL SPECIAL CONDITIONS
• Delete Section B. l .b . Wall Thickness under DA-6 PIPE INSTALLED BY OTHER THAN OPEN CUT
in its entirety and replace it with the following:
b. Wall Thickness: 0.375 in . minimum (0.5 for railroad crossings), unless otherwise specified in
DA-127 PIPELINES CROSSING HIGHWAYS, STREETS AND RAILROADS BY BORING ,
TUNNELING OR OPEN CUT.
PART DA -ADDITIONAL SPECIAL CONDITIONS
• Delete the table at the end of Section B . l .a under DA-I 27 PIPELINES CROSSING HIGHWAYS ,
STREETS AND RAILROADS BY BORING , TUNNELING OR OPEN CUT in its entirety and replace
it with the following table:
Casing Diameter -Utility Line Min. Wall Thickness
42" -Water Line A 0 .656"
42" -Water Line C 0.406"
54" -Sewer Line D 0.844"
42" -Sewer line E 0 .562"
-
All other provisions of the contract documents, plans and specifications shall remain unchanged.
Failure to return a signed copy of the addendum with the Proposal shall be grounds for rendering the bid non-
responsive. A signed copy of this addendum shall be placed into the Proposal at the time of bid submittal.
RECEIPT ACKNOWLEDGED:
By•~/~
~7
Company: C: ,t 4 '1' S.Q,l
Department of Engineering
A. Douglas Rademaker, P.E.
Director By:~~~~ ~~~l~~~~~ ~
J
Tony Sholola , P.E.
Engineering Manager (DOE)
ADDENDUM NO. 1
'
ADDENDUM NO. 2
CITY OF FORT WORTH
DEPARTMENT OF ENGINEERING
SH 121 T Southwest Parkway Water & Sanitary Sewer Main Relocations,
Part 1: 24-inch Water & 36-inch Sanitary Sewer Main at Bellaire Drive, DOE No. 5502
Part 5: 24-inch Water & Sanitary Sewer Main at ill 20, DOE No. 5503
Part 7A: 21-inch Sanitary Sewer Main at Overton Ridge Blvd ., DOE No. 5504
Water Project No. P264-603 l 70020483
Sewer Project No . P274-703170020483
City Project No. 00204
Addendum No. 2. Issue Date: December 14, 2006
Bid Receipt Date (revised): December 21, 2006
This addendum forms part of the contract documents referenced above and modifies the original Contract
Documents . Acknowledge receipt of this addendum by signing and attaching it to the Contract Documents
!"!!l!J (inside). Note receipt of the Addendum in the Bid -Proposal and on the outer envelope of your bid.
!"""'!
PART B -PROPOSAL
• Replace the existing Proposal Section (pages B-1 to B -23) with the attached revised proposal:
"PROPOSAL -ADDENDUM No. 2" (pages B-1 R to B-23R)
PART DA-ADDITIONAL SPECIAL CONDITIONS
• Delete DA-40 Omit in its entirety and replace it with the following:
DA-40 CONCRETE RIPRAP
1. GENERAL: The following shall govern the furnishing and placing of concrete riprap as shown
on the plans or as directed by the Engineer.
2. MATERIALS : Concrete for riprap shall be placed in accordance with the details and to the
dimensions shown on the plans or as established by the Engineer. Unless otherwise shown on the
plans, concrete riprap shall be reinforced using wire or bar reinforcement.
The concrete shall be 3000 PSI at 28 days , Class A.
Wire reinforcement shall be six (6) by six (6) inch No . 6 plain electric welded reinforcing fabric or
its equal. A minimum lap of six (6) inches shall be used at all splices. At the edge of the riprap, the
wire fabric shall not be less than one (I) inch, no more than three (3) inches from the edge of the
concrete and shall have no wire projecting beyond the last member parallel to the edge of the
concrete.
Reinforcement shall be supported properly throughout the placement to maintain its position
equidistance from the top and bottom surface of the slab.
If the slopes and bottom of the trench for toe walls are dry and not consolidated properly, the
Engineer may require the entire area to be sprinkled, or sprinkled and consolidated before the
concrete is placed . All surfaces shall be moist when concrete is placed.
-
-
After the concrete has been placed, compacted, and shaped to conform to the dimensions shown on
the plans , and after it has set sufficiently to avoid slumping, the surface shall be finished with a
wooden float to se cure a reasonably smooth surface.
3 . PAYMENT: Payment for concrete riprap in place shall be made at the unit price bid in the
Proposal multiplied by the quantity of material used. Bid price will be full compensation for
placing all materials , and for all labor, tools, equipment, and incidentals necessary to complete the
work.
Payment for all necessary excavation below natural ground, and bottom or slope of the excavated
channel will be included in the bid price.
CONSTRUCTION PLANS
• Sheet W2 -Line C on Sheet W2 is revised as attached on Sheet W2A
All other provisions of the contract documents , plans and specifications shall remain unchanged.
Failure to return a signed copy of the addendum with the Proposal shall be grounds for rendering the bid non-
responsive . A signed copy of this addendum shall be placed into the Proposal at the time of bid submittal.
Company:~Co""-----/Z/,,-~---'-1'_51_~--
Department of Engineering
A. Douglas Rademaker, P.E.
Director
Tony Sholola, P.E .
Engineering Manager (DOE)
ADDENDUM NO. 2
Notice to Bidders
Comprehensive Notice to Bidders
Special Instructions to Bidders
TABLE OF CONTENTS
Minority and Women Business Enterprises Specifications
Proposal
General Conditions
Supplementary Conditions to Part C
Special Conditions
Additional Special Conditions
Special Specifications
Certificate of Insurance
Contractor Compliance with Worker's Compensation Law
Vendor Compliance to State Law
Maintenance, Payment and Performance Bonds
Contract
Geotechnical Bore Logs
Part
A
A
A
B
B
C
Cl
D
DA
E
F
F
F
F
G
Appendix A
PART A
PART A-NOTICE TO BIDDERS
Sealed proposals for the following project:
SH 121 T Southwest Parkway Water & Sanitary Sewer Main Relocations,
Part 1: 24-inch Water & 36-inch Sanitary Sewer Main at Bellaire Drive, DOE No. 5502
Part 5: 24-inch Water & Sanitary Sewer Main at IH 20, DOE No. 5503
Part 7A: 21-inch Sanitary Sewer Main at Overton Ridge Blvd., DOE No. 5504
in Fort Worth, Texas
Water Project No. P264-603170020483
Sewer Project No. P274-703170020483
City Project No. 00204
Addressed to Mr. Charles R . Boswell, City Manager of the City of Fort Worth, Texas, will be received
at the Purchasing Office until 1 :30 p.m., Thursday, December l4, 2006 and then publicly opened and ~e r ;4Jd. ti I
read aloud at 2:00 p.m. in the Council Chambers. ;2.I
Plans, General Contract Documents and Specifications for this project may be obtained in the office of
the Department of Engineering, City of Fort Worth, l 000 Throckmorton Street, Fort Worth , Texas
76102. A sixty dollar ($60.00) non-refundable fee is required for each set of plans and documents.
These documents contain additional information for prospective bidders. Please note that plans will
be available for pick up on Tuesday, November 21, 2006.
The major work on the above referenced project shall consist of the following:
Water Line Improvements
924 LF 24" Water Line by Open Cut
485 LF 24" Water Line by Other than Open Cut
3 EA 24" Gate Valve
Sewer Line Improvements
639 LF 36" Sanitary Sewer Line
237 LF 24" Sanitary Sewer Line
622 LF 24" Sanitary Sewer Line by Other than Open Cut
1, 112 LF 21" Sanitary Sewer Line
229 LF 8" Sanitary Sewer Line
4 EA Junction Sanitary Sewer Manhole
1 EA Modified Type "A" Manhole
1 EA Standard 6-foot Diameter Manhole
5 EA Standard 5-foot Diameter Manhole
3 EA Standard 4-foot Diameter Manhole
For additional information, please contact Mr. Liam Conlon, Project Manager, City of Fort Worth-
Department of Engineering at (817) 392-6824 or Mr. Carl T. DeZee, P.E., Project Manager, Kimley-
Hom and Associates, Inc ., at (817) 335-6511.
ADVERTISING DATES:
November 16, 2006
November 22, 2006
Fort Worth, Texas
PART A-COMPREHENSIVE NOTICE TO BIDDERS
Sealed proposals for the following project:
SH 121 T Southwest Parkway Water & Sanitary Sewer Main Relocations,
Part 1: 24-inch Water & 36-inch Sanitary Sewer Main at Bellaire Drive, DOE No. 5502
Part 5: 24-inch Water & Sanitary Sewer Main at IH 20, DOE No. 5503
Part 7A: 21-inch Sanitary Sewer Main at Overton Ridge Blvd., DOE No. 5504
in Fort Worth, Texas
Water Project No. P264-603170020483
Sewer Project No. P274-703170020483
City Project No. 00204
Addressed to Mr. Char les Boswell, City Manager of the City of Fort Worth , Texas , will be received at
the Purchasing Office until 1 :30 p .m., Thursday, December ).A', 2006 and then publicly opened and p r )def it:/
read aloud at 2 :00 p.m. in the Council Chambers. 21 e
Plans , General Contract Documents and Specifications for this project may be obtained in the office of
the Fort Worth Department of Engineering, 1000 Throckmorton Street, Fort Worth, Texas 76102. A
sixty dollar ($60.00) non-refundable fee is required for each set of plans and documents. These
documents contain additional information for prospective bidders. Please note that plans will be
available for pick up on Tuesday, November 21, 2006.
All Bidders will be required to comply with Provision 5159a of"Vemon 'sAnnotated Civil Statutes" of
the State of Texas with respect to the payment of prevailing wage rates and City Ordinance no. 7400
(Fort Worth City Code Sections 13-A-221 through l 3-A-29) prohibiting discrimination in the
employment practices.
Bid security is required in accordance with paragraph 2 of the Special Instructions to Bidders.
The major work on the above referenced project shall consist of the following:
Water Line Improvements
924 LF 24" Water Line by Open Cut
485 LF 24 " Water Line by Other than Open Cut
3 EA 24" Gate Valve
Sewer Line Improvements
639 LF 36" Sanitary Sewer Line
237 LF 24" Sanitary Sewer Line
622 LF 24" Sanitary Sewer Line by Other than Open Cut
1, 112 LF 21" Sanitary Sewer Line
229 LF 8" Sanitary Sewer Line
4 EA Junction Sanitary Sewer Manhole
1 EA Modified Type "A" Manhole
1 EA Standard 6-foot Diameter Manhole
5 EA Standard 5-foot Diameter Manhole
3 EA Standard 4-foot Diameter Manhole
Included in the above will be all other miscellaneous items of construction as outlined in the Plans,
General Contract Documents and Specifications.
The City reserves the right to reject any and /or all bids and waive any and/or all formalities. AWARD
OF CONTRACT: No bid may be withdrawn until the expiration of ninety (90) days from the date bids
are opened. The award of contract, if made, will be within ninety (90) days after the opening of bids,
but in no case will the award be made until all the necessary investigation are made as to the
responsibility of the bidder to whom it is proposed to award the Contract.
Bidders are responsible for obtaining all addenda to the contract documents and acknowledging
receipt of the addenda by initialing the appropriate spaces on the PROPOSAL form(s). Bidders must
also acknowledge receipt of the Addendum on the outside of their bid envelope. Bids that do not
acknowledge receipt of all addenda may be rejected as being non-responsive. Information regarding
the status of addenda may be obtained by contacting the City of Fort Worth Department of
Engineering at (817) 392-7910.
Bidders shall not separate, detach or remove any portion, segment or sheets from the contract
document at any time. Bidders must complete the proposal section(s) and submit the complete
specifications book or face rejection of the bid as non-responsive. It is recommended that the bidder
make a copy of the forms included in the Minority and Women Business Enterprise section for
submittal within the time-line stated below or the bidder may request a copy of said forms from the
City Project Manager named in this solicitation.
In accord with City of Fort Worth Ordinance No. 15530, the City of Fort Worth has goals for
the participation of minority business enterprises and women business enterprises in City
contracts. A copy of the Ordinance can be obtained from the Office of the City Secretary. The
bidder shall submit the MBE/WBE UTILIZATION FORM, SUBCONTRACTOR/SUPPLIER
UTILIZATION FORM, PRIME CONTRACTOR WAIVER FORM and/or the GOOD FAITH
EFFORT FORM ("with Documentation") and/or the JOINT VENTURE FORM as
appropriate. The Documentation must be received by the managing department no later than
5:00 p.m., five (5) City business days after the bid opening date. The bidder shall obtain a
receipt from the appropriate employee of the managing department to whom delivery was
made. Such receipt shall be evidence that the documentation was received by the City. Failure
to comply shall render the bid non-responsive.
The managing department for this project is the Department of Engineering.
For additional information, please contact Mr. Liam Conlon, Project Manager, City of Fort Worth-
Department of Engineering at (817) 392-6824 or Mr. Carl T. DeZee, P.E., Project Manager, Kimley-
Hom and Associates, Inc., at (817) 335-6511.
CHARLES BOSWELL
CITY MANAGER
ADVERTISING DATES:
November 16, 2006
November 22, 2006
Fort Worth, Texas
By: -~~~
MARTY HENDRIX
CITY SECRETARY
Tony Sholola, P.E., Engineering Manager,
Department of Engineering,
SPECIAL INSTRUCTIONS TO BIDDERS
1) PREOUALIFICATION REQUIREMENTS: All contractors submitting bids are required
to be prequalified by the Fort Worth Water Department prior to submitting bids. This
prequalification process will establish a bid limit based on a technical evaluation and
financial analysis of the contractor. It is the bidder 's responsibility to submit the following
documentation: a current financial statement, an acceptable experience record , an acceptable
equipment schedule and any other documents the Department may deem necessary, to the
Director of the Water Department at least seven (7) calendar days prior to the date of the
opening of bids .
a) The financial statement required shall have been prepared by an independent certified
public accountant or an independent public accountant holding a valid permit issued by
an appropriate State licensing agency and shall have been so prepared as to reflect the
financial status to the submitting company . This statement must be current and not more
than one (1) year old . In the case that a bidding date falls within the time a new
statement is being prepared, the previous statement shall be updated by proper
verification .
b) For an experience record to be considered to be acceptable for a giv en project, it must
reflect the experience of the firm seeking qualification in work of both the same nature
and technical level as that of the project for which bids are to be received.
c) The Director of the Water Department shall be the sole judge as to the acceptability for
financial qualification to bid on any Fort Worth Water Department project.
d) Bids received in excess of the bid limit shall be considered non-responsive and will be
rejected as such.
e) The City, in its sole discretion, may reject any bid for failure to demonstrate experience
and/or expertise.
f) Any proposals submitted by a non-prequalified bidder shall be returned unopened, and if
inadvertently opened , shall not be considered.
g) The City will attempt to notify prospective bidders whose qualifications (financial or
experience) are not deemed to be appropriate to the nature and/or magnitude of the
project on which bids are to be received . Failure to notify shall not be a waiver of any
necessary prequalification.
2. BID SECURITY: A cashier's check, or an acceptable bidder's bond , payable to the City of
Fort Worth, in an amount of not less than five (5%) percent of the largest possible total of the
bid submitted must accompany the bid, and is subject to forfeiture in the event the successful
bidder fails to execute the Contract Documents within ten (10) days after the contract has
been awarded To be an acceptable surety on the bid bond, the surety must be authorized to
do business in the state of Texas. In addition, the surety must (1) hold a certificate of
authority from the Untied States secretary of the treasury to qualify as a surety on obligations
permitted or required under federal Jaw; or (2) have obtained reinsurance for any liability in
excess of $100,000 from a reinsurer that is authorized and admitted as a reinsurer in the state
06/04/03
of Texas and is the holder of a ce rtificate of authority from th e Untied States secretary of the
treasury to qualify as a surety on obligations permitted or required under federal law .
Satisfactory proof of any s uch reinsurance shall be provided to the City upon request. The
City, in its sole discretion , will determine the adequacy of the proof required herein.
3 . BONDS: A performance bond , a payment bond, and a maintenance bond each for one
hundred (100 %) percent of the contract price will be required , Reference C 3-3 .7.
4 . WAGE RATES:
Section C3-3 .13 of the General Conditions is deleted and replaced with the following :
(a) The contractor shall comply with all requirements of Chapter 2258 , Texas Government
Code, including the payment of not less than the rates determined by the City Council of the
City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258, Texas
Government Code. Such prevailing wage rates are included in these contract documents.
(b) The contractor shall , for a period of three (3) years following the date of acceptance of
the work, maintain records that show (i) the name and occupation of each worker employed
by the contractor in the construction of the work provided for in this contract; and (ii) the
actual per diem wages paid to each worker. These records shall be open at all reasonable
hours for inspection by the City. The provisions of D-3 Right to Audit pertain to this
inspection.
( c) The contractor shall include in its subcontracts and /or shall otherwise require all of its
subcontractors to comply with paragraphs (a) and (b) above.
(d) With each partial payment estimate or payroll period, whichever is less, an affidavit
stating that the contractor has complied with the requirements of Chapter 2258 , Texas
Government Code.
The contractor shall post the prevailing wage rates in a conspicuous place at the site of the
project at all times.
5. AMBIGUITY: In the case of ambiguity or lack of clearness in stating prices in the
Proposal , the City reserv es the right to adopt the most advantageous construction thereof to
the City or to reject the Proposal.
6. BIDDER LICENSE: Bidder must be a licensed Contractor in the State of Texas.
7. NONRESIDENT BIDDERS: Pursuant to Article 601g, Texas Revised Civil Statutes, the
City of Fort Worth will not award this contract to a nonresident bidder unless the
nonresident's bid is lower than the lowest bid submitted by a responsible Texas resident
bidder by the same amount that a Texas resident bidder would be required to underbid a
nonresident bidder to obtain a comparable contract in the state in which the nonresident's
principal place of business in located.
"Nonresident bidder" means a bidder whose principal place of business is not in this state,
but excludes a contractor whose ultimate parent company or majority owner has its principal
place of business in this state.
06/04/03
This provision does not apply if this contract involves federal funds .
The appropriate blanks of the Proposal must be filled out by all nonresident bidders in order
for the bid to meet specifications. The failure of a nonresident contractor to do so will
automatically disqualify that bidder .
8 . PAYMENT: If the bid amount is $25 ,000.00 or less , the contract amount shall be paid
within forty-five ( 45) calendar days after completion and acceptance by the City.
9. AGE: In accordance with the policy ("Policy") of the Executive Branch of the Federal
Government, Contractor covenants that neither it nor any of its officers , members , agents
employees , program participants or subcontractors, while engaged in performing this
contract, shall, in connection with the employment, advancement or discharge of employees
or in connection with the terms, conditions or privileges of their employment, discriminate
against persons because of their age except on the bases of a bona fide occupational
qualification , retirement plan or statutory requirement.
Contractor further covenants that neither it nor its officers , members, agents , employees ,
subcontractors, program participants , or persons acting on their behalf, shall specify, in
solicitations or advertisements for employees to work on this contract, a maximum age limit
for such employment unless the specified maximum age limit is based upon a bona fide
occupational qualification, retirement plan or statutory requirements .
Contractor warrants it will fully comply with the policy and will defend, indemnify and hold
City harmless against any claims or allegations asserted by third parties or subcontractor
against City arising out of Contractor's and/or its subcontractors' alleged failure to comply
with the above referenced Policy concerning age discrimination in the performance of this
agreement.
10 . DISABILITY: In accordance with the provisions of the Americans With Disabilities Act of
1990 ("ADA"), Contractor warrants that it and any and all of its subcontractors will not
unlawfully discriminate on the basis of disability in the provision of services to the general
public , nor in the availability, terms and/or conditions of employment for applicants for
employment with , or employees of Contractor or any of its subcontractors . Contractor
warrants it will fully comply with ADA's provisions and any other applicable federal, state
and local laws concerning disability and will defend, indemnify and hold City harmless
against any claims or allegations asserted by third parties or subcontractors against City
arising out of Contractor's and/or its subcontractors' alleged failure to comply with the above
referenced laws concerning disability discrimination in the performance of this agreement.
11 . MINORITY AND WOMEN BUSINESS ENTERPRISES: In accord with City of Fort
Worth Ordinance No. 15530, the City of Fort Worth has goals for the participation of
minority business enterprises and women business enterprises in City contracts . A copy of
the Ordinance can be obtained from the Office of the City Secretary. The bidder shall submit
the MBE/WBE UTILIZATION FORM, SUBCONTRACTOR/SUPPLIER UTILIZATION
FORM, PRIME CONTRACTOR W AIYER FORM and/or the GOOD FAITH EFFORT
FORM ("with Documentation") and/or the JOINT VENTURE FORM as appropriate. The
Documentati on must be received by the managing department no later than 5:00 p .m., five
06/04/03
(5) City business days after the bid opening date. The bidder shall obtain a receipt from the
appropriate employee of the managing department to whom delivery was made . Such receipt
shall be evidence that the documentation was received by the City . Failure to comply shall
render the bid non-responsive.
Upon request, Contractor agrees to provide the Owner complete and accurate information
regarding actual work performed by a Minority Business Enterprise (MBE) and/or women
business enterprise (WBE) on the contract and payment thereof. Contractor further agrees to
permit any audit and/or examination of any books , records or files in its possession that will
substantiate the actual work performed by an MBE and/or WBE. The misrepresentation of
facts ( other than a negligent misrepresentation) and /or commission of fraud by the
Contractor will be grounds for termination of the contract and /or initiating action under
appropriate Federal, State or local laws or ordinances relating to false statements. Further,
any such misrepresentation of facts (other than a negligent misrepresentation) and/or
commission of fraud will result in the Contractor being determined to be irresponsible and
barred from participating in City work for a period ohime of not less than three (3) years.
12. FINAL PAYMENT, ACCEPTANCE AND WARRANTY:
a) The contractor will receive full payment (less retainage) from the city for each pay
period.
b) Payment of the retainage will be included with the final payment after acceptance of the
project as being complete .
c) The project shall be deemed complete and accepted by the City as of the date the final
punch list has been completed, as evidenced by a written statement signed by the
contractor and the City.
d) The warranty period shall begin as of the date that the final punch list has been
completed.
e) Bills Paid Affidavit and Consent of Surety shall be required prior to the final payment
becoming due and payable.
f) In the event that the Bills Paid Affidavit and Consent of Surety have been delivered to
the city and there is a dispute regarding (i) final quantities , or (ii) liquidated damages,
city shall make a progress payment in the amount that city deems due and payable.
g) In the event of a dispute regarding either final quantities or liquidated damages, the
parties shall attempt to resolve the differences within 30 calendar days.
06/04/03
PARTB
FORTW°ORTH
"'-,-.•. ~ City of Fort Worth
Minority and Women Business Enterprise Specifications
SPECIAL INSTRUCTIONS FOR BIDDERS
APPLICATION OF POLICY
If the total dollar value of the contract is $25,000 or more, the M/WBE goal is applicable.
If the total dollar value of the contract is less than $25 ,000 , the M/WBE oal is not applicable .
POLICY STATEMENT
It is the policy of the City of Fort Worth to ensure the full and equitable participation by Minority and Women Business
Enterprises (M/WBE) i n the procurement of all goods and services to the 'City on a contractual basis. All requirements
and regulations stated in the City 's current Minority and Women Business Enterprise Ordinance apply to th is bid .
M/WBE PROJECT GOALS
T he Ci ty's M/WB E goal on this project is _j_Q_% of th~ total bid (Base bid appl ies to Parks and Community Services).
COMPLIANCE TO BID SPECIFICATIONS
On City contracts of $25 ,000 or more , bidders are required to comply with the intent of the City's M/WBE Ordinance by
either of the following:
1. Meet or exceed the above stated M/WBE goal, or
2. Good Faith Effort documentation, or;
3 . Waiver documentation, or;
4. Joint Venture .
1. Subcontractor Utilization Form, if goal is received by 5:00 p.m ., five (5) City business days after the bid
met or exceeded : open ing date , exc lusive of the bid opening date .
2. Good Faith Effort and Subcontractor received by 5:00 p.m ., five (5) City business days after the bid
Utilization Form , if part icipation is less than opening date, exclus ive of the bid opening date .
stated goal :
3. Good Faith Effort and Subcontractor received by 5:00 p.m ., five (5) City bus i ness days after the bid
Utilization Form , if no M/WBE participation : opening date, exclusive of the bid opening date.
4. Prime Contractor Waiver Form , if you will received by 5:00 p.m., five (5) City business days after the bid
perform all subcontracting /supplier work : opening date, exclusive of the bid openinQ date .
5. Joint Venture Form , if utilize a joint venture received by 5:00 p.m., five (5) City bus iness days after the bid
to met or exceed goal. opening date, exclusive of the bid opening date .
FAILURE TO COMPLY WITH THE CITY'S M/W~E ORDINANCE, WILL RESULT IN THE BID BEING CONSIDERED
NON-RESPONSIVE TO SPECIFICATIONS
Any questions , please contact the M/WBE Office at (817) 392-6104.
Rev. 11/11/05
ATTACHMENT 1A
FORT WORTH ---.....------
I'.) Page 1 of 4
''2
City of Fort Worth 1 'o6 P
0 7, . <ts Subcontractors/Suppliers Utilization Form 14'
PRIME COMPANY NAME : Check applicable block to describe prime
M/W/DBE NON-M/W/DBE
BID DATE
I ~/ r3-1 / O&,
City's M/WBE Project Goal:
/i %
Prime's M BE Project Utilization:
%
{Jnfr PatJ/~i8 !1N~~'31 'f&j
'Se~, Pt77 -7031 7oa;J.o
Identify all subcontractors/suppliers you will use on this project
Failure to complete this form, in its entirety with requested documentation , and received by the Managing
Department on or before 5:00 p.m . five (5) City business days after bid opening , exclusive of bid opening date ,
will result in the bid being considered non-responsive to bid specifications .
The undersigned Offerer agrees to enter · into a formal agreement with the M/WBE firm(s) listed in this
utilization schedule , conditioned upon execution of a contract with the City of Fort Worth. The intentional
and/or knowing misrepresentation of facts is grounds for consideration of disqualification and will result in the
bid being considered non-responsive to bid specifications
M/WBEs listed toward meeting the project goal must be located in the nine (9) county marketplace or
currently doing business in the marketplace at the time of bid. Marketplace is the geographic area of Tarrant,
Parker, Johnson , Collin , Dallas , Denton , Ell is, Kaufman and Rockwall counties .
Identify each Tier level. Tier is the level of subcontracting below the prime contractor, i.e ., a direct
payment from the prime contractor to a subcontractor is considered 1st tier, a payment by a subcontractor to
its supplier is considered 2nd tier
ALL M/WBEs MUST BE CERTIFIED BEFORE CONTRACT AWARD.
Certification means those firms , located or doing business at the time of bid open ing within the Marketplace , that have
been determined to be bonafide minority or women businesses by the North Central Texas Regional Certification
Agency (NCTRCA), or the Texas Department of Transportation (TX DOT), highway division . Disadvantaged Business
Enterp ri se (DBE) is synonymous with Minority/Women Business Enterprise (M/WBE).
If hauling services are · utilized, the prime will be given credit as long as the M/WBE listed owns and
operates at least one fully licensed and operational truck to be used on the contract. The M/WBE may lease
trucks from another M/WBE firm , including M/WBE owner-operators , and rece ive full M/WBE credit. The
M/WBE may lease trucks from non-M/Wl;3Es, including owner-operators , but will only receive credit for the
fees and commissions 'earrii3d by the M/WBE as outlined in the lease aQreerilent. " ·
Rev. 5/30 /03
FORTWORTH
~ " ...... ,... .. ---I L LI u u ru,.q, I N
ATTACHMENT 1A
Page 2 of 4
Primes are requ ired to identify ALL subcontractors/suppl iers , regardless of status ; i.e., Minority , Women and non -M/WBEs .
Please list M/WBE firms first , use addit ional sheets if necessary.
Certification N
(check one) 0
SUBCONTRACTOR/SUPPLIER T n
Company Name i N T Detail Detail
C X M Subcontracting Work Supplies Purchased Dollar Amount Address e M w
Telephone/Fax r B B T D w
R 0 B E E C T E
A
ty'<Ac,¥,·~ 'f-
ROB ERT GRA ADOS T R UC KJ NG H-tt t,\, l +-$5 I too. 00
4 608 Sandage I
\ / Se,trpluS Fort Wo rth , Tex as 76 11 5 v (8 17) 875-2400
Co nc.-N, f e.,
COWTOWN RE DI-MIX /l.lCI.; fh ;x j; 8' g/ &,{){), oO
PO Box 162327
Fort Wort h, Te xas 76161 I ./ v
V (8 17)759-191 9 f (817)759-171 6
+-/yo/ ro rn CJ,, I e,, "'--
CENTEX SE EDING, Inc. S-e-e-d i~
'r It./ 3CJO · oo PO Bo x 2077 I v Kell er, Texas 76 11 6 I
(8 17) 306 -85 10 fax (817) 306-8901
,v
Magnum Ma nh o le Co mpan y r () s P" e,+ ,· ()Y\ $ J0 1 '-/0o ,00
314 S. Kirb y Stree t
I v a-&-Lr r-i-es Garland , Texas
v(214) 687 -2293 fa x(972) 2 3 1-3934
n>,~, r; \t ,~s
$ ~ ggl °!b0,00
NATION AL WATERWORKS -;-\) o \.J---LS PO Box 840700
Da ll as, Texas 75284 I ,/ (800) 252 -1 557
.
Rev. 5/30/03
FORT WORTH
~
Total Dollar Amount of M/WBE Subcontractors/Suppl iers
Total Dollar Amount of Non-M/WBE Subcontractors/Suppliers
ATTACHMENT 1A
Page 4 of 4
1 2 -21 -06 POJ :45 I N
$ /tt,5 ;oo.00
I
$ ~88, 1~D·
oO
TOTAL DOLLAR AMOUNT OF ALL ·suBCONTRACTORS/SUPPLIERS $ ~~ O&D·or>
The Contractor will not make additions, deletions, or substitutions to this certified list without the prior approval
of the Minority and Women Business Enterprise Office Manager or designee through the submittal of a
Request for Approval of Change/Addition. Any unjustified change or deletion shall be a material breach of
contract and may result in debarment in accord with the procedures outlined in the ordinance. The contractor
shall submit a detailed explanation of how the requested change/addition or deletion will affect the committed
M/WBE goal. If the detail explanation is not submitted, it will affect the final compliance determination.
By affixing a signature to this form , the Offerer further agrees to provide, directly to the City upon request,
complete and accurate information regarding actual work performed by all subcontractors, including
M/W/DBE(s) arrangements submitted with the bid. The Offerer also agrees to allow an audit and/or
examination of any books , records and files held by their company. The bidder agrees to allow the
transmission of interviews with owners, principals , officers , employees and applicable
subcontractors/suppliers/contractors participating on the contract that will substantiate the actual work
performed by the M/W/DBE(s) on this contract, by an authorized officer or employee of the City . Any
intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment
from City work for a period of not less than three (3) years and for initiating action under Federal , State or
Local laws concerning false statements . Any failure to comply with this ordinance and create a material
breach of contract may result in a determination of an irresponsible Offerer and barred from participating in
City work for a period of time not less than one (1) year.
~~ame/Title (if different) ~cA-...,C
(iJ 1 )5 :>L{ , I '1 y ':J C '6'/ i) 5 ~'-I -455 le,
~elephone and/or Fax
•
Company Name
cq:p 60f: \<SLt lJg
Address
k;{l. UJ D-< .\::.h --r 'f t lo I\ q
City/State/Zip l Date 1 itf ~1/01.o
Rev . 5/30/03
ATTACHMENT 1C
FORTW"ORTH . .__ w· ---12-2,_06
City of Fort Worth Po 7 . A
• '+ 6 IN
Page 1 of 3
Good Faith Effort Form
PRIME COMPANY NAME: Check applicable block to describe
M/W/DBE
(p
City's M/WBE Project Goal : I~ %
If you have failed to secure M/WBE participation and you have,subcontracting and/or supplier opportunities or if your
DBE participation is less than the City's proj4llct goal, you must complete this form.
If the bidder's method of compliance with the M/WBE goal is based upon demonstration of a
"good faith effort", the bidder will have the burden of correctly and accurately preparing and
submitting the documentation required by the City.· Compliance with each item, 1 thru 6 below,
shall satisfy the Good Faith Effort requirement absent proof of fraud , intentional and/or
knowing misrepresentation the facts or intentional discrimination by the bidder.
Failure to complete this form, in its entirety with supporting documentation, and received by the
Managing Department on or before 5:00 p.m. five (5) City business days after bid opening, exclusive of bid
opening date, will result in the bid being considered non-responsive to bid specifications.
1.) Please list each and every subcontracting and/or supplier opportunity} for the completion of this
project, regardless of whether it is to be provided by a M/WBE or non-M/WBE. (DO NOT LIST NAMES
OF FIRMS) On Combined Projects, list each subcontracting and or supplier opportunity through the
2°a tier.
(Use additional sheets, if necessary)
List of Subcontracting Opportunities List of Supplier Opportunities
Rev. 05/30/03
72 -2 7-Q 6 ATTACHMENT1C
PO 1 : 4 6 I N Page 2 of 3
2.) Obtain a current (not more than three (3) months old from the bid open date) list of M/WBE
subcontractors and/or suppliers from the City's M/WBE Office.
__ v{e s Date of Listing /0 I 0 ? / 0~
__ No
3.) Did you solicit bids from M/WBE firms, within the subcontracting and/or supplier areas previously
listed, at least ten calendar days prior to bid opening by mail, exclusive of the day the bids are
opened?
~ es (If yes , attach M/WBE mail listing to include name of firm and address and a dated copy of letter mailed.)
__ No
4.) Did you solicit bids from M/WBE firms, within the subcontracting and/or supplier areas previously
listed, at least ten calendar days prior to bid opening by telephone, exclusive of the day the bids are
opened?
__6es (If yes , attach list to include name of M/WBE firm, person contacted , phone number and date and time of contact.)
__ No
NOTE: A facsimile may be used to comply with either 3 or 4, but may not be used for both. If a facsimile
is used, attach the fax confirmation,. which is to provide M/WBE name, date, time, fax number and
documentation faxed.
NOTE: If the list of M/WBEs for a particular subcontracting/supplier opportunity is ten (10) or less, the
bidder must contact the entire list to be in compliance with questions 3 and 4. If the list of M/WBEs for a
particular subcontracting/supplier opportunity is ten (10) or more, the bidder must contact at least two-
thirds (2/3) of the list within such area· of opportunity, but not less than ten to be in compliance with
questions 3 and 4.
5.) Did you provide plans and specifications to potential M/WBEs or information regarding the location of
plans and specifications in order to assist the M/WBEs?
_0es
__ No
6.) Submit documentation if M/WBE quotes were rejected. The documentation submitted should be in
the forms of an affidavit, include a detailed explanation of why the M/WBE was rejected and any
supporting documentation the bidder wishes to be considered by the City. In the event of a bona fide
dispute concerning quotes, the bidder will provide for confidential in-camera access to and inspection
of any relevant documentation by City personnel.
(Please use additional sheets, if necessary, and attach.)
Company Name Telephone Contact Person Scope of Work Reason for Rejection
~J 1 n.fJ (). till rf~ 4. I )/1, JIA/LY/1 ./ --
ADDITIONAL INFORMATION:
Rev . 05/30/03
ATTACHMENT 1C
Page 3 of 3
Please provide additional information you feel will further explain yo_y r good and honest efforts to obtain
M/WBE participation on this project. <? ,2 l,
06
I /JI
The bidder further agrees to provide, directly to the City upon request, complete and
accurate information regarding actual work performed on this contract, the payment
thereof and any proposed changes to the original arrangements submitted with this bid.
The bidder also agrees to allow an audit and/or examination of any books, records and
files held by their company that will substantiate the actual work performed on this
contract, by an authorized officer or employee of the City.
Any intentional and/or knowing misrepresentation of facts will be grounds for
terminating the contract or debarment from City work for a period of not less than three
(3) years and for initiating action under Federal, State or Local laws concerning false
statements. Any failure to comply with this ordinance and creates a material breach of
contract may result in a determination of an irresponsible offeror and barred from
participating in City work for a period of time not less than one (1) year.
The undersigned certifies that the information provided and the M/WBE(s) listed
was/were contacted in good faith. It is understood that any M/WBE(s) listed in
Atta chm t 1 C ill be co d, and the reasons for not using them will be verified by
the c· M E
Title eoro~c Cot'\'vfv\)tA {oYJ 1X1L,f
Company Name
Contact Name and Title (if different)·
( ~11).1a:,y ,,7t..,J~ {8r1) 5~'f 'S/5.5(o
~hone Number Fax Number
-=PO -&i t 64 Y g-
Address ~1YzirUl ;a 1 & 11 ~
\eker ct ~.1 COOod-s e c. CJ)(!\_,
ail Ad ress
16'} ;f.1 ) 0 &
Date / /
Rev. 05/30/03
TO: Mr. Charles Boswell
City Manager
Fort Worth, Texas
PROPOSAL -ADDENDUM No. 2
FOR: SH 121 T Southwest Parkway Water· & Sanitary Sewer Main Relocations,
Part 1: 24-inch Water & 36-inch Sanitary Sewer Main at Bellaire Drive, DOE No. 5502
Part 5: 24-inch Water & Sanitary Sewer Main at Ill 20, DOE No. 5503
Part 7A: 21-inch Sanitary Sewer Main at Overton Ridge Blvd., DOE No. 5504
in Fort Worth, Texas
City Project No. 00204
Water Project No. P264-603170020483
Sewer Project No. P274-703170020483
Pursuant to the foregoing "Notice to Bidders," the undersigned has thoroughly examined the plans,
specifications and the site, understands the amount of work to be done, and hereby proposes to do all the
work and furnish all labor, equipment an materials necessary to fully complete all the work as provided in
the plans and specifications and subject to the inspection and approval of the Director, Department of
Engineering of the City of Fort Worth.
Upon acceptance of this proposal by the City Council, the bidder is bound to execute a contract and
furnish Performance , Maintenance Bond, and Payment Bond approved by the City of Fort Worth for
performing and completing the construction work within the time stated and for the following sum, to-
wit
PART 1: 24-INCH WATER & 36-INCH SANITARY SEWER MAIN AT BELLAIRE DRIVE,
DOE No. 5502
Section A -Water Main Relocations
Pay
Item
I.
2.
3 .
Estimated Unit
Quanti
640 LF
405 LF
20 LF
,\l)l)J·\:Ul i M "10 ~
Name of Pay Item with
Unit Price in Words
24-inch Bar-Wrapped Concrete Steel
Cylinder Water Pipe AWWA C303 by
Open Cut (All Depths) (Restrained) with
backfill Per Item D-24 and DA-123 @
ZOcee huada/tt,;d'( Dollars
And #0 Cents
Per Unit
42-inch Steel Casing and Stainless Steel
Spacers by Open Cut Per Item DA-6 @
hu. c_ ~ vf.tJ.Jre J {!;f.lf. Dollars
And &'O Cents
Per Unit
16-inch Ductile Iron Pipe, Pressure Class
250 (Restrained) by Open Cut (All Depths)
with backfill Per Item D-~j,
Oa e hundrt? :£ty Dollars
And Cents
Per Unit
B -lR
Unit Bid
Price
$ 330t2o
$ isa .Ot
$ LS::-0 {)IJ
Amount
Bid
$2 !.f._ 20Q.OO
$Lcf-Z 25~-bo
'
$ j a0_0 .oo ,
Pay Estimated Unit
Item Quanti
4. I EA
5 . I EA
6. I L S
7. 0 .1 TN
8 . 2 EA
9. 66 0 L F
10 . 626 LF
11. 130 S Y
.,\])l)J '\J)l !iv! '-iO. 2
Name of Pay Item with
Unit Price in Word s
16-in c h Res ilien t Seat Gat e Va lve wi th
Va ult R e: 4/02 @
--rw, Lu., t. A ~(A r.r& n r1 D o ll a r s
A nd /1/Q Cents
Pe r U ni t
2-in c h Combin a ti o n Ai r R e lease a nd
Vacuum R e li ef V a lve w ith V a ult @
J:o.C&[ t6Q1.1 S.0 od Do ll ars
A nd ,.vO Cent s
P er U nit
B a r-Wrappe d Conc re te St ee l Cy lind e r Type
F ittin gs@
~,, t_ h 0!1 S C..tl d_ D o ll a r s
A nd ~a. Cent s
Pe r U nit
D ucti le Iro n Pipe F itt in gs@
-Je11 {QQ"1.$.€H1d D o ll a r s
A nd A/0 Cents
P e r U nit
Ex pl oratory Excavatio n (D-Ho le) P e r Item
D -5 1 @
One ±.b.aLtJ.S.0nd.. D o ll ar s
A nd A/0 Cents
P e r U nit
S it e S pec ific T re n c h Safety Syst e m P e r
It e m D -2 6 @
-rA,a .. D o ll a rs
A nd /f/() Cents
P er U n it
A ba nd o n Existi ng 24-in c h Water Main
F ill e d w ith Cem e nt S lu rry P e r Ite m DA-1 19
@
!Wet:1.tc1-
I
£;v~ D o ll a r s
A nd tt/0 Cent s
P e r U nit
H ydro mulch Seedin g Per It e m D -45 @
h've Do ll a r s
And µa_ Ce nt s
P e r U nit
B -2R
Unit Bid
Price
$ I 2 1100 -~(J
$ t ()/)C?_.00
$ 14 0()()./)0
$ /0 Ooo.oo
$ ?fl.{}_Q .00
$ 3. Oo
$ 25:0..Q
$ S:OQ
Amount
Bid
$ I ,2 tJoO. oo
$ % ()()(J. 00
$ LO, Ooo .oo
$ l (J_00 -00
$,ZfJQQ .oo
$ t fJ..o... oo ,
$~ <i,so .oo
$ ,s....o.oo
Pay Estimated U nit
Item Quan ti
12. I LS
Name of Pay Item wit h
Unit Price in Words
Storm Water Pollution Prev e nti on
Implementation Pe r It em D-68 @
~O f:1, thQ0-..S.at::vf Dollars
And tJ!.f)_ Cents
Per Unit
Unit Bid
Price
$ ~ 000.00
Amount
Bid
$ i~@ -t1{)
SUBTOTAL PART l,SECTION A $ iJ'Zt 730. !JO
(Tran sfer Subtota l to Page B-6R)
List of Ductile Iron Fittings for Part l Water Line Relocations:
Quantity of Fittings Size of Fitting Type of Fitting Weight per Total Weight
Fittin lbs. lb s.
I 16-inch Plug "2.0t) 20 0
Total Weight 2 0 () lbs. ( 0 , I Tons)
/\ I) I) I ·. '; f)l I :'vl \ O '2 B -3R
Section B -San itary Sewer Main Relocations
Pay Estimated Unit
Item Quanti
I. 639 LF
2. 400 LF
3. 36 LF
4. 20 LF
5. 2 EA
6. I EA
7. I EA
Name of Pay Item with
Unit Price in Words
*36-lnch Sanitary Sewer Pipe by Open Cut
(All Depths) with backfill Per Item D-24 @
-:fi&a h.«.ndred /:.'£tit. Dollars ,
And ,;</0 Cents
Per Unit
54-inch Steel Casing and Stainless Steel
Spacers by Open Cut Per Item DA-6 @
,r;t._e h.fdr:u:ife.J 5,·x._-t't.-£·ve... Dollars
And &!'.12 Cents
Per Unit
* 12-inch Sanitary Sewer Pipe by Open Cut
(All Depths) with backfill Per Item D-24 @
(2a e. hundrej_f,-£-l'I-Dol lars
And NQ Cents
Per Unit
8-inch SDR-35 PVC Sanitary Sewer Pipe
by Open Cut (All Depths) with backfill Per
Item D-24 @
Qa e. h 1.1.n rlred Do llars
And .A/0 Cents
Per Uni t
Junction Sanitary Sewer Manhole Per Item
DA-131, RE: J-4/D6 @
7/::u'rt'j. t~at&.I. an/_ Dollars
And .:3!'.Q Cents
Per Unit
Std. 6-Foot Diameter Sanitary Sewer
Manhole, to 6' deep Per Item D-27 @
..S,·,r_ fb.0.1.dg,nJ Dollars
And A/0 Cents
Per Unit
Std. 4-Foot Diameter Sanitary Sewer
Manhole, to 6' deep Per Item D-27 @
;::OU C. t.~ Q t.,tJ.g_ !:J.,/ Dollars
And A/(2_ Cents
Per Un it
* Contractor must complete the C ity approved product form at the end of this section .
. \Dl )F \Jf)l ii\•1 \JO. 2 B-4R
Unit Bid
Price
$ ..<S .. a.atJ
$ S~S".Oo
$ IS.a,()_o
$ /J)Q.00
$ 30. {)(}IJ.M
$ t., aotJ.oo
$ 'j,.I} NJ. 00
A m ount
Bid
$/SZ 7.~.dt
$224, !JOO._Oi
$ s t;oo .o..o
'
$ ~ tJOtJ. OtJ
$ d_0,000 .0()
$ t. oa.~. O.tJ ,
$ ~()0~-0.Q
Pay
Item
8 .
9.
10 .
11.
12 .
13.
14.
I 5 .
Estimated Unit
Quanti
13 VF
13 VF
2 EA
I EA
73 VF
685 LF
2 EA
30 LF
Name of Pay Item with
U nit P rice in Words
Extra Depth for 6-Foot Diameter Sanitary
Sewer Manholes Greater than 6 Feet Deep
Per Item D-27 @
-Ji,,) Q ~ IA Q dr_erl £.I. £-6..v Dollars
I
And NO C ents
Per Unit
Extra Depth for 4-Foot Diameter Sanitary
Sewer Manholes Greater than 6 Feet Deep
Per Item D-27@
..-.-tJ "1.tJ drcd i wa Do ll a rs
An d NQ Cents
P er Un it
Concrete Collar for Manhole Per Item D-27
@
~,-k'.'.e. tJ l,:',.adr~J Dollars
And /f,I() Cents
Per Unit
Water Tight Manhole Insert for Manhole
Per Item D-27 @
tPa.e ~ k!ll dre. d Do llars
And ~Q Cents
Pe r Unit
Interior Manhole Protective Coating Per
Item DA-I I , DA-14 or DA-15 @
7WQ b. u. CJ dr e_ ,./ Dollars
An d /1/0 Cents
P e r Unit
Site Specific Trench Safety System Per
Item D-26 @
-rh.c.ee Dollars
And A/0 Cents
Per Unit
Abandon Existing Sanitary Sewer Manhole
Per Item DA-120 @
· E,·£teen b.Y.t:1.dr.::d Do llars
An d /VQ Cents
P er Unit
Abandon Existing 42-inch Sanitary Sewer
Main Filled with Cement Slurry Per Item
DA-I 19 @
Fo. r ti{._ Do ll a rs
I
And /VQ Cents
Per Uni t
B -SR
Unit Bid
Price
$ 25().0u
$ 2.0.0.00
$ StJ()_.Oo
$ !._oo.oo
$ .2 {){J. 0(2
$ 3.0o
$ /, 500.Qt)
$ ~Q .OQ
Amount
Bid
$] ;;,.so.oo
7
$,Z t()o. o.a
$ ~ tJtJ tJ. 00
$ Lt20 .oo
$ Lt too.(!)
$ :2, 0 ss. OtJ
$ 3 ooo . 0()
$ t2or2..~
Pay Estimated Unit
Item Quan ti
16. 10 LF
17. 601 LF
18. 1,42 5 LF
19. 685 LF
20. 4 EA
21. 225 SY
22. I LS
Name of Pay Item with
Unit Price in Words
Abandon Existing 39-inch Sanitary Sewer
Main Filled with Cement Slurry Per Item
DA-119 @
-r6.;c.b1.-r,·fLe. Do llars
And ~o Cents
Per Unit
Abandon Existing 36-inch Sanitary Sewer
Main Filled with Cement Slurry Per Item
DA-119 @
16:c.-1:. 'I-Dollars
And /VQ Cents
Per Unit
Pre-Construction Television Inspection of
Sanitary Sewer Lines Per Item D-35 @
;::,· ve. Do llars
And ~o Cents
P er Unit
Post-Construction Television Inspection of
Sanitary Sewer Lines Per Item D-38 @
16ree. Dollars
And ~o Cents
Per Unit
Vacuum Testing of Sanitary Sewer
Manholes Per Item D-36 @
()tl.e_ tb. (J_(d J. CJ. t:J / Do llars
And HO Cents
P er Unit
Hydromulch Seeding Per Item D-45 @
;::,·v, Dollars
And .tVO Cents
Per Unit
Storm Water Pollution Prevention
Implementation Per Item D-68 @
Faf6, tha~S.{!.ad_ Dollars
And /1(0 Cents
Per Unit
Unit Bid
Price
$ .35.0o
$ 3600
$ 5. tJo
$ 3.do
$ 4 t)a_o.otJ
$ s. tJo
$ iOtJO .~a
Amount
B id
$ 3StJ .ao
$ ~ tJ3tJ. {t,
$ 2.1..d..S.Oi
$ i oss.~
$ ~ t)a_t). 00
$ t L2.£.00
$ ~ oa_c...o.o
SUBTOTAL PART I, SECTION B $ 52 Z tz ro. 00
SUBTOTAL PART I, SECTION A $ l/ Cf Z 73 0 . 0 0
TOTAL PART I -(SECTION A and SECTION B) $ 225,370.00
(Transfer Total to Page B-20R)
AD DE\JD l l f\11 \iO. 2 B-6R
CITY APPROVED PRODUCT FORM
for
Part 1: 24-inch Water Main & 36-inch Sanitary Sewer Main at Bellaire Drive -City Project
No . 00204 , DOE Project No . 5502
*CONTRACTOR SHALL SELECT TYPE OF PIPE TO BE USED:
ST ANDA RD SP E CIFICATION NO. PIPE SIZE
El-04 with T-Lock Interior Linin g 36 "
~ E 1-06 with Protecto 40 I Interior Lining 12 " thru 36"
DA-124 12 " thru 36"
El-25 4" thru 15 "
El -27 4 " thru I 5"
El-28 I 8" thru 27 "
~ EI00-2 4 " thru 48 "
Consult the "City of Fort Worth , T exas standard Product List" to obtain the Ge neric/Trade Name
and the Manufacture for the pipe s li ste d above .
Failure to provide the in fonnation required above may result in rejection of bid as non-responsive.
Only products or methods listed above will be a ll owed for use in this project. Any s ub stitution sha ll
result in rejection of bid as non-responsive .
!\DDF\!Dl ·M \10. 2 B-7R
PART 5: 24-INCH WATER & SANITARY SEWER MAIN AT 1H 20, DOE No. 5503
Section A -Water Main Relocations
Pay Estimated Un it
Item Quan ti
la . 284 LF
lb . 284 LF
Name of Pay Item w ith
Unit Price in Words
24-inch Ductile Iron Pipe, Pressure Class 250
(Restrained) by Open Cut Per Item DA-I I 9 @
5,·,x b.Y.oJr~J f,·£tv Dollars
I
And ~'2 Cents
Per Unit
24-inch Bar-Wrapped Concrete Steel
Cylinder Water Pipe AWWA C303 by
Open Cut (All Depths) (Restrained) with
backfill Per Item D-24 and DA-123 @
/Vtl /]/ !) Dollars
And Cents
Per Unit
Unit Bid
Price
$ ~SfJ.o_()
$ /ti()__ 8/Q
Amount
Bid
$LJ'i 6_0o .oo
$ ~o !31/J
*Note: Bids sho uld be s ubmitted for only one of the pipe material alternates a or b.
2a. 560 LF 24-inch Ductile Iron Pipe, Pressure Class
250 (Restrained) by Other than Open Cut
w/42" Steel Casing and Stainless Steel
Spacers Per Item DA-6 @
E ~ 6t ~~{Jdre.J {·ft,({_ Dollars
And A/0 Cents $ i.25.~o $ '-I ti {} (JO .rk
Per Unit
2b. 560 LF 24-inch Bar-Wrapped Concrete Steel
Cylinder Water Pipe A WW A C303 Type by
Other than Open Cut (Restrained) w/42"
Steel Casing and Stainless Steel Spacers Pe r
Item DA-6 @
A/I) AL/J Dollars
And Cents $ ,#t? '1 I IJ $ /1-'() 81(]
Per Unit
*Note: Bids s hould be s ubmitted for only one of the pipe material a lternates a or b.
3a. 3.0 TN 24-inch Ductile Iron Pipe Fittings @
-[et)_ l:/i._e_(df__at1.d Dollars
And .#(2_ Cents $ f4_~!}~.#() $ .10. ~a.(2.~0
Per Unit
3b. I LS Bar-Wrapped Concrete Steel Cyl ind er Type
Fittings@
A/0 t1D Dollars
And Cents $ A'O 81D $ /tl'O 3/iJ
Per Unit
*Note: Bids should be submitted for only one of the pipe material alternates a or b.
.-\D l )L'\iDl ;\1 \!O. 2 B -8R
Pay Estimated Unit
Item Quan ti
4 . 50 LF
5. 21 LF
6 . 40 LF
7 . 3 EA
8 . I EA
9. 1.6 TN
10 . I EA
11. I EA
,\!)!)!· \'!)l i!'vl \'() 2
Name of Pay Item with
Unit P rice in Words
42-inch S tee l Casing and Stainless Steel
Spacers Pe r by Open Cut Item DA-6 @
;:,·f'.e D. vtrJdred Dollars
And ,,v() Cents
Per Unit
16-inch Ductile Iron Pipe, Pressure Class
250 (Restrained) by Open Cut (All Depths)
with backfill Per Item D-24 @
fov1.r h 0, f\ Jr eJ f.· £ t '/-Dollars
And &12 Cents
Per Unit
12-inch Ductile Iron Pipe, Pressure Class
350 (Restrained) by Open Cut (All Depths)
with backfill Per Item D -24 @
flicee h yndre/ .P.·£ty Dollars
And A/0 Cents
Per Unit
24 -i nch Resilient Seat Gate Valve with
Vault Re: 4/D2@
--fuu.a tt,/--e ,~~ t I Li Q U.SJ< n/ Dollars
And N'!Z Cents
Per Unit
12-inch Resilient Seat Gate Valve with Box
R e: 3/DI@
--ft.oo. t..i {)_(df(i.11/ Dollars
And A/0 Cents
Per Unit
Ductile Iron Pipe Fittings@
;:;;_"1_{_ t/1_f2.t< .J a. a/ Dollars
And ,c/(2_ Cents
Per Unit
2-i nch Combination Air Release and
Vacuum Relief Valve with Vault @
h1:1c tno. (,J.,iC<nd Doll ar s
A nd A/0 Cents
Per Unit
6-inch Blow Off Valve and Vault @
.51i. {~{)_~Sand Dollars
And A/Q Cents
Per Unit
B-9R
Unit Bid
Price
$ sr2.a_. ~tJ
$ l/50.00
$ 3.56.00
$,lJ_/)dtl_.0()_
$ 2;_ tJ a_a_. d 0
$ 't-tJ (2_(2_. t ()
$ ~Qa_o.()o
$ '~()_Q.()o
Amount
Bid
$25, 0()(). oo
$ 2 l/S(). do
$ L~ 000 .00
$ J''/,&M.00
$ 2. I} tJ()_. a()
$ i lf_(}tJ.tJd
$ ~ a_d_r2_. a_o
$ ~ 0..tN..O~
Pay Estimated Unit
Item Quanti
12. 2 EA
13. 195 LF
14 . 822 LF
15 . 20 LF
16 . 30 SY
17 . 1,095 SY
18 . I EA
ADD l:\.i!)! ;:'-1 '-J( l . 2
Name of Pay It e m with
Unit Price in Words
Exp loratory Excavation (D-Hole) Per Item
D-51@
(} [}_ e.. tha1t1s.{J.{l J Dollars
And /f/Q Cents
Per Unit
Site Specific Trench Safety System Per
Item D-26 @
-rh.c.e. e_ Dollars
And A/0 Cents
Per Unit
Abandon Existing 16-inch Water Main
Filled with Cement S lu rry Per Item DA-119
@
1W e..n t'I-Dollars
And ..-VQ Cents
Per Unit
Concrete Curb & Gutter Re placement Per
Item DA-24 @
7!,/~i.'1--Dollars
And ,,# () Cents
Per Unit
Concrete Sidewalk and Driveway
Replacement Per Item D-20 @
h '/i\L Dollars
}
And /1/'2. Cents
Per Unit
Hydromulch Seeding Per Item 0-45 @
A ·vec Dollars
And A/0 Cents
Per Unit
Remove Existing Gate Valve and Deliver to
Field Operations @
tlne fll.Qe&ia.n. d Dollars
And ~Q Cents
Per Unit
B -IOR
Unit Bid
Price
$ LtJilO~
$ 3.oa
$ 20.00
$ 30.00
$ 5().00
$ S.00
$ I, IHJ.a..Qo
Amount
Bid
$ .2< ()0(). fJO
$ Sgs . oo
$ /4, 'IYtJ.tJo
$ ~o~_{)o
$ 1,soo.00
$ S, 'L ZS.&t
$ L. ~o.o.. (10
Pay
Item
19.
20 .
Estimated Unit
Quanti
I LS
135 SY
Name of Pay Item with
Unit Price in Words
Stonn Water Pollution Prevention
Implementation Per Item D-68 @
Co"1 r t.hr1.t:1f..~11d. Dollars
And ~o. Cents
Per Unit
6-inch Concrete Riprap Per Item DA-40 @
s,·!..tv Dollars
I
And A/Q Cents
Per Unit
Unit Bid
Price
$ t ~O(}. 0{}
$ 6.tJ ... ~a
Amount
Bid
$ 'I, a_()_ O.Q o
$ RlflO .oo
SUBTOTAL PART 5, SECTION A $ 8&! Z /SO. t)O
List of Ductile Iron Fittings for Part 5 Water Line Relocations:
Quantity of Fittings Size of Fitting Type of Fitting
I 24 -in ch x I 2-inch MJ Tee
'l-24-inch x I 6-inch MJ Reducer
I I 2-inch x I 0-inch MJ Reducer
L 24-inch 45 degree Bend
'2-24-inch 22 .5 degree Bend
9 I 6-inch 22 .5 degree Bend
'?_ I 6-inch I I .25 degree Bend
'L I 6-inch Solid Sleeve
"Z..... I 0-inch Solid Sleeve
I I 6-inch Plug
(Transfer Subtotal to Page B-I 5R)
Weight per
Fittin lbs.
r-oo
'f:O 0
7 00
5 DO
rn o
1..f.f) ()
'{DO
.?oO
I ()O
coo
Total Weight
lbs.
5 00
J>o o
'2... () <)
/{)0 0
/i>oO
f" 0
fOO
~() 0
<,..0 0
2 C, ()
Total Weight & / d O lbs. ( 3, O ~ Tons)
(Note: All fittings may not be needed if alternate b is chosen.)
AD D l:.'\i Dl l :VI !0. 2 B -I JR
Section B -Sa ni tary Sewer Relocations
Pay Estim ated U nit
Item Quan ti
I. 237 LF
2. 622 LF
3. 27 LF
4. I EA
5. 2 EA
6 . I EA
7. I EA
Na me o f Pay Item wit h
Unit P rice in Words
*24-inch Sanitary Sewer Pipe by Open Cut
(All Depths) with backfi ll Per Item D-24 @
f"ou r 6 &tndre/ £· £t.y. Do llars
An d d{_O Cents
Per Unit
*24-inch Sanitary Sewer Pipe by Other than
Open Cut w/42" Steel Cas ing and Stainless
Steel Spacers Per Item DA-6 @
£j ht b w1dn•l t1uttzty-£'vd)ollars
And /</0 Cents
Per Unit
* I 0 -inch Sanitary Sewer Pipe by Open Cut
(All Depths) with backfill Per Item D-24 @
-r1:u.~ 6.'.t!!JJrei Dollars
An d A/() Cents
Per Unit
Junction Sanitary Sewer Manhole Per Item
DA-131, RE: l/D7 and 2/D7 @
FQc.t~ tb 0. '1 if!.t:1.d Do llars
And ..V'2 Cents
Per Unit
Std. 5-Foot Diameter Sanitary Sewer
Manhole, to 6' deep Per Item D-27 @
,C/fL.e tb.a u ~a 11 d.. Dollars
And ~Q Cents
Per Unit
Std. 4-Foot Diameter Sanitary Sewer
Manhole, to 6 ' deep Per Item D-27 @
h>Ld.C. -tA {l_(d.f.e.a d Doll a rs
And t!lL.t2. Cents
Pe r Unit
Modified Type "A" 5-Foot Diameter
Sanitary Sewer Manhole Per Item D-27 @
2 e. vf! a t.¥. -.P, · ve. A u.11J rf'd Do ll a rs
And /VO Cents
Pe r Unit
* Contractor must complete the City approved product form at the end of this section .
,\DDL :f)1 1~vl NO. 2 B -12R
Unit Bid
Price
$ 'i_S (). ao
$ J'2S.()o
$ 3tJc. Oo
$ ~t? j(}(}_.dO
$ 5;.. Q(J.(2.J).O
$ '/,.J./)Q . (){)
$ 7. s IJCJ. ~
Amo un t
Bid
$1._0~ ~i.0.tA'
$ 513, ISO. ob
$ J;_/O().OO
$ '14_!} oo. oo
$ ii). M. d. ~o
$ ~ f/..OtJ. a.o
$ Z s__oa.. a.a
Pay Estimated Unit
Item Quan ti
8 . 34 VF
9. 18 VF
10. 3 EA
11. I EA
12 . 97 VF
13 . 28 1 LF
14 . I EA
15. 826 LF
/\l)DL . 'DL lfVI , ·o . 2
Name of Pay Item with
Unit Price in Words
Extra Depth for 5-Foot Diameter Sanitary
Sewer M anholes Greater than 6 ' Deep Per
It e m D-27 @
'ltila b ,.~w d, e d £, "f. t ¥ Dollars
And ,N(?_ Cents
Per Unit
Extra Depth for 4-Foot Diameter Sanitary
Sewer Manholes Greater than 6 ' Deep Per
Item D-27 @
-fwo. b. vt nd,!.J Dollars
And ~a Cents
Per Unit
Concrete Collar for Manhole Per Item D-27
@
;=; (/" b.w(Jdre/ Dollars
And Cents
Per Unit
W ate r Tight Manhole In sert for Manhole
P e r Item D-27 @
tJ{)_e Af1.tJdreJ Dollars
And /VO Cents
Per Unit
Inte rior Manhole Protecti ve Coating Per
It e m DA-11 , DA-14 o r DA-15 @
ft.tJ Q tJ.0.11J red Dollars
And /VQ Cents
Per Unit
Site Specific Trench Safety System Per
It em D-26 @
Ih.c.e.e. Dollars
And /VO Cents
Per Unit
Abandon Existing Sanitary Sewer Manhole
Per Item DA-120 @
F,·£tu,, b. ua.dn/ Dollars
And ,,vp Cents
Per Unit
Abandon Existing 24-inch Sanitary Sewer
Main Filled with Cement Slurry Per Item
DA-119 @
Ju2e{J_ ty.-f,'ve. Dol lars
And NO Cents
Per Unit
B -13R
Unit Bid
Price
$ 25._0.Qo
i 2_()_Q.OO
$ so.o..fl..o
$ JfJtt ()o
$ 2t0.0{)
$ 3. oo.
$ I r.~a..Po
$ 2£0.D
Amount
Bid
$ ~ SJJ.Q .00
$ i (?_otJ .O.O
$ ~So.a.OQ
$ /00 .()()
$ I 4. 'f_Pd . 0()
$ Jl/3. Q~
$ tSiQ . PO
$::20, ~so .oo .,
Pay Estimated Unit
Item Quan ti
16. 53 LF
17 . 1,243 LF
18 . 903 LF
19 . 5 EA
20. 50 LF
21. 240 SY
22. 600 SY
23 . I LS
i\1)1)1:.\.J!)l IM \iO. 2
Name of Pay Item with
Unit Price in Words
Abandon Existing 18-inch Sanitary Sewer
Main Filled with Cement Slurry Per Item
DA-119 @
/bfl. ea. t. 'z:'.: Dollars
i
And .NO Cents
Per Unit
Pre-Construction Television Inspection of
Sanitary Sewer Lines Per Item D-35 @
;::/ ve... Dollars
And A/0 Cents
Per Unit
Post-Construction Television Inspection of
Sanitary Sewer Lines Per Item 0-38 @
--Z:-hf'ee. Dollars
And /VO Cents
Per Unit
Vacuum Testing of Sanitary Sewer
Manholes Per Item D-36 @
{)tJ..e tha.tAJ.end Do llars
And tJt. Q Cents
Per Unit
Concrete Curb and Gutter Replacement Per
Item DA-24 @
76.t'c. tv Dollars
I
And /f/0 Cents
Per Unit
Concrete Pavement Repair Per Figure
2000-2 @
5; Kt, 11 --t:.1 '1,t,e. Dollars
'
And .#j2 Cents
P er Unit
H y dromulch Seeding Per Item D-45 @
h '11..~ Dollars
And .A/0 Cents
Per Unit
Storm Water Pollution Prevention
Implementation Per Item D -68 @
f'our t6QIA,S,~nd_ Do llars
And A/D Cents
Per Unit
B -14R
Unit Bid
Price
$ .20. Oo
$ S.()o
$ 3.00
$ l 11. a 0. ./U.
$ 30.()_Q
$ ~ S". Oo
$ S.OQ
$ ~ooo_.oo
Amount
Bid
$ L O(;_ o. CJ()
$ /,, 2/S.~()
$ .z zaz(}o
$ rt2ao_. Qo
$ t.IOd... 00
$ L5,. t.,_ dtJ.~o
$ l aoo..a()
$ ':I_ QQQ .00 I
SUBTOTAL PART 5, SECTION B $ 7£ ~ S7 7. () 0
SUBTOTAL PART 5, SECTION A $ ir; Z IS cJ . 0 0
TOTAL PART 5 -(SECTION A a nd SECTION B) $ /, &, St 7 2 7. M
CITY APPROVED PRODUCT FORM
for
(Transfer Total to Page B -20R)
Part 5: 24-i nch Water & Sanitary Sewer Main at IH 20 -City Project No . 00204 ,
DOE Project No . 5503
*CONTRACTOR SHALL SELECT TYPE OF PIPE TO BE USED:
ST AND ARD SPECIFICATION NO. PIPE SIZE
El-04 with T-Lock Interior Lining 24"
,L': E 1-06 with Protecto 401 Interior Lining JO " thru 24"
DA-124 10 " thru 24"
El-25 4 " thru 15 "
E l-27 4" thru 15 "
E l-2 8 18 " thru 27"
,_____ E l 00-2 4" thru 48 "
Consult the "City of Fort Worth , Texas sta nd ard Product List" to obtain th e Generic/Trade N ame
and the Manufacture for the pipes li ste d above.
Failure to provide the infonnation required above may result in rejection of bid as non-responsive .
Only produ cts o r meth o ds liste d above w ill be allowed for u se in thi s project. Any s ubstitution s hall
re s ult in reje cti o n of bid as non-res ponsive .
_,\l)l)L l [)l lfVl i () 2 B - J SR
Part 7A: 21-inch Sa n itary Sewer Main at Overton Ridge Blvd., DOE No. 5504
Pay Es timated U nit
Ite m Quan ti
I. 1,11 2 LF
2. 209 LF
3. I EA
4 . 3 EA
5. I EA
6. 3 1 VF
7 . 4 VF
Name of Pay Item with
Unit Price i n Word s
*2 1-in ch Sa nitary Sewe r P ipe by O pen Cut
(A ll De pth s) w ith bac kfill Pe r It em D-24@
fh r ee htA11dcel Dollars
And &'2 Cents
Per Un it
*8-in ch Sa nit ary Sewe r Pip e by O pen Cut
(A ll De pth s) with backfill Per It em D-24@
One. J1&.{).cfre~ /',l._t.v Dollars
I
And /VO Cents
Per Unit
Ju nc ti o n Sanitary Sewe r Manh o le Per It em
DA-1 3 1, RE : 3/D 7 and 4/D 7 @
J/J.,'rfit. t~ol,!.f{1.a.d Dollars
I
And ~12 Cents
Per Unit
Std . 5-Foo t Di ameter Sa ni tary Sewe r
Ma nh o le, to 6 ' dee p Per It em D-27 @
F/ve f./, (2u.£a n / Dollars
And ~() Cents
Per Unit
Std. 4-Foo t Di ameter Sa nit ary Sewe r
Ma nh o le, to 6 ' d ee p Per It em D-27 @
;::Q(&. c:. t-./iQr.&SCt nd Dollars
And dt::_(2, Cents
Pe r Unit
Ex tra De pth fo r 5-Foo t Di ameter Sa nit ary
Sewer Ma nh o les Grea ter th an 6' Dee p Per
It em D-27 @
~o /J.u,,Jrf'/._ Dollars
And &/'.12 Cents
Per Unit
Ex tra De pth fo r 4-Foo t Di amete r Sa nit ary
Sewe r M anh oles Gr ea ter th an 6 ' D ee p Per
It em D-27@
O.t1.e /J..Y,.a.d.r..d .Sevedc1..-l1(fo ll ars
And &Q Cents
Per Un it
* Contrac to r m u st comple te t he City approve d p ro du ct fo rm at the e nd of th is sectio n .
.\1)1)1.'-:[)l '1\1 '.;(!, 2 B-16R
Unit Bid
Price
$ 3_ 00 .00
$ /50.00
$ 3()£00~~0
$ S,~(2_()..dO
$ 'i (}(}_a_. Oo
$ 200.00
$ L7S.ao
Amount
B id
$ 333. {g_Oo.to
$ 3t35a.oo
$ JO,O()_Q.00
$ {.£ tJo_o_. 00
$ ~/}(2_0.00
$ ~. 21Jo.oo
$ 7tJ(l oo
Pay Estimated Unit
Item Quan ti
8. 4 EA
9 . I EA
JO . 3 8 VF
I I. 80 LF
12. 90 LF
13. 1,32 1 LF
14 . 3 EA
15. 1,057 LF
/\l )l)J-.'\i[)\ •!Vl 10 . 2
Name of Pay Item with
Unit Price in Words
Co ncrete Co llar for Manh o le Per Item D-2 7
@
r/ /le-h_ Ul'.] Jred Dollars
And ,</~ Cents
Per Unit
Water Tight Manhole In se rt s for Manhole
Per Item D-27 @
t2lJ. ea O.r&tJ.ducl Dollars
And #Q Cents
Per Unit
Interior Manhole Protective Coating Per
Item DA-11, DA-14 or DA-15 @
/00 /J.undre/ Dollars
And ~'2 Cents
Per Unit
Co ncrete Enca se ment of 18-inch Sanitary
Sewe r Pip e Per It em D-49@
r-;£tv Dollars
I
And A/0 Cents
Per Unit
Co ncret e Encasement of 8-inch Sanitary
Sewer Pipe Per Item D-49 @
rQ.c. t¥-Dollars
And &Q Cents
Per Unit
Site Specific Trench Safety System Per
Item D-26 @
nc.ee. Dollars
And '1<'.Q Cents
Per Unit
Abandon Exis ting Sanitary Sewer Manhole
Per Item DA -120 @
0.ll.e tb.o.1&..J..a11J Dollars
And &.a. Cents
Per Unit
Abandon Ex isting 18-inch Sanitary Sewer
Main Filled w ith Cement Slurry Per Item
DA-119 @
ffec?t:1. tv Dollars
I
And ;i.10 Cents
Per Unit
B -17R
Unit Bid
Price
$ Sfl..Q .(}_tJ
$ 1{20.00
$ ,?oo.oo
$ S~.oo
$ '-/(}. 0 0
$ 3.aa
~ i,(20~.0Q
$ ,2/J.Oo
Amount
Bid
$ 26IJIJ.OO
$ ltJ0 .00
$ Z 6' 00.00
$ ~ 000.00
$ 3.,~00..00
$ 3. 2,s,to
$ .i'. ~a.4.~o
$ 21, /7'Q .i:lo
Pay Est imated U nit
Item Q ua n ti
16. 20 LF
17 . 974 SY
18 . 1,502 LF
19 . 1,32 1 LF
20 . 5 EA
21. 53 SY
22 . I LS
Name of Pay Ite m with
Unit P rice in Wo rds
Ab and o n Exi stin g 8-in c h Sa nit ary Sewe r
Mai n F ill ed with Ce me nt S lu rry Per It em
DA-11 9 @
;:,-£.. t ~ e tz Dollars
And ~o Cents
Per Unit
18 -inch Rock RipR a p Pe r It em DA-39 @
.ie ~{.ll 6/. -£,·,,.., Do ll ar s
And A/Q Ce nt s
Per Unit
Pre-Co nstructi on T e lev is ion In s pe cti on of
Sa nit ary Sewe r Line s Per It em D-35 @
,,C","v~ Dollars
And A-' 0 Cents
Pe r Un it
Pos t-Co nstru cti o n T e lev ision In spec ti o n of
Sa nit ary Sewe r L in es Per It em D -3 8 @
-rA £.,e-Do llars
And dL_(l_ Cents
Per Unit
Vac uum T es tin g of Sani tary Sewe r
Ma nh o les Per It em D-36 @
~,·Vt'_ b_t,t[J_ d.nJ Dollars
And &.a Cents
Per Un it
Hydro mu lc h See din g Per It em D-45 @
;:-,·v~ Dollars
And .-vo Cents
Per Unit
Storm Wat er Po lluti on Pr eve nti on
Impl eme nt ati on Per It em D-68 @
ra~r-t~o.u.S.g_t:1d Dollars
And ;1/Q Ce nts
Per Unit
Unit Bid
Price
$ IS. oo
$ ff.00
$ S: ()o
$ 3. tJo
$ Sl)()_.(}_o
$ s. ~ IJ
$ ~ 12_~(!_./)0
Amount
B id
$ 3 00.0()
$ 7? /J .<;0111 ,
~ z. s 1..0..ao
$ 3, 7~]./~
$ -<. S~(}_.QO
$ .2.6 S .(!_O
$ '£. OCl._O. 0~
TOTALPART7A $ S57 JY/.00
(Transfer'Tota l to Page B-20 R)
B -18R
CITY APPROVED PRODUCT FORM
for
Part 7 A: 21-inch Sanitary Sewer Main at Overton Ridge Blvd. -City Project No . 00204,
DOE Project No. 5304
*CONTRACTOR SHALL SELECT TYPE OF PIPE TO BE USED:
ST AND ARD SPECIFICATION NO .
______ E 1-04 with T-Lock Interior Linin g
______ E 1-06 with Protecto 40 I Interior Lining
DA-124 ------
/El-25
El-27 ------
~ EI00-2
PIPE S IZ E
21 "
8" thru 24"
8" thru 24 "
4" thru 15 "
4" thru 15 "
4 " thru 48"
Consult the "City of Fort Worth, T exas standard Product Li st" to obtain the G e neric/Tra de Name
and the Manufacture for the pipes li sted above .
Failure to provide the information required above may result in r ejection of bid as non-respo nsive.
Only products or methods listed above will be allowed for use in this project. Any substitution s hall
result in rejection of bid as non-res pon sive .
• \l)l)L"JD UM NO 2 B -19R
SUMMARY OF BIDS
Total Part 1: 24-inch Water & 36-inch Sanitary
Sewer Main at Bellaire Drive, DOE No. 5502
Total Part 5: 24-inch Water & Sanitary Sewer
Main at IH 20, DOE No. 5503
Total Part 7A: 21-inch Sanitary Sewer Main
at Overton Ridge Blvd., DOE No. 5504
Grand Total (Parts 1, 5, and 7A)
$
$
$
$
975,370.00
'
4 ~5}, 727.()0
55 Z 3lf /. 00
j, /J l/, 9 3t. 00
(Award of contract, if made, shall be to the overall responsive low bidder of Parts 1, 5, and
7 A combined.)
.·\DDl ·.:\JDllM \JO. 2 B -20R
PROPOSAL
MATERIAL SUPPLIER INFORMATION FORM-36, 24, and 21 inch Pipe
DUCTILE IRON PIPE
The ductile iron pipe and valve supplier information form bound with this project manual shall be
provided by the Contractor at the time that bids were submitted.
l/5. /J 1f e
Name of Manufacturer Type of Pipe
J Home Office Address of Manufacturer
Location of plant in which pipe and fittings are to be manufactured
A WWA C303 CONCRETE PRESSURE PIPE, BAR-WRAPPED STEEL CYLINDER TYPE
The concrete cylinder pipe supplier information form bound with this project manual shall be provided by
the Contractor at the time that bids were submitted .
Name of Manufacturer Type of Pipe
Dt1-1-1A f , -r-:; ~5
~ 7
Home Office Address of Manufacturer
Location of plant in which pipe and fitti~gs are to be manufactured
B -21R
PROPOSAL
MATERIAL SUPPLIER INFORMATION FORM-16, 12, 10, and 8 inch Pipe
DUCTILE IRON PIPE
The ductile iron pipe and valve supplier information form bound with this project manual shall be
provided by the Contractor at the time that bids were submitted.
Name of Manufacturer Type of Pipe
A L
Home Office Address of Manufacturer
.,
Location of plant in which pipe and fittings are to be manufactured
PVC PIPE
The PVC pipe and valve supplier information form bound with this project manual shall be provided by
the Contractor at the time that bids were submitted .
Name of Manufacturer Type of Pipe
Home Office Address of Manufacturer
7
Location of plant in which pipe and fittings are to be manufactured
.\!)I)!-. 1 l)l !M NO. 2 B -22R
PROPOSAL
Within ten ( 10) days of notification by City, the undersigned will execute the formal contract and deliver
an approved Surety Bond and s uch other bonds as required by the Contract Documents, for the faithful
perform a nce of this Contract. The attached bid security in the amount of$ is to
bec o me the property of the City of Fort Worth , Texas, in the event the contract and bond or bonds are not
executed and delivered within the time above set forth as liquidated damages for the delay and additional
work caused th e reby .
The undersi g ned bidder verified that he has obtained at least one set of the General Contract Documents
and General Specifications for Water Department Projects dated January 1, 1978, and that he has read and
thoroughl y understands all the requirements a nd conditions of those General Documents, and the specific
Contract Documents and appurtenant plans .
The undersigned assures that its employees and applicants for employment and those of any labor
organization, subcontractors, or employment agency in either furnishing of referring employee applicants
to the undersigned are not discriminated against as prohibited by the terms of City Ordinance No. 7278 as
amended by the City Ordinance No . 7400.
The bidder agrees to begin construction within 10 calendar days after issue of the work order, and to
complete the contract within 200 calendar days as set forth in the written work order to be furnished by
the Owner. The work order will be iss ued no later than 90 days after the award of the contract.
A . The principal place of business of our company is in the State of ___________ _
Non-resident bidders in the State of , our principal place of business, are
required to be percent lower than resident bidders by state law . A copy of the statute
is attached .
Non-resident bidders in the State of ________ , our principal place of business, are not
required to underbid resident bidders.
@ The principal place of business of our company or our pare nt company or majority owner is in the
State of Texas.
Rec e ipt is acknowledged of the following addenda:
Addendum No . I (initials) ft
Addendum No. 2 (initials) d1C,,-
Addendum No. 3 (initials) ___ _
(SEAL) if Bidder is Corporation
Date: /'2 /2.,1 /c,!'.;
I I
B -23R
Respectfully submitted,
~LP :.:::c.::fu
I
Title: &e,5,·Jea t
Address: P 0. Box l5<t'Lcf
Ea cf hlac±b TX 7~ //9
Telephone: &17-Ss V-17 93
-
\
.....,,,
J ..
~.'-..r
/.
,I
'--
-t"":
-I,
( ..
't
~ II:
,· -?1
'··
,.'
r •
,,
• ,,
SI
~ . ,
'
\
' '
~
"I
-•l
~
"" • .;,
I
',. ,,
( '
.. '
..
?
i
' ..
',,
i
. '
'
., .
. ...
f,
~·,
....
~
··~ ... ,,'
\
' .
PARTC
• ,,
,
I
.. ,,,
>1'
... , .fi'
..
.'
'
• A
. ·\
'
. ...
\
;.
"'
I •• t
¥
•" '
~
,.
{
7,
" ,•
. "
,. '
~
" '
~ , ., .
(
, ..
~
,:
'°•T.
\
r
' ' :
t·
' ..
~ ..
' .,
.· ..,, •I'
.«·
\'
J,f',.._
~fkl
..... .,.
> .
" i•
'" '
'.
;,-~-.... ,.
" ' t
' f
·,"
(-
"'~· ,;,. . :,. ~ . . ,, ..
' ..
7
J .,.
.. '
•I''
;
..• '••
:..
~··
.. .,
\
i.,,er,
' .;
•,
' ..... ;.-•1,,..
~ ...
-1/ Jtf"\ '.':.:
~ . :t_.>t .,
,,
.,
.r {;1 t
, __ r;,, t~·>
} ..
..
'!.
, ,.
,,
> !
, ..
__,
PART C -GENERAL CONDITIONS
TABLE OF CONTENTS
NOVEMBER 1, 1987
TABLE OF CONTENTS
Cl-I DEFINITIONS Cl-I (1)
Cl-I.I Definition of Terms Cl-I (1)
Cl-1.2 Contract Documents Cl-I (2)
C 1-1.3 Notice to Bidders Cl-I (2)
Cl-1.4 Proposal Cl-I (2)
Cl-1.5 Bidder Cl-I (2)
Cl-1.6 General Conditions Cl-I (2)
Cl-1.7 Special Conditions Cl-I (2)
Cl-1.8 Specifications Cl-I (2)
Cl-1.9 Bonds Cl-I (2)
Cl-I.IO Contract Cl-I (3)
Cl-1.11 Plans Cl -I (3)
Cl-1.12 City Cl -I (3)
Cl-1.13 City Council Cl -I (3)
Cl-1.14 Mayor Cl-I (3) -Cl-1.15 City Manager Cl-I (3)
Cl-1.16 City Attorney Cl-I (3)
Cl-1.17 Director of Public Works Cl-I (3)
-. Cl-1.18 Director, City Water Department Cl-I (3)
Cl-1.19 Engineer Cl-I (3)
Cl-1.20 Contractor Cl-I (3)
Cl-1.21 Sureties Cl-I (4)
Cl-1.22 The Work or Project Cl-I (4)
Cl-1.23 Working Day Cl-I (4)
,_ Cl-1.24 Calendar Days Cl -I (4)
Cl-1.25 Legal Holidays Cl-I (4)
Cl-1.26 Abbreviations Cl-I (4) ,_. Cl -1.27 Change Order Cl -I (5)
Cl -1.28 Paved Streets and Alleys Cl -I (5)
Cl-1.29 Unpaved Streets or Alleys Cl-I (6)
Cl -1.30 City Street Cl-I (6)
C 1-1.31 Roadway Cl-I (6)
Cl-1.32 Gravel Street Cl-I (6)
C2-2 INTERPRETATION AND PREPARATION
OF PROPOSAL ,r
C2-2 .1 Proposal Form C2-2 (1)
C2-2.2 Interpretation of Quantities C2-2 (1)
C2-2.3 Examination of Contract Documents and Site of Project C2 -2 (2)
C2-2.4 Submitting of Proposal C2-2 (2)
C2-2.5 Rejection of Proposals C2-2 (3)
(1)
C2-2 .6
C2-2.7
C2-2.8
C2-2 .9
C2-2.10
C2-2.11
C2-2.12
C3-3
C3-3.1
C3-3.2
C3-3.3
C3-3.4
C3-3.5
C3-3.6
C3-3.7
C3-3.8
C3-3.9
C-3-3.10
C3-3.11
C3-3.12
C3-3 .13
C3-3 .14
C3-3.15
C4-4
C4-4 .1
C4-4.2
C4-4 .3
C4-4.4
C4-4.5
C4-4 .6
C4-4 .7
CS-5
C5-5.1
CS-5 .2
CS-5.3
CS-5.4
CS-5.5
CS-5 .6
CS-5.7
C5-5.8
Bid Security
Delivery of Proposal
Withdrawing Proposals
Telegraphic Modifications of Proposals
Public Opening of Proposal
Irregular Pro p osals
Disqualification of Bidders
AW ARD AND EXECUTION OF DOCUMENTS:
Consideration of Proposals
Minority Business Enterprise/Women Business
Enterprise Compliance
Equal Employment Provisions
Withdrawal of Proposals
A ward of Contract
Return of Proposal Securities
Bonds
Execution of Contract
Failure to Ex ecute Contract
Beginning Work
Insurance
Contractor 's Obligations
Weekly Payrolls
Contractor's Contract Administration
Venue
SCOPE OF WORK
Intent of Contract Documents
Special Provisions
Increased or Decreased Quantities
Alteration of Contract Documents
Extra Work
Schedule of Operation
Progress Schedules for Water and Sewer Plant Facilities
CONTROL OF WORK AND MATERIALS
Authority of Engineer
Conformity with Plans
Coordination of Contract Documents
Cooperation of Contractor
Emergency and/or Rectification Work
Field Office
Construction Stakes
Authority and Duties of City Inspector
(2)
C2-2 (3)
C2-2 (3)
C2-2 (3)
C2-2 (3)
C2-2 (4)
C2-2 (4)
C2-2 (4)
C3-3 (1)
C3-3 (1)
C3-3 (1)
C3-3 (1)
C3-3 (2)
C3-3 (2)
C3-3 (2)
C3-3 (3)
C3-3 (3)
C3-3 (4)
C3-3 (4)
C3-3 (6)
C3-3 (6)
C3-3 (6)
C3-3 (7)
C4-4 (1)
C4-4 (1)
C4-4 (1)
C4-4 (2)
C4-4 (2)
C4 -4 (3)
C4 -4 (4)
C5-5 (1)
C5-5 (1)
CS-5 (1)
CS-5 (2)
C5-5 (2)
CS-5 (3)
CS-5 (3)
CS-5 (3)
-·
',,
--
C5-5.9
C5-5.10
C5-5.11
C5-5.12
C5-5.13
C5-5.14
C5-5.15
C5-5.16
C5-5.17
C5-5.18
.C6-6
C6 -6.1
C6-6.2
C6-6.3
C6-6.4
C6-6.5
C6-6.6
C6-6.7
C6-6.8
C6-6 .9
C6-6.10
C6.6.11
C6-6.12
C6-6.13
C6-6.14
C6-6.15
C6-6.16
C6 -6.17
C6-6.18
C6-6.19
C6-6.20
C6-6.21
C7-7
C7-7.1
C7-7.2
C7-7.3
C7-7.4
C7-7.5
C7-7.6
C7-7.7
C7-7.8
C7-7.9
Inspection
Removal of Defective and Unauthorized Work
Substitute Materials or Equipment
Samples and Tests of Materials
Storage of Materials
Existing Structures and Utilities
Interruption of Service
Mutual Responsibility of Contractors
Clean-Up
Final Inspection
LEGAL RELATIONS AND PUBLIC RESPONSIBILITY
Laws to be Observed
Permits and Licenses
Patented Devices, Materials, and Processes
Sanitary Provisions
Public Safety and Convenience
Privileges f Contractor in Streets, Alleys,
and Right-of-Way
Railway Crossings
Barricades, Warnings and Flagmen
Use of Explosives, Drop Weight, Etc.
Work Within Easements
Independent Contractor
Contractor's Responsibility for Damage Claims
Contractor's Claim for Damages
Adjustment or Relocation of Public Utilities, Etc .
Temporary Sewer and Drain Connections
Arrangement and Charges for Water Furnished by the City
Use of a Section or Portion of the Work
Contractor's Responsibility for the Work
No Waiver of Legal Rights
Personal Liability of Public Officials
State Sales Tax
PROSECUTION AND PROGRESS
Subletting
Assignment of Contract
Prosecution of The Work
Limitation of Operations
Character of Workmen and Equipment
Work Schedule
Time of Commencement and Completion
Extension of Time Completion
Delays
(3)
C5-5 (4)
C5-5 (4)
C5-5 (4)
C5-5 (5)
C5-5 (5)
C5-5 (5)
C5-5 (6)
C5-5 (7)
C5-5 (7)
C5-5 (8)
C6-6 (1)
C6-6 (1)
C6-6 (1)
C6-6 (1)
C6-6 (2)
C6-6 (3)
C6-6 (3)
C6-6 (3)
C6-6 (4)
C6 -6 (5)
C6-6 (6)
C6 -6 (6)
C6 -6 (8)
C6-6 (8)
C6-6 (8)
C6-6 (9)
C6-6 (9)
C6-6 (9)
C6-6 (9)
C6-6 (10)
C6 -6 (10)
C7-7 (1)
C7-7 (1)
C7-7(1)
C7-7 (2)
C7-7 (2)
C7-7 (3)
C7-7 (3)
C7-7(3)
C7-7 (4)
C7-7.10
C7-7.1I
C7-7 .12
C7-7.13
C7-7.14
C7-7.15
C7-7.16
C7-7.17
C8-8
C8-8. l
C8-8.2
C8-8.3
C8-8.4
C8-8.5
C8-8.6
C8-8 .7
C8-8 .8
C8-8.9
C8-8.10
C8-8.11
C8-8.12
C8-8.13
Time of Completion
Suspension by Court Order
Temporary Suspension
Termination of Contract due to National Emergency
Suspension or Abandonment of the Work
and Annulment of the Contract:
Fulfillment of Contract
Termination for Convenience of the Owner
Safety Methods and Practices
MEASUREMENT AND PAYMENT
Measurement Of Quantities
Unit Prices
Lump Sum
Scope of Payment
Partial Estimates and Retainage
Withholding Payment
Final Acceptance
Final Payment
Adequacy of Design
General Guaranty
Subsidiary Work
Miscellaneous Placement of Material
Record Documents
(4)
',
C7-7 (4)
C7-7(5)
C7-7 (5)
C7-7(6)
C7-7 (6)
C7-7 (8)
C7-7 (8)
C7-7 (11)
C8-8 (1)
C8-8 (1)
C8-8 (1)
C8-8 (1)
C8-8 (2)
C8-8 (3)
C8-8 (3)
C8-8 (3)
C8-8 (4)
C8-8 (4)
C8-8 (4)
C8-8 (4)
C8-8 (4)
'.
.....
--
PART C-GENERAL CONDITIONS
Cl-1 DEFINITIONS
SECTION Cl-1 DEFINITIONS
Cl-1.1 DEFINITIONS OF TERMS : Whenever in these Contract Documents the
following terms or pronouns in place of them are used, the intent and meaning shall be
understood and interpreted as follows:
Cl-1.2 CONTRACT DOCUMENTS : The Contract Documents are in all of the written
and drawn documents , such as specifications, bonds, addenda, plans, etc ., which govern
the terms and performance of the contract. These are contained on the General Contract
Documents and the Special Contract Documents.
a. GENERAL CONTRACT DOCUMENTS: The General Contract
Documents govern all Water Department Projects and Include the
following Items
PART A-NOTICE TO BIDDERS
PART B -PROPOSAL
PART C-GENERAL CONDITIONS
PART D -SPECIAL CONDITIONS
PART E-SPECIFICATIONS
PERMITS/EASEMENTS
PART F-BONDS
PART G-CONTRACT
(Sample)
(Sample)
(CITY)
(Developer)
White
White
Canary Yell ow
-Brown
Green
El-White
E2-Golden Rod
E2A-White
Blue
(Sample) White
(Sample) White
b. SPECIAL CONTRACT DOCUMENTS: The Special Contract
Documents are prepared for each specific project as a supplement to the
General Contract Documents and include the following items:
PART A-NOTICE TO BIDDERS (Advertisement) same as above
PART B -PROPOSAL (Bid)
PART C -GENERAL CONDITIONS
PART D-SPECIAL CONDITIONS
PART E-SPECIFICATIONS
PERMITS/EASEMENTS
PART F -BONDS
PART G,. CONTRACT
PART H -PLANS (Usually bound separately)
Cl-1 (1)
C 1-1.3 NOTICE TO BIDDERS : All of the legal publications either actually published
in public advertising mediums or furnished direct to interested parties pertaining to the
work contemplated under the Contract Documents constitutes the notice to bidders.
C 1-1.4 PROPOSAL: The completed written and signed offer or tender of a bidder to
perform the work which the Owner desires to have done , together with the bid security ,
constitutes the Proposal , which becomes binding upon the Bidder when it is officially
received by the Owner , has been publicly opened and read and not rejected by the Owner.
Cl-1.5 BIDDER: Any person , persons , firm, partnership , company, association ,
corporation, acting directl y or through a duly authorized representative, submitting a
proposal for performing the work contemplated under the Contract Documents,
constitutes a bidder.
Cl-1.6 GENERAL CONDITIONS: The General Conditions are the usual construction
and contract requirements which govern the performance of the work so that it will be
carried on in accordance with the customary procedure , the local statutes, and
requirements of the City of Fort Worth's charter and promulgated ordinances.
Whenever there may be a conflict between the General Conditions and the Special
Conditions , the latter shall take precedence ..
Cl-1.7 SPECIAL CONDITIONS: Special conditions are the specific requirements
which are necessary for the particular project covered by the Contract Documents and not
specifically covered in the General Conditions. When considered with the General
Conditions and other elements of the Contract Documents they provide the information
which the Contractor and Owner should have in order to gain a thorough knowledge of
the project.
C 1-1.8 SPECIFICATIONS: The Specifications is that section or part of the Contract
Documents which set forth in detail the requirements which must be met by all materials ,
construction, workmanship, equipment and services in order to render a completed an
useful project. Whenever reference is made to standard specifications , regulations ,
requirements, statutes , etc ., such referred to documents shall become a part of the
Contract Documents just as though they were embodied therein .
Cl-1.9 BONDS : The bond or bonds are the written guarantee or security furnished by
the Contractor for prompt and faithful performance of the contract and include the
following:
a . Performance Bond (see paragraph C3-3 .7)
b. Payment Bond (see paragraph C3-3 .7)
c. Maintenance Bond (see paragraph C3-3 .7)
d. Proposal or Bid Security (see Special Instructions to Bidders, Part A and
C2-2 .6)
Cl-1 (2)
---
-
-
C 1-1.10 CONTRACT: The Contract is a formal signed agreement between the owner
and the Contractor covering the mutual understanding of the two contracting parties
about the project to be completed under the Contract Documents .
C 1-1.11 PLANS: The plans are the drawings or reproductions therefrom made by the
Owner's representative showing in detail the location , dimension and position of the
various elements of the project, including such profiles , typical cross-sections, layout
diagrams, working drawings , preliminary drawings and such supplemental drawings as
the Owner may issue to clarify other drawings or for the purpose of showing changes in
the work hereinafter authorized by the Owner. The plans are usually bound separately
from the other parts of the Contract Documents , but they are part of the Contract
Documents just as though they were bound therein.
Cl-1.12 CITY : The City of Fort Worth, Texas, a municipal corporation, authorized and
chartered under the Texas State Statutes , acting by and through its governing body or its
City Manager, each of which is required by charter to perform specific duties.
Responsibility for final enforcement of the Contracts involving the City of Fort Worth is
by Charter vested in the City Manager. The terms City and Owner are synonymous .
C 1-1.13 CITY COUNCIL: The duly elected and qualified governing body of the City
of Fort Worth, Texas.
Cl-1.14 MAYOR: The officially elected Mayor, or in his absence, the Mayor Pro tern
of the City of Fort Worth, Texas .
C 1-1.15 CITY MANAGER: The officially appointed and authorized City Manager of
the City of Fort Worth, Texas, or his duly authorized representative.
Cl-1.16 CITY ATTORNEY : The officially appointed City Attorney of the City of Fort
Worth, Texas, or his duly authorized representative .
C 1-1.17 DIRECTOR OF PUBLIC WORKS: The officially appointed official of the City
of Fort Worth, Texas, referred to in the charter as the City Engineer, or his duly
authorized representative.
Cl-1.18 DIRECTOR, CITY WATER DEPARTMENT: The officially appointed
Director of the City Water Department of the City of Fort Worth, Texas, or his duly
authorized representative, assistant, or agents.
Cl-1.19 ENGINEER: The Director of Public Works, the Director of the Fort Worth
City Water Department, or their duly authorized assistants, agents, engineers, inspectors ,
or superintendents , acting within the scope of the particular duties entrusted to them.
Cl-1.20 CONTRACTOR: The person, person's, partnership, company, firm, association,
or corporation , entering into a contract with the Owner for the execution of work, acting
directly or through a duly authorized representative. A sub-contractor is a person, firm,
Cl-1 (3)
corporation, supplying labor and materials or only labor, for the work at the site of the
project.
Cl-1.21 SURETIES: The Corporate bodies which are bound by such bonds as are
required with and for the Contractor. The sureties engaged are to be fully responsible for
the entire and satisfactory fulfillment of the Contract and for any and all requirements as
set forth in the Contract Documents and approved changes therein .
Cl-1.22 THE WORK OR PROJECT: The completed work contemplated in and
covered by the Contract Documents, including but not limited to the furnishing of all
labor , materials , tools , equipment, and incidentals necessary to produce a completed and
serviceable project.
Cl-1.23 WORKING DAY: A working day is defined as a calendar day , not including
Saturdays, Sundays, and legal holidays, in which weather or other conditions not under
the control of the Contractor permit the performance of the principal unit of work for a
period of not less than seven (7) hours between 7:00 a.m. and 6:00 p.m., with exceptions
as permitted in paragraph C7-7.6
C 1-1.24 CALENDAR DAYS: A calendar day is any day of the week or month, no days
being excepted.
Cl-1.25: LEGAL HOLIDAYS: Legal holidays shall be observed as prescribed by the
City Council of the City of Fort Worth for observance by City employees as follows:
1.
2.
3.
4 .
5.
6 .
7.
8.
9.
New Year's day
M.L. King, Jr. Birthday
Memorial Day
Independence Day
Labor Day
Thanksgiving Day
Thanksgiving Friday
Christmas Day
Such other days in lieu of holidays as
the City Counci l may determine
January 1
Third Monday in January
Last Monday in May
July 4
First Monday in September
Fourth Thursday in November
Forth Friday in November
December 25
When one of the above named holidays or a special holiday is declared by the City
Council, falls on a Saturday, the holiday shall be observed on the preceding Friday, or if
it falls on Sunday, it shall be observed on the following Monday, by those employees
working on working day operations. Employees working calendar day operations will
consider the calendar as the holiday .
Cl-1.26 ABBREVIATIONS: Whenever the abbreviations defined herein appear in the
Contract Documents, the intent and meaning shall be as follows:
Cl-1 (4)
-
-
-
' ---
. ....:
AASHTO American Association of State MGD Million Gallons
Highway Transportation Officials per Day
ASCE American Society of Civil CFS Cubic Foot per
Engineers Second
IAW In Accordance With Min. Minimum
ASTM American Society of Testing Mono . Monolithic
Materials % Percentum
AWWA American Water Works R Radius
Association I.D. Inside Diameter
ASA American Standards Association O .D. Outside Diameter
HI Hydraulic Institute Elev. Elevation
Asph. Asphalt F Fahrenheit
Ave. Avenue C Centigrade
Bl vd . Boulev ard In. Inch
CI Cast Iron Ft. Foot
CL Center Line St. Street
GI Galvanized Iron CY Cubic Yard
Lin . Linear or Lineal Yd. Yard
lb . Pound SY Square yard
MH Manhole L.F . Linear Foot
Max . Maximum D.I. Ductile Iron
Cl-1.27 CHANGE ORDER: A "Change Order" is a written supplemental agreement
between the Owner and the Contractor covering some added or deducted item or feature
which may be found necessary and which was not specifically included in the scope of
the project on which bids were submitted. Increase in unit quantities stated in the
proposal are not the subject matter of a Change Order unless the increase or decrease is
more than 25% of the amount of the particular item or items in the original proposal.
All "Change Orders" shall be prepared by the City from information as necessary
furnished by the Contractor.
C 1-1.28 PAVED STREETS AND ALLEYS: A paved street or alley shall be defined as
a street or alley having one of the following types of wearing surfaces applied over the
natural unimproved surface:
1. Any type of asphaltic concrete with or without separate base material.
2. Any type of asphalt surface treatment, not including an oiled surface, with
or without separate base material.
3 . Brick, with or without separate base material.
4. Concrete, with or without separate base material.
5. Any combination of the above .
Cl-1 (5)
Cl-1.29 UNPAVED STREETS OR ALLEYS: An unpaved street, alley, roadway or
other surface is any area except those defined for "Paved Streets and Alleys ."
Cl-1.30 CITY STREET: A city street is defined as that area between the right-of-way
lines as the street is dedicated.
C 1-1.31 ROADWAY: The roadway is defined as the area between parallel lines two
(2') back of the curb lines or four ('4) feet back of the average edge of pavement where
no curb exists .
Cl-1.32 GRAVEL STREET: A gravel street is an unimproved street to which has been
added one or more applications of gravel or similar material other than the natural
material found on the street surface before any improvement was made.
'.
Cl-1 (6)
-
-
SECTION C -GENERAL CONDITIONS
C2-2 INTERPRETATION AND
PREPARATION OF PROPOSAL
SECTION C2-2 INTERPRETATION AND PREPARATION OF PROPOSAL
C2-2.1 PROPOSAL FORM : The Owner will furnish bidders with Proposal form, which
will contain an itemized list of the items of work to be done or materials to be furnished
and upon which bid prices are requested. The Proposal form will state the Bidder's
general understanding of the project to be completed, provide a space for furnishing the
amount of bid security, and state the basis for entering into a formal contract. The Owner
will furnish forms for the Bidder's "Experience Record," "Equipment Schedule," and
"Financial Statement," all of which must be properly executed and filed with the Director
of the City Water Department one week prior to the hour for opening of bids .
The financial statement required shall have been prepared by an independent certified
public accountant or an independent public accountant holding a valid permit issued by
an appropriate state licensing agency, and shall have been so prepared as to reflect the
current financial status. This statement must be current and no more than one (1) year old.
In the case that bidding date falls within the time a new statement is being prepared, the
previous statement shall be updated by proper verification. Liquid assets in the amount of
ten (10) percent of the estimated project cost will be required .
For an experience record to be considered to be acceptable for a given project, it must
reflect the experience of the firm seeking qualification in work of both the same nature
and magnitude as that of the project for which bids are to be received, and such
experience must have been completed not more than five (5) years prior to the date on
which Bids are to be received. The Director of the Water Department shall be sole judge
as to the acceptability of experience for qualification to bid on any Fort Worth Water
Department project.
The prospective bidder shall schedule the equipment he has available for the project and
state that he will rent such additional equipment as may be required to complete the
project on which he submits a bid.
C2-2.2 INTERPRETATION OF QUANTITIES: The quantities of work and materials
to be furnished as may be listed in the proposal forms or other parts of the Contract
Documents will be considered as approximate only and will be used for the purpose of
comparing bids on a uniform basis. Payment will be made to the Contractor for only the
actual quantities of work performed or materials furnished in strict accordance with the
Contract Documents and Plans. The quantities of work to be performed and materials to
be furnished may be increased or decreased as hereinafter provided, without in any way
invalidating the unit prices bid or any other requirements of the Contract Documents.
C2-2(1)
C2-2.3 EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF PROJECT:
Bidders are advised that the Contract Documents on file with the Owner shall constitute
all of the information which the Owner will furnish. All additional information and data
which the Owner will supply after promulgation of the formal contract documents shall
be issued in the form of written addenda and shall become part of the Contract
Documents just as though such addenda were actually written into the original Contract
Documents.
Bidders are required, prior to filing of proposal, to read and become familiar with the
Contract Documents , to visit the site of the project and examine carefully all local
conditions , to inform them se lves by their own independent research and investigations ,
tests , boring, and by such other means as may be necessary to gain a complete knowledge
of the conditions which will be encountered during construction of the project. They must
judge for themselves the difficulties of the work and all attending circumstances affecting
the cost of doing the wo rk or the time required for its completion, and obtain all
information required to make an intelligent proposal. No information given by the Owner
or any representative of th e Owner other than that contained in the Contract Documents
and officially promulgated addenda thereto , shall be binding upon the Owner. Bidders
shall rely exclusively and solely upon their own estimates , investigation, research , tests,
explorations , and other data which are necessary for full and complete information upon
which the proposal is to be based. It is mutually agreed that the submission of a proposal
is prima-facie evidence that the bidder has made the investigation, examinations and tests
herein required. Claims for additional compensation due to variations between conditions
actually encountered in construction and as indicated in the Contract Documents will not
be allowed.
The logs of Soil Borings, if any, on the plans are for general information only and may
not be correct. Neither the Owner nor the Engineer guarantee that the data shown is
representative of conditions which actually exist.
C2-2.4 SUBMITTING OF PROPOSAL: The Bidder shall submit his Proposal on the
form furnished by the Owner. All blank spaces applicable to the project contained in the
form shall be correctly filled in and the Bidder shall state the prices, written in ink in both
words and numerals , for which he proposes to do work contemplated or furnish the
materials required. All such prices shall be written legibly . In case of discrepancy
between price written in words and the price written in numerals, the price most
advantageous to the City shall govern.
If a proposal is submitted by an individual , his or her name must be signed by him (her)
or his (her) dul y authorized agent. If a proposal is submitted by a firm, association, or
partnership , the name and address of each member of the firm , association, or partnership,
or by person duly authorized. If a proposal is submitted by a company or corporation, the
company or corporation name and business address must be given , and the proposal
signed by an official or duly authorized agent. The corporate seal must be affixed. Power
C2-2(2)
_ _,
of Attorney authorizing agents or others to sign proposal must be properly certified and
must be in writing and submitted with the proposal.
C2-2.5 REJECTION OF PROPOSALS: Proposals may be rejected if they show any
alteration of words or figures, additions not called for , conditional or uncalled for
alternate bids , erasures , or irregularities of any kind , or contain unbalanced value of any
items. Proposal tendered or delivered after the official time designated for receipt of
proposal shall be returned to the Bidder unopened.
C2-2.6 BID SECURITY : No proposal will be considered unless it is accompanied by a
"Proposal Security" of the character and the amount indicated in the "Notice to Bidders"
and the "Proposal." The Bid Security is required by the Owner as evidence of good faith
on the part of the Bidder, and by way of a guaranty that if awarded the contract, the
Bidder will within the required time execute a formal contract and furnish the required
performance and other bonds. The bid security of the three lowest bidders will be retained
until the contract is awarded or other disposition is made thereof. The bid security of all
other bidders may be returned promptly after the canvass of bids .
C2-2.7 DELIVERY OF PROPOSAL: No proposal will be considered unless it is
delivered , accompanied by its proper Bid Security, to the City Manager or his
representative in the official place of business as set forth in the "Notice to Bidders." It is
the Bidder's sole responsibility to deliver the proposal at the proper time to the proper
place. The mere fact that a proposal was dispatched will not be considered. The Bidder
must have the proposal actually delivered. Each proposal shall be in a sealed envelope
plainly marker with the word "PROPOSAL," and the name or description of the project
as designated in the "Notice to Bidders ." The envelope shall be addressed to the City
Manager, City Hall , Fort Worth , Texas.
C2-2 .8 WITHDRAWING PROPOSALS: Proposals actually filed with the City
Manager cannot be withdrawn prior to the time set for opening proposals . A request for
non-consideration must be made in writing , addressed to the City Manager, and filed with
him prior to the time set for opening of proposals . After all proposals not requested for
non-consideration are opened and publicly read aloud, the proposals for which non-
consideration requests have been properly filed may, at the option of the Owner, be
returned unopened.
C2-2.9 TELEGRAHIC MODIFICATIONS OF PROPOSALS: Any Bidder may modify
his proposal by telegraphic communication at any time prior to the time set for opening
proposals , provided · such telegraphic communication is received by the City Manager
prior to the said proposal opening time, and provided further , that the City Manager is
satisfied that a written and duly authenticated confirmation of such telegraphic
communication over the signature of the bidder was mailed prior to the proposal opening
time. If such confirmation is not received within forty-eight ( 48) hours after the proposal
opening time , no further consideration will be given to the proposal.
C2-2(3)
C2-2.10 PUBLIC OPENING OF PROPOSAL : Proposals which have been properly
filed and for which no "Non-consideration Request" has been received will be publicly
opened and read aloud by the City Manager or his authorized representative at the time
and place indicated in the ''Notice to Bidders." All proposals which have been opened and
read will remain on file with the Owner until the contract has been awarded . Bidders or
their authorized representatives are invited to be present for the opening of bids.
C2-2.11 IRREGULAR PROPOSALS : Proposals shall be considered as "Irregular" if
they show any omissions , alterations of form , additions , or conditions not called for ,
unauthorized alternate bids , or irregularities of any kind. However, the Owrter reserves
the right to waive any all irregularities and to make the award of the contract to the best
interest of the City . Tendering a proposal after the closing hour is an irregularity which
can not be waived:
C2-2.12 DISQUALIFICATION OF BIDDERS: Bidders may be disqualified and their
proposals not considered for any of, but not limited to , the following reasons:
a) Reasons for believing that collusion exists among bidders .
b) Reasonable grounds for believing that any bidder is interested in more than
one proposal for work contemplated.
c) The bidder being interested in any litigation against the Owner or where
the Owner may have a claim against or be engaged in litigation against the
bidder.
d) The bidder being in arrears on any existing contract or having defaulted on
a previous contract.
e) The bidder having performed a prior contract in an unsatisfactory manner.
f) Lack of competency as revealed by financial statement, experience
statement, equipment schedule, and such inquiries as the Owner may see
fit to make .
g) Uncompleted work which, in the judgment of the Owner, will prevent or
hinder the prompt completion of additional work if awarded.
h) The bidder not filing with the Owner, one week in advance of the hour of
the opening of proposals the following:
1. Financial Statement showing the financial condition of the bidder
as sp ecified in Part "A" -Special Instructions
2 . A current experience record showing especially the projects of a
nature similar to the one under consideration, which have been
succ essfully completed by the Bidder.
3. An equipment schedule showing the equipment the bidder has
available for use on the project.
The Bid Proposal of the bidder who , in the judgment of the Engineer, is disqualified
under the requirements stated herein, shall be set aside and not opened.
C2-2(4)
PART C -GENERAL CONDITIONS
C3-3 AW ARD AND EXECUTION OF
DOCUMENTS
SECTION C3-3 A WARD AND EXECUTION OF DOCUMENTS:
C3-3. l CONSIDERATION OF PROPOSALS: After proposals have been opened and
read aloud, the proposals will be tabulated on the basis of the quoted prices , the quantities
shown in the proposal , and the application of such formulas or other methods of bringing
items to a common basis as may be established in the Contract Documents.
The total obtained by taking the sum of the products of the unit prices quoted and the
estimated quantities plus any lump sum items and such other quoted amounts as may
enter into the cost of the completed project will be considered as the amount of the bid .
Until the ward of the contract is made by the Owner, the right will be reserved to reject
any or all proposals and waive technicalities , to re-advertise for new proposals, or to
proceed with the work in any manner as may be considered for the best interest of the
Owner.
C3-3.2 MINORITY BUSINESS ENTERPRISE/WOMEN-OWNED BUSINESS
ENTERPRISE COMPLIANCE: Contractor agrees to provide ·to Owner, upon request,
complete and accurate information regarding actual work performed by a Minority
Business Enterprise (MBE) and/or a Woman-owned Business Enterprise (WBE) on the
contract and the payment therefor. Contractor further agrees , upon request by the Owner,
to allow and audit and/or an examination of any books , records, or files in the possession
of the Contractor that will substantiate the actual work performed by an MWE or WBE.
Any material misrepresentation of any nature will be grounds for termination of the
contract and for initiating any action under appropriate federal , state or local laws and
ordinances relating to false statements; further, any such misrepresentation may be
grounds for disqualification of Contractor at Owner's discretion for bidding on future
Contracts with the Owner for a period of time of not less than six (6) months.
C3-3.3 EQUAL EMPLOYMENT PROVISIONS: The Contractor shall comply with
Current City Ordinances prohibitin·g discrimination in employment practices. The
Contractor shall post the required notice to that effect on the project site , and at his
request, will be provided assistance by the City of Fort Worth 's Equal Employment
Officer who will refer any qualified applicant he may have on file in his office to the
Contractor. Appropriate notices may be acquired from the Equal Employment Officer.
C3-3.4 WITHDRAW AL OF PROPOSALS: After a proposal has been read by the
Owner, it cannot be withdrawn by the Bidder within forty-five (45) days after the date on
which the proposals were opened.
C3-3 (1)
C 3-3.5 A WARD OF CONTRACT: The Owner reserves the right to withhold final
action on the proposals for a reasonable time, not to exceed forty-five ( 45) days after the
date of opening proposals, and in no event will an award be made until after
investigations have been made as to the responsibility of the proposed awardee .
The award of the contract, if award is made, will be to the lowest and best responsive
bidder.
The award of the contract shall not become effective until the Owner has notified the
Contractor in writing of such award.
C3-3.6 RETURN OF PROPOSAL SECURITIES: As soon as proposed price totals
have been determined for comparison of bids, the Owner may, at its discretion, return the
proposal security which accompanied the proposals which, in its judgment, would not be
considered for the award. All other proposal securities, usually those of the three lowest
bidders, will be retained by the Owner until the required contract has been executed and
bond furnished or the Owner has otherwise disposed of the bids, after which they will be
returned by the City Secretary.
C3-3.7 BONDS: With the execution and delivery of the Contract Documents, the
Contractor shall furnish to , and file with the owner in the amounts herein required, the
following bonds:
a. PERFORMANCE BOND: A good and sufficient performance bond in
the amount of not less than 100 percent of the amount of the contract, as
evidenced by the proposal tabulation or otherwise, guaranteeing the full
and faithful execution of the work and performance of the contract, and for
the protection of the Owner and all other persons against damage by
reason of negligence of the Contractor, or improper execution of the work
or use of inferior materials. This performance bond shall guarantee the
payment for all labor, materials, equipment, supplies, and services used in
the construction of the work, and shall remain in full force and effect until
· provisions as above stipulated are accomplished and final payment is made
on the project by the City.
b. MAINTENANCE BOND: A good and sufficient maintenance bond, in
the amount of not less than 100 percent of the amount of the contract, as
evidenced by the proposal tabulation or otherwise, guaranteeing the
prompt, full and faithful performance of the general guaranty which is set
forth in paragraph C8-8.10.
c. PAYMENT BOND: A good and sufficient payment bond, in the
amount of not less than 100 percent of. the amount of the contract, as
evidenced by the proposal tabulation or otherwise, guaranteeing the
prompt, full and faithful payment of all claimants as defined in Article
C3-3 (2)
d.
5160, Revised Civil Statutes of Texas, 1925, as amended by House Bill
344 , Acts 56 1h Legislature, Regular Session, 1959, effective April 27,
1959 , and/or the latest version thereof, supplying labor and materials in the
prosecution of the work provided for in the contract being constructed
under these specifications. Payment Bond shall remain in force until all
payments as above stipulated are made.
OTHER BONDS : Such other bonds as may be required by these
Contract Documents shall be furnished by the Contractor.
No sureties will be accepted by the Owner which are at the time in default or delinquent
on any bonds or which are interested in any litigation against the Owner. All bonds shall
be made on the forms furnished by the Owner and shall be executed by an approved
surety company doing business in the City of Fort Worth, Texas , and which is acceptable
to the Owner. In order to be acceptable, the name of the surety shall be included on the
current U.S. Treasury list of acceptable sureties , and the amount of bond written by any
one acceptable company shall not exceed the amount shown on the Treasury list for that
company. Each bond shall be properly executed by both the Contractor and Surety
Company .
Should any surety on the contract be determined unsatisfactory at any time by the Owner,
notice will be given the Contractor to that effect and the Contractor shall immediately
provide a new surety satisfactory to the Owner. No payment will be made under the
contract until the new surety or sureties, as required, have qualified and have been
accepted by the Owner. The contract shall not be operative nor will any payments be due
or paid until approval of the bonds by the Owner.
C3-3.8 EXECUTION OF CONTRACT: Within ten (10) days after the Owner has
appropriate resolution, or otherwise , awarded the contract, the Contractor shall execute
and file with the Owner, the Contract and such bonds as may be required in the Contract
Documents.
No Contract shall be binding upon the Owner until it has been attested by the City
Secretary , approved as to form and legality by the City Attorney, and executed for the
Owner by either the Mayor or City Manager.
C3-3 .9 FAILURE TO EXECUTE CONTRACT: The failure of the Awardee to
execute the required bond or bonds or to sign the required contract within ten (10) days
after the contract is awarded shall be considered by the owner as an abandonment of his
proposal; and the owner may annual the Award . By reason of the uncertainty of the
market prices of material and labor , and it being impracticable and difficult to accurately
determine the amount of damages occurring to the owner by reason of said awardee 's
failure to execute said bonds and contract within ten (10) days , the proposal security
accompanying the proposal shall be the agreed amount of damages which the Owner will
C3-3 (3)
suffer by reason of such failure on the part of the Awardee and shall thereupon
immediately by forfeited to the Owner.
The filing of a proposal will be considered as acceptance of this provision by the Bidder.
C-3-3 .10 BEGINNING WORK : The Contractor shall not commence work until
authorized in writing to do so by the Owner. Should the Contractor fail to commence
work at the site of the project within the time stipulated in the written authorization
usually termed "Work Order" or "Proceed Order", it is agreed that the Surety Company
will , within ten (10) days after the commencement date set forth in such written
authorization, commence the physical execution of the contract.
C3-3.11 INSURANCE : The Contractor shall not commence work under this
contract until he has obtained all insurance required under the Contract Documents, and
such insurance has been approved by the Owner. The prime Contractor shall be
responsible for delivering to the Owner the sub-contractor's certificate of insurance for
approval. The prime Contractor shall indicate on the certificate of insurance included in
the documents for execution whether or not his insurance covers sub-contractors. It is the
intention of the Owner that the insurance coverage required herein shall include the
coverage of all sub-contractors.
a. COMPENSATION INSURANCE : The Contractor shall maintain,
during the life of this contract, Worker's Compensation Insurance on all of
his employees to be engaged in work on the project under this contract,
and for all sub-contractors. In case any class of employees engaged in
hazardous work on the project under this contract is not protected under
the Worker's Compensation Statute, the Contractor shall provide adequate
employer 's general liability insurance for the protection of such of his
employees not so protected .
b.
C.
COMPREHENSIVE GENERAL LIABILITY INSURANCE: The
Contractor Shall procure and shall maintain during the life of this contract,
Comprehensive General Liability Insurance (Public Liability and Property
Damage Insurance) in the amount not less than $500,000 covering each
occurrence on account of bodily injury, including death, and in an amount
not less than $500,000 covering each occurrence on account of property
damage with $2,000,000 umbrella policy coverage.
ADDITIONAL LIABILITY: The Contractor shall furnish
insurance as a separate policies or by additional endorsement to one of the
above-mentioned policies, and in the amount as set forth for public
liability and property damage, the following insurance:
1. Contingent Liability ( covers General Contractor's Liability for acts
of sub-contractors).
C3-3 (4)
2. Blasting, prior to any blasting being done .
3. Collapse of buildings or structures adjacent to excavation ill
excavation are performed adjacent to same).
4 . Damage to underground utilities for $500 ,000 .
5 . Builder's risk (where above-ground structures are involved).
6. Contractual Liability ( covers all indemnification requirements of
Contract).
d. AUTOMOBILE INSURANCE -BODILY INJURY AND PROPERTY
DAMAGE: The Contractor shall procure and maintain during the life of
this Contract, Comprehensive Automobile Liability Insurance in an
amount not less than $250 ,000 for injuries including accidental death to
any one person and subject to the same limit for each person an amount
not less than $500 ,000 on account of one accident, and automobile
property damage insurance in an amount not less than $100,000 .
e. SCOPE OF INSURANCE AND SPECIAL HAZARD: The insurance
required under the above paragraphs shall provide adequate protection for
the Contractor and his sub-contractors , respectively, against · damage
claims which may arise from operations under this contract, whether such
operations be by the insured or by anyone directly or indirectly employed
by him , and also against any of the following special hazards which may
be encountered in the performance of the Contract.
f. PROOF OF CARRIAGE OF INSURANCE: The Contractor shall furnish
the owner with satisfactory proof of coverage by insurance required in
these Contract Documents in the amounts and by carriers satisfactory to
the Owner. (Sample attached .) All insurance requirements made upon the
Contractor shall apply to the sub-contractors , should the Prime
Contractor's insurance not cover the sub-contractor's work operations .
g. LOCAL AGENT FOR INSURANCE AND BONDING: The insurance
and bonding companies with whom the Contractor 's insurance and
C3-3 (5)
performance , payment, maintenance and all such other bonds are written ,
shall be represented by an agent or agents having an office located within
the city limits of the City of Fort Worth. Tarrant County, Texas . Each such
agent shall be a duly qualified , one upon whom authority and power to act
on behalf of the insurance and /or bonding company to negotiate and settle
with the City of Fort Worth , or any other claimant, and claims that the City
of Fort Worth or other claimant or any property owner who has been
damaged , may have against the Contractor, insurance , and/or bonding
company . If the local insurance representative is not so empowered by the
insurance or bonding companies , then such authority must be vested in a
local agent or claims officer residing in the Metroplex, the Fort Worth-
Dallas area . The name of the agent, or agents shall be set forth on all such
bonds and certificates of insurance.
C3-3.12 CONTRACTOR'S OBLIGATIONS: Under the Contract, the Contractor
shall pay for all materials, labor and services when due .
C3-3.13 WEEKLY PAYROLLS : A certified copy of each payroll covering payment
of wages to all persons engaged in work on the project at the site of the project shall be
furnished to the Owner 's representative within seven (7) days after the close of each
payroll period. A copy or copies of the applicable minimum wage rates as set forth in the
Contract Documents shall be kept posted in a conspicuous place at the site of the project
at all times during the course of the Contract. Copies of the wage rates will be furnished
the Contractor, by the Owner; however, posting and protection of the wage rates shall be
the responsibility of the Contractor.
C3-3.14 CONTRACTOR 'S CONTRACT ADMINISTRATION: Any Contractor,
whether a person, persons, partnership , company, firm, association, corporation or other
who is approved to do business with and enters into a contract with the City for
construction of water and/or sanitary sewer facilities , will have or shall establish a fully
operational business office within the Fort Worth-Dallas metropolitan area. The
Contractor shall charge , delegate , or assign this office ( or he may delegate his Project
Superintendent) with full authority to transact all business actions required in the
performance of the Contract. This local authority shall be made responsible to act for the
Contractor in all matters made responsible to act for the Contractor in all matters
pertaining to the work go verned by the Contract whether it be administrative or other
wise and as such shall be empowered, thus delegated and directed, to settle all material,
labor or other expenditure, all claims against work or any other mater associated such as
maintaining adequate and appropriate insurance or security coverage for the project. Such
local authority for the administration of the work under the Contract shall be maintained
until all business transactions executed as part of the Contract are complete.
Should the Contractor's principal base of operations be other than in the Fort Worth-
Dallas metropolitan area, notification of the Contractor's assignment of local authority
shall be made in writing to the Engineer in advance of any work on the project, all
C3-3 (6)
appropriately signed and sealed, as applicable, by the Contractor's responsible offices
with the understanding that this written assignment of authority to the local representative
shall become part of the project Contract as though bound directly into the project
documents. The intent of these requirements is that all matters associated with the
Contractor 's administration, whether it be oriented in furthering the work, or other, be
governed direct by local authority. This same requirement is imposed on insurance and
surety coverage . Should the Contractor's local representative fail to perform to the
satisfaction of the Engineer, the Engineer, at his sole discretion, may demand that. such
local representative be replaced and the Engineer may, at his sole discretion , stop all work
until a new local authority satisfactory to the Engineer is assigned. No credit of working
time will be allowed for periods in which work stoppages are in effect for this reason .
C3-3.15 VENUE: Venue of any action hereinunder shall be exclusively in Tarrant
County, Texas.
'"'
C3-3 (7)
1,
SECTION C4-4 SCOPE OF WORK
PART C-GENERAL CONDITIONS
C4-4 SCOPE OF WORK
C4-4.1 INTENT OF CONTRACT DOCUMENTS: It is the definite intention of these
Contract Documents to provide for a complete, useful project which the Contractor
undertakes to construct or furnish, all in full compliance with the requirements and intent
of the Contract Documents. It is definitely understood that the Contractor shall do all
work as provided for in the Contract Documents , shall do all extra or special work as may
be considered by the Owner as necessary to complete the project in a satisfactory and
acceptable manner. The Contractor shall, unless otherwise specifically stated in these
Contract Documents, furnish all labor, tools , materials, machinery, equipment, special
services, and incidentals necessary to the prosecution and completion of the project.
C4-4.2 SPECIAL PROVISIONS: Should any work or conditions which are not
thoroughly and satisfactorily stipulated or covered by General or Special Conditions of
these Contract Documents be anticipated , or should there be any additional proposed
work which is not covered by these Contract Documents, the "Special Provisions"
covering all such work will be prepared by the Owner previous to the time of receiving
bids or proposals for any such work and furnished to the Bidder in the form of Addenda.
All such "Special Provisions" shall be considered to be part of the Contract Documents
just as though they were originally written therein.
C4-4.3 INCREASED OR DECREASED QUANTITIES: The Owner reserves the right
to alter the quantities of the work to be performed or to extend or shorten the
improvements at any time when and as found to be necessary, and the Contractor shall
perform the work as altered , increased or decreased at the unit prices. Such increased or
decreased quantity shall not be more than twenty-five (25) percent of the contemplated
quantity of such item or items. When such changes increase or decrease the original
quantity of any item or items of work to be done or materials to be furnished by the 25
percent or more, then either party to the contract shall upon written request to the other
party be entitled to a revised consideration upon that portion of the work above or below
the 25 percent of the original quantity stated in the proposal; such revised consideration
to be determined by special agreement or as hereinafter provided for "Extra Work." No
allowance will be made for any changes in anticipated profits not shall such changes be
considered as waiving or invalidating any conditions or provisions of the Contract
Documents.
Variations in quantities of sanitary sewer pipes in depth categories, shall be interpreted
herein as applying to overall quantities of sanitary sewer pipe in each pipe size, but not to
the various depth categories.
C4-4 (1)
C4-4.4 ALTERATION OF CONTRACT DOCU MENTS : By Change order, the
owner reserves the right to make such changes in the Contract Documents and in the
character or quantities of the work as may be necessary or desirable to insure completion
in the most satisfactory manner, provided such changes do not materially alter the
original Contract Documents or change the general nature of the project as a whole. Such
changes shall not be considered as waiving or in v alidating any condition or provision of
the Contract Documents .
C4-4.5 EXTRA WORK: Additional work made necessary by changes and alterations
of the Contract Documents or of quantities or for other reasons for which no prices are
provided in the Contract Documents, shall be defined as "Extra Work" and shall be
performed by the Contractor in accordance with these Contract Documents or approved
additions thereto; provided however, that before any extra work is begun a "Change
order" shall be executed or written order issued by the Owner to do the work for
payments or credits as shall be determined by one or more combination of the following
methods:
a . Unit bid price previousl y approved.
b. An agreed lump sum.
c. The actual reasonable cost of (1) labor, (2) rental of equipment used on the
extra work for the time so used at Associated General Contractors of
America current equipment rental rates, (3) materials entering
permanently into the project, and (4) actual cost of insurance, bonds, and
social securi ty as determined by the Owner, plus a fixed fee to be agreed
upon but not to exceed 10 percent of the actual cost of such extra work.
The fixed fee is not to include any additional profit to the Contractor for
rental of equipment owner by him and used for extra work. The fee shall
be full and complete compensation to cover the cost of superintendence,
overhead, ot her profit, general and all other expense not included in (1 ),
(2), (3), and (4) above. The Contractor shall keep accurate cost records on
the form and in the method suggested by the Owner and shall give the
Owner access to all accounts, bills, vouchers, and records relating to the
Extra Work.
No "Change Order" shall become effective until it has been approved and signed by each
of the Contracting Parties.
No claim for Extra Work of any kind will be allowed unless ordered in writing by the
Owner. In case any orders or instructions, either oral or written, appear to the Contractor
to involve Extra Work for which he should receive compensation, he shall make written
request to the Engineer for written orders authorizing such Extra Work, prior to
beginning such work.
C4-4 (2)
Should a difference ari s e as to what does or dose not constitute Extra Work, or as to the
payment thereof, and the Engineer insists upon its performance, the Contractor shall
proceed with the work after making written request for written orders and shall keep
accurate account of the actual reasonable cost thereof as provided under method (Item C).
Claims for extra work will not be paid unless the Contractor shall file his claim with the
Owner within five (5) days before the time for making the first estimate after such work
is done and unless the claim is supported by satisfactory vouchers and certified payrolls
covering all labor and materials expended upon said Extra Work.
The Contractor shall furnish the Owner such installation records of all dev iations from
the original Contract Documents as may be necessary to enable the Owner to prepare for
permanent record a corrected set of plans showing the actual installation.
The compensation agreed upon for "Extra Work" whether or not initiated by a "Change
Order" shall be a full , complete and final payment for all costs Contractor incurs as a
result or relating to the change or extra work, whether said costs are known, unknown,
foreseen or unforeseen at that time, including without limitation, any costs for delay,
e x tended overhead, ripple or impact cost, or any other effect on changed or unchanged
work as a result of the change or extra work.
C4-4.6 SCHEDULE OF OPERATION: Before commencing any work under this
contract, the Contractor shall submit to the Owner and receive the Owner's approval
thereof, a "Schedule of Operations," showing by a straight line method the date of
commencing and finishing each of the major elements of the Contract. There shall be also
shown the estimated monthly cost of work for which estimates are to be expected. There
shall be presented also a composite graph showing the anticipated progress of
construction with the time being plotted horizontally and percentage of completion
plotted vertically. The prngress charts shall be prepared on 8-1/2" x 11" sheets and at
least five black or blue line prints shall be furnished to the Owner.
C4-4. 7 PROGRESS SCHEDULES FOR WATER AND SEWER PLANT FACILITIES:
Within ten (10) days prior to submission of the first monthly progress payment, the
Contractor shall prepare and submit to the owner for approval six copies of the schedule
in which the Contractor proposes to carry on activities (including procurement of
materials, plans, and equipment) and the contemplated dates for completing the same.
The schedule shall be in the form of a time schedule Critical Path Method (CPM)
network diagram. As the work progresses, the Contractor shall enter on the diagram the
actual progress at the end of each partial payment period or at such intervals as directed
by the Engineer. The Contractor shall also revise the schedule to reflect any adjustments
in contract time approved by the Engineer. Three copies of the updated schedule shall be
delivered at such intervals as directed by the Engineer.
As a minimum, the construction schedule shall incorporate all work elements and
activities indicated in the proposal and in the technical specifications.
C4-4 (3)
Prior to the final drafting of the detailed construction schedule, the Contractor shall
review the draft schedule with the Engineer to ensure the Contractor's understanding of
the contract requirements .
The following guidelines shall be adhered to in preparing the construction schedule:
a. Milestone dates and final project completion dates shall be developed to
conform to the time constraints , sequencing requirements and completion
time.
b . The construction progress shall be divided into activities with time
durations of approximately fourteen days (14) days and construction
values not to exceed $50 ,000. Fabrication, delivery and submittal activities
are exceptions to this guideline.
c. Durations shall be in calendar days and normal holidays and weather
conditions over the duration of the contract shall be accounted for within
the duration of each activity.
d. One critical path shall be shown on the construction schedule.
e . Float time is defined as the amount of time between the earliest start date
and the late st start date of a chain of activities of the CPM construction
schedule. Float time is not for the exclusive use or benefit of either the
Contractor or the Owner.
f . Thirty days shall be used for submittal review unless otherwise specified.
The construction schedule shall as a minimum, be divided into general categories as
indicated in the Proposal and Technical Specifications and each general category shall be
broken down into activities in enough detail to achieve activities of approximately
fourteen (14) days duration .
For each general category, the construction schedule shall identify all trades or
subcontracts whose work is represented by activities that follow the guidelines of this
Section. ,
For each of the trades or subcontracts , the construction schedule shall indicate the
following procurements , construction and preacceptance activities and events in their
logical sequence for equipment and materials .
1. Preparation and transmittal of submittals
2. Submittal review periods.
3. Shop fabric ation and delivery.
C4 -4 (4)
.,..
...
-
4.
5.
6.
7 .
8 .
9 .
Erection or installation.
Transmittal of manufacturer's operation and maintenance instructions .
Installed equipment and materials testing.
Owner's operator instruction (if applicable).
Final inspection.
Operational testing.
If, in the opinion of the Owner, work accomplished falls behind that scheduled, the
Contractor shall take such action as necessary to improve his progress . In addition, the
Owner may require the Contractor to submit a revised schedule demonstrating his
program and proposed plan to make up lag in scheduled progress and to insure
completion of the work within the contract time. If the owner finds the proposed p lan not
acceptable , he may require the Contractor to increase the work force , the construction
plant and equipment, the number of work shifts or overtime operations without additional
cost to the Owner .
Failure of the Contractor to comply with these requirements shall be considered grounds
for determination by the Owner that the Contractor is failing to prosecute the work with
diligence as will insure its completion within the time specified.
C4-4 (5)
.,,.
PART C -GENERAL CONDITIONS
CS-5 CONTROL OF WORK AND
MATERIALS
SECTION CS-5 CONTROL OF WORK AND MATERIALS
CS-5.1 AUTHORITY OF ENGINEER: The work shall be performed to the
satisfaction of the Engineer and in strict compliance with the Contract Documents . The
Engineer shall decide all questions which arise as to the quality and acceptability of the
materials furnished , work performed, rate of progress of the work, overall sequence of the
construction, interpretation of the Contract Documents, acceptable fulfillment of the
Contract, compensation, mutual rights between Contractor and Owner under these
Contract Documents , supervision of the work, resumption of operations , and all other
questions or disputes which may arise . Engineer will not be responsible for Contractor's
means , methods , techniques , sequence or procedures · of construction, or the safety
precaution and programs incident thereto, and he will not be responsible for Contractor's
failure to perform the work in accordance with the contract documents.
The Engineer shall determine the amount and quality of the work completed and
materials furnished , and his decisions and estimates shall be final. His estimates in such
event shall be a condition to the right of the Contractor to receive money due him under
the Contract. The Owner shall have executive authority to enforce and make effective
such necessary decisions and orders as the Contractor fails to carry out promptly.
In the event of any dispute between the Engineer and Contractor over the decision of the
Engineer on an y such matters , the Engineer must, within a reasonable time , upon written
request of the Contractor, render and deliver to both the owner and Contractor, a written
decision on the matter in controversy.
CS-5.2 CONFORMITY WITH PLANS : The finished project in all cases shall
conform with lines, grades, cross-sections, finish, and dimensions shown on the plans or
any other requirements other wise described in the Contract Documents. Any deviation
from the approved Contract Documents required by the Engineer during construction will
in all cases be determined by the Engineer and authorized by the Owner by Change
Order.
CS-5.3 COORDINATION OF CONTRACT DOCUMENTS: The Contract
Documents are made up of several sections, which, taken together , are intended to
describe and pro vide for a complete and useful project, and any requirements appearing
in one of the sections is as binding as though it occurred in all sections. In case of
discrepancies , figured dimension shall govern over scaled dimensions, plans shall govern
over specifications , special conditions shall govern over general conditions and standard
specification, and quantities shown on the plans shall govern over those shown in the
proposal. The Contractor shall not take advantage of any apparent error or omission in
CS-5 (1)
the Contract Documents , and the owner shall be permitted to make such corrections or
interpretations as may be deemed necessary for fulfillment of the intent of the Contract
Documents. In the event the Contractor discovers an apparent error or discrepancy, he
shall immediately call this condition to the attention of the Engineer. In the event of a
conflict in drawings, specifications , or other portions of the Contract Documents which
were not reported prior to the award of Contract , the Contractor shall be deemed to have
quoted the most expensive resolution of the conflict.
CS-5.4 COOPERATION OF CONTRACTOR: The Contractor will be furnished
with three sets of Contract Documents and shall have available on the site of the project
at all times , one set of such Contract Documents.
The Contractor shall give to the work the constant attention necessary to facilitate the
progress thereof and shall cooperate with the Engineer, his inspector, and other
Contractors in every possib le way .
The Contractor shall at all t imes have competent personnel available to the project site for
proper performance of the work . The Contractor shall provide and maintain at all times at
the site of the project a competent, Engl ish-speaking superintendent and an assistant who
are fully authorized to act as the Contractor's agent on the work. Such superintendent and
his assistant shall be capable of reading and understanding the Contract Documents and
shall receive and fulfill instructions from the Owner, the Engineer, or his authorized
representatives . Pursuant to this responsibility of the Contractor, the Contractor shall
designate in writing to the project superintendent, to act as the Contractor's agent on the
work. Such assistant project superintendent shall be a resident of Tarrant County, Texas,
and shall be subject to call , as is the project superintendent, at any time of the day or
night on any day of the week on which the Engineer determines that circumstances
require the presence on the project site of a representative of the Contractor to adequately
provide for the safety or convenience of the traveling public or the owners of property
across which the project extends or the safety of the property contiguous to the project
routing .
The Contractor shall provide all facilities to enable the Engineer and his inspector to
examine and inspect the workmanship and materials entering into the work.
CS-5 .5 EMERGENCY AND/OR RECTIFICATION WORK: When, in the opinion
of the Owner or Engineer , a condition of emergency exists related to any part of the
work, the Contractor, or the Contractor through his designated representative, shall
respond with dispatch to a verbal request made by the Owner or Engineer to alleviate the
emergency condition . Such a response shall occur day or night, whether the project is
scheduled on a calendar-day or a working-day basis .
Should the Contractor fail to respond to a request from the Engineer to rectify any
discrepancies , omissions, or correction necessary to conform with the requirements of the
project specifications or plans , the Engineer shall give the Contractor written notice that
such work or changes are to be performed. The written notice shall direct attention to the
CS-5 (2)
...
discrepant condition and request the Contractor to take remedi al action to correct the
condition . In the event the Contractor does not take positi ve steps to fulfill this written
request , or does not shoe just cause for not taking the proper action , within 24 hours , the
City may take such remedial action with City forces or by contract. The City shall deduct
an amount equal to the entire costs for such remedial action, plus 25%, from any funds
due the Contractor on the project.
C5-5.6 FIELD OFFIC E : The Contractor shall provide, at no extra compensation, an
adequate field office for use of the Engineer, if specifically called for. The field office
shall be not less than 10 x 14 feet in floor area, substantially constructed, well heated , air
conditioned , lighted , and weather proof, so that documents will not be damaged. by the
elements.
C5-5 .7 CONTRUCTION STAKES: The City , through its Engineer, will furnish
the Contractor with all lines , grades, and measurements necessary to the proper
prosecution and control of the work contracted under these Contract Documents, and
lines , grades and measurements will be established by means of stakes or other customary
method of marking as may be found consistent with good practice .
These stakes or markings shall be set sufficiently in advance of construction operations to
avoid delay . Such stakes or markings as may be established for Contractor's use or
guidance shall be preserved by the Contractor until he is authorized by the Engineer to
remove them. Whenever , in the opinion of the Engineer, any stakes or markings have
been carelessl y or willfully destroyed, disturbed, or removed by the Contractor or any of
his emplo yees , the full cost of replacing such stakes or marks plus 25% will be charged
against the Contractor, and the full amount will be deducted from payment due the
Contractor.
C5-5.8 AUTHORITY AND DUTIES OF CITY INSPECTOR: City Inspectors will
be authorized to inspect all work done and to be done and all materials furnished. Such
inspection may extend to all or any part of the work, and the preparation or
manufacturing of the materials to be used or equipment to be installed. A City Inspector
may be stationed on the work to report to the Engineer as to the progress of the work and
the manner in which it is being performed , to report any evidence that the materials being
furnished or the work being performed by the Contractor fails to fulfill the requirements
of the Contract Documents , and to call the attention of the Contractor to any such failure
or other infringements. Such inspection or lack of inspection will not relieve the
Contractor from any obligation to perform the work in accordance with the requirements
of the Contract Documents. In case of any dispute arising between the Contractor and the
City Inspector as to the materials or equipment furnished or the manner of performing the
work, the City Inspector will have the authority to reject materials or equipment, and/or
to suspend work until the question at issue can be referred to and decided by the
Engineer. The City Inspector will not , however, be authorized to revoke, alter, enlarge, or
:release any requirement of these Contract Documents, nor to approve or accept any
portion or section of the work, nor to issue any instructions contrary tot he requirement s
of the Contract Documents. The City Inspector will in no case act as superintendent or
C5-5 (3)
foreman or perform any other duties for the Contractor, or interfere with the management
or operation of the work. He will not accept from the Contractor any compensation in any
form for performing any duties . The Contractor shall regard and obey the directions and
instructions of the City Inspector or Engineer when the same are consistent with the
obligations of the Contract Documents of the Contract Documents, provided, however,
should the Contractor obj ect to any orders or instructions or the City Inspector, the
Contractor may within six days make written appeal to the Engineer for his decision on
the matter in Controversy.
C5-5.9 INSPECTION: The Contractor shall furnish the Engineer with every
reasonable facility for ascertaining whether or not the work as performed is in accordance
with the requirements of the Contract Documents. If the Engineer so requests , the
Contractor shall, at any time before acceptance of the work, remove or uncover such
portion of the finished work as may be directed. After examination , the Contractor shall
restore said portions of the work to the standard required by the Contract Documents .
Should the work exposed or examined prove acceptable, the uncovering or removing and
replacing of the covering or making good of the parts removed shall be paid for as extra
work, but should Work so exposed or examined prove to be unacceptable , the uncovering
or removing and replacin g of all adjacent defective or damaged parts shall be at the
Contractor 's expense. No work shall be done or materials used without suitable
supervision or inspection.
C5-5.10 REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK: All
work , materials, or equipment which has been rejected shall be remedied or removed and
replaced in an acceptable manner by the Contractor at this expense. Work done beyond
the lines and grades given or as shown on the plans, except as herein specially provided,
or any Extra Work done wi thout written authority, will be considered as unauthorized and
done at the expense of the Contractor and will not be paid for by the Owner. Work so
done may be ordered remo ved at the Contractor 's expense. Upon the failure on the part of
the Contractor to comply with any order of the Engineer made under the provisions of
this paragraph, the Engineer will have the authority to cause defective work to be
remedied or removed and replaced and unauthorized work to be removed, and the cost
thereof may be deducted from any money due or to become due tot he Contractor. Failure
to require the removal of any defective or unauthorized work shall not constitute
acceptance of such work.
CS-5.11 SUBSTITUTE MATERIALS OR EQUIPMENT: If the Specifications ,
law, ordinance, codes or regulations permit Contractor to furnish or use a substitute that
is equal to any material or equipment specified, and if Contractor wishes to furnish or use
a proposed substitute, he shall, prior to the preconstruction conference , make written
application to ENGINEER for appro v al of such substitute certifying in writing that the
proposed substitute will pe rform adequately the function called for by the general design,
be similar and of equal substance to that specified and be suited to the same use and
capable of performing the same function as that specified ; and identifying all variations
of the proposed substitute from that specified and indicating available maintenance
C5-5 (4)
-
.....
service . No substitute shall be ordered or installed without written approval of Engineer
who will be the judge of the equality and may require Contractor to furnish such other
data about the proposed substitute as he considers pertinent. No substitute shall be
ordered or installed without such performance guarantee and bonds as Owner may
require which shall be furnished at Contractor's expense. Contractor shall indemnify and
hold harmless Owner and Engineer and anyone directly or indirectly employees by either
of them from and against the claims, damages, losses and expenses (including attorneys
fees) arising out of the use of substituted materials or equipment.
CS-5.12 SAMPLES AND TESTS OF MATERIALS: Where, in the opinion of the
Engineer, or as called for in the Contract Documents, tests of materials or equipment are
necessary, such tests will be made at the expense of and paid for direct to the testing
agency by the Owner unless other wise specifically provided. The failure of the Owner to
make any tests of materials shall in no way relieve the contractor of his responsibility of
furnishing materials and equipment fully conforming to the requirements of the Contract
Documents. Tests and sampling of materials, unless otherwise specified, will be made in
accordance with the latest methods prescribed by the American Society for Testing
Materials or specific requirements of the Owner. The Contractor shall provide such
facilities as the Engineer may require for collecting and forwarding samples and shall not,
without specific written permission of the Engineer, use materials represented by the
samples until tests have been made and the materials approved for use. The Contractor
will furnish adequate samples without charge to the Owner.
In case of concrete, the aggregates, design minimum, and the mixing and transporting
equipment 'shall be approved by the Engineer before any concrete is placed, and the
Contractor shall be responsible for replacing any concrete which does not meet the
requirements of the Contract Documents. Tests shall be made at least 9 days prior to the
placing of concrete, using samples from the same aggregate, cement, and mortar which
are to be used later in the concrete. Should the source of supply change, new tests shall be
made prior to the use of new materials.
CS-5 .13 STORAGE OF MATERIALS: All materials which are to be used in the
construction contract shall be stored so as to insure the preservation of quality and fitness
of the work. When directed by the Engineer, they shall be placed on wooden platforms or
other hard, clean durable surfaces and not on the ground, and shall be placed under cover
when directed. Stored materials shall be placed and located so as to facilitate prompt
inspection.
CS-5.14 EXISTING STRUCTURES AND UTILITIES : The location and dimensions
shown on the plans relative to the existing utilities are based on the best information
available. Omission from, the inclusion of utility locations on the Plans is not to be
considered as nonexistence of, or a definite location of, existing underground utilities.
The location of many gas mains, water mains, conduits, sewer lines and service lines for
all utilities, etc., is unknown to the Owner, and the Owner assumes no responsibility for
failure to show any or all such structures and utilities on the plans or to show them in
their exact location. It is mutually agreed that such failure will not be considered
CS-5 (5)
sufficient basis for claims for additional compensation for Extra Work or for increasing
the pay quantities in any manner whatsoever, unless an obstruction encountered is such as
to necessitate changes in the lines and grades of considerable magnitude or requires the
building of special works, p rovision of which is not made in these Contract Documents,
in which case the provision in these Contract Documents for Extra Work shall apply .
It shall be the Contractor 's responsibility to verify locations of the adjacent and/or
conflicting utilities sufficiently in advance of construction in order that he may negotiate
such local adjustments as necessary in the construction process to provide adequate
clearances . The Contractor shall take all necessary precautions in order to protect all
existing utilities, structures , and service lines. Verification of existing utilities, structures ,
and service lines shall include notification of all utility companies at least forty-eight ( 48)
hours in advance of construction including exploratory excavation if necessary. All
verification of utilities and their adjustment shall be considered subsidiary work.
CS-5 .15 INTERRUPTION OF SERVICE:
a . Normal Prosecution: In the normal prosecution of work where the
interruption of service is necessary, the Contractor, at least 24 hours in
advance, shall be required to :
1. Notify the Water Department's Distribution Division as to
location, time, and schedule of service interruption.
2 . Notify each customer personally through responsible personnel as
to the time and schedule of the interruption of their service, or
3 . In the event that personal notification of a customer cannot be
made, a prepared tag form shall be attached to the customer's door
knob . The tag shall be durable in composition, and in large bold
letters shall say:
..
CS-5 (6)
...
-
.....
...,
b.
"NOTICE"
Due to Utility Improvement in your neighborhood, your
(water) (sewer) service will be interrupted on ____ _
between the hours of and ----
This inconvenience will be as short as possible.
Thank You,
Contractor
Address Phone
Emergency: In the event that an unforeseen service interruption occurs,
notice shall be as above, but immediate.
C5-5.16 MUTUAL RESPONSIBILITY OF CONTRACTORS : If, through act or
neglect on the part of the Contractor, or any other Contractor or any sub-contractor shall
suffer loss or damage of the work, the Contractor agrees to settle with such other
Contractor or sub-contractor by agreement or arbitration. If such other Contractor or sub-
contractor shall assert any claim against the owner on account of damage alleged .to have
been sustained, the owner will notify the Contractor, who shall indemnify and save
harmless the owner against any such claim.
C5-5.17 CLEAN-UP: Clean-up of surplus and/or waste materials accumulated on
the job site during the prosecution of the work under these Contract Documents shall be
accomplished in keeping with a daily routine established to the satisfaction of the
Engineer. Twenty-four (24) hours after written notice is given the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the Engineer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct
action as the Engineer deems appropriate to correct the clean-up deficiencies cited to the
Contractor in the written notice, and the costs of such direct action, plus 25 % of such
costs, shall be deducted from the monies due or to become due to the Contractor.
Upon the completion of the project as a whole as covered by these Contract Documents,
and before final acceptance and final payment will be made, the Contractor shall clean
and remove from the site of the project all surplus and discarded materials, temporary
structures , and debris of every kind. He shall leave the site of all work in a neat and
orderly condition equal to that which originally existed. Surplus and waste materials
removed from the site of the work shall be disposed of at locations satisfactory to the
Engineer. The Contractor shall thoroughly clean all equipment and materials installed by
him and shall deliver over such materials and equipment in a bright, clean, polished and
new appearing condition. No extra compensation will be made to the Contractor for any
clean-up required on the project:
C5-5 (7)
CS-5.18 FINAL INSPECTION: Whenever the work provided for in and
contemplated under the Contract Documents has been satisfactorily completed and final
clean-up performed, the Engineer will notify the proper officials of the Owner and
request that a Final Inspection be made . Such inspection will be made within 10 days
after such notification . Aft er such final inspection, if the work and materials and
equipment are found sati sfactory, the Contractor will be notified in writing of the
acceptance of the same after the proper resolution has been passed by the City Council.
No time charge will be made against the Contractor between said date of notification of
the Engineer and the date of final inspection of the work .
,, '
C5-5 (8)
.....
-
-
-
PART C -GENERAL CONDITIONS
C6-6 LEGAL RELATIONS AND PUBLIC
RESPONSIBILITY
SECTION C6-6 LEGAL RELATIONS AND PUBLIC RESPONSIBILITY
C6-6.1 LAWS TO BE OBSERVED: The Contractor shall at all times observe and
comply with all Federal and State Laws and City ordinances and regulations which in any
way affect the conduct of the work or his operations , and shall observe and comply with
all orders , laws , ordinances and regulations which exist or which may be enacted later by
bodies having jurisdiction or authority for such enactment. No plea or misunderstanding
or ignorance thereof will be considered. The Contractor and his Sureties shall indemnify
and save harmless the City and all of its officers , agents , and employees against any and
all claims or liability arising from or based on the violation of any such law, ordinance ,
regulation , or order , whether it be by himself or his employees .
C6-6.2 PERMITS AND LICENSES: The Contractor shall procure all permits and
licenses , pay all charges , costs and fees , and give all notices necessary and incident to the
due and lawful prosecution of the work.
C6-6.3 PATENTED DEVICES, MATERIALS, AND PROCESSES: If the Contractor
is required or desires to use any design , device , material , or process covered by letter,
patent, or copyright, he shall provide for such use by suitable legal agreement with the
patentee or owner of such patent, letter, or copyrighted design. It is mutually agreed and
understood that without exception the contract price shall include all royalties or cost
arising from patents , trademarks, and copyrights in any way involved in the work. The
Contractor and his sureties shall indemnify and save harmless the Owner from any and all
claims for infringement by reason of the use of any such trade-mark or copyright in
connection with the work agreed to be performed under these Contract Documents, and
shall indemnify the Owner for any cost, expense , or damage which it may be obliged to
pay by reason of such infringement at any time during the prosecution of the work or after
completion of the work, provided, however, that the Owner will assume the responsibility
to defend any and all suits brought for the infringement of any patent claimed to be
infringed upon the design , type of construction or material or equipment specified in the
Contract Documents furnished the Contractor by the Owner, and to hold the Contractor
harmless on account of such suits .
C6-6.4 SANITARY PROVISIONS: The Contractor shall establish and enforce
among his employees such regulations in regard to cleanliness and disposal of garbage
and waste as will tend to prevent the inception and spread of infectious or contagious
diseases and to effecti vely prevent the creation of a nuisance about the work on any
property either public or private, and such regulations as are required by Law shall be put
into immediate force and effect by the Contractor. The necessary sanitary conveniences
for use of laborers on the work, properly secluded from public observation, shall be
constructed and maintained by the Contractor and their use shall be strictly enforced by
C6-6(1)
the Contractor. All such fa cilities shall be kept in a clean and sanitary condition , free from
objectionable odors so as not to cause a nuisance. All sanitary laws and regulations of the
State of Texas and the City shall be strictly complied with .
C6-6.5 PUBLIC SAFETY AND CONVENIENCE: Materials or equipment stored
about the work shall be pl aced and used , and the work shall at all times be so conducted,
as to cause no greater obstruction or inconvenience to the public than is considered to be
absolutely necessary by the Engineer. The Contractor is required to maintain at all times
all phases of his work in such a manner as not to impair the safety or convenience of the
public , including , but not limited to , safe and convenient 'ingress and egress to the
property contiguous tot he work area. The Contractor shall make adequate provisions to
render reasonable ingress and egress for normal vehicular traffic, except during actual
trenching or pipe installation operations , at all driveway crossings . Such provisions may
include bridging , placement or crushed stone or gravel or such other means of providing
proper ingress and egress for the property served by the driveway as the Engineer may
approve as appropriate . Such other means may include the diversion of driveway traffic,
with specific approval by the Engineer, If diversion of traffic is approved by the Engineer
at any location , the Contractor may make arrangements satisfactory to the Engineer for
the diversion of traffic , and shall , at his expense , provide all materials and perform all
work necessary for the construction and maintenance of roadways and bridges for such
diversion of traffic. Sidewalks must not be obstructed except by special permission of the
Engineer.
The materials excavated and the construction materials such as pipe used in construction
of the work shall be placed so as not to endanger the work or prevent free access to all
fire hydrants , fire alarm bo xes , police call boxes , water valves , gas valves, or manholes in
the vicinity. The Owner reserves the right to remedy any neglect on the part of the
Contractor as regards to public convenience and safety which may come to its attention,
after twenty-four hours no t ice in writing to the Contractor, save in cases of emergency
when it shall have the right to remedy any neglect without notice, and in either case, the
cost of such work or materials furnished by the Owner or by the City shall be deducted
from the monies due or to become due to the Contractor.
The Contractor, after approval of the Engineer, shall notify the Fire Department
Headquarters, Traffic Engineer, and Police Department, when any street or alley is
requested to be closed or obstructed or any fire hydrant is to be made inaccessible , and
when so directed by the Engineer , shall keep any street, streets, or highways in condition
for unobstructed use by fire apparatus . The Contractor shall promptly notify the Fire
Department Headquarters when all such obstructed streets, alleys , or hydrants are placed
back in service .
Where the Contractor is required to construct temporary bridges or make other
arrangements for crossing over ditches or streams , his responsibility for accidents in
connection with such crossings shall include the roadway approaches as well as the
structures of such crossings.
C6-6(2)
-
-
-
-
The Contractor shall at all times conduct his operation and use of construction machinery
so as not to damage or destroy trees and scrubs located in close proximity to or on the site
of the work . Wherever any such damage may be done , the Contractor shall immediately
satisfy all claims of property owners , and no payment will be made by the Owner in
settlement of such claims . The Contractor shall file with th e Engineer a written statement
showing all such claims adjusted .
C6-6.6 PRIVILEGE S OF CONTRACTOR IN STREETS, ALLEYS, AND
RIGHT -OF-WAY : For the performance of the contract , the Contractor will be
permitted to use and occupy such portions of the public streets and alleys , or other public
places or other rights-of-way as provided for in the ordinances of the City , as shown in
the Contract Documents , or as may be specifically authorized in writing by the Engineer.
A reasonable amount of tools , materials , and equipment for construction purposes may be
stored in such space, but no more than is necessary to avoid delay in the construction
operations. Excavated and waste materials shall be piled or staked in such a way as not to
interfere with the use of spaces that may be designated to be left free and unobstructed
and so as not to inconvenience occupants of adjacent property. If the street is occupied by
railroad tracks , the work shall be carried on in such manner as not to interfere with the
operation of trains , loading or unloading of cars , etc. Other contractors of the Owner may ,
for all purposes required by the contract , enter upon the work and premises used by the
Contractor and shall be pro vided all reasonable facilities and assistance for the
completion of adjoining work. Any additional grounds desired by the Contractor for his
use shall be provided by him at his own cost and expense .
C6-6 . 7 RAILWAY CROSSINGS: When the work encroaches upon any right -of-way
of any railroad, the City will secure the necessary easement for the work. Where the
railroad tracks are to be crossed, the Contractor shall observe all the regulations and
instructions of the railroad company as to the methods of performing the work and take
all precautions for the safety of property and the public . Negotiations with the railway
companies for the permits shall be done by and through the City . The Contractor shall
give the City Notice not less than five days prior to the time of his intentions to begin
work on that portion of the project which is related to the railway properties . The
Contractor will not be given extra compensation for such railway crossings unless
specifically set forth in the Contract Documents.
C6 -6.8 BARRICADES, WARNINGS AND WATCHMEN: Where the work is
carried on in or adjacent to any street , alley , or public place , the Contractor shall at his
own expense furnish, erect, and maintain such barricades, fences , lights , and danger
signals , shall provide such watchman , and shall take all such other precautionary
measures for the protection of persons or property and of the work as are necessary.
Barricades and fences shall be painted in a color that will be visible at night. From sunset
to sunrise the Contractor shall furnish and maintain at least one easily visible burning
light at each barricade . A sufficient number of barricades shall be erected and maintained
to keep pedestrians away from , and vehicles from being driven on or into , any work under
C6-6(3)
construction or being maintained . The Contractor shall furnish watchmen and keep them
at their respective assignments in sufficient numbers to protect the work and prevent
accident or damage.
All installations and procedures shall be consistent with provisions set forth in the "1980
Texas Manual on Uniform Traffic Control Devices for Streets and Highways " issued
under the authority of the "State of Te xas Uniform Act Regulating Traffic on Highways ",
codified as Article 6701d Veron 's Ci vil Statues , pertinent section being Section Nos . 27,
29 , 30 and 31.
The Contractor will not remove any regulatory sign , instructional sign , street name sign ,
or other sign which has be en erected by the City . If it is determined that a sign must be
removed to permit required construction, the Contractor shall contact the Transportation
and Public Works Department, Signs and Markings Division (phone number 871-8075),
to remove the sign. In case of regulatory signs , the Contractor must replace the permanent
sign with a temporary sign meeting the requirements of the above referred manual and
such temporary sign must be installed prior to the removal of the permanent sign . If the
temporary sign is not installed correctly or if it does not meet the required specifications,
the permanent sign shall be left in place until the temporary sign requirements are met.
When construction work is completed to the extent that the permanent sign can be re-
installed , the Contractor shall again contact the Signs and Markings Division to re-install
the permanent sign and shall leave his temporary sign in place until such re-installation is
completed .
The Contractor will be held responsible foe all damage to the work or the public due to
failure of barricades , signs, fences , lights , or watchmen to protect them. Whenever
evidence is found of such damage to the work the Engineer may order the damaged
portion immediately remo ved and replaced by the Contractor at the Contractor 's own
expense. The Contractor 's responsibility for the maintenance of barricades, signs , fences
and lights , and for providing watchmen shall not cease until the project shall have been
completed and accepted by the Owner.
No compensation , except as specifically provided in these Contract Documents, will be
paid to the Contractor for the Work and materials involved in the constructing, providing ,
and maintaining of barricades , signs , fences , and lights or salaries of watchmen, for the
subsequent removal and disposal of such barricades, signs, or for any other incidentals
necessary for the proper protection, safety, and convenience of the public during the
contract period, as this work is considered to be subsidiary to the several items for which
unit or lump sum prices are requested in the Proposal.
C6-6 .9 USE OF EXPLOSIVES, DROP WEIGHT, ETC.: Should the Contractor
elect to use explosives , dro p weight, etc ., in the prosecution of the work, the utmost care
shall be exercised at all times so as not to endanger life or property . The Contractor shall
notify the proper representative of any public service corporation, any company,
individual, or utility, and the Owner, not less than twenty-four hours in advance of the use
C6-6(4)
. ..,,
-
-
--·
·-
-
of any activity which might damage or endanger their or his property along or adjacent to
the work.
Where the use of explosives is to be permitted on the project, as specified in the Special
Conditions Documents, or the use of explosives is requested, the Contractor shall submit
notice to the Engineer in writing twenty-four hours prior to commencing and shall furnish
evidence that he has insurance coverage to protect against any damages and/or injuries
arising out of such use of explosives .
C6-6.10 WORK WITHIN EASEMENTS : Where the work passes over, through, or
into private property, the Owner will provide such right-of-way or easement privileges, as
the City may deem necessary for the prosecution of the work. Any additional rights-of-
way or work area considered necessary by the Contractor shall be provided by him at his
expense. Such additional rights-of-way or work area shall be acquired for the benefit of
the City. The City shall be notified in writing as to the rights so acquired before work
begins in the affected area. The Contractor shall not enter upon private property for any
purpose without having previously obtained permission from the owner of such property .
The Contractor will not be allowed to store equipment or material on private property
unless and until the specified approval of the property owner has been secured in writing
by the Contractor and a copy furnished to the Engineer. Unless specifically provided
otherwise, the Contractor shall clear all rights-of-way or easements of obstructions which
must be removed to make possible proper prosecution of the work as a part of the project
construction operations. The Contractor shall be responsible for the preservation of and
shall use every precaution to prevent damage to, all tress, shrubbery, plants, lawns,
fences , culverts, curbing, and all other types of structures or improvements, to all water,
sewer, and gas lines, to all conduits, overhead pole lines, or appurtenances thereof,
including the construction of temporary fences and to all other public or private property
adjacent to the work.
The Contractor shall notify the proper representatives of the owners or occupants of the
public or private lands of interest in lands which might be affected by the work. Such
notice shall be made at least 48 hours in advance of the beginning of the work. Notices
shall be applicable to both public and private utility companies or any corporation,
company, individual, or other, either as owners or occupants, whose land or interest in
land might be affected by the work. The Contractor shall be responsible for all damage or
injury to property of any character resulting from any act, omission, neglect, or
misconduct in the manner or method or execution of the work, or at any time due to
defective work , material, or equipment.
When and where any direct or indirect or injury is done to public or private property on
account of any act, omission, neglect, or misconduct in the execution of the work, or in
consequence of non-execution thereof on the part of the Contractor, he shall restore or
have restored as his cost and expense such property to a condition at least equal to that
existing before such damage or injury was done, by repairing, rebuilding , or otherwise
C6-6(5)
replacing and restoring as may be directed by the Owner , or he shall make good such
damages or injury in a manner acceptable to the owner of the property and the Engineer.
All fences encountered an d removed during construction of this project shall be restored
to the original or a better than original condition upon completion of this project. When
wire fencing , either wir e mesh or barbed wire is to be crossed, the Contractor shall set
cross brace posts on either side of the permanent easement before the fence is cut. Should
additional fence cuts be ne cessary , the Contractor shall provide cross-braced posts at the
point of the proposed cut in addition to the cross braced posts provided at the permanent
easements limits, before the fence is cut.
Temporary fencing shall be erected in place of the fencing removed whenever the work is
not in progress and when the site is vacated overnight , and/or at all times to prevent
livestock from entering th e construction area. The cost for fence removal , temporary
closures and replacement shall be subsidiary to the various items bid in the project
proposal. Therefore, no separate payment shall be allowed for any service associated with
this work .
In case of failure on th e part of the Contractor to restore such property or to make good
such damage or injury, th e Owner may , upon 48 hour written notice under ordinary
circumstances , and without notice when a nuisance or hazardous condition results,
proceed to repair , rebuild, or otherwise restore such property as may be determined by the
Owner to be necessary, an d the cost thereby will be deducted from any monies due to or
to become due to the Contractor under this contract.
C6.6. l 1 INDEPENDENT CONTRACTOR: It is understood and agreed by the
parties hereto that the Co ntractor shall perform all work and services hereunder as an
independent contractor , and not as an officer, agent, servant, or employee of the Owner.
Contractor shall have exclusive control of and exclusive right to control the details of all
work and services performed hereunder, and all persons performing the same, and shall
be solely responsible for the acts and omissions of its officers , agents, servants,
employees , contractor, subcontractors, licensees and invitees. The doctrine of respondeat
superior shall not apply as between Owner and Contractor, its officers, agents, employees,
contractors and subcontractors , and nothing herein shall be construed as creating a
partnership or joint enterpri se between Owner and Contractor.
C6-6 .12 CONTRACTOR 'S RESPONSIBILITY FOR DAMAGE CLAIMS: Contractor
covenants and agrees to , and does hereby indemnify, hold harmless and defend Owner, its
officers , agents , servants , and employees from and against any and all claims or suits for
property damage or loss and/or personal injury , including death, to any and all persons , of
whatsoever kind or character, whether real or asserted , arising out of or in connection
with, directly or indirectly, the work and services to be performed hereunder by the
Contractor, its officers , agents, employees, contractors, subcontractors, licensees or
invitees , whether or not caused, in whole or in apart, by alleged negligence on the part of
officers , agents, employee s , contractors , subcontractors , licensees or invitees of the
C6-6(6)
_ _,
-
-
Owner; and said Contractor does hereby covenant and agree to assume all liability and
responsibility of Owner , its officers , agents , servants, and employees for property damage
or loss, and/or personal injuries , including death, to any and all person of whatsoever kind
or character, whether real or asserted , arising out of or in connection with , directly or
indirectly , the work and services to be performed hereunder by the Contractor, its
officers , agents , employees , contractors , s_ubcontractors , licensees or invitees , whether or
not caused , in whole or in apart, by alleged negligence of officers , agents , employees ,
contractors , subcontractors , licensees or invitees of the Owner. Contractor likewise
covenants and agrees to , and does hereby , indemnify and hold harmless Owner from and
against any and all injuries , loss or damages to property of the Owner during the
performance of any of the terms and conditions of this Contract , whether arising out of or
in connection with or resulting from , in whole or in apart, any and all alleged acts of
omission of officers, agents , employees , contractors, subcontractors, licensees, or invitees
of the Owner.
In the event a written claim for damages against the contractor or its subcontractors
remains unsettled at the time all work on the project has been completed to the
satisfaction of the Director of the Water Department, as evidenced by a final inspection ,
final payment to the Contractor shall not be recommended to the Director of the Water
Department for a period of 30 days after the date of such final inspection , unless the
Contractor shall submit written evidence satisfactory to the Director that the claim has
been settled and a release has been obtained from the claimant involved .
If the claims concerned remains unsettled as of the expiration of the above 30-day period ,
the Contractor may be deemed to be entitled to a semi-final payment for work completed ,
such semi-final payment to be in the amount equal to the total dollar amount then due less
the dollar value of any written claims pending against the Contractor arising out of
performance of such work, and such semi-final payment may then be recommended by
the Director.
The Director shall not recommend final payment to a Contractor against whom such a
claim for damages is outstanding for a period of six months following the date of the
acceptance of the work performed unless the Contractor submits evidence in writing
satisfactory tot he Director that :
1. The claim has been settled and a release has been obtained from the
claimant involved, or
2. Good faith efforts have been made to settle such outstanding claims , and
such good faith efforts have failed.
If condition (1) above is met at any time within the six month period, the Director shall
recommend that the final payment to the Contractor be made. If condition (2) above is
met at any time within the six month period, the Director may recommend that final
payment to the Contractor be made. At the expiration of the six month period, the
C6-6(7)
Director may recommend that final payment be mad e if all other work has been
performed and all other ob ligations of the Contractor have been met to the satisfaction of
the Director.
The Director may, if he deems it appropriate, refuse to accept bids on other Water
Department Contract work from a Contractor against whom a claim for damages is
outstanding as a result of work performed under a City Contract.
C6-6 .13 CONTRACTOR'S CLAIM FOR DAMAGES: Should the Contractor claim
compensation foe any alle ged damage by reason of the acts or omissions of the Owner , he
shall within three days after the actual sustaining of such alleged damage, make a written
statement to the Engineer , setting out in detail the nature of the alleged damage , and on or
before the 25th day of the month succeeding that in which ant such damage is claimed to
have been sustained , the Contractor shall file with the Engineer an itemized statement of
the details and the amount of such alleged damage and , upon request, shall give the
Engineer access to all books of account , receipts, vouchers, bills of lading , and other
books or papers containing any evidence as to the amount of such alleged damage . Unless
such statements shall be filed as hereinabove required, the Contractor's claim for
compensation shall be wai ved , and he shall not be entitled to payment on account of such
damages.
C6-6 .14 ADJUSTMENT OR RELOCATION OF PUBLIC UTILITIES, ETC.: In case
it is necessary to change , move, or alter in any manner the property of a public utility or
others, the said property shall not be moved or interfered with until orders thereupon have
been issued by the Engineer. The right is reserved to the owners of public utilities to enter
the geographical limits of the Contract for the purpose of making such changes or repairs
to the property that may be necessary by the performance of this Contract.
C6-6.15 TEMPORARY SEWER AND DRAIN CONNECTIONS: When existing
sewer lines have to be taken up or removed , the Contractor shall , at his own expense and
cost , provide and maintain temporary outlets and connections for all private or public
drains and sewers. The Contractor shall also take care of all sewage and drainage which
will be received from thes e drains and sewers, and for this purpose he shall provide and
maintain,· at his own cost and expense , adequate pumping facilities and temporary outlets
or divisions.
The Contractor, at his own cost and expense, shall construct such troughs, pipes , or other
structures necessary , and be prepared at all times to dispose of drainage and sewage
received from these tempo rary connections until such times as the permanent connections
are built and are in servic e . The existing sewers and connections shall be kept in service
and maintained under the Contract, except when specified or ordered to be abandoned by
the Engineer. All water , sewage , and other waste shall be disposed of in a satisfactory
manner so that no nuisan ce is created and so that the work under construction will be
adequately protected.
C6 -6(8)
-
-
' ~-
-
--
-
'--
C6-6. l 6 ARRANGEMENT AND CHARGES FOR WATER FURNISHED BY THE
CITY : When the Contractor desires to use City water in connection with any construction
work, he shall make complete and satisfactory arrangements with the Fort Worth City
Water Department for so doing .
City water furnished to the Contractor shall be delivered to the Contractor from a
connection on an existing City main. All piping required beyond the point of delivery
shall be installed by the Contractor at his own expense.
The Contractor's responsibility in the use of all existing fire hydrant and/or valves is
detailed in Section E2-l .2 USE OF FIRE HYDRANTS AND VALVES in these General
Contract Documents.
When meters are . used to measure the water, the charges, if any, for water will be made at
the regular established rates. When meters are not used, the charges, if any, will be as
prescribed by the City ordinance , or where no ordinances applies , payment shall be made
on estimates and rates established by the Director of the Fort Worth Water Department.
C 6-6.17 USE OF A SECTION OR PORTION OF THE WORK: Whenever, in the
opinion of the Engineer , any section or portion of the work or any structure is in suitable
condition, it may be put into use upon the written notice of the Engineer, and such usage
shall not be held to be in any way an acceptance of said work or structure or any part
thereof or as a waiver of any of the provisions of these Contract Documents . All
necessary repairs and removals of any section of the work so put into use , due to defective
materials or workmanship , equipment, or deficient operations on the part of the
Contractor, shall be performed by the Contractor at his expense.
C6-6.18 CONTRACTOR'S RESPONSIBILITY FOR THE WORK : Until written
acceptance by the Owner as provided for in these Contract Documents, the work shall be
under the charge and care of the Contractor, and he shall take every necessary precaution
to prevent injury or damage to the work or any part thereof by action of the elements or
from any cause whatsoever, whether arising from the execution or nonexecution of the
work. The Contractor shall rebuild, repair, restore, and make good at his own expense all
injuries or damage to any portion of the work occasioned by any of the hereinabove
causes .
C6-6.19 NO WAIVER OF LEGAL RIGHTS: Inspection by the Engineer or any
order by the Owner by payment of money or any payment for or acceptance of any work,
or any extension of time, or any possession taken by the City shall not operate as. a waiver
of any provision of the Contract Documents. Any waiver of any breach or Contract shall
not be held to be a waiver of any other or subsequent breach.
The Owner reserves the right to correct any error that may be discovered in any estimate
that may have been paid and to adjust the same to meet the requirements of the Contract
Documents .
C6-6(9)
C6-6.20 PERSONAL LIABILITY OF PUBLIC OFFICIALS: In carrying out the
provisions of these Contract Documents or in exercising any power of authority granted
thereunder, there shall be no liability upon the authorized representative of the Owner,
either personally or other wise as they are agents and representatives of the City.
C6-6 .21 STATE SALES TAX: On a contract awarded by the City of Fort Worth, and
organization which qualifies for exemption pursuant the provisions of Article 20.04 (H)
of the Texas Limited Sales , Excise , and Use Tax Act, the Contractor may purchase, rent
or lease all materials , supplies and equipment used or consumed in the performance of
this contract by issuing to his supplier an exemption certificate in lieu of the tax, said
exemption certificate to comply with State Comptroller's Ruling .007. Any such
exemption certificate issued to the Contractor in lieu of the tax shall be subject to and
shall comply with the provision of State Comptroller's Ruling .011, and any other
applicable State Comptroller's rulings pertaining to the Texas Limited Sales, Excise, and
Use Tax Act.
On a contract awarded by a developer for the construction of a publicly-owner
improvement in a street right-of-way or other easement which has been dedicated to the
public and the City of Fort Worth , an organization which qualifies for exemption
pursuant the provisions of Article 20.04 (H) of the Texas Limited Sales, Excise, and Use
Tax Act, the Contractor can probably be exempted in the same manner stated above .
Texas Limited Sales, Excise, and Use Tax Act permits and information can be obtained
from:
Comptroller of Public Accounts
Sales Tax Division
Capitol Station
Austin, TX
C6-6(10)
-
-
-
-
-
-
,_
PART C-GENERAL CONDITIONS
C7-7 PROSECUTION AND PROGRESS
SECTION C7-7 PROSECUTION AND PROGRESS:
C7-7.1 SUBLETTING: The Contractor shall perform with his own organization,
and with the assistance of workmen under his immediate superintendance, work of a
value of not less than fifty (50%) percent of the value embraced on the contract. If the
Contractor sublets any part of the work to be done under these Contract Documents , he
will not under any circumstances be relieved of the responsibility and obligation assumed
under these Contract Documents. All transactions of the Engineer will be with the
Contractor. Subcontractors will be considered only in the capacity of employees or
workmen of the Contractor and shall be subject tot he same requirements as to character
and competency . The Owner will not recognize any subcontractor on the work. The
Contractor shall at all times, when the work is in operation, be represented either in
person o.r by a superintendent or other designated representatives.
C7-7.2 ASSIGNMENT OF CONTRACT: The Contractor shall not assign, transfer,
sublet , or otherwise dispose of the contract or his rights , title , or interest in or to the same
or any part thereof without the previous consent of the Owner expressed by resolution of
the City Council and concurred in by the Sureties.
If the Contractor does, without such previous consent, assign, transfer, sublet, convey, or
otherwise dispose of the contract or his right, title, or interest therein or any part thereof,
to any person or persons , partnership , company, firm , or corporation, or does by
bankruptcy , voluntary or involuntary, or by assignment under the insolvency laws of any
states, attempt to dispose of the contract may, at the option of the Owner be revoked and
annulled, unless the Sureties shall successfully complete said contract, and in the event of
any such revocation or annulment, any monies due or to become due under or by virtue of
said contract shall be retained by the Owner as liquidated damages for the reason that it
would be impracticable and extremely difficult to fix the actual damages.
C7-7.3 PROSECUTION OF THE WORK: Prior to beginning any construction
operations , the Contractor shall submit to the Engineer in five or more copies, if
requested by the Engineer, a progress schedule preferably in chart or diagram form, or a
brief outlining in detail and step by step the manner of prosecuting the work and ordering
materials and equipment which he expects to follow in order to complete the project in
the scheduled time. There shall be submitted a table of estimated amounts to be earned by
the Contractor during each monthly estimate period.
The Contractor shall commence the work to be performed under this contract within the
time limit stated in these Contract Documents and shall conduct the work in a continuous
manner and with sufficient equipment, materials, and labor as is necessary to insure its
completion within the time limit.
C7-7(1)
The sequence requested of all construction operations shall be at all times as specified in
the Special Contract Documents. Any Deviation from such sequencing shall be submitted
to the Engineer for his approval. Contractor shall not proceed with any deviation until he
has received written approval from the Engineer. Such specification or approval by the
Engineer shall not relieve the Contractor from full responsibility of the complete
performance of the Contract.
The contract time may be changed only as set forth in Section C7-7.8 EXTENSION OF
TIME OF COMPLETION of this Agreement, and a progress schedule shall not constitute
a change in the contract time.
C7-7.4 LIMITATION OF OPERATIONS: The working operations shall at all
times be conducted by the Contractor so as to create a minimum amount of inconvenience
to the public . At any time when, in the judgment of the Engineer, the Contractor has
obstructed or closed or is carrying on operations in a portion of a street or public way
greater than is necessary for proper execution of the work, the Engineer may require the
Contractor to finish the section on which operations are in progress before the work is
commenced on any additional section or street.
C7-7.5 CHARACTER OF WORKMEN AND EQUIPMENT: Local labor shall be
used by the Contractor when it is available. The Contractor may bring from outside the
City of Fort Worth his key men and his superintendent. All other workmen, including
equipment operators, may be imported only after the local supply is exhausted. The
Contractor shall employ only such superintendents, foremen, and workmen who are
careful, competent, and fully qualified to perform the duties and tasks assigned to them,
and the Engineer may demand and secure the summary dismissal of any person or persons
employed by the Contractor in or about or on the work who, in the opinion of the Owner,
shall misconduct himself or to be found to be incompetent, disrespectful, intemperate,
dishonest, or otherwise objectionable or neglectful in the proper performance of his or
their duties, or who neglect or refuses to comply with or carry out the direction of the
owner, and such person or persons shall not be employed again thereon without written
consent of the Engineer.
All workmen shall have sufficient skill , ability, and experience to properly perform the
work assigned to them and operate any equipment necessary to properly carry out the
performance of the assigned duties.
The Contractor shall furnish and maintain on the work all such equipment as is
considered to be necessary for the prosecution of the work in an acceptable manner and at
a satisfactory rate of progress. All equipment , tools, and machinery used for handling
materials and executing any part of the work shall be subject to the approval of the
Engineer and shall be maintained in a satisfactory, safe and efficient working condition.
Equipment on any portion of the work shall be such that no injury to the work. Workmen
or adjacent property will result from its use . ·
C7-7(2)
-
-
...
-
-
C7-7.6 WORK SCHEDULE: Elapsed working days shall be computed starting
with the first day of the work completed as defined in Cl-1.23 "WORKING DAYS" or
the date stipulated in the "WORK ORDER" for beginning work, whichever comes first.
Nothing in these Contract Documents shall be construed as prohibiting the Contractor
from working on Saturday, Sunday or Legal Holidays, providing that the following
requirements are met:
a. A request to work on a specific Saturday, Sunday or Legal Holiday must
be made to the Engineer no later that the preceding Thursday.
b. Any work to be done on the project on such a specific Saturday, Sunday or
Legal Holiday must be, in the opinion of the Engineer, essential to the
timely completion of the project.
The Engineer's decision shall be final in response to such a request for approval to work
on a specific Saturday, Sl,lilday or Legal Holiday, and no extra compensation shall be
allowed to the Contractor for any work performed on such a specific Saturday, Sunday or
Legal Holiday.
Calendar Days shall be defined in C 1-1.24 and the Contractor may work as he so desires.
C7-7.7 TIME OF COMMENCEMENT AND COMPLETION: The Contractor shall
commence the working operations within the time specified in the Contract Documents
and set forth in the Work Order. Failure to do so shall be considered by the owner as
abandonment of the Contract by the Contractor and the Owner may proceed as he sees fit.
The Contractor shall maintain a rate of progress such as will insure that the whole work
will be performed and the premises cleaned up in accordance with the Contract
Documents and within the time established in such documents and such extension of time
as may be properly authorized.
C7-7 .8 EXTENSION OF TIME COMPLETION: The Contractor's request for an
extension of time of completion shall be considered only when the request for such
extension is submitted in writing to the Engineer within seven days from and after the
time alleged cause of delay shall occurred. Should an extension of the time of completion
be requested such request will be forwarded to the City Council for approval.
In adjusting the contract time for completion of work, consideration will be given to
unforeseen causes beyond the control of and without the fault or negligence of the
Contractor, fire , flood, tornadoes, epidemics, quarantine restrictions, strikes, embargoes,
or delays of sub-contractors due to such causes.
C7-7(3)
When the date of completion is based on a calendar day bid, a request for extension of
time because of inclement weather will not be considered. A request for extension of time
due to inability to obtain supplies and materials will be considered only when a review of
the Contractor's purchase order dates and other pertinent data as requested by the
Engineer indicates that the Contractor has made a bonafide attempt to secure delivery on
schedule. This shall include efforts to obtain the supplies and materials from alternate
sources in case the first source cannot make delivery .
If satisfactory execution and completion of the contract should require work and materials
in greater amounts or quantities than those set forth in the approved Contract Documents,
then the contract time mat be increased by Change Order.
C7-7.9 DELAYS: The Contractor shall receive no compensation for delays or
hindrances to the work, except when direct and unavoidable extra cost to the Contractor
is caused by the failure of the City to provide information or material, if any, which is to
be furnished by the City . When such extra compensation is claimed, a written statement
thereof shall be presented by the Contractor to the Engineer and if by the Engineer found
correct, shall be approved and referred by the Engineer to the City Council for final
approval or disapproval; and the action thereon by the Ci ty Council shall be final and
binding. If delay is caused by specific orders given by the Engineer to stop work, or by
the performance of extra work , or by the failure of the City to provide material or
necessary instructions for carrying on the work, then such delay will entitle the Contractor
to an equivalent extension of time, his application for shall, however, be subject to the
approval of the City Council: and no such extension of time shall release the Contractor
or the surety on his performance bond from all his obligations hereunder which shall
remain in full force until the discharge of the contract.
C7-7.10 TIME OF COMPLETION: The time of completion is an essential
element of the Contract. Each bidder shall indicate in the appropriate place on the last
page of the proposal, the number of working days or calendar days that he will require to
fully complete this contract or the time of completion will be specified by the City in the
proposal section of the Contract Documents .
The number of days indicated shall be a realistic estimate of the time required to complete
the work covered by the specific contract being bid upon . The amount of time so stated
by the successful bidder or the City will become the time of completion specified in the
Contract Documents.
For each calendar day that any work shall remain uncompleted after the time specified in
the Contract Documents, or increased time granted by the Owner, or as automatically
increased by additional wo rk or materials ordered after the contract is signed, the sum per
day given in the following schedule, unless otherwise specified in other parts of the
Contract Documents, will be deducted from the monies due the Contractor, not as a
penalty, but as liquidated damages suffered by the Owner.
C7 -7(4)
-
-
-
'--
AMOUNT OF CONTRACT AMOUNT OF
LIQUIDATED
DAMAGES
PER DAY
Less than $ 5,000 inclusive $ 35.00
$ 5,001 to $ 15 ,000 inclusive $ 45 .00
$ 15 ,001 to $ 25 ,000 inclusive $ 63 .00
$ 25 ,001 to $ 50 ,000 inclusive $ 105 .00
$ 50 ,001 to $ 100 ,000 inclusive $ 154 .00
$ 100,001 to $ 500 ,000 inclusive $ 210.00
$ 500 ,001 to $1 ,000 ,000 inclusive $ 315 .00
$ 1,000,001 to $2,000,000 inclusive $ 420.00
$2,000,000 and over $ 630.00
The parties hereto understand and agree that any harm to the City caused by the
Contractor's delay in completing the work hereunder in the time specified by the Contract
Documents would be incapable or very difficult to calculate due to lack of accurate
information, and that the "Amount of Liquidated Damages Per Day", as set out above, is
a reasonable forecast of just compensation due the City for harm caused by any delay .
C?-7.11 SUSPENSION BY COURT ORDER: The Contractor shall suspend
operations on such part or parts of the work ordered by any court, and will not be entitled
to additional compensation by virtue of such court order. Neither will he be liable to the
City in the vent the work is suspended by a Court Order. Neither will the Owner be liable
to the Contractor by virtue of any Court Order or action for which the Owner is not solely
responsible .
C?-7 .12 TEMPORARY SUSPENSION: The Owner shall have the right to suspend
the work operation wholly or in part for such period or periods of time as he 1p.ay deem
necessary due to unsuitable weather conditions or any other unsuitable conditions which
in the opinion of the Owner or Engineer cause further prosecution of the work to be
unsatisfactory or detrimental to the interest of the project. During temporary suspension
of the work covered by this contract, for any reason, the Owner will make no extra
payment for stand-by time of construction equipment and/or construction crews .
If it should become necessary to suspend work for an indefinite period, the Contractor
shall store all materials in such manner that they will not obstruct or impede the public
unnecessarily nor become damaged in any way, and he shall take every precaution to
prevent damage or deterioration of the work performed; he shall provide suitable drainage
about the work, and erect temporary structures where necessary.
Should the Contractor not be able to complete a portion of the project due to causes
beyond the control of and without the fault or negligence of the Contractor as set forth in
Paragraph C7 -7.8 EXTENSION OF THE TIME OF COMPLETION, and should it be
C7 -7(5)
determined by mutual consent of the Contractor and the Engineer that a solution to allow
construction to proceed is not available within a reasonable period of time, then the
Contractor may be reimbursed for the cost of moving his equipment off the job and
returning the necessary equipment to the job when it is determined by the Engineer that
construction may be resumed . Such reimbursement shall be based on actual cost to the
Contractor of moving the equipment and no profit will be allowed .
No reimbursement shall be allowed if the equipment is moved to another construction
project for the City of Fort Worth.
The Contractor shall not suspend work without written notice from the Engineer and shall
proceed with the work operations promptly when notified by the Engineer to so resume
operations.
C7-7.13 TERMINATION OF CONTRACT DUE TO NATIONAL EMERGENCY:
Whenever, because of National Emergency, so declared by the president of the United
States or other lawful authority , it becomes impossible for the Contractor to obtain all of
the necessary labor, materials, and equipment for the prosecution of the work with
reasonable continuity for a period of two months, the Contractor shall within seven days
notify the City in writing, giving a detailed statement of the efforts which have been made
and listing all necessary items of labor, materials, and equipment not obtainable. If, after
investigations , the owner finds that such conditions existing and that the inability of the
Contractor to proceed is not attributable in whole or in part to the fault or neglect of the
Contractor, than if the Owner cannot after reasonable effort assist the Contractor in
procuring and making available the necessary labor, materials , and equipment within
thirty days , the Contractor my request the owner to terminate the contract and the owner
may comply with the request, and the termination shall be conditioned and based upon a
final settlement mutually acceptable to both the Owner and the Contractor and final
payment shall be made in accordance with the terms of the agreed settlement, which shall
include. But not be limited to the payment for all work executed but not anticipated
profits on work which has not been performed .
C7-7.14 SUSPENSION OR ABANDONMENT OF THE WORK AND ANNULMENT
OF THE CONTRACT: The work operations on all or any portion or section of the
work under Contract shall be suspended immediately on written order of the Engineer or
the Contract may be declared canceled by the City Council for any good and sufficient
cause. The following, by way of example, but not of limitation, may be considered
grounds for suspension or cancellation:
a. Failure of the Contractor to commence work operations within the time
specified in the Work Order issued by the Owner.
b. Substantial evidence that progress of the work operations by the
Contractor is insufficient to complete the work within the specified time .
C7-7(6)
. ..,.,
-
, __
-
-
-
C • Failure of the Contractor to provide and maintain sufficient labor and ·
equipment to properly execute the working operations .
d. Substantial evidence that the Contractor has abandoned the work.
e . Substantial evidence that the Contractor has become insolvent or bankrupt,
or otherwise financially unable to carry on the work satisfactorily .
f. Failure on the part of the Contractor to observe any requirements of the
Contract Documents or to comply with any orders given by the Engineer
or Owner provided for in these Contract Documents.
g .
h .
1.
Failure of the Contractor promptly to make good any defect in materials or
workmanship , or any defects of any nature the correction of which has
been directed in writing by the Engineer or the Owner.
Substantial evidence of collusion for the purpose of ilfegally procuring a
contract or perpetrating fraud on the City in the construction of work under
contract.
A substantial indication that the Contractor has made an unauthorized
assignment of the contract or any funds due therefrom for the benefit of
any creditor or for any other purpose.
J. If the Contractor shall for any cause whatsoever not carry on the working
operation in an acceptable manner.
k . If the Contractor commences legal action against the Owner .
A Copy of the suspension order or action of the City Council shall be served on the
Contractor 's Sureties. When work is suspended for any cause or causes , or when the
contract is canceled, the Contractor shall discontinue the work or such part thereof as the
owner shall designate , whereupon the Sureties may, at their option, assume the contract
or that portion thereof which the Owner has ordered the Contractor to discontinue, and
may perform the same or may, with written consent of the owner, sublet the work or that
portion of the work as taken over, provided however, that the Sureties shall exercise their
option, if at all , within two weeks after the written notice to discontinue the work has
been served upon the Contractor and upon the Sureties or their authorized agents. The
Sureties, in such event shall assume the Contractor's place in all respects, and shall be
paid by the Owner for all work performed by them in accordance with the terms of the
Contract Documents . All monies remaining due the Contractor at the time of this default
shall thereupon become due and payable to the Sureties as the work progresses , subject to
all of the terms of the Contract Documents.
C7-7(7)
In case the Sureties do not , within the hereinabove specified time, exercise their right and
option to assume the contract responsibilities , or that portion thereof which the Owner
has ordered the Contractor to discontinue, then the Owner shall have the power to
complete , by contract or otherwise, as it may determine, the work herein described or
such work thereof as it may deem necessary, and the Contractor hereto agrees that the
Owner shall have the right to take possession of and use any materials, plants, tools,
equipment , supplies , and property of any kind provided by the Contractor for the purpose
of carrying on the work and to procure other tools, equipment, materials, la,bor and
property for the completion of the work , and to charge to the account of the Contractor of
said contract expense for labor, materials, tools , equipment, and all expenses incidental
thereto. The expense so ch arged shall be deducted by the owner from such monies as may
be due or may become due at any time thereafter to the Contractor under and by virtue of
the Contract or any part thereof. The Owner shall not be required to obtain the lowest bid
for the work completing the contract, but the expense to be deducted shall be the actual
cost of the owner of such work
In case such expenses shall exceed the amount which would have been payable under the
Contract if the same had been completed by the Contract, then the Contractor and his
Sureties shall pay the amount of such excess to the City on notice from the Owner of the
excess due . When any particular part of the work is being carried on by the Owner by
contract or otherwise under the provisions of this section, the Contractor shall continue
the remainder of the work in conformity with the terms of the Contract Documents and in
such a manner as to not hinder or interfere with the performance of the work by the
Owner.
C7-7 .15 FULFILLMENT OF CONTRACT:The Contract will be considered as having
been fulfilled , save as prov ided in any bond or bonds or by law, when all the work and all
sections or parts of the project covered by the Contract Documents have been finished
and completed, the final inspection made by the Engineer, and the final acceptance and
final payment made by the Owner.
C7-7.16 TERMINATION FOR CONVENIENCE OF THE OWNER:
The performance of the work under this contract may be terminated by the Owner in
whole, or from time to time in part, in accordance with this section, whenever the Owner
shall determine that such termination is in the best interest of the Owner.
A. NOTICE OF TERMINATION : Any Termination shall be effected by
mailing a notice of the termination to the Contractor specifying the extent
to which performance of work under the contract is terminated, and the
date upon which such termination becomes effective . Receipt of the notice
shall be deemed conclusively presumed and established when the letter is
placed in the United States Postal Service Mail by the Owner. Further, it
shall be deemed conclusively presumed and established that such
termination is made with just cause as therein stated; and no proof in any
C7-7(8)
B.
-
-
-
....
claim, demand or suit shall be required of the Owner regarding such
discretionary action
CONTRACTOR ACTION: After receipt of a notice of termination,
and except as otherwise directed by the Engineer, the Contractor shall:
1. Stop work under the contract on the date and to the extent
specified in the notice of termination;
2 . place no further orders or subcontracts for materials,
services or facilities except as may be necessary for
completion of such portion of the work under the contract
as is not terminated;
3. terminate all orders and subcontracts to the extent that they
relate to the performance of the work terminated by notice
of termination;
4. transfer title to the Owner and deliver in the manner, at the
times, and to the extent, if any, directed by the Engineer:
a.
b.
the fabricated or unfabricated parts, work in
progress, completed work, supplies and other
material produced as a part of, or acquired in
connection with the performance of, the work
terminated by the notice of the termination; and
The completed, or partially completed plans,
drawings, information and other property which, if
the contract had been completed, would have been
required to be furnished to the Owner.
5. complete performance of such work as shall not have been
terminated by the notice of termination; and
6. Take such action as may be necessary, or as the Engineer
may direct, for the protection and preservation of the
property related to its contract which is in the possession of
the Contractor and in which the owner has or may acquire
the rest.
At a time not later than 30 days after the termination date specified in the
notice of termination, the Contractor may submit to the Engineer a list,
certified as to quantity and quality, of any or all items of termination
inventory not previously disposed of, exclusive of items the disposition of
C7-7(9)
which has been directed or authorized by Engineer, Not later than 15 days
thereafter , the owner shall accept title to such items provided, that the list
submitted shall be subject to verification by the Engineer upon removal of
the items or, if the items are stored, within 45 days from the date of
submission of the list , and any necessary adjustments to correct the list as
submitted, shall be made prior to final settlement.
C. TERMINATION CLAIM: Within 60 days after the notice of
termination , the Contractor shall submit his termination claim to the
Engineer in the form and with the certification prescribed by the Engineer.
Unless one or more extensions in writing are granted by the Owner upon
request of the Contractor, made in writing within such 60-day period or
authorized extension thereof, any and all such claims shall be conclusively
deemed waived .
D. AMOUNTS: Subject to the prov1s10ns of Item C7-7.l(C), the
Contractor and the Owner may agree upon the whole or any part of the
amount or amounts to be paid to the Contractor by reason of the total or
partial termination of the work pursuant hereto; provided, that such agreed
amount or amounts shall never exceed the total contract price reduced by
the amount of payments otherwise made and as further reduced by the
contract price work not terminated. The contract shall be amended
accordingly , and the Contractor shall be paid the agreed amount. No
amount shall be due for lost or anticipated profits> Nothing in C7-7. l 6(E)
hereafter, prescribing the amount to be paid to the Contractor by reason of
the termination of work pursuant to this section, shall be deemed to limit ,
restrict or otherwise determine or affect the amount or amounts which may
be agreed upon to be paid to the Contractor pursuant to this paragraph.
E. FAIL URE TO AGREE: In the event of the failure of the Contractor
and the Owner to agree as provided in C7-7.16(D) upon the whole amount
to be paid to the Contractor by reason of the termination of the work
pursuant to this section , the Owner shall determine, on the basis of
information available to it, the amount, if any, due to the Contractor by
reason of the termination and shall pay to the Contractor the amounts
determined. No amount shall be due for lost or anticipated profits.
F. DEDUCTIONS: In arriving at the amount due the Contractor under
this section there shall be deducted;
1. all unliquidated advance or other payments on account
theretofore made to the Contractor, applicable to the
terminated portion of this contract ;
C7-7(10)
_.,
-
-
·-
-
-
-
-
G.
H.
2. any claim which the Owner may have against the
Contractor in connection with this contract ; and
3. the agreed price for, or the proceeds of the sale of, any
materials, supplies or other things kept by the Contractor or
sold , pursuant to the provisions of this clause , and not
otherwise recovered by or credited to the Owner.
ADJUSTMENT: If the termination hereunder be partial, prior to the
settlement of the terminated portion of this contract, the Contractor may
file with the Engineer a request in writing for an equitable adjustment of
the price or prices specified in the contract relating to the continued
portion of the contract (the portion not terminated by notice of
termination), such equitable adjustment as may be agreed upon shall be
made in such price or prices; noting contained herein, however, shall limit
the right of the owner and the Contractor to agree upon the amount or
amounts to be paid tot he Contractor for the completion of the continued
portion of the contract when said contract does not contain an established
contract price for such continued portion.
NO LIMITATION OF RIGHTS: Noting contained in this section shall
limit or alter the rights which the Owner may have for termination of this
contract under C7-7.14 hereof entitled "SUSPENSION OR
ABANDONMENT OF THE WORK AND ANNULMENT OF
CONTRACT" or any other right which the Owner may have for default or
breach of contract by Contractor.
C7-7.17 SAFETY METHODS AND PRACTICES: The Contractor shall be
responsible for initiating, maintaining and supervising all safety precautions and
programs in connection with the work at all times and shall assume all responsibilities for
their enforcement.
The Contractor shall comply with federal, state, and local laws, ordinances, and
regulations so as to protect person and property from injury, including death, or damage
in connection with the work.
C7-7(11)
-,.
-
---
-
....
PART C -GENERAL CONDITIONS
C8-8 MEASUREMENT AND PAYMENT
SECTION C8-8 MEASUREMENT AND PAYMENT
C8-8.1 MEASUREMENT OF QUANTITIES: The determination of quantities of
work performed by the Contractor and authorized by the Contract Documents acceptably
completed under the terms of the Contract Documents shall be made by the Engineer,
based on measurements made by the Engineer. These measurements will be made
according to the United States Standard Measurements used in common practice, and will
be the actual length, area, solid contents, numbers , and weights of the materials and item
installed.
C8-8.2 UNIT PRICES: When in the Proposal a "Unit Price" is set forth, the said
"Unit Price" shall include the furnishing by the . Contractor of all labor, tools, materials,
machinery, equipment, appliances and appurtenances necessary for the construction of
and the completion in a manner acceptable to the Engineer of all work to be done under
these Contract Documents.
The "Unit Price" shall include all permanent and temporary protection of overhead,
surface, and underground structures, cleanup, finishing costs, overhead expense, bond,
insurance, patent fees, royalties, risk due to the elements and other clauses, delays,
profits, injuries, damages claims, taxes, and all other items not specifically mentioned that
may be required to fully construct each item of the work complete in place and in a
satisfactory condition for operation.
C8-8 .3 LUMP SUM: When in the Proposal a "Lump Sum" is set forth, the said
"Lump Sum" shall represent the total cost for the Contractor to furnish all labor, tools,
materials, machinery, equipment, appurtenances, and all subsidiary work necessary for
the construction and completion of all the work to provide a complete and functional item
as detailed in the Special Contract Documents and/or Plans.
C8-8.4 SCOPE OF PAYMENT: The Contractor shall receive and accept the
compensation as herein provided, in full payment for furnishing all labor, tools, materials,
and incidentals for performing all work contemplated and embraced under these Contract
Documents, for all loss and damage arising out of the nature of the work or from the
action of the elements, for any unforeseen defects or obstructions which may arise or be
encountered during the prosecution which may arise or be encountered during the
prosecution of the work at any time before its final acceptance by the Owner, (except as
provided in paragraph CS-5.14) for all risks of whatever description connected with the
prosecution of the work, for all expenses incurred by or in consequence of the suspension
or discontinuance of such prosecution of the working operations as herein specified, or
any and all infringements of patents, trademarks, copyrights, or other legal reservations,
C8-8(1)
and for completing the work in an acceptable manner according to the terms of the
Contract Documents .
The payment of any current or partial estimate prior to the final acceptance of the work by
the Owner shall in no way constitute an acknowledgment of the acceptance of the work,
materials , or equipment, nor in any way prejudice or affect the obligations of the
Contractor to repair , correct, renew, or replace at his own and proper expense any defects
or imperfections in the con struction or in the strength or quality of the material used or
equipment or machinery furnished in or about the construction of the work under contract
and its appurtenances, or any damage due or attributed to such defects , which defects ,
imperfections , or damage shall have been discovered on or before the final inspection and
acceptance of the work or d uring the one year guaranty period after the final acceptance.
The Owner shall be the sole judge of such defects , imperfections, or damage, and the
Contractor shall be liable to the Owner for failure to correct the same as provided herein .
C8-8 .5 PARTIAL ESTIMATES AND RETAINAGE: Between the 1st and the 5th
day of each month , the Contractor shall submit to the Engineer a statement showing an
estimate of the value of the work done during the previous month, or estimate period
under the Contract Documents. Not later than the 1 oth day of the month , the Engineer
shall verify such estimate , and if it is found to be acceptable and the value of the work
performed since the last partial payment was made exceeds one hundred dollars ($100.00)
inn amount, 90% of such estimated sum will be paid to the Contractor if the total contract
amount is less than $400,000.00, or 95% of such estimated sum will be paid to the
Contractor if the total contract amount is $400,000.00 or greater, within twenty-five (25)
days after the regular estimate period. The City will have the option of preparing
estimates on forms furnished by the City. The partial estimates may include acceptable
nonperishable materials del ivered to the work which are to be incorporated into the work
as a permanent part thereof, but which at the time of the estimate have not been installed
(such payment will be allowed on a basis of 85% of the net invoice value thereof). The
Contractor shall furnish the Engineer such information as he may request to aid him as a
guide in the verification or the preparation of partial estimates.
It is understood that partial estimates from month to month will be approximate only, all
partial monthly estimates and payment will be subject to correction in the estimate
rendered following the discovery of an error in any previous estimate, and such estimate
shall not, in any respect, be taken as an admission of the Owner of the amount of work
done or of its quantity of sufficiency, or as an acceptance of the work done or the release
of the Contractor of any of his responsibilities under the Contract Documents.
The City reserves the right to withhold the payment of any monthly estimate if the
Contractor fails to perform the work strictly in accordance with the specifications or
provisions of this Contract.
C8 -8(2)
-
-
-
C8-8.6 WITHHOLDING PAYMENT: Payment on any estimate or estimates may
be held in abeyance if the performance of the construction operations is not in accordance
with the requirements of the Contract Documents.
C8-8. 7 FINAL ACCEPTANCE: Whenever the improvements provided for by
the Contract Documents shall have been completed and all requirements of the Contract
Documents shall have been fulfilled on the part of the Contractor, the Contractor shall
notify the Engineer in writing that the improvements are ready for final inspection. The
Engineer shall notify the appropriate officials of the Owner, will within a reasonable time
make such final inspection, and if the work is satisfactory, in an acceptable condition, and
has been completed in accordance with the terms of the Contract Documents and all
approved modifications thereof, the Engineer will initiate the processing of the final
estimate and recommend final acceptance of the project and final payment thereof as
outlines in paragraph C8-8.8 below.
C8-8.8 FINAL PAYMENT: Whenever all the improvements provided for by the
Contract Documents and all approved modifications thereof shall have been completed
and all requirements of the Contract Documents have been fulfilled on the part of the
Contractor, a final estimate showing the value of the work will be prepared by the
Engineer as soon as the necessary measurements, computations , and checks can be made.
All prior estimates upon which payment has been made are subject to necessary
corrections or re visions in the final payment.
The amount of the final estimate, less previous payments and any sums that have been
deducted or retained under the provisions of the Contract Documents, will be paid to the
Contractor within 60 days after the final acceptance by the Owner on a proper resolution
of the City Council, provided the Contractor has furnished to the owner satisfactory
evidence of compliance as follows: Prior to submission of the final estimate for payment,
the Contractor shall execute an affidavit as furnished by the City, certifying that;
A. all persons , firms, associations , corporations, or other organizations
furnishing labor and/or materials have been paid in full ,
B. that the wage scale established by the City Council in the City of Fort
Worth has been paid, and
C . that there are no claims pending for personal mJury and/or property
damages.
The acceptance by the Contractor of the last or final payment as aforesaid shall operate as
and shall release the owner from all claims or liabilities under the Contract for anything
done or furnished or relating to the work under the Contract Documents or any act or
neglect of said City relating to or connected with the Contract.
C8-8(3)
The making of the final payment by the Owner shall not relieve the Contractor of any
guarantees or other requirements of the Contract Documents which specifically continue
thereafter.
C8-8.9 ADEQUACY OF DESIGN : It is understood that the Owner believes it
has employed competent engineers and designers to prepare the Contract Documents and
all modifications of the approved Contract Documents . It is, therefore, agreed that the
Owner shall be responsible for the adequacy of its own design features, sufficiency of the
Contract Documents , the safety of the structure, and the practicability of the operations of
the completed project, provided the Contractor has complied with the requirements of the
said Contract Documents , all approved modifications thereof, and additions and
alterations thereof approved in writing by the Owner. The burden of proof of such
compliance shall be upon the Contractor to show that he has complied with the Contract
Documents , approved modifications thereof, and all alterations thereof.
C8-8 .10 GENERAL GUARANTY: Neither the final certificate of payment nor
any provision in the Contract Documents nor partial or entire occupancy or use of the
premises by the Owner shall constitute an acceptance of the work not done in accordance
with the Contract Documents or relieve the Contractor of liability in respect to any
express warranties or responsibility for faulty materials or workmanship. The Contractor
shall remedy any defects or damages in the work and pay for any damage to the other
work resulting therefrom which shall appear within a period of one year from the date of
final acceptance of the work unless a longer period is specified and shall furnish a good
and sufficient maintenance bond in the amount of 100 percent of the amount of the
contract which shall assure the performance of the general guaranty as above outlined.
The Owner will give notice of observed defects with reasonable promptness.
C8-8 . l 1 SUBSIDIARY WORK: Any and all work specifically governed by
documentary requirements for the project, such as conditions imposed by the Plans, the
General Contract Documents or these Special Contract Documents, in which no specific
item for bid has been provided for in the Proposal, shall be considered as a subsidiary
item of work, the cost of which shall be included in the price bid in the Proposal, for each
bid item. Surface restoration, rock excavation and cleanup are general items of work
which fall in the category of subsidiary work.
C8-8.12 MISCELLANEOUS PLACEMENT OF MATERIAL: Material may be
allocated under various bid items in the Proposal to establish unit prices for
miscellaneous placement of material. These materials shall be used only when directed by
the Engineer, depending on field conditions . Payment for miscellaneous placement of
material will be made for only that amount of material used, measured to the nearest one-
tenth unit. Payment for miscellaneous placement of material shall be in accordance with
the General Contract Documents regardless of the actual amount used for the Project.
C8-8.13 RECORD DOCUMENTS: The Contractor shall keep on record a copy
of all specifications, plans, addenda, modifications, shop drawings and samples at the
C8-8(4)
. ....,.;,, ,,,
-·
,.,
'
,,
.!\,•, ..... ,.: "'.
' i '
"'"'l>, ,.
,'
site , in good order and annotated to show all changes made during the construction
process. These shall be delivered to the Engineer upon completion of the work.
,, ..
...
( .
•.
C8-8(5) . / ,,
,, .
"-
•f
·'
. l
.r
',
,, -
,,,
" ,;
.t
'~
r
. •, ,.
.. , ..
' .
1
'
,' I
',
.1
J '
' .,
... , ..
. '
'· ~
"·
;
,'
.....
!.'"-"
,
'".'!'
t. ,.·
,,<"'"~,~e
'•,
·~
·,;.·
~··
''
)
~
. ,
"· . ~fl ~
I, '.
I
I•
•'
j
,t
{, .,,
~-
I
' ..
,· i
.. ,
' ~· ,
' I'
..
. -· !, . ,.,..
;
t'
'
'\
'.
...
..
' '
..
.. '·.,. ~ ....
·,'!\/;
~ ~ !' ~-~ :4 .. ~~_,''· .. ... _
..
',.
r
.
''
. ' ~ . ,. "'i ..
~c. 1C
• . /r ,.1
.,. .
.. ~
~ .
t
PART Cl
~-
\
., . '
,• '
If,, ..
,#,.
" ,,...,. ... ......
,;
, . ii,
~ • ,..: i':' .. \ .-. ~ ~ '·
; ..
J;
. .
• l ' ·~
< i
, ..... f'
.. . '
•.
,'t
'•
,;I• .
'
,.-
I ,,. \:
, ..
•
•p
, ... ..,
T ..
.;•
' t ..
-
-
·-
. _,
-
.....
SECTION Cl:
SUPPLEMENTARY CONDITIONS TO PART C-GENERAL CONDITIONS
A General
B,
C.
D .
These Supplementary Conditions amend or supplement the General Conditions of the
Contract and other provisions of the Contract Documents as indicated below. Provisions
which are not so amended or supplemented remain in full force and affect.
C8-8.5 PARTIAL ESTIMATES AND RETAINAGE: Page C8-8 (2), should be deleted in
its entirety and replaced with the following:
Partial pay estimates shall be submitted by the Contractor or prepared by the City on the
5th day and 20th day of each month that the work is in progress . The estimate shall be
proceeded by the City on the 10th day and 25th day respectively. Estimates will be paid
within 25 days following the end of the estimate period, less the appropriate retainage as
set out below. Partial pay estimates may include acceptable nonperishable materials
delivered to the work place which are to be incorporated into the work as a permanent
part thereof, but which at the time of the pay estimate have not been so installed. If such
materials are included within a pay estimate, payment shall be based upon 85% of the net
voice value thereof. The Contractor will furnish the Engineer such information as may be
reasonably requested to aid in the verification or the preparation of the pay estimate.
For contracts of less than $400,000 at the time of execution, retainage shall be ten per
cent (10%). For contracts of $400,000 or more at the time of execution, retainage shall be
five percent (5%).
Contractor shall pay subcontractors in accord with the subcontract agreement within five
(5) business days after receipt by Contractor of the payment by City . Contractor's failure
to make the required payments to subcontractors will authorize the City to withhold
future payments from the Contractor until compliance with this paragraph is
accomplished.
It is understood that the partial pay estimates will be approximate only, and all partial pay
estimates and payment of same will be subject to correction in the estimate rendered
following the discovery of the mistake in any previous estimate. Partial payment by
Owner for the amount of work done or of its quality or sufficiency or acceptance of the
work done; shall not release the Contractor of any of its responsibilities under the
Contract Documents .
The City reserves the right to withhold the payment of any partial estimate if the
Contractor fails to perform the work in strict accordance with the specifications or other
provisions of this contract.
Part C -General Conditions: Paragraph C3-3.l 1 of the General Conditions is deleted and
replaced with D-3 of Part D -Special Conditions.
C3-3.11 INSURANCE: Page C3-3 (5): Delete subparagraph "g. LOCAL AGENT FOR
INSURANCE AND BONDING"
Revised
10/24/02
Pg. 1
E. C6-6.12 CONTRACTOR'S RESPONSIBLITY FOR DAMAGE CLAIMS: Page C6-6
(6), is deleted in its entirety and replaced with the following:
Contractor covenants and agrees to indemnify City's engineer and architect, and their
personnel at the project site for Contractor 's sole. negligence. In addition, Contractor
covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
Owner, its officers , servants and employees , from and against any and all claims or suits
for property loss , property damage , personal injury, including death, arising out of, or
alleged to arise out of, the work and services to be performed hereunder by Contractor, its
officers , agents , employees, subcontractors , licensees or invitees, whether or not any
such iniury, damage or death is caused, in whole or in part, by the negligence or
alleged negligence of Owner, its officers, servants, or employees. Contractor likewise
covenants and agrees to indemnify and hold harmless the Owner from and against any
and all injuries to Owner's officers, servants and employees and any damage, loss or
destruction to property of the Owner arising from the performance of any of the terms and
conditions of this Contract, whether or not any such iniury or damage is caused in
whole or in part by the negligence or alleged negligence of Owner, its officers, servants
or employees.
In the event Owner receives a written claim for damages against the Contractor or its
subcontractors prior to final payment, final payment shall not be made until Contractor
either (a) submits to Owner satisfactory evidence that the claim has been settled and/or a
release from the claimant involved, or (b) provides Owner with a letter from Contractor's
liability insurance carrier that the claim has been referred to the insurance carrier.
The Director may , if he deems it appropriate, refuse to accept bids on other City of Fort
Worth public work from a Contractor against whom a claim for damages is outstanding
as a result of work performed under a City Contract.
F. INCREASED OR DECREASED QUANTITIES: Part C -General Conditions, Section
C4-4 SCOPE OF WORK, Page C 4-4 (1 ), revise paragraph C4-4.3 INCREASED OR
DECREASED QUANTITIES to read as follows:
The Owner reserves the right to alter the quantities of the work to be performed or to
extend or shorten the improvements at any time when and as found to be necessary, and
the Contractor shall perform the work as altered, increased or decreased at the unit prices
as established in the contract documents. No allowance will be made for any changes in
lost or anticipated profits nor shall such changes be considered as waiving or invalidating
any conditions or provisions of the Contract Documents.
Variations in quantities of sanitary sewer pipes in depth categories shall be interpreted
herein as applying to the overall quantities of sanitary sewer pipe in each pipe size but not
to the various depth categories.
Revised
10 /24/02
Pg.2
-
-
--
G . C3-3.1 l INSURANCE: Page C3-3 (6): Add subparagraph "h. ADDITIONAL
INSURANCE REQUIREMENTS "
a. The City, its officers, employees and servants shall be endorsed as an additional
insured on Contractor's insurance policies excepting employer's liability insurance
coverage under Contractor's workers' compensation insurance policy .
b . Certificates of insurance shall be delivered to the City of Fort Worth, contract
administrator in the respective department as specified in the bid documents, 1000
Throckmorton Street, Fort Worth, TX 76102, prior to commencement of work on the
contracted project.
c. Any failure on part of the City to request required insurance documentation shall not
constitute a waiver of the insurance requirements specified herein.
d. Each insurance policy shall be endorsed to provide the City a minimum thirty days
notice of cancellation, non-renewal, and/or material change in policy terms or coverage.
A ten days notice shall be acceptable in the event of non-payment of premium.
e . Insurers must be authorized to do business in the State of Texas and have a current
A.M. Best rating of A: VII or equivalent measure of financial strength and solvency.
f. Deductible limits , or self-funded retention limits , on each policy must not exceed
$10,000.00 per occurrence unless otherwise approved by the City.
g. Other than worker 's compensation insurance, in lieu of traditional insurance, City may
consider alternative coverage or risk treatment measures through insurance pools or risk
retention groups. The City must approve in writing any alternative coverage.
h. Workers' compensation insurance policy(s) covering employees employed on the
project shall be endorsed with a waiver of subrogation providing rights of recovery in
favor of the City.
i. City shall not be responsible for the direct payment of insurance premium costs for
contractor's insurance.
j. Contractor's insurance policies shall each be endorsed to provide that such insurance is
primary protection and any self-funded or commercial coverage maintained by_ City shall
not be called upon to contribute to loss recovery.
k. In the course of the project, Contractor shall report, in a timely manner, to City's
officially designated contract administrator any known loss occurrence which could give
rise to a liability claim or lawsuit or which could result in a property loss. ·
Revised
10/24/02
Pg. 3
H.
I. Contractor's liability shall not be limited to the specified amounts of insurance
required herein.
m. Upon the request of City, Contractor shall provide complete copies of all insurance
policies required by these contract documents.
C8-8.4 SCOPE OF PAYMENT: Delete C8-8.4, Scope of Payment at page C8-8(1) is
deleted in its entirety and replaced with the following:
The Contractor shall receive and accept the compensation as herein provided, in full
payment for furnishing all labor, tools , materials, and incidentals for performing all work
contemplated and embraced under these Contract Documents, for all loss and damage
arising out of the nature of the work or from the action of the elements, for any
unforeseen defects or obstructions which may arise or be encountered during the
prosecution which may arise or be encountered during the prosecution of the work at any
time before its final acceptance by the Owner, (except as provided in paragraph CS-5 .14)
for all risks of whatever description connected with the prosecution of the work, for all
expenses incurred by or in consequence of the suspension or discontinuance of such
prosecution of the working operations as herein specified, or any and all infringements of
patents , trademarks, copyrights, or other legal reservations, and for completing the work
in an acceptable manner according to the terms of the Contract Documents.
The payment of any current or partial estimate prior to the final acceptance of the work by
the Owner shall in no way constitute an acknowledgment of the acceptance of the work,
materials, or equipment, nor in any way prejudice or affect the obligations of the
Contractor to repair, correct, renew, or replace at his own and proper expense any defects
or imperfections in the construction or in the strength or quality of the material used or
equipment or machinery furnished in or about the construction of the work under contract
and its appurtenances, or any damage due or attributed to such defects, which defects,
imperfections, or damage shall have been discovered on or before the final inspection and
acceptance of the work or during the two (2) year guaranty period after the final
acceptance. The Owner shall be the sole judge of such defects, imperfections, or damage,
and the Contractor shall be liable to the Owner for failure to correct the same as provided
herein .
I. C8-8.10 GENERAL GUARANTY: Delete C8-8.10, General Guaranty at page C8-8(4) is
deleted in its entirety and replaced with the following:
Neither the final certificate of payment nor any provision in the Contract Documents, nor
partial or entire occupancy or use of the premises by the Owner shall constitute an
acceptance of work not done in accordance with the Contract Documents or relieve the
Contractor of liability in respect to any express warranties or responsibility for faulty
materials or workmanship. The Contractor shall remedy any defects or damages in the
work and pay for any damage to other work or property resulting therefrom which shall
appear within a period of two (2) years from the date of final acceptance of the work
Revised
10/24/02
Pg.4
..,,.
..:
....
J.
unless a longer period is specified and shall furnish a good and sufficient maintenance
bond in the amount of 100 percent of the amount of the contract which shall assure the
performance of the general guaranty as above outlined. The Owner will give notice of
observed defects with reasonable promptness.
Any reference to any shorter period of time of warranty contained elsewhere within the
specifications shall be resolved in favor of this specifications , it being the City 's intent
that the Contractor guarantee its work for a period of two (2) years following the date of
acceptance of the project.
In the Special Instructions to Bidders, TPW contracts place the following in lieu of the
existing paragraph 2.
Part C -General Conditions, Section C2-2 INTERPRETATION AND PREPARATION
OF PROPOSAL, Page C2-2 (3) exchange paragraphs C2-2.7, C2-2.8 and C2-2.9 with the
following:
C2-2 .7 DELIVERY OF PROPOSAL: No proposal will be considered unless it is
delivered , accompanied by its proper Bid Security, to the Purchasing Manager or his
representative at the official location and stated time set forth in the "Notice to Bidders ."
It is the Bidder's sole responsibility to deliver the proposal at the proper time to the proper
place. The mere fact that a proposal was dispatched will not be considered. The Bidders
must have the proposal actually delivered. Each proposal shall be in a sealed envelope
plainly marked with the word "PROPOSAL," and the name or description of the project
as designated in the "Notice to Bidders ." The envelope shall be addressed to the
Purchasing Manager, City of Fort Worth Purchasing Division, P .O. Box 17027, Fort
Worth, Texas 76102 .
C2-2.8 WITHDRAWING PROPOSALS: Proposals actually filed with the Purchasing
Manager cannot be withdrawn prior to the time set for opening proposals . A request for
non-consideration of a proposal must be made in writing, addressed to the City Manager,
and filed with him prior to the time set for the opening of proposals. After all proposals
not requested for non-consideration are opened and publicly read aloud , the proposals for
which non-consideration requests have been properly filed may, at the option of the
Owner, be returned unopened.
C2-2.9 TELEGRAPHIC MODIFICATION OF PROPOSALS : Any bidder may modify
his proposal by telegraphic communication at any time prior to the time set for opening
proposals , provided such telegraphic communication is received by the Purchasing
Manager prior to the said proposal opening time, and provided further, that the City
Manager is satisfied that a written and duly authenticated confirmation of such
telegraphic communication over the signature of the bidder was mailed prior to the
proposal opening time . If such confirmation is not received within forty-eight ( 48) hours
after the proposal opening time, no further consideration will be given to the proposal
Revised
10/24/02
Pg. 5
K. C3-3.7 BONDS (CITY LET PROJECTS): Reference Part C, General Conditions , dated
November 1, 1987 ; (City let projects) make the following revisions :
1. Page C3-3(3); the paragraph after paragraph C3-3.7d Other Bonds should be revised to
read:
In order for a surety to be acceptable to the City, the surety must (1) hold a certificate of
authority from the United States secretary of the treasury to qualify as a surety on
obligations permitted or required under federal law; or (2) have obtained reinsurance for
any liability in excess of $100 ,000 from a reinsurer that is authorized and admitted as a
reinsurer in the state of Texas and is the holder of a certificate of authority from the
Untied States secretary of the treasury to qualify as a surety on obligations permitted or
required under federal law. Satisfactory proof of any such reinsurance shall be provided
to the City upon request. The City, in its sole discretion, will determine the adequacy of
the proof required here in.
2. Pg . C3-3(4) Paragraph C3-3 .l 1 INSURANCE delete subparagraph "a .
COMPENSATION INSURANCE".
3. Pg . C3-3(5), Paragraph C3-3 .11 INSURANCE delete subparagraph "g. LOCAL
AGENT FOR INSURANCE AND BONDING".
L. RIGHT TO AUDIT: Part C -General Conditions, Section C8-8
MEASUREMENT AND PAYMENT, Page C8-8 (5), add the following:
C8-8.14 RIGHT TO AUDIT :
(a) Contractor agrees that the City shali, until the expiration of three (3) years after final
payment under this contract, have access to and the right to examine and photocopy any
directly pertinent books , documents, papers and records of the Contractor involving
transactions relating to this contract. Contractor agrees that the City shall have access
during normal working hours to all necessary Contractor facilities and shall be provided
adequate and appropriate work space in order to conduct audits in compliance with the
provisions of this section. The City shall give contractor reasonable advance notice of
intended audits.
(b) Contractor further a grees to include in all its subcontracts hereunder a provision to the
effect that the subcontractor agrees that the City shall, until the expiration of three (3)
years after final payment under the subcontract, have access to and the right to examine
and photocopy any directly pertinent books, documents, papers and records of such
subcontractor, involving transactions to the subcontract, and further , that City shall
have access during normal working hours to all subcontractor facilities , and shall be
provided adequate and appropriate work space, in order to conduct audits in compliance
with the provisions of this article. City shall give subcontractor reasonable advance
notice of intended audits.
Revised
10/24/02
Pg.6
. .,,
-
·-
M .
N.
0.
( c) Contractor and subcontractor agree to photocopy such documents as may be requested
by the City. The City agrees to reimburse the Contractor for the cost of copies as follows :
1. 50 copies and under -10 cents per page
2. More than 50 copies -85 cents for the first page plus
fifteen cents for each page thereafter
SITE PREPARATION:
The Contractor shall clear rights-of-way or easements of obstruction which must be
removed to make possible proper prosecution of the work as a part of this project
construction operations. The contractor's attention is directed to paragraph C6-6. l O work
within easements, page C6-6(5), part C -General Conditions of the Water Department
General Contract Document and General Specifications .
Clearing and restoration shall be considered as incidental to construction and all costs
incurred will be considered to be included in the Linear Foot price of the pipe.
Reference Part C -General Conditions, Section C6-6.8 BARRICADES, WARNINGS
AND WATCHMEN:
1. Wherever the word Watchmen appears in this paragraph, it shall be changed to the
word flagmen.
2 . In the first paragraph, lines five (5) and six (6), change the phrase take all such other
precautionary measures to take all reasonable necessary measures.
MINORITY/WOMEN BUSINESS ENTERPRISE COMPLIANCE:
. Reference Part C (General Conditions), Section C3-3.2 Entitled "MINORITY BUSINESS
ENTERPRISE/WOMEN-OWNED BUSINESS ENTERPRISE COMPLIANCE" shall be
deleted in its entirety and replaced with the following:
Upon request, Contractor agrees to provide to Owner complete and accurate information
regarding actual work performed by a Minority Business Enterprise (MBE) and/or a
Woman Business Enterprise (WBE) on the contract and payment therefore . Contractor
further agrees to permit an audit and/or examination of any books, records or files in its
possession that will substantiate the actual work performed by an MBE and/or WBE. The
misrepresentation of facts ( other than a negligent misrepresentation) and/or the
commission of fraud by the Contractor will be grounds for termination of the contract
and/or initiating action under appropriate federal, state or local laws or ordinances
relating to false statements ; further, any such misrepresentation ( other than negligent
misrepresentation) and/or commission of fraud will result in the Contractor being
Revised
10/24/02
Pg. 7
determined to be irresponsible and barred from participating-in City work for a period of
time of not less than thee (3) years.
P. WAGE RA TES : Section C3-3.13 of the General Conditions is deleted and replaced with
the following:
(a) The contractor shall comply with all requirements of Chapter 2258, Texas
Government Code, including the payment of not less than the rates determined by the
City Council of the City of Fort Worth to be the prevailing wage rates in accordance with
Chapter 2258, Texas Government Code . Such prevailing wage rates are included in these
contract documents.
(b) The contractor shall, for a period of three (3) years following the date of acceptance of
the work, maintain records that show (i) the name and occupation of each worker
employed by the contractor in the construction of the work provided for in this contract;
and (ii) the actual per diem wages paid to each worker. These records shall be open at all
reasonable hours for inspection by the City. The provisions of Section C-1, L. Right to
Audit (Rev. 9/30/02) pertain to this inspection.
( c) The contractor shall include in its subcontracts and/or shall otherwise require all of its
subcontractors to comply with paragraphs (a) and (b) above .
( d) With each partial payment estimate or payroll period, whichever is less, an affidavit
stating that the contractor has complied with the requirements of Chapter 2258, Texas
Government Code.
The contractor shall post the prevailing wage rates in a conspicuous place at the site of
the project at all times.
Revised
10/24/02
Pg. 8
PARTD
PART D -SPECIAL CONDITIONS
GENERAL ....................................................................................................................... 3
COORDINATION MEETING ........................................................................................... 4
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW ................. 5
COORDINATION WITH FORT WORTH WATER DEPARTMENT .................................. 7
CROSSING OF EXISTING UTILITIES ............................................................................ 7
EXISTING UTILITIES AND IMPROVEMENTS ............................................................... 7
CONSTRUCTION TRAFFIC OVER PIPELINES ............................................................. 8
TRAFFIC CONTROL ....................................................................................................... 9
DETOURS ....................................................................................................................... 9
EXAMINATION OF SITE ................................................................................................. 9
ZONING COMPLIANCE ................................................................................................ 10
WATER FOR CONSTRUCTION .................................................................................... 10
WASTE MATERIAL ....................................................................................................... 10
PROJECT CLEANUP AND FINAL ACCEPTANCE ....................................................... 10
CONSTRUCTION SCHEDULE AND SEQUENCING OF WORK .................................. 10
SAFETY RESTRICTIONS-WORK NEAR HIGH VOLTAGE LINES ............................. 11
BID QUANTITIES ........................................................................................................... 11
CUTTING OF CONCRETE ........................................................ : ............................ : ...... 11
PROJECT DESIGNATION SIGN ................................................................................... 11
CONCRETE SIDEWALK AND DRIVEWAY REPLACEMENT ....................................... 12
MISCELLANEOUS PLACEMENT OF MATERIAL. ........................................................ 12
CRUSHED LIMESTONE BACKFILL. ............................................................................. 12
2:27 CONCRETE ........................................................................................................... 12
TRENCH EXCAVATION, BACKFILL, AND COMPACTION .......................................... 13
TRENCH PAVEMENT (PERMANENT) REPAIR (E2-19) FOR UTILITY CUTS ............ 14
SITE SPECIFIC TRENCH SAFETY SYSTEM (COVERS ALL PROJECTS) ................. 15
SANITARY SEWER MANHOLES .......................................................................... : ....... 16
SANITARY SEWER SERVICES .................................................................................... 18
REMOVAL, SALVAGE, AND ABANDONMENT OF EXISTING FACILITIES ................ 20
DETECTABLE WARNING TAPES ................................................................................ 22
PIPE CLEANING ............................................................................................................ 22
DISPOSAL OF SPOIL/FILL MATERIAL ........................................................................ 22
MECHANICS AND MATERIALMEN'S LIEN .................................................................. 23
SUBSTITUTIONS .......................................................................................................... 23
PRE-CONSTRUCTION TELEVISION INSPECTION OF SANITARY SEWER ............. 23
VACUUM TESTING OF SANITARY SEWER MANHOLES ........................................... 26
BYPASS PUMPING ....................................................................................................... 27
POST-CONSTRUCTION TELEVISION INSPECTION OF SANITARY SEWER ........... 28
SAMPLES AND QUALITY CONTROL TESTING ...................................... , ................... 29
TEMPORARY EROSION, SEDIMENT, AND WATER POLLUTION CONTROL (FOR
DISTURBED AREAS LESS THAN 1 ACRE) ................................................................. 30
INGRESS AND EGRESS/OBSTRUCTION OF ACCESS TO DRIVES ......................... 31
PROTECTION OF TREES, PLANTS AND SOIL ........................................................... 31
SITE RESTORATION .................................................................................................... 32
CITY OF FORT WORTH STANDARD PRODUCT LIST ................................................ 32
TOPSOIL, SODDING, SEEDING & HYDROMULCHING ............................... : .............. 32
CONFINED SPACE ENTRY PROGRAM ...................................................................... 37
SUBSTANTIAL COMPLETION INSPECTION/FINAL INSPECTION ............................. 37
EXCAVATION NEAR TREES (WHERE IDENTIFIED ON THE PLANS) ....................... 38
CONCRETE ENCASEMENT OF SEWER PIPE ............................................................ 38
CLAY DAM ..................................................................................................................... 38
EXP LORA TORY EXCAVATION (D-HOLE) ................................................................... 39
INSTALLATION OF WATER FACILITIES ..................................................................... 39
11/29/04 SC-1
0-60
0-61
0-62
0-63
0-64
0-65
0-66
0-67
0-68
0-69
0-70
0-71
0-72
0-73
11/29/04
PART D -SPECIAL CONDITIONS
Polyvinyl Chloride (PVC) Water Pipe ........................................................................ 39
Blocking ..................................................................................................................... 39
Type of Casing Pipe .................................................................................................. 39
Tie-Ins ....................................................................................................................... 40
Connection of Existing Mains .................................................................................... 40
Valve Cut-lns ............................................................................................................. 40
Water Services .......................................................................................................... 41
2 -lnch Temporary Service Line ................................................................................. 43
Purging and Steril ization of Water Lines .................................................................. .43
Work Near Pressure Plane Boundaries .................................................................... 44
Water Sample Station ............................................................................................... 44
Ductile Iron and Gray Iron Fittings ............................................................................ 45
SPRINKLING FOR DUST CONTROL ........................................................................... 45
DEWATERING ............................................................................................................... 45
TRENCH EXCAVATION ON DEEP TRENCHES ......................................................... .45
TREE PRUNING ............................................................................................................ 45
TREE REMOVAL ........................................................................................................... 46
TEST HOLES ................................................................................................................. 46
PUBLIC NOTIFICATION PRIOR TO BEGINNING CONSTRUCTION AND
NOTIFICATION OF TEMPORARY WATER SERVICE INTERRUPTION DURING
CONSTRUCTION .......................................................................................................... 47
TRAFFIC BUTTONS ...................................................................................................... 48
SANITARY SEWER SERVICE CLEANOUTS .............................................................. .48
TEMPORARY PAVEMENT REPAIR ............................................................................. 48
CONSTRUCTION STAKES ........................................................................................... 48
EASEMENTS AND PERMITS ....................................................................................... 49
PRE-CONSTRUCTION NEIGHBORHOOD MEETING ................................................ .49
WAGE RATES .............................................................................................................. 49
REMOVAL AND DISPOSAL OF ASBESTOS CEMENT PIPE ...................................... 51
STORM WATER POLLUTION PREVENTION (FOR DISTURBED AREAS GREATER
THAN 1 ACRE) .............................................................................................................. 51
COORDINATION WITH THE CITY'S REPRESENTATIVE FOR OPERATIONS OF
EXISTING WATER SYSTEMS ...................................................................................... 53
ADDITIONAL SUBMITTALS FOR CONTRACT AWARD .............................................. 53
EARLY WARNING SYSTEM FOR CONSTRUCTION .................................................. 54
AIR POLLUTION WATCH DAYS .................................................................................. 54
FEE FOR STREET USE PERMITS AND RE-INSPECTIONS ...................................... 55
SC-2
-
PART D -SPECIAL CONDITIONS
This Part D -Special Conditions is complimentary to Part C -General Conditions and Part C1 -
Supplementary Conditions to Part C of the Contract. Anything contained . in this Part D that is
additive to any provision in Part C -General Conditions and part C1 -Supplementary Conditions
to Part C of the Contract are to be read together. Any conflict between Part C -General
Conditions and Part C1 -Supplementary Conditions of the Contract and this Part D, Part D shall
control .
FOR: SH 121T Southwest Parkway Water & Sanitary Sewer Main Relocations
Part 1: 24-inch Water & 36-inch Sanitary Sewer Main at Bellaire Drive, DOE No. 5502
Part 5: 24-inch Water & Sanitary Sewer Main at IH 20, DOE No. 5503
Part 7A: 21-inch Sanitary Sewer Main at Overton Ridge Blvd., DOE No. 5504
In Fort Worth, Texas
Water Project No. P264-603170020483
Sewer Project No. P274-703170020483
City Project No. 00204
D-1 GENERAL
The order or precedence in case of conflicts or discrepancies between various parts of the
Contract Documents subject to the ruling of the Engineer shall generally , but not necessarily,
follow the guidelines listed below :
1. Plans
2. Contract Documents
3 . SpecialCondWons
The following Special Conditions shall be applicable to this project under the provisions stated
above . The Contractor shall be responsible for defects in this project due to faulty materials and
workmanship, or both , for a period of two (2) years from date of final acceptance of this project by
the City of Fort Worth and will be required to replace at his expense any part or all of this project
which becomes defective due to these causes.
Subject to modifications as herein contained, the Fort Worth Water Department's General
Contract Documents and General Specifications, with latest revisions, are made a part of the
General Contract Documents for this project. The Plans, these Special Contract Documents and
the rules, regulations, requirements, instructions, drawings or details referred to by manufacturers
name , or identification include therein as specifying, referring or implying product control,
performance, quality, or other shall be binding upon the contractor. The specifications and
drawings shall be considered cooperative; therefore, work or material called for by one and not
shown or mentioned in the other shall be accomplished or furnished in a faithful manner as
though required by all.
Any Contractor performing any work on Fort Worth water or sanitary sewer facilities must be pre~
qualified with the Water Department to perform such work in accordance with procedures
described in the current Fort Worth Water Department General Specifications, which general
specifications shall govern performance of all such work .
This contract and project, where applicable, may also be governed by the two following published .
specifications, except as modified by these Special Provisions :
1. STANDARD SPECIFICATIONS FOR STREET AND STORM DRAIN CONSTRUCTION -
CITY OF FORT WORTH
11/29/04 SC-3
PART D -SPECIAL CONDITIONS
2 . STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION -NORTH
CENTRAL TEXAS
Any conflict between these cont ract documents and the above 2 publications shall be resolved in
favor of these contract documen ts .
A copy of either of these specifi c ations may be purchased at the office of the Transportation and
Public Works Director, 1000 T h rockmorton Street, 2nd Floor, Municipal Building , Fort Worth ,
Texas 76102 . The specificatio ns applicable to each pay item are indicated by the call-out for the
pay item by the designer. If not shown , then applicable published specifications in either of these
documents may be followed at the discretion of the Contractor. General Provisions shall be those
of the Fort Worth document rather than Division 1 of the North Central Texas document.
Bidders shall not separate, detach or remove any portion, segment or sheets from the
contract document at any time. Failure to bid or fully execute contract without retaining
contract documents intact may be grounds for designating bids as "non-responsive" and
rejecting bids or voiding contract as appropriate as determined by the City Engineer.
INTERPRETATION AND PREPARATION OF PROPOSAL :
A. DELIVERY OF PROPOSAL: No proposal will be considered unless it is delivered,
accompanied by its proper Bid Security , to the Purchasing Manager or his representative at
the official location and stated time set forth in the "Notice to Bidders". It is the Bidder's sole
responsibility to deliver the proposal at the proper time to the proper place . The mere fact that
a proposal was dispatched will not be considered . The Bidders must have the proposal
actually delivered . Each proposal shall be in a sealed envelope plainly marked with the word
"PROPOSAL", and the name or description of the project as designated in the "Notice to
Bidders". The envelope shall be addressed to the Purchasing Manager, City of Fort Worth
Purchasing Division , PO Box 17027 , Fort Worth , Texas 76102.
B. WITHDRAWING PROPOSALS: Proposals actually filed with the Purchasing Manager cannot
be withdrawn prior to the time set for opening proposals. A request for non-consideration of a
proposal must be made in writing, addressed to the City Manager, and filed with him prior to
the time set for the opening of proposals . After all proposals not requested for non-
consideration are opened and publicly read aloud, the proposals for which non-consideration
requests have been properly filed may, at the option of the Owner, be returned unopened .
C. TELEGRAPHIC MODIFICATION OF PROPOSALS: Any bidder may modify his proposal by
telegraphic communication at any time prior to the time set for opening proposals, provided
such telegraphic communication is received by the Purchasing Manager prior to the said
proposal opening time , and p rovided further, that the City Manager is satisfied that a written
and duly authenticated confi rmation of such telegraphic communication over the signature of
the bidder was mailed prior to the proposal opening time . If such confirmation is not received
within forty-eight (48) hours after the proposal opening time, no further consideration will be
given to the proposal.
D-2 COORDINATION MEETING
For coordination purposes, weekly meetings at the job site may be required to maintain the
project on the desired schedule . The contractor shall be present at all meetings .
11 /29/04 SC-4
-
PART D -SPECIAL CONDITlONS
D-3 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
A. Definitions :
1. Certification of coverage ("certificate"). A copy of a certificate of insurance, a certificate of
authority to self-insure issued by the commission, or a coverage agreement (TWCC-81,
TWCC-82, TWCC-83 , or TWCC-84), showing statutory workers' compensation insurance
coverage for the person's or entity's employees providing services on a project, for the
duration of the project.
2. Duration of the project -includes the time from the beginning of the work on the project
until the contractor's/person's work on the project has been completed and accepted by
the governmental entity .
3. Persons providing services on the project ("subcontractor" in §406.096)-includes all
persons or entities performing all or part of the services the contractor has undertaken to
perform on the project, regardless of whether that person contracted directly with the
contractor and regardless of whether that person has employees . This includes , without
limitation, independent contractors, subcontractors, leasing companies, motor carriers,
owner operators , employees of any such entity, or employees of any entity which
furnishes persons to provide services on the project. "Services" include , without limitation,
providing, hauling , or delivering equipment or materials, or providing labor, transportation ,
or other services related to a project. "Services" does not include activities unrelated to
the project, such as food/beverage vendors, office supply deliveries, and delivery of
portable toilets.
B. The Contractor shall provide coverage, based on proper reporting of classification codes and
payroll amounts and filing of any coverage agreements, which meets the statutory
requirements of Texas Labor Code, Section 401 .011 (44) or all employees of the Contractor
providing services on the project, for the duration of the project.
C. The Contractor must provide a certificate of coverage to the governmental entity prior to being
awarded the contract.
D. If the coverage period shown on the contractor's .current certificate of coverage ends during
the duration of the project, the contractor must, prior to the end of the coverage period, file a
new certificate of coverage with the governmental entity showing that coverage has been
extended.
E. The Contractor shall obtain from each person providing services on a project, and provide the
governmental entity:
1. A certificate of coverage, prior to that person beginning work on the project, so the
governmental entity will have on file certificates of coverage showing coverage for all
persons providing services on the project; and
2. No later than seven days after receipt by the contractor, a new certificate of coverage
showing extension of coverage, if the coverage period shown on the current certificate of
coverage ends during the duration of the project.
F. The contractor shall retain all required certificates of coverage for the duration of the project
and for one year thereafter.
11/29/04 SC-5
PART D -SPECIAL CONDITIONS
G. The contractor shall notify the governmental entity in writing by certified mail or personal
del ivery , within ten (10) days after the contractor knew or should have known ,, of any change
that materially affects the prov ision of coverage of any person providing services on the
project.
H. The contractor shall post on each project site a notice, in the text, form and manner
prescribed by the Texas Worker's Compensation Commission, informing all persons prov iding
services on the project that t hey are required to be covered, and stating how a person may
verify coverage and report lack of coverage .
I. The contractor shall contractually require each person with whom it contracts to provide
services on a project , to:
1. Provide coverage , based on proper reporting on classification codes and payroll amounts
and filing of any coverage agreements, which meets the statutory requirements of Texas
Labor Code , Section 401 .011 (44) for all of its employees providing services on the project,
for the duration of the project ;
2 . Provide to the Contractor, prior to that person beginning work on the project , a certificate
of coverage showing that coverage is being provided for all employees of the person
providing services on the project, for the duration of the project;
3. Provide the Contractor, prior to the end of the coverage period, a new certificate of
coverage showing exten s ion of coverage, if the coverage period shown on the current
certificate of coverage ends during the duration of the project;
4. Obtain from each other person with whom it contracts, and provide to the Contractor:
a.) A certificate of coverage , prior to the other person beginning work on the project; and
b.) A new certificate of coverage showing extension of . coverage, prior to the end of the
coverage period, if the coverage period shown on the current certificate of coverage
ends during the duration of the project.
5. Retain all required certificates of coverage on file for the duration of the project and for one
year thereafter.
6. Notify the governmental entity in writing by certified mail or personal delivery, within ten
(10) days after the person knew or should have known, of any change that materially
affects the provision of coverage of any person providing services on the project; and
7. Contractually require ea c h person with whom it contracts, to perform as required by
paragraphs (1 )-(7), with the certificates of coverage to be provided to the person for whom
they are prov iding services .
8. By signing this contract or providing or causing to be provided a certificate of coverage ,
the contractor is representing to the governmental entity that all employees of the
contractor who will provide services on the project will be covered by worker's
compensation coverage for the duration of the project, that the coverage will be based on
proper reporting of classification codes and payroll amounts, and that all coverage
agreements will be filed with the appropriate insurance carrier or , in the case of a self-
insured , with the commission's Division of Self-Insurance Regulation. Providing false or
11/29/04 SC-6
-
PART D -SPECIAL CONDITIONS
misleading information may subject the contractor to administrative, criminal, civil
penalties or other civil actions.
9 . The contractor's failure to comply with any of these provisions is a breach of contract by
the contractor which entitles the governmental entity to declare the contract void if the
contractor does not remedy the breach within ten days after receipt of notice of breach
from the governmental entity.
J . The contractor shall post a notice on each project site informing all persons providing services
on the project that they are required to be covered, and stating how a person may verify
current coverage and report failure to provide coverage . This notice does not satisfy other
posting requirements imposed by the Texas Worker's Compensation Act or other Texas
Worker's Compensation Commission rules. This notice must be printed with a title in at least
30 point bold type and text in at least 19 point normal type , and shall be in both English and
Spanish and any other language common to the worker population. The text for the notices
shall be the following text , without any additional words or changes:
"REQUIRED WORKER'S COMPENSATION COVERAGE
The law requires that each person working on this site or providing services related to this
construction project must be covered by workers' compensation insurance. This includes
persons providing, hauling, or delivering equipment or materials , or providing labor or
transportation or other service related to the project, regardless of the identity of their
employer or status as an employee ."
Call the Texas Worker's Compensation Commission at (512)440-3789 to receive information
on the legal requirement for coverage, to verify whether your employer has provided the
required coverage, or to report an employer's failure to provide coverage".
D-4 COORDINATION WITH FORT WORTH WATER DEPARTMENT
During the construction of this project, it will be necessary to deactivate, for a period of time,
existing lines . The Contractor shall be required to coordinate with the Water Department to
determine the best times for deactivating and activating those lines.
D-5 CROSSING OF EXISTING UTILITIES
Where a proposed water line crosses over a sanitary sewer or sanitary_sewer service line and/or
proposed sewer line crosses over a water line and the clear vertical distance is less than 9 feet
barrel to barrel , the sanitary sewer or san itary sewer service line shall be made watertight or be
constructed of ductile iron pipe. The Engineer shall determine the required length of replacement.
The material for sanitary sewer mains and sanitary sewer laterals shall be Class 51 Ductile Iron
Pipe with polyethylene wrapping . The material for sanitary sewer service lines shall be extra
strength cast iron soil pipe with polyethylene wrapping. Adapter fittings shall be a urethane or
neoprene coupling ASTM C-425 with series 300 stainless steel compression straps . Backfill,
fittings, tie-ins and all other associated appurtenances required are deemed subsidiary work, the
cost of which shall be included in the price bid in the Proposal for each bid item .
D-6 EXISTING UTILITIES AND IMPROVEMENTS
The plans show the locations of all known surface and subsurface structures . However, the
Owner assumes no responsibility for failure to show any or all of these structures on the Plans , or
to show them in their exact location . It is mutually agreed that such failure shall not be
11/29/04 SC-7
PART D -SPECIAL CONDITIONS
considered sufficient basis for claims for additional compensation for extra work or for increasing
the pay quantities in any manner whatsoever.
The Contractor shall be responsible for verifying the locations of and protecting all existing
utilities , service lines, or other property exposed by his construction operations. Contractor shall
make all necessary provisions (as approved or authorized by the applicable utility company) for
the support, protection and/or temporary relocation of all utility poles, gas lines, telephone cables,
utility services, water mains, sanitary sewer lines , electrical cables, drainage pipes, and all other
utilities and structures both above and below. ground during construction . It is understood that the
Contractor is not responsible for the permanent relocation of existing utilities in direct conflict with
the proposed construction. The Contractor is liable for all damages done to such existing facilities
as a result of his operations and any and all cost incurred for the protection and/or temporary
relocation of such facilities are deemed subsidiary work and the cost of same and shall be
included in the cost bid per linear foot of pipe installed. NO ADDITIONAL COMPENSATION
WILL BE ALLOWED .
Where existing utilities or service lines are cut, broken or damaged the Contractor shall replace or
repair the utilities or service lines with the same type of original material and construction , or
better, unless otherwise shown or noted ori the plans, at his own cost and expense . The
Contractor shall immediately notify the Owner of the damaged utility or service line. He shall
cooperate with the Owners of all utilities to locate existing underground facilities and notify the
Engineer of any conflicts in grades and alignment.
In case it is necessary to change or move the property of any owner of a public utility , such
property shall not be moved or interfered with until ordered to do so by the Engineer. The right is
reserved to the owner of public utilities to enter upon the limits of the project for the purpose of
making such changes or repairs of their property that may be made necessary by performance of
this contract.
The utility lines and conduits shown on the plans are for information only and are not guaranteed -
by the City of the Engineer to be accurate as to extent, location , and depth; they are shown on the
plans as the best information available at the time of design, from the owners of the utilities
involved and from evidences found on the ground.
D-7 CONSTRUCTION TRAFFIC OVER PIPELINES
It is apparent that certain constr uction vehicles could exceed the load bearing capacity of the pipe
under shallow bury conditions . It will be the responsibility of the Contractor to protect both the new
line and the existing lines from these possibly excessive loads. The Contractor shall not, at any
time, cross the existing or new pipe with a truck delivering new pipe to the site. Any damage to
the existing or new pipe will be repaired or replaced by the Contractor, at the Contractor's
expense, to the satisfaction of the City.
In locations where it is not permissible to cross the existing or proposed pipes without additional
protection the Contractor may elect to provide additional protection of the pipes so that more
frequent crossings of the pipes are allowed. It still is, however, the responsibility of the Contractor
to repair any damage to the existing or proposed lines, if the damage results from any phase of
his construction operation.
11/29/04 SC-8
PART D -SPECIAL CONDITIONS
D-8 TRAFFIC CONTROL
A traffic control plan is included in the plans for this project. All other provisions of this section
apply.
The contractor will be required to obtain a "Street Use Permit" prior to starting work . As part of
the "Street Use Permit" a traffic control plan is required . The Contractor shall be responsible for
providing traffic control during the construction of this project consistent with the provisions set
forth in the "Latest Edition Texas Manual on Un iform Traffic Control Devices for Streets and
Highways" issued under the authority of the "State of Texas Uniform Act Regulating Traffic on
Highways ," codified as Article 6701 d Vernon 's Civil Statutes , pertinent sections being Section
Nos. 27 , 29 , 30 and 31.
A traffic control plan shall be submitted for review to Mr. Charles R. Burkett. City Traffic Engineer
at (817) 871-8770, at the pre-construction conference. Although work will not begin until the
traffic control plan has been reviewed, the Contractor's time will begin in accordance with the time
frame established in the Notice to the Contractor.
The Contractor will not remove any regulatory sign , instructional sign, street name sign or other
sign , which has been erected by the City . If it is determined that a sign must be removed to
permit required construction , the Contractor shall contact the Transportation and Public Works
Department, Signs and Markings Division , (Phone Number 871-7738) to remove the sign. In the
case of regulatory signs , the Contractor must replace the permanent sign with a temporary sign
meeting the requirements of the above-referenced manual and such temporary sign must be
installed prior to the removal of the permanent sign. If the temporary sign is not installed correctly
or if it does not meet the required specifications , the permanent sign shall be left in place until the
temporary sign requirements are met. When construction work is · completed to the extent that the
permanent sign can be reinstalled, the Contractor shall again contact the Signs and Markings
Division to reinstall the permanent sign and shall leave his temporary sign in place until such
reinstallation is completed .
Work shall not be performed on certain locations/streets during "peak traffic periods " as
determination by the City Traffic Engineer and in accordance with the applicable provision of the
"City of Fort Worth Traffic Control Handbook for Constructi_on and Maintenance Work Areas."
The cost of the traffic control is subsidiary work and the cost of same shall be included in the price
bid for pipe complete in place as bid in the Proposal, and no other compensation will be allowed .
D-9 DETOURS
The contractor shall prosecute his work in such a manner as to create a minimum of interruption
to traffic and pedestrian facilities and to the flow of vehicular and pedestrian traffic within the
project area.
D-10 EXAMINATION OF SITE
It shall be the responsibility of the prospective bidder to visit the project site and make such
examinations and explorations as may be necessary to determine all conditions , which may affect
construction of this project. Particular attention should be given to methods of providing ingress
and egress to adjacent private and public properties , procedures for protecting existing
improvements and disposition of all materials to be removed. Proper consideration should be
given to these details during the preparation of the Proposal and all unusual conditions, which
may give, rise to later contingencies should be brought to the attention of the Owner prior to the
submission of the Proposal.
11129/04 SC-9
PART D -SPECIAL CONDITIONS
D-11 ZONING COMPLIANCE
During the construction of th is project, the Contractor shall comply with present zoning
requirements of the City of Fort Worth in the use of vacant property for storage purposes .
D-12 WATER FOR CONSTRUCTION
The Contractor at his own expense will furnish water for construction .
D-13 WASTE MATERIAL
All waste material shall become the property of the Contractor and shall be disposed of by the
Contractor at locations approved by the Engineer. All material shall be disposed of in such a
manner as to present a neat appearance and to not obstruct proper drainage or to cause injury to
street improvements or to abutting property .
D-14 PROJECT CLEANUP AND FINAL ACCEPTANCE
The Contractor shall be aware that keeping the project site in a neat and orderly condition is
considered an integral part of the contracted work and as such shall be considered subsidiary to the
appropriate bid items. Clean up work shall be done as directed by the Engineer as the work
progresses or as . needed. If, in the opinion of the Engineer it is necessary, clean-up shall be done
on a daily basis . Clean up work shall include, but not be limited to:
• Sweeping the street clean of dirt or debris
• Storing excess material in appropriate and organized manner
• Keeping trash of any kind off of residents' property
If the Engineer does not feel that the jobsite has been kept in an orderly condition, on the next
estimate payment (and all subsequent payments until completed) of the appropriate bid item(s)
will be reduced by 25%.
Final cleanup work shall be done for this project as soon as all construction has been completed.
No more than seven days shall elapse after completion of construction before the roadway, right-
of-way, or easement is cleaned up to the satisfaction of the Engineer. The Contractor shall make
a final cleanup of all parts of the work before acceptance by the City of Fort Worth or its
representative. This cleanup shall include removal of all objectionable rocks, pieces of asphalt or
concrete and other construction materials, and in general preparing the site of the work in an
orderly manner and appearance. The City of Fort Worth Department of Engineering shall give
final acceptance of the completed project work .
D-15 CONSTRUCTION SCHEDULE AND SEQUENCING OF WORK
Prior to executing the Contract, it shall be the responsibility of the Contractor to furnish a schedule
outlining the anticipated time for each phase of construction with starting and completion dates,
including sufficient time being allowed for cleanup. The Contractor shall not commence with
water and/or sanitary sewer installation until such ti _me that the survey cut-sheets have been
rep~ived f[Qm the City _ipsp~ctor.
11/29/04 SC-10
PART D -SPECIAL CONDITIONS
D-16 SAFETY RESTRICTIONS -WORK NEAR HIGH VOLTAGE LINES
The following procedures will be followed regarding the subject item on this contract:
1. A warning sign not less than five inches by seven inches, pa inted yellow with black letters
that are legible at twelve feet shall be placed inside and outside vehicles such as cranes,
derricks, power shovels, drilling rigs, pile drivers , hoisting equipment or similar apparatus.
The warning sign shall read as follows : "WARNING -UNLAWFUL TO OPERATE THIS
EQUIPMENT WITHIN SIX FEET OF HIGH VOLTAGE LINES."
2 . Equipment that may be operated within ten feet of high voltage lines shall have insulating
cage-type of guard about the boom or arm, except back hoes or dippers, and insulator
links on the lift hook connections.
3. When necessary to work within six feet of high voltage electric lines , notification shall be
given the power company (ONCORE) who will erect temporary mechanical barriers , de-
energize the lines, or raise or lower the lines . The work done by the power company shall
not be at the expense of the City of Fort Worth . The notifying department shall maintain
an accurate log of all such calls to ONCORE, and shall record action taken in each case .
4 . The Contractor is required to make arrangements with the ONCORE company for the
temporary relocation or raising of high voltage lines at the Contractor's sole cost and
expense.
5. No person shall work within six feet of a high voltage line without protection having been
taken as outlined in Paragraph (3).
D-17 BID QUANTITIES
Bid quantities of the various items in the proposal are for comparison only and may not reflect the
actual quantities . There is no limit to which a bid item can be increased or decreased.
Contractor shall not be entitled to renegotiation of unit prices regardless of the final measured
quantities. To the extent that C4-4.3 conflicts with this provision, this provision controls. No claim
will be considered for lost or anticipated profits based upon differences in estimated quantities
versus actual quantities .
D-18 CUTTING OF CONCRETE
When existing concrete is cut, such cuts shall be made with a concrete saw. All sawing shall be
subsidiary to the unit cost of the respective item.
D-19 PROJECT DESIGNATION SIGN
Project signs are required at all locations. It shall be in accordance with the attached Figure 30
(dated 9-18-96). The signs may be mounted on skids or posts. The Engineer shall approve the
exact locations and methods of mounting. In addit ion to the 4' x 8' project signs, project signs
shall be attached to barricades used where manhole rehabilitation or replacement is being
conducted . Signs suspended from barricading shall be placed in such a way that signs do not
interfere with reflective paint or coloring on the barricades . Barricade signs shall be in
accordance with Figure 30, except that they shall be 1'-0" by 2'-0" in size . The information box
shall have the following information:
11129/04 SC-11
PART D -SPECIAL CONDITIONS
For Questions on this Project Ca ll :
(817) 871-8306 M-F 7:30 am to 4:30 p.m.
or
(8 17)871-8300 Nights and Weekends
Any and all cost for the required materials, labor, and equipment necessary for the furnishing of
Project Signs shall be considered as a subsidiary cost of the project and no additional
compensation will be allowed .
D-20 CONCRETE SIDEWALK AND DRIVEWAY REPLACEMENT
At locations in the project where mains are required to be placed under existing sidewalks and/or
driveways , such sidewalks and /or driveways shall be completely replaced for the full existing
width, between existing construction or expansion joints with 3000 psi concrete with reinforcing
steel on a sand cushion in ac cordance with City of Fort Worth Transportation/Public Works
Department Standard Specifications for Construction, Item 504.
At locations where mains are required to be placed under existing curb and gutter, such curb and
gutter shall be replaced to match type and geometry of the removed curb and gutter shall be
installed in accordance with City of Fort Worth Public Works Department Standard Specification
for Construction, Item 502.
Payment for cutting , backfill , co ncrete , forming materials and all other associated appurtenances
required, shall be included in the square yard price of the bid item for concrete sidewalk or
driveway repair.
D-21 MISCELLANEOUS PLACEMENT OF MATERIAL
Material has been allocated un der various bid items in the Proposal to establish unit prices for
miscellaneous placement of ma terial. These materials shall be used only when directed by the
Engineer, depending on field co nditions . Payment for miscellaneous placement of material will be
made for only that amount of material used, measured to the nearest one-tenth unit. Payment for
miscellaneous placement of material shall be in accordance with the General Contract
Documents regardless of the act ual amount used for the project.
D-22 CRUSHED LIMESTONE BACKFILL
Where specified on the plans or directed by the Engineer, Crushed Limestone shall be used for
trench backfill on this project. The material shall conform to Public Works Standard Specifications
for Street and Storm Drain Co nstruction Division 2 Item 208.2 -Materials and Division 2 Item
208.3 -Materials Sources . Trench backfill and compaction shall meet the requirements of E2-2
Excavation and Backfill, Construction Specifications , Gen·eral Contract Documents.
Payment for crushed limestone backfill in place shall be made at the unit price bid in the Proposal
multiplied by the quantity of material used measured in accordance with E2-2.16 Measurement of
Backfill Materials , Construction Specifications, and General Contract Documents.
D-23 2:27 CONCRETE
Transportation and Public Works Department typical sections for Pavement and Trench Repair for
Utility Cuts Figures 1 through 5 refer to using 2:27 Concrete as base repair. Since this call-out
includes the word "concrete", the consistent interpretation of the Transportation and Public Works
Department is that this ratio specifies two (2) sacks of cement per cubic yard of concrete .
11 /29/04 SC-12
PART D -SPECIAL CONDlTIONS
D-24 TRENCH EXCAVATION, BACKFILL, AND COMPACTION
Trench excavation and backfill under parking lots, driveways, gravel surfaced roads , within
easements, and within existing or future R.O .W. shall be in accordance with Sections E1-2
Backfill and E2-2 Excavation and Backfill of the General Contract
Documents and Specifications except as specified herein.
1. TRENCH EXCAVATION : In accordance with Section E2-2 Excavation and Backfill, if the
stated maximum trench widths are exceeded, either through accident or otherwise, and if the
Engineer determines that the design loadings of the pipe will be exceeded , the Contractor will be
required to support the pipe with an improved trench bottom. The expense of such remedial
measures shall be entirely the Contractor's own. All trenching operations shall be confined to the
width of permanent rights-of-way, permanent easements, and any temporary construction
easements. All excavation shall be in strict compliance with the Trench Safety Systems Special
Condition of this document.
2. TRENCH BACKFILL: Trenches which lie outside of existing or future pavement shall be
backfilled above the top of the embedment material with Type "C" backfill material. Excavated
material used for Type "C" backfill must be mechanically compacted unless the Contractor can
furnish the Engineer with satisfactory evidence that the P.I. of the excavated material is less than
8 . Such evidence shall be a test report from an independent testing laboratory and must include
representative samples of soils in all involved areas, with a map showing the location and depth
of the various test holes. If excavated material is obviously granular in nature, containing little or
no plastic material, the Engineer may waive the test report requirement. See E1-2.3, Type "C" or
"D" Backfill, and E2-2.11 Trench Backfill for additional requirements. When Type "C" back-fill
material is not suitable, at the direction of the Engineer, Type "B" backfill material shall be used .
In general, all backfill material for trenches in existing paved streets shall be in accordance with
Figure A. Sand material specified in Figure A shall be obtained from an approved source and
shall consist of durable particles free of thin or elongated pieces, lumps of clay, soil, loam or
vegetable matter and shall meet the following gradation:
• Less than 10% passing the #200 sieve
• P.I. = 10 or less
Additionally, the crushed limestone embedment gradation specified in Section E1-3 Crushed
Limestone for Embedment of the General Contract Documents and Specifications shall be
replaced with the following:
Sieve Size
1"
1/2"
3/8"
#4
#8
% Retained
0-10
40-75
55-90
90-100
95-100
All other provisions of this section shall remain the same.
3. TRENCH COMPACTION: All trench backfill shall be placed in lifts per E2-2.9 Backfill.
Trenches which lie outside existing or future pavements shall be compacted to a minimum of 90%
Standard Proctor Density (A.S.T.M . 0698) by mechanical devices specifically designed for
compaction or a combination of methods subject to approval by the Engineer.
11/29/04 SC-13
PART D -SPECIAL CONDITIONS
Trenches which lie under existing or future pavement shall be backfilled per Figure A with 95%
Standard Proctor Density by mechanical devices specifically designed for compaction or a
combination of methods subject to approval by the Engineer. Backfill material to be compacted
as described above must be within +-4% of its optimum moisture content. The top two (2) feet of
sewer line trenches and the top eighteen (18) inches of water line may be rolled in with heavy
equipment tires, provided it is placed in lifts appropriate to the material being used and the
operation can be performed without damage to the installed pipe.
The City , at its own expense, will perform trench compaction tests per A.S.T.M. standards on all
trench backfill. Any retesting re quired as a result of failure to compact the backfill material to
meet the standards will be at the expense of the Contractor and will be billed at the commercial
rates as determined by the City . These soil density tests shall be performed at two (2) foot
vertical intervals beginning at a level two (2) feet above the top of the installed pipe and
continuing to the top of the completed backfill at intervals along the trench not to exceed 300
linear feet. The Contractor will be responsible for providing access and trench safety system to
the level of trench backfill to be tested . No extra compensation will be allowed for exposing the
backfill layer to be tested or providing trench safety system for tests conducted by the City.
4 . MEASUREMENT AND PAYMENT: All material, with the exception of Type "B" backfill, and
labor costs of excavation and backfill will be included in the price bid per linear foot of water and
sewer pipe. Type "B" backfill shall be paid for at a pre-bid unit price of $15 .00 per cubic yard .
D-25 TRENCH PAVEMENT (PERMANENT) REPAIR (E2-19) FOR UTILITY CUTS
The unit price bid under the appropriate bid item of the proposal shall cover all cost for providing
pavement repair equal to or superior in composition , th ickness, etc., to existing pavement as
detailed in the Public Works Department typical sections for Pavement and Trench Repair for
Utility Cuts , Figures 2000-1 through 2000-3 .
The results of the street cores t hat were conducted on the project streets, to determine HMAC
depths on existing streets , are provided in these specifications and contract documents.
All required paving cuts shall be made w ith a concrete saw in a true and straight line on both
sides of the trench , a minimum of twelve (12) inches outside the trench walls. The trench shall be
backfilled and the top nine (9) inches shall be filled with required materials as shown on paving
details, compacted and level with the finished street surface. This finished grade shall be
maintained in a serviceable condition until the paving has been replaced. All residential
driveways shall be accessible at night and over weekends .
It has been determined by the Transportation and Public Works Department that the strip of
existing HMAC pavement between the existing gutter and the edge of the trench pavement repair
will not hold up if such strip of ex isting pavement is two (2) feet or less in width.
Therefore, at the locations in the project where the trench wall is three (3) feet or less from the lip
of the existing gutter, the Cont ractor shall be required to remove the existing paving to such
gutter. The pavement repair shall then be made from a minimum distance of twelve (12) inches
outside the trench wall nearest the center of the street to the gutter line.
The pavement shall be replaced within a maximum of five (5) working days, providing job
placement conditiO!lS will permit repaving . If paving conditions are not suitable for repaving, in the
opinion of the Owner, the repaving shall be done at the earliest possible date .
11/29/04 SC-14
PART D -SPECIAL CONDITIONS
A permit must be obtained from the Department of Engineering Construction Services Section by
the Contractor in conformance with Ordinance No. 3449 and/or Ordinance No . 792 to make utility
cuts in the street. The Department of Engineering will inspect the paving repair after construction.
This permit requirement may be waived if work is being done under a Performance Bond and
inspected by the Department of Engineering .
D-26 SITE SPECIFIC TRENCH SAFETY SYSTEM (COVERS ALL PROJECTS)
A. GENERAL: This specification covers the trench safety requirements for all trench excavations
exceeding depth of five (5) feet in order to protect workers from cave-ins. The requirements
of this item govern all trenches for mains, manholes, vaults, service lines, and all other
appurtenances. The design for the trench safety shall be signed and sealed by a Registered
Professional Engineer licensed in Texas. The trench safety plan shall be specific for each
water and/or sanitary sewer line included in the project.
8. STANDARDS: The latest version of the U.S. Department of Labor , Occupational Safety and
Health Administration Standards, 29 CFR Part 1926, Sub-Part P -Excavations , are hereby
made a part of this specification and shall be the minimum governing requirements for trench
safety .
C. DEFINITIONS :
1. TRENCHES -A trench is referred to as a narrow excavation made below the surface of
the ground in which the depth is greater than the width, where the width measured at the
bottom is not greater than fifteen (15) feet.
2. BENCHING SYSTEM -Benching means excavating the sides of a trench to form one or a
series of horizontal level or steps , usually with vertical or near-vertical surfaces between
levels.
3. SLOPING SYSTEM -Sloping means excavating to form sides of a trench that are inclined
away from the excavation .
4. SHIELD SYSTEM -Shields used in trenches are generally referred to as "trench boxes " or
"trench shields ". Shield means a structure that is able to withstand the forces imposed on
it by a cave-in and protect workers within the structure . Shields can be permanent
structures or can be designed to be portable and move along as the work progresses.
Shields can be either pre-manufactured or job-built in accordance with OSHA standards.
5. SHORING SYSTEM -Shoring means a structure such as a metal hydraulic, mechanical or ·
timber system that supports the sides of a trench and which is designed to prevent cave-
ins. Shoring systems are generally comprised of cross-braces , vertical rails, (uprights),
horizontal rails (wales) and/or sheeting .
D. MEASUREMENT -Trench depth is the vertical measurement from the top of the existing
ground to the bottom of embedment or bottom of excavation . The quantity of trench safety
systems shall be based on the linear foot amount of trench depth greater than five (5) feet.
E . PAYMENT -Payment shall be full compensation for safety system design, labor, tools,
materials , equipment and incidentals necessary for the installation and removal of trench
safety systems .
11129/04 SC-15
PART D -SPECIAL CONDITIONS
D-27 SANITARY SEWER MANHOLES
A. GENERAL : The installation, replacement, and/or rehabilitation of sanitary sewer manholes
will be required as shown on the plans , and/or as described in these Special Contract
Documents in addition to those located in the field and identified by the Engineer. All
manholes shall be in accordance with sections E1-14 Materials for Sanitary Sewer Manholes ,
Valve Vaults , Etc., and E2-14 Vault and Manhole Construction of the General Contract
Documents and Specifications , unless amended or superseded by requirements of this
Special Condition. For new sewer line installations, the Contractor shall temporarily plug all
lines at every open manhole under construction in order to keep debris out of the dry sewer
lines . The plugs shall not be removed until the applicable manhole complete with cone
section has been constructe d and the lid installed to keep out debris as a result of additional
construction .
1. CONCRETE COLLARS : Concrete collars will be required on all manholes specified as
per Figure 121.
2 . WATERTIGHT MANHOLE INSERTS: Watertight gasket manhole inserts shall be
installed in all sanitary sewer manholes. Inserts shall be constructed in accordance with
Fort Worth Water Department Standard E100-4 and shall be fitted and installed according
to the manufacturer's recommendations . Stainless Steel manhole inserts shall be
required for all pipe diameters 18 " and greater.
3. LIFT HOLES : All lift holes shall be plugged with a pre-cast concrete plug. The lift hole
shall be sealed on the outside of the manhole with Ram-Nek or an approved equal
sealant. The lift hole shall be sealed on the inside of the manhole with quick setting
cement grout.
4 . FINAL RIM ELEVATIONS : Manhole rims in parkways, lawns and other improved lands
shall be at an elevation not more than one (1) nor less than one-half (1/2) inch above the
surrounding ground. Backfill shall provide a uniform slope from the top of manhole casting
for not less than three (3) feet each direction to existing finish grade of the ground. The
grade of all surfaces sha ll be checked for proper slope and grade by string lining the entire
area regarded near the manhole.
Manholes in open fields , unimproved land , or drainage courses shall be at an elevation
shown on the drawings or minimum of 6 inches above grade .
5. MANHOLE COVERS: A ll lids shall have pick slots in lieu of pick holes. Manhole frames
and covers shall be McKinley, Type N , with indented top design, or equal, with pick slots .
Covers shall set flush wit h the rim of the frame and shall have no larger than 1/8-inch gap
between the frame and cover. Bearing surfaces shall be machine finished . Locking
manhole lids and frames will be restricted to locations within the 100-year floodplain and
areas specifically designated on the plans. Certain teed Ductile Iron Manhole Lids and
Frames are acceptable for use where locking lids are specified .
6. SHALLOW CONE MANHOLES: Shallow manhole construction will be used when
manhole depth is four (4) feet or less. All shallow cone manholes shall be built in
accordance with Figure 105. All shallow cone manholes shall have a cast iron lid and
frame with pick slots. NOTE: MANHOLES PER FIGURE 106 WILL NOT BE ALLOWED .
7. MANHOLE STEPS : No manhole steps are to be installed on any sanitary sewer manhole .
11/29/04 SC-16
-
PART D -SPECIAL CONDITIONS
8. EXTERIOR SURFACE COATING: Exterior surfaces of all manholes shall be coated with
two mop coats of coal tar epoxy, Koppers "Bitumastic Super Service Black" Tnemec "46-
450 Heavy Tnemecol ," or equal to, a minimum or 14 mils dry film thickness.
9. MANHOLE JOINT SEALING: All interior and/or exterior joints on concrete manhole
sections constructed for the City of Fort Worth Water Department, excluding only the joints
using a trapped type performed 0-ring rubber gasket shall require Bitumastic joint
sealants as per Figure M.
This sealant shall be pre-formed and trowelable Bitumastic as manufactured by Kent-Seal,
Ram-Nek, E-Z Stick, or equal. The joint sealer shall be supplied in either extruded pipe
form or suitable cross-sectional area or flat-tape and shall be sized as recommended by
the manufacturer and approved by the Engineer. The joint sealer shall be protected by a
suitable removable wrapper and shall not in any way depend on oxidation, evaporation, or
any other chemical action for either its adhesive properties or cohesive strength. The
Joint sealer shall remain totally flexible without shrinking, hardening, or oxidizing
regardless of the length of time it is exposed to the elements . The manufacturer shall
furnish an affidavit attesting to the successful use of the product as a pre-formed flexible
joint sealant on concrete pipe and manhole sections for a period of at least five years.
B. EXECUTION :
1. INSTALLATION OF JOINT SEALANT: Each grade adjustment ring and manhole frame
shall be sealed with the above-specified materials . All surfaces to be in contact with the
joint sealant shall be thoroughly cleaned of dirt, sand, mud, or other foreign matter. The
manufacturer shall apply a primer to all surfaces prior to installing the joint sealant in
accordance with the recommendations. The protective wrapper shall remain on the joint
sealant until immediately prior to the placement of the pipe in the trench. After removal of
the protective wrapper, the joint sealant shall be kept clean. Install frames and cover over
manhole opening with the bottom of the rings resting on Bitumastic joint sealer. Frames
and grade rings shall rest on two (2) rows (inside and outside) of Bitumastic joint sealer.
2. SEALING AND/OR ADJUSTING EXISTING MANHOLES: Excavate (rectangular full
depth saw cut if in pavement) adjacent to the manhole to expose the entire manhole frame
and a minimum of 6 inches of the manhole wall keeping the sides of the trench nearly
vertical.
11/29/04
Remove manhole frame from the manhole structure and observe the condition of the
frame and grade rings. Any frame or grade ring that is not suitable for use as determined
by the Engineer shall be replaced. Grade rings that are constructed of brick, block
materials other than pre-cast concrete rings, or where necessary and approved by the
Engineer, shall be replaced with a pre-cast flattop section. Pre-cast concrete rings, or a
pre-cast concrete flattop section will be the only adjustments allowed.
In brick or block manholes, replace the upper portion of the manhole to a point 24 inches
below the frame. If the walls or cone section below this level are structurally unsound,
notify the Engineer prior to replacement of the grade rings and manhole frame. Existing
brickwork, if damaged by the Contractor, shall be replaced at the Contractor's expense .
Wire brush manhole frame and exposed manhole surfaces to remove dirt and loose
debris. Coat exposed manhole surfaces with an approved bonding agent followed by an
application of quick setting hydraulic cement to provide a smooth working surface.
SC-17
PART D -SPECIAL CONDITIONS
. If the inside diameter of the manhole is too large to safely support new adjustment rings or
frames, a flat top section shall be installed .
Joint surfaces between the frames , adjustment rings , and cone section shall be free of dirt,
stones , debris and voids to ensure a watertight seal. Place flexible gasket joint material
along the inside and outside edge of each joint, or use trowelable material in lieu of pre-
formed gasket material. Position the butt joint of each length of joint material on opposite
sides of the manhole . No steel shims , wood , stones , or any material not specifically
accepted by the Enginee r may be used to obtain final surface elevation of the manhole
frame.
In paved areas or future paved areas, castings shall be installed by using a straight edge
not less than ten (10) feet long so that the top of the casting will conform to the slope and
finish elevation of the paved surface . The top of the casting shall be 1 /8 inch below the
finished elevation . Allowances for the compression of the joint material shall be made to
assure a proper final grade elevation.
3. EXPOSED EXTERIOR SURFACES: All exposed exterior surfaces shall be coated with
two mop coats of coal tar epoxy. Kopper "Bitumastic Super Service Black"; Tnemec "46-
450 Heavy Tnemecol ", or equal, to a minimum of 14 mils dry film thickness.
4. The exterior surface of all pre-cast section joints shall be thoroughly cleaned with a wire
brush and then waterproofed with a 1/2-inch thick coat of trowelable bitumastic joint
sealant from 6-inches below to 6-inches above the joint. The coated joint shall then be
wrapped with 6 mil plastic to protect the sealant from damage during backfilling .
C. MEASUREMENT AND PAYMENT: The price bid for new manhole installations shall include
all labor, equipment, and materials necessary for construction of the manhole including, but
not limited to, joint sealing , lift hole sealing and exterior surface coating. Payment shall not
include pavement replacement, which if required, shall be paid separately.
The price bid for reconstruct ion of existing manholes shall include all labor equipment and
materials necessary for const ruction of new manhole, including , but not limited to , excavation,
backfill , disposal of materials, joint sealing, lift hole sealing and exterior surface coating .
Payment shall not include pavement replacement, which if required, shall be paid separately .
The price bid for adjusting and/or sealing of existing manholes shall include all labor,
equipment and materials necessary for adjusting and/or sealing the manhole, including but
not limited to, joint sealing, lift hole sealing, and exterior surface coating.
Payment for concrete collars will be made per each. Payment for manhole inserts will be
made per each.
D-28 SANITARY SEWER SERVICES
Any reconnection , relocation, re-routes , replacement, or new sanitary sewer service shall be
required as shown on the plans , and/or as described in these Special Contact Documents in
addition to those located in the field and identified by the Engineer as active sewer taps . The
service connections shall be constructed . by the Contractor utilizing standard factory
manufactured tees . City approved factory manufactured saddle taps may be used, but only as
directed by the Engineer. The decision to use saddle taps as opposed to tees shall be made on a
case-by-case basis. The Contractor shall be responsible for coordinating the scheduling of
tapping crews with building owners and the Engineer in order that the work be performed in an
11129/04 SC-18
PART D -SPECIAL CONDITIONS
expeditious manner. A minimum of 24 hours advance notice shall be given when taps will be
required. Severed service connections shall be maintained as specified in section C6-6 .15 .
D. SEWER SERVICE RECONNECTION : When sewer service reconnection is called for the
Contractor shall vertically adjust the existing sewer service line as required for reconnection
and furnish a new tap. The fittings used for vertical adjustment shall consist of a maximum
bend of 45 degrees . The tap shall be located so as to line up with the service line and avoid
any horizontal adjustment. For open cut applications , all sanitary sewer service lines shall be
replaced to the property or easement line , or as directed by the Engineer. Sanitary sewer
services on sewers being rehabilitated using pipe enlargement methods shall be replaced to
the property or easement line or as directed by the Engineer. Procedures listed below for
Sewer Service Replacement shall be adhered to for the installation of any sewer service line
including the incidental four (4) feet of service line which is included in the price bid for
Sanitary Sewer Taps. Payment for work such as backfill, saddles, tees, fittings incidental four
(4) feet of service line and all other associated appurtenances required shall be included in
the price bid for Sanitary Sewer Taps.
E. SEWER SERVICE REPLACEMENT : All building sewer services encountered during
construction shall be adjusted and/or replaced by the Contractor as d irected by the Engineer
as required for the connection of the sewer service line. If the sewer service line is in such
condition or adjustment necessitates the replacement of the sewer service line, all work shall
be performed by a licensed plumber. The Engineer shall determine the length of the
replacement. All sewer services shall be installed at a minimum of two (2) percent slope or as
approved by the Engineer. For situations involving sewer service re-routing, whether on
public or private property, the City shall provide line and grade for the sewer service lines as
shown on the project plans . Prior to installing the applicable sewer main or lateral and the
necessary service lines , the Contractor shall verify (by de-holing at the building clean -out) the
elevations (shown on the plans) at the building clean-out and compare the data with the
elevation at the proposed connection point on the sewer main , in order to ensure that the two
(2) percent minimum slope (or as specified by the Engineer) requirement is satisfied .
Elevations shall also be verified at all bend locations on the service re-route . All applicable
sewer .mains, laterals and affected service lines that are installed without pre-construction de-
holing at the affected residences (to verify design elevations) shall be removed and replaced
as necessary at the Contractor's expense in the event grade conflicts are brought to light after
de-holing is conducted. All elevation information obtained by the Contractor shall be
submitted to the Inspector. The Engineer shall be immediately notified in the event that the
two (2) percent minimum slope is not satisfied . If the· Contractor determines that a different
alignment for the re-route is more beneficial than shown on the plans , the Contractor shall
obtain and submit all relevant elevation information for the new alignment to the Inspector and
shall be responsible for ensuring that the two (2) percent minimum grade (or as approved by
the Engineer) is satisfied . Prior to backfilling, the Contractor shall double check the grade of
the installed service line and submit signed documentation verifying that the line has been
installed as designed to the Engineer. The Contractor, at its sole expense, shall be required to
uncover any sewer service for which no grade verification has been submitted. All re-routes
that are not installed as designed or fail to meet the City code shall be reinstalled at the
Contractor's expense. The Contractor shall ensure that the service line is backfilled and
compacted in accordance with the City Plumbing Code . Connection to the existing sewer
service line shall be made with appropriate adapter fittings. The fitting shall be a urethane or
neoprene coupling A.S.T.M. C-425 with series 300 stainless steel compression straps. The
Contractor shall remove the existing clean-out and plug the abandoned sewer service line .
11/29/04 SC-19
PART D -SPECIAL CONDITIONS
The contractor shall utilize schedule 40 PVC for all sanitary sewer service re-routes or
relocations located on private property . Furthermore, the contractor shall utilize the services
of a licensed plumber for all service line work on private property . Permit(s) must be obtained
from the City of Fort Worth Development Department for all service line work on private
property and all work related to the service line must be approved by a City of Fort Worth
Plumbing Inspector. A copy of the plumbing permit shall be provided to the Engineer prior to
beginning work on the sanitary sewer service re-route and proof of final acceptance by the
Plumbing Inspector shall be provided to the Engineer upon completion of the sanitary sewer
re-route.
Payment for work and materials such as backfill , removal of existing clean-outs, plugging the
abandoned sewer service li ne, double checking the grade of the installed service line, pipe
fittings, surface restoration on private property (to match existing), and all other associated
work for service replacemen ts in excess of four (4) linear feet shall be included in the linear
foot price bid for sanitary sewer service line replacement on private property or public right of
way. Payment for all work and material involving the "tap" shall be included in the price bid for
sanitary sewer service taps .
D-29 REMOVAL, SALVAGE, AND ABANDONMENT OF EXISTING FACILITIES
Any removal , salvaging and/or abandonment of existing facilities will necessarily be required as
shown on the plans , and/or des c ribed in these Special Contract Documents in addition to those
located in the field and identified by the Engineer. This work shall be done in accordance with
Section E2-1 .5 Salvaging of Material and E2-2 . 7 Removing Pipe , of the . General Contract
Documents and Specifications , unless amended or superseded by requirements of this Special
Condition.
A. SALVAGE OF EXISTING WATER METER AND METER BOX: Existing water meter and
meter box shall be removed and returned to the Water Department warehouse by the
Contractor in accordance with Section E2-1.5 Salvaging of Materials.
B. SALVAGE OF EXISTING WATER METER AND CONCRETE VAULT LID: Existing water
meter and concrete vault lid shall be removed and returned to the Water Department
warehouse by the Contracto r in accordance with Section E2-1.5 Salvaging of Materials. The
concrete vault shall be demolished in place to a point not less than 18 inches below final
grade. The concrete vault shall then be backfilled and compacted in accordance with backfill
method as specified in Section E2-2.9 Backfill. Backfill material shall be suitable excavated
material approved by the Engineer. . Surface restoration shall be compatible with existing
surrounding surface and grade.
C. SALVAGE OF EXISTING FIRE HYDRANTS: Existing fire hydrants shall be removed and
returned to the Water Department warehouse by the Contractor in accordance with Section
E2-1.5 Salvaging of Materials . The void shall be backfilled and compacted in accordance with
backfill method as specifie d in Section E2-2 .9 Backfill. Backfill material shall be suitable
excavated material approved by the Engineer. Surface restoration shall be compatible with
existing surrounding surfa ce and grade.
D. SALVAGE OF EXISTING GATE VALVE: Existing gate valve and valve box and lid shall be
removed and returned to the Water Department warehouse by the Contractor in accordance
with Section E2-1 .5 Salvaging of Materials. The void area caused by the valve removal
shall be backfilled and compacted in accordance with backfill method as specified in Section
E2-2.9 Backfill. Backfill material shall be suitable excavated material approved by the
Engineer. Surface restorat ion shall be compatible with existing surrounding surface and
11/29/04 SC-20
PART D -SPECIAL CONDITIONS
grade . If the valve is in a concrete vault, the vault shall be demolished in place to a point no
less than 18" below final grade.
E . ABANDONMENT OF EXISTING GATE VALVE: Existing gate valve and box lid shall be
abandoned by first closing the valve to the fully closed position and demolishing the valve box
in place to a point not less than 18 inches below final grade. Concrete shall then be used as
backfill material to match existing grade.
F. ABANDONMENT OF EXISTING VAULTS : Vaults to be demolished in place shall have top
slab and lid removed and vault walls demolished to a point not less than 18" below final grade.
The void area caused shall then be backfilled and compacted in accordance with backfill
method as specified in Section E2-2.9 Backfill. Backfill material shall be suitable excavated
material approved by the Engineer. Surface restoration shall be compatible with the existing
surrounding grade .
G. ABANDONMENT OF MANHOLES: Manholes to be abandoned in place shall have all pipes
entering or exiting the structure plugged with lean concrete . Manhole top or cone section
shall be removed to the top of the full barrel diameter section , or to point not less than 18
inches below final grade. The structure shall then be backfilled and compacted in accordance
with backfill method as specified in Section E2-2 .9 Backfill . Backfill material may be either
clean washed sand of clean , suitable excavated material approved by the Engineer. Surface
restoration shall be compatible with surrounding service surface . Payment for work involved
in backfilling , plugging of pipe(s) and all other appurtenances required , shall be included in the
appropriate bid item -Abandon Existing Sewer Manhole.
H. REMOVAL OF MANHOLES: Manholes to be removed shall have all pipes entering or exiting
the structure disconnected . The complete manhole, including top or cone section , all full
barrel diameter section , and base section shall be removed. The excavation shall then be
backfilled and compacted in accordance with backfill method as specified in Section E2-2.9
Backfill. Backfill material may be with Type C Backfill or Type B Backfill, as approved by the
Engineer. Surface restoration shall be compatible with surrounding surface.
I. CUTTING AND PLUGGING EXISTING MAINS: At various locations on this project, it may be
required to cut, plug, and block existing water mains/services or sanitary sewer
mains/services in order to abandon these lines. Cutting and plugging existing mains and/or
services shall be considered as incidental and all costs incurred will be considered to be
included in the linear foot bid price of the pipe, unless separate trenching is required.
J. REMOVAL OF EXISTING PIPE: Where removal of the existing pipe is required , it shall be the
Contractor's responsibility to properly dispose of all removed pipe. All removed valves, fire
hydrants and meter boxes shall be delivered to Water Department Field Operation, Storage
Yard.
C. PAYMENT: Payment for all work and material involved in salvaging, abandoning and/or
removing existing facilities shail be included in the linear foot bid price of the pipe, except as
follows : separate payment will be made for removal of all fire hydrants , gate valves 16 inch
and larger, and sanitary sewer manholes, regardless of location .
Payment will be made for salvaging , abandoning and/or removing all other existing facilities
when said facility is not being replaced in the same trench (i.e., when removal requires a
separate trench).
11129/04 SC-21
PART D -SPECIAL CONDITIONS
L. ABANDONMENT OF EXISTING SEWER LINES: Where pians call for abandonment of
existing sewer mains after the construction of a new sewer main, the Contractor shall be
responsible for TV inspection of 100% of the existing sewer main to be abandoned to make a
final determination that all existing service connections have been relocated to the new main.
Once this determination has been made, the existing main will be abandoned as indicated
above in Item I.
D-30 DETECTABLE WARNING TAPES
Detectable underground utility warning tapes which can be located from the surface by a pipe
detector shall be installed directly above non-metallic water and sanitary sewer pipe. The
detectable tape shall be "Detect Tape" manufactured by Allen Systems, Inc . or approved equal,
and shall consist of a minimum thickness 0.35 mils solid aluminum foil encased in a protective
inert plastic jacket that is imperv ious to all known alkalis, acids, chemical reagents and solvents
found in the soil. The minimum overall thickness of the tape shall be 5 .5 mils, and the width shall
not be less than two inches with a minimum unit weight of 2~ pounds/1 inch/100'. The tape shall
be color coded and imprinted with the message as follows:
Type of Utility Color Code
Water Safety Blue
Sewer Safety Green
Legends
Caution! Buried Water Line Below
Caution! Buried Sewer Line Below
Installation of detectable tapes shall be per manufacturer's recommendations and shall be as
close to the grade as is practical for optimum protection and detectability. Allow a minimum of 18
inches between the tape and the pipe. Payment for work such as backfill, bedding, blocking,
detectable tapes, and all other associated appurtenances required shall be included in the unit
·price bid for the appropriate bid item(s).
D-31 PIPE CLEANING
Joints shall be wiped and then inspected for proper installation by the inspectors. Each joint shall
be swept daily and kept clean during installation . A temporary night plug shall be installed on all
exposed pipe ends during any period of work stoppage .
D-32 DISPOSAL OF SPOIUFILL MATERIAL
Prior to the disposing of any spoil/fill material, the Contractor shall advise the Director of
Engineering Department, acting as the City of Fort Worth's Flood Plain Administrator
("Administrator"), of the location of all sites where the Contractor intends to dispose of such
material. Contractor shall not dispose of such material until the proposed sites have been
determined by the Administrator to meet the requirements of the Flood Plain Ordinances of the
City of Fort Worth (Ordinance No. 10056). All disposal sites must be approved by the
Administrator to ensure that filling is not occurring within a floodplain without a permit. A floodplain
permit can be issued upon approval of necessary Engineering studies. No fill permit is required if
disposal sites are not in a floodplain . Approval of the Contractor's disposal sites shall be
evidenced by a letter signed by the Administrator stating that the site is not in a known flood plain
or by a Flood Plain Fill Permit authorizing fill within the flood plain. Any expenses associated with
obtaining the fill permit, including any necessary Engineering studies, shall be at the Contractor's
expense . In the event that the Contractor disposes of spoil/fill material at a site without a fill
permit or a letter from the administrator approving the disposal site, upon notification by the
Director of Engineering Department, Contractor shall remove the spoil/fill material at its expense
and dispose of such materials in accordance with the Ordinances of the City and this section.
11/29/04 SC-22
PART D -SPECIAL CONDITIONS
D-33 MECHANICS AND MATERIALMEN'S LIEN
The Contractor shall be required to execute a release of mechanics and material men's liens
upon receipt of payment.
D-34 SUBSTITUTIONS
The specifications for materials set out the minimum standard of quality, which the City believes
necessary to procure a satisfactory project. No substitutions will be permitted until the Contractor
has received written permission of the Engineer to make a substitution for the material, which has
been specified . Where the term "or equal", or "or approved equal" is used, it is understood that if
a material, product, or piece of equipment bearing the name so used is furnished, it will be
approvable, as the particular trade name was used for the purpose of establishing a standard of
quality acceptable to the City. If a product of any other name is proposed for use, the Engineer's
approval thereof must be obtained before the Contractor procures the proposed substitute.
Where the term "or equal", or "or approved equal" is not used in the specifications, this does not
necessarily exclude alternative items or material or equipment which may accomplish the
intended purpose. However, the Contractor shall have the full responsibility of proving that the
proposed substitution is , in fact, equal, and the Engineer, as the representative of the City, shall
be the sole judge of the acceptability of substitutions. The provisions of this sub-section as
related to "substitutions" shall be applicable to all sections of these specifications.
D-35 PRE-CONSTRUCTION TELEVISION INSPECTION OF SANITARY SEWER
A. GENERAL: Prior to the reconstruction, ALL sections of existing sanitary sewer lines to be
abandoned , removed (except where being replaced in the same location), or rehabilitated
(pipe enlargement, cured-in-place pipe, fold and form pipe, slip-line, etc.), shall be cleaned,
and a television inspection performed to identify any active sewer service taps, other sewer
laterals and their location. Work shall consist of furnishing all labor, material, and equipment
necessary for the cleaning and inspection of the sewer lines by means of closed circuit
television . Satisfactory precautions shall be taken to protect the sewer lines from damage that
might be inflicted by the improper use of cleaning equipment.
1. HIGH VELOCITY JET (HYDROCLEANING) EQUIPMENT: The high-velocity sewer line
cleaning equipment shall be constructed for easy and safe operation. The equipment
shall also have a selection of two or more high-velocity nozzles. The nozzles shall be
capable of producing a scouring action from 15 to 45 degrees in all size lines designated
to be cleaned . Equipment shall also include a high-velocity gun for washing and scouring
manhole walls and floor. The gun shall be capable of producing flows from a fine spray to
a solid stream. The equipment shall carry its own water tank, auxiliary engines, pumps,
and hydraulically driven hose reel.
Hydraulically Propelled Equipment shall be of a movable dam type and be constructed in
such a way that a portion of the dam may be collapsed at any time during the cleaning
operation to protect against flooding of the sewer. The movable dam shall be equal in
diameter around the outer periphery to ensure removal of grease. If sewer cleaning balls
or other equipment, which cannot be collapsed, is used, special precautions to prevent
flooding of the sewers and public or private property shall be taken . The flow of sewage
present in the sewer lines shall be utilized to provide necessary fluid for hydraulic cleaning
devices whenever possible.
2. CLEANING PROCEDURES: The designated sewer manholes shall be cleaned using
high-velocity jet equipment. The equipment shall be capable of removing dirt, grease,
11129/04 SC-23
PART D -SPECIAL CONDITIONS
rocks, sand, and other materials and obstructions from the sewer lines and manholes. If
cleaning of an entire section cannot be successfully performed from one manhole, the
equipment shall be set up on the other manhole and cleaning again attempted. If, again,
successful cleaning cannot be performed or equipment fails to traverse the entire manhole
section, it will be assumed that a major blockage exists, and the cleaning effort shall be
abandoned. When additional quantities of water from fire hydrants are necessary to avoid
delay in normal working procedures, the water shall be conserved and not used
unnecessarily. No fire hydrant shall be obstructed in case of a fire in the area served by
the hydrant. Before using any water from the City Water Distribution System, the
Contractor shall apply for and receive permission from the Water Department. The
Contractor shall be responsible for the water meter and related charges for the setup,
including the water usage bill. All expenses shall be considered incidental to cleaning.
3. DEBRIS REMOVAL AND DISPOSAL: All sludge, dirt, sand, rock, grease, and other solid
or semisolid material resulting from the cleaning operation shall be removed at the
downstream manhole of the section being cleaned. Passing material from manhole
section to manhole section, which could cause line stoppages, accumulations of sand in
wet wells, or damage pumping equipment, shall not be permitted.
4 . All solids or semisolid resulting from the cleaning operations shall be removed from the
site and disposed of at a site designated by the Engineer. All materials shall be removed
from the site no less often than at the end of each workday and disposed of at no
additional cost to the City.
5. UNDER NO CIRCUMSTANCE SHALL SEWAGE OR SOLIDS REMOVED THEREFROM
BE DUMPED ONTO STREETS OR INTO DITCHES, CATCH BASINS, STORM DRAINS
OR SANITARY SEWER MANHOLES .
6. TELEVISION INSPECTION EQUIPMENT: The television camera used for the inspection
shall be one specifically designed and constructed for such inspection. Lighting for the
camera shall be suitable to allow a clear picture of the entire periphery of the pipe. The
camera shall be operative in 100% humidity conditions. The camera, television monitor,
and other components of the video system shall be capable of producing picture quality to
the satisfaction of the Engineer; and if unsatisfactory, equipment shall be removed and no
payment will be made for an unsatisfactory inspection .
B. EXECUTION:
1. TELEVISION INSPECTION: The camera shall be moved through the line in either
direction at a moderate rate, stopping when necessary to permit proper documentation of
any sewer service taps . In no case will the television camera be pulled at a speed greater
than 30 feet per minute. Manual winches, power winches, TV cable, and powered rewinds
or other devices that do not obstruct the camera view or interfere with proper
documentation shall be used to move the camera through the sewer line.
11/29/04
When manually operated winches are used to pull the television camera through the line,
telephones or other suitable means of communications shall be set up between the two
manholes of the section being inspected to ensure good communications between
members of the crew.
SC-24
PART D -SPECIAL CONDITIONS
The importance of accurate distance measurements is emphasized . All television
inspection videotapes shall have a footage counter. Measurement for location of sewer
service taps shall be above ground by means of meter device. Marking on the cable, or
the like , which would require interpolation for depth of manhole , will not be allowed .
Accuracy of the distance meter shall be checked by use of a walking meter, roll-a-tape, or
other suitable device, and the accuracy shall be satisfactory to the Engineer.
The City makes no guarantee that all of the sanitary sewers to be entered are clear for the
passage of a camera. The methods used for securing passage of the camera are to be at
the option of the Contractor. The cost of retrieving the Television camera , under all
circumstances , when it becomes lodged during inspection, shall be incidental to Television
inspection .
2. DOCUMENTATION : Television Inspection Logs : Printed location records shall be kept by
the Contractor and will clearly show the location in relation to an adjacent manhole of each
sewer service taps observed during inspection. In addition, other points of significance
such as locations of unusual conditions, roots, storm sewer connections, broken pipe,
presence of scale and corrosion, and other discernible features will be recorded, and a
copy of such records will be supplied to the City.
3. PHOTOGRAPHS: Instant developing, 35 mm, or other standard-size photographs of the
television picture of problems shall be taken by the Contractor upon request of the
Engineer, as long as such photographing does not interfere with the Contractor's
operations .
4 . VIDEOTAPE RECORDINGS: The purpose of tape recording shall be to supply a visual
and audio record of problem areas of the lines that may be replayed. Video tape
recording playback shall be at the same speed that it was recorded . The television tapes
shall be furnished to the City for review immediately upon completion of the television
inspection and may be retained a maximum of 30 calendar days .
Equipment shall be provided to the City by the Contractor for review of the tapes . The
Engineer will return tapes to the Contractor upon completion of review. Tapes shall not be
erased without the permission of the Engineer. If the tapes are of such poor quality that
the Engineer is unable to evaluate the condition of the sewer line or to locate service
connections, the Contractor shall be required to re-televise and provide a good tape of the
line at no additional cost to the City. If a good tape cannot be provided of such quality that
can be reviewed by the Engineer, no payment for televising this portion shall be made.
Also, no payment shall be made for portions of lines not televised or portions where
manholes cannot be negotiated with the television camera.
THE TAPES SHALL BE SUBMITTED TO THE ENGINEER PRIOR TO CONSTRUCTION
FOR REVIEW AND DETERMINATION OF SAGS . Upon completion of review of the
tapes by the Engineer, the Contractor will be notified as to which sections of the sanitary
sewer are to be corrected. The Engineer will return tapes to the Contractor upon
completion of review.
All costs associated with this work shall be incidental to unit prices bid for items under
Television Inspection of the Proposal.
C. PAYMENT OF CLEANING AND PRE-CONSTRUCTION TELEVISION INSPECTION OF
SANITARY SEWERS: The cost for Pre-Construction Cleaning and Television Inspection of
11129104 SC-25
PART D -SPECIAL CONDITIONS
sanitary sewers shall be pe r linear foot of sewer actually televised. The Contractor shall
provide the Engineer with tapes of a quality that the particular piece of sewer can be readily
evaluated as to existing sewer conditions and for providing appropriate means for review of
the tapes by the Engineer including collection and removal, transportation and disposal of
sand and debris from the sewers to a legal dump site.
Television inspection shall include necessary cleaning (hydraulic jet or mechanical cleaner) to
provide video image required for line analysis .
The primary purpose of cleaning is for television inspection and rehabilitation ; when a portion
of a line is not or cannot be televised or rehabilitated, the cleaning of that portion of line shall
be incidental and no paymen t shall be made.
The City makes no guarantee that all of the sanitary sewers to be entered are clear for the
passage of a camera. The methods used for securing passage of the camera are to be at the
option of the Contractor, and the costs must be included in the bid price for TV Inspections .
The cost of retrieving the TV Camera , under all circumstances, when it becomes lodged
during inspection , shall be incidental to TV Inspection .
The item shall also include all costs of installing and maintaining any bypass pumping
required to provide reliable , regular sewer service to the area residents. All bypa·ss pumping
shall be incidental to the project.
D-36 VACUUM TESTING OF SANITARY SEWER MANHOLES
D. GENERAL: This item shall govern the vacuum testing of all newly constructed sanitary sewer
manholes .
8. EXECUTION:
1. TEST PROCEDURE: Manholes shall be vacuum tested prior to any interior grouting with
all connections in place. Lift holes shall be plugged, and all drop-connections and gas
sealing connections shall be installed prior to testing.
11/29/04
The sewer lines entering the manhole shall be plugged and braced to prevent the plugs
from being drawn into the manhole. The plugs shall be installed in the lines beyond the
drop-connections , gas sealing connections, etc. The test head shall be placed inside the
frame at the top of the manhole and inflated in accordance with the manufacturer's
recommendations. A vacuum of ten inches of mercury (10"Hg) shall be drawn and the
vacuum pump will be turned off. With the valve closed, the level of vacuum shall be read
after the required test time. The required test time shall be determined from the Table I
below in accordance with ASTM C1244-93:
SC-26
PART D -SPECIAL CONDITIONS
Table I
MINIMUM TIME REQUIRED FOR VACUUM DROP
OF 1" Hg (1 O"Hg -9"Hg) (SEC)
Depth of MH. 48-lnch Dia. 60-lnch Dia.
(FT.) Manhole Manhole
0 to 16' 40 sec . 52 sec .
18 ' 45 sec. 59 sec.
20' 50 sec. 65 sec.
22' 55 sec . 72 sec.
24' 59 sec . 78 sec.
26' 64 sec. 85 sec.
28' 69 sec. 91 sec.
30' 74 sec. 98 sec.
For Each 5 sec. 6 sec.
Additional 2'
1. ACCEPTANCE : The manhole shall be considered acceptable, if the drop in the level of
vacuum is less than one-inch of mercury (1" Hg) after the required test time. Any
manhole, which fails to pass the initial test , must be repaired by either pressure grouting
through the manhole wall or digging to expose the exterior wall of the manhole in order to
locate the leak and seal it with an epoxy sealant. The manhole shall be retested as
described above until it has successfully passed the test.
Following completion of a successful test, the manhole shall be restored to its normal
condition, all temporary plugs shall be removed, all braces, equipment, and debris shall be
removed and disposed of in a manner satisfactory to the Engineer.
C. PAYMENT: Payment for vacuum testing of sanitary sewer manholes shall be paid at the
contract price per each vacuum test. This price shall include all material, labor, equipment,
and all incidentals , including all bypass pumping , required to complete the test as specified
herein .
D-37 BYPASS PUMPING
The Contractor shall bypass the sewage around the section or sections of sewer to be
rehabilitated and/or replaced. The bypass shall be made by plugging existing upstream manhole
and pumping the sewage into a downstream manhole or adjacent system or other method as may
be approved by the Engineer. The pump and bypass lines shall be of adequate capacity and size
to handle the flow without sewage backup occurring to facilities connected to the sewer.
Provisions shall be made at driveways and street crossings to perm it safe vehicular travel without
interrupting flow in the bypass system . Under no circumstances will the Contractor be permitted
to discharge sewage into the trenches. Payment shall be incidental to rehabilitation or
replacement of the sewer line.
11/29/04 SC-27
PART D -SPECIAL CONDITIONS
D-38 POST-CONSTRUCTION TELEVISION INSPECTION OF SANITARY SEWER
A. GENERAL: After construction, ALL sections of sanitary sewer lines shall have a television
inspection performed by an independent sub-Contractor hired by the prime Contractor.
Work shall consist of furnishing all labor, material, and equipment necessary for inspection of
the sewer lines by means of closed circuit television. Satisfactory precautions shall be taken
to protect the sewer lines from damage that might be inflicted by the improper use of cleaning
equipment.
B . TELEVISION INSPECTION EQUIPMENT: The television camera used for the inspection
shall be one specifically designed and constructed for such inspection. Lighting for the
camera shall be operative in 100% humidity conditions . The camera , television monitor, and
other components of the video system shall be capable of producing picture quality to the
satisfaction of the Engineer; and if unsatisfactory, equipment shall be removed and no
payment will be made for an unsatisfactory inspection .
C. EXECUTION:
1. TELEVISION INSPECTION : The camera shall be moved through the line in either
direction at a moderate rate , stopping when necessary to permit proper documentation of
any sewer service taps . In no case will the television camera be pulled at a speed greater
than 30 feet per minute. Manual winches , power winches, TV cable, and powered rewinds
or other devices that do not obstruct the camera view or interfere with proper
documentation shall be used to move the camera through the sewer line . No more than
2000 linear feet of pipe will be televised at one time for review by the Engineer.
When manually operated winches are used to pull the television camera through the line,
telephones or other suitable means of communications shall be set up between the two
manholes of the section being inspected to ensure good communications between
members of the crew .
The importance of accurate distance measurements is emphasized. All television
inspection video tapes shall have a footage counter. Measurement for location of sewer
service taps shall be above ground by means of meter device . Marking on the cable, or
the like, which would require interpolation for depth of manhole, will not be allowed.
Accuracy of the distance meter shall be checked by use of a walking meter, roll-a-tape, or
other suitable device , and the accuracy shall be satisfactory to the Engineer.
The City makes no guara ntee that all of the sanitary sewers to be entered are clear for the
passage of a camera. The methods used for securing passage of the camera are to be at
the option of the Contractor. The cost or retrieving the Television camera, under all
circumstances , when it becomes lodged during inspection , shall be incidental to Television
inspection.
Sanitary sewer mains must be laced with enough water to fill all low pints. The television
inspection must be done immediately following the lacing of the main with no water flow. If
sewer is active, flow must be restricted to provide a clear image of sewer being inspected .
2. DOCUMENTATION: Television Inspection Logs: Printed location records shall be kept by
the Contractor and will clearly show the location in relation to an adjacent manhole of each
sewer service tap observed during inspection . All television logs shall be referenced to
stationing as shown on the plans . A copy of these television logs will be supplied to the
City.
11/29/04 SC-28
PART D -SPECIAL CONDITIONS
3. PHOTOGRAPHS: Instant developing, 35 mm, or other standard-size photographs of the
television picture of problems shall be taken by the Contractor upon request of the
Engineer, as long as such photographing does not interfere with the Contractor's
operations.
4. VIDEOTAPE RECORDINGS: The purpose of tape recording shall be to supply a visual
and audio record of problem areas of the lines that may be replayed . Video tape
recording playback shall be at the same speed that it was recorded. The television tapes
shall be furnished to the City for review immediately upon completion of the television
inspection and may be retained a maximum of 30 calendar days . Equipment shall be
provided to the City by the Contractor for review of the tapes. Tapes will be returned to
the Contractor upon completion of review by the Engineer. Tapes shall not be erased
without the permission of the Engineer.
If the tapes are of such poor quality that the Engineer is unable to evaluate the condition of
the sewer line or to locate service connections. the Contractor shall be required to re-
televise and provide a good tape of the line at no additional cost to the City . If a good tape
cannot be provided of such quality that can be reviewed by the Engineer, no payment for
televising this portion shall be made. Also, no payment shall be made for portions of lines
not televised or portions where manholes cannot be negotiated with the television camera.
D. PAYMENT OF POST-CONSTRUCTION TELEVISION INSPECTION OF SANITARY
SEWERS: The cost for post-construction Television Inspection of sanitary sewers shall be
per linear foot of sewer televised. The Contractor shall provide the Engineer with tapes of a
quality that the particular piece of sewer can be readily evaluated as to sewer conditions and
for providing appropriate means for review of the tapes by the Engineer.
Television inspection shall include necessary clean ing (hydraulic jet or mechanical cleaner) to
provide video image required for line analysis . The quantity of TV inspection shall be
measured as the total length of new pipe installed . All costs associated with this work shall be
included in the appropriate bid item -Post-Construction Television Inspection.
The item shall also include all costs of installing and maintaining any bypass pumping
required to provide reliable, regular sewer service to the area residents . All bypass pumping
shall be incidental to the project.
D-39 SAMPLES AND QUALITY CONTROL TESTING
A. The Contractor shall furnish, at its own expense , certifications by a private laboratory for all
materials proposed to be used on the project, including a mix design for any asphaltic and/or
Portland cement concrete to be used, and gradation analysis for sand and crushed stone to
be used along with the name of the pit from which the material was taken. The contractor
shall provide manufacturer's certifications for all manufactured items to be used in the project
and will bear any expense related thereto .
B. Tests of the design concrete mix shall be made by the contractor's laboratory at least nine
days prior to the placing of concrete using the same aggregate , cement , and mortar which are
to be used later in the concrete . The Contractor shall provide a certified copy of the test
results to the City.
C. Quality control testing of in-place material on this project will be performed by the city at its
own expense . Any retesting required as a result of failure of the material to meet project
specifications will be at the expense of the contractor and will be billed at commercial rates as
11129/04 SC-29
PART D -SPECIAL CONDITIONS
determined by the City. The failure of the City to make any tests of materials shall in no way
relieve the contractor of its responsibility to furnish materials and equipment conforming to the
requirements of the contract.
D. Not less than 24 hours notice shall be provided to the City by the Contractor for operations
requiring testing. The Contractor shall provide access and trench safety system (if required)
for the site to be tested, and any work effort involved is deemed to be included in the unit price
for the item being tested .
E. The Contractor shall provide a copy of the trip ticket for each load of fill material delivered to
the job site. The ticket shall specify the name of the pit supplying the fill material.
D-40 TEMPORARY EROSION , SEDIMENT, AND WATER POLLUTION CONTROL (FOR
DISTURBED AREAS LESS THAN 1 ACRE)
A. DESCRIPTION: This item shall consist of temporary soil erosion sediment and water pollution
control measures de~med necessary by the Engineer for the duration of the contract. These
control measures shall at no time be used as a substitute for the permanent control measures
unless otherwise directed by the Engineer and they shall not include measures taken by the
CONTRACTOR to control conditions created by his construction operations. The temporary
measures shall include dikes, dams, berms, sediment basins, fiber mats, jute netting,
temporary seeding, straw mulch , asphalt mulch, plastic liners, rubble . liners, baled-hay retards,
dikes , slope drains and other devices.
B. CONSTRUCTION REQUIREMENTS: The Engineer has the authority to define erodible earth
and the authority to limit the surface area of erodible-earth material exposed by preparing
right-of-way, clearing and grubbing, the surface area of erodible-earth material exposed by
excavation, borrow and to direct the CONTRACTOR to provide temporary pollution-control
measures to prevent contamination of adjacent streams, other water courses, lakes, ponds or
other areas of water impoundment. Such work may involve the construction of temporary
berms, dikes, dams, sediment basins, slope drains and use of temporary mulches, mats,
seeding, or other control devices or methods directed by the Engineer as necessary to control
soil erosion. Temporary pollution-control measures shall be used to prevent or correct
erosion that may develop during construction prior to installation of permanent pollution
control features, but are not associated with permanent control features on the project. The
Engineer will limit the area of preparing right-of-way, clearing and grubbing, excavation and
borrow to be proportional to the CONTRACTOR'S capability and progress in keeping the
finish grading, mulching, seeding, and other such permanent pollution-control measures .
current in accordance with the accepted schedule . Should seasonal conditions make such
limitations unrealistic, temporary soil-erosion..:control measures shall be performed as directed
by the Engineer.
2 . Waste or disposal areas and construction roads shall be located and constructed in a
manner that will minimize the amount of sediment entering streams .
3. Frequent fordings of live streams will not be permitted; therefore, temporary bridges or
other structures shall be used wherever an appreciable number of stream crossings are
necessary. Unless otherwise approved in writing by the Engineer, mechanized equipment
shall not be operated in live streams.
4. When work areas or material sources are located in or adjacent to live streams, such
areas shall be separated from the stream by a dike or other barrier to keep sediment from
11/29/04 SC-30
PART D -SPECIAL CONDITIONS
entering a flowing stream. Care shall be taken during the construction and removal of
such barriers to minimize the muddying of a stream.
5. All waterways shall be cleared as soon as practicable of false work, piling, debris or other
obstructions placed during construction operations that are not a part of the finished work .
6 . The Contractor shall take sufficient precautions to prevent pollution of streams, lakes and
reservoirs with fuels, oils , bitumen, calcium chloride or other harmful materials . He shall
conduct and schedule his operations so as to avoid or minimize siltation of streams, lakes
and reservoirs and to avoid interference with movement of migratory fish. ·
C. MEASUREMENT AND PAYMENT : All work, materials and equipment necessary to provide
temporary erosion control shall be considered subsidiary to the contract and no extra pay will
be given for this work .
D-41 INGRESS AND EGRESS/OBSTRUCTION OF ACCESS TO DRIVES
The Contractor shall provide ingress and egress to the property being crossed by this
construction and adjacent property when construction is not in progress and at night. Drives shall
be left accessible at night, on weekends , and during holidays. The Contractor shall conduct his
activities to minimize obstruction of access to drives and property during the progress of
construction. Notification shall be made to an owner prior to his driveway being removed and/or
rebuilt.
D-42 PROTECTION OF TREES, PLANTS AND SOIL
All property along and adjacent to the Contractors' operations including lawns, yards, shrubs,
trees, etc., shall be preserved or restored after completion of the work, to a condition equal to or
better than existed prior to start of work .
Any trees or other landscape features scarred or damaged by the Contractor's operations shall be
restored or replaced at the Contractor's expense. Trimming or pruning to facilitate the work will
be permitted only by experienced workmen in an approved manner (No trimming or pruning
without the property owners ' consent). Pruned limbs of 1" diameter or larger shall be thoroughly
treated as soon as possible with a tree wound dressing.
By ordinance, the Contractor must obtain a permit from the City Forester before any work
(tdmming, removal, or root pruning) can be done on trees or shrubs growing on public property
including street Rights-of-Ways and designated alleys. This permit can be obtained by calling the
Forestry Office at 871-5738. All tree work shall be in compliance with pruning standards for Class
II Pruning as described by the National Arborist Association . A copy of these standards can be
provided by calling the above number. Any damage to public trees due to negligence by the
Contractor shall be assessed using the current formula for Shade Tree Evaluation as defined by
the International Society of Arboriculture. Payment for negligent damage to public trees shall be
made to the City of Fort Worth and may be withheld from funds due the Contractor by the City.
To prevent the spread of the Oak Wilt fungus, all wounds on Live Oak and Red Oak trees shall be
immediately sealed using a commercial pruning paint.
No separate payment will be made for any of the work involved for this item and all costs incurred
will be considered a subsidiary cost of the project.
11129/04 SC -31
PART D -SPECIAL CONDITIONS
D-43 SITE RESTORATION
The contractor shall be responsible for restoring the site to original grade and condition after
completion of his operations subject to approval of the Engineer. The basis for approval by the
Engineer will be grade restoration to plus minus one-tenth (0 .1) of a foot.
D-44 CITY OF FORT WORTH STANDARD PRODUCT LIST
Proposed products subm itted in the bid documents must appear in the latest "City of Fort Worth
Standard Product List, for the bid to be considered responsive . Products and processes listed in
the "City of Fort Worth Standard Product List shall be considered to meet City of Fort Worth
minimum technical requirements .
D-45 TOPSOIL, SODDING, SEEDING & HYDROMULCHING
This item shall be performed in accordance with the City of Fort Worth Parks arid Community
Services Department Specifications for Topsoil, Sodding and Seeding .
1. TOPSOIL
DESCRIPTION: This item will consist of furnishing and placing a minimum of six (6) inches of
topsoil, free from rock and foreign material , in all parkways and medians to the lines and
grades as establ ished by the Engineer.
CONSTRUCTION METHODS: Topsoil will be secured from borrow sources as required to
supplement material secured from street excavation . All excavated materials from streets
which is suitable for topsoil will be used in the parkways and medians before any topsoil is
obtained from a borrow so u rce . Topsoil material secured from street excavation shall be
stockpiled at locations approved by the Engineer, and at completion of grading and paving
operations , topsoil shall be placed on parkway areas so as to provide a minimum six (6)
inches of compacted depth of topsoil parkways.
2. SODDING
DESCRIPTION : Sodding will cons ist of furnishing and planting Bermuda, Buffalo or St.
Augustine grass in the areas between the curbs and walks, on terraces, in median strips, on
embankments or cut slopes, or in such areas as designated on the Drawings and in
accordance with the requirements of this Specification . Recommended Buffalo grass varieties
for sodding are Prairie and 609.
MATERIALS: Sod shall consist of live and growing Bermuda, Buffalo or St. Augustine grass
secured from sources where the soil is fertile. Sod to be placed during the dormant state of
these grasses shall be alive and acceptable. Bermuda and Buffalo grass sod shall have a
healthy, virile root system of dense , thickly matted .roots throughout a two (2) inch minimum
thickness of native soil attached to the roots. St. Augustine grass sod shall have a healthy,
virile root system of dense, t h ickly matted roots throughout a one (1) inch minimum thickness
of native soil attached to the roots.
The sod shall be free from obnoxious weeds or other grasses and shall not contain any matter
deleterious to its growth or which might affect its subsistence or hardiness when transplanted.
Sod to be placed between curb and walk and on terraces shall be the same type grass as
adjacent grass or existing lawn.
11129/04 SC-32
PART D -SPECIAL CONDITIONS
Care shall be taken at all times to retain native soil on the roots of the sod during the process
of excavating, hauling, and planting. Sod material shall be kept moist from the time it is dug
until planted. When so directed by the Engineer, the sod existing at the source shall be
watered to the extent required prior to excavating. Sod material shall be planted within three
days after it is excavated.
CONSTRUCTION METHODS: After the designated areas have been completed to the lines,
grades, and cross-sections shown on the Drawings and as provided for in other items of the
contract, sodding of the type specified shall be performed in accordance with the
requirements hereinafter described. Sodding shall be either "spot" or "block"; either Bermuda,
Buffalo or St. Augustine grass .
a. Spot Sodding
Furrows parallel to the curb line or sidewalk lines, twelve (12) inches on centers or to the
dimensions shown on the Drawings, shall be opened on areas to be sodded. In all
furrows, sod approximately three (3) inches square shall be placed on twelve (12) inch
centers at proper depth so that the top of the sod shall not be more than one-half (1/2)
inch below the finished grade. Holes of equivalent depth and spacing may be used
instead of furrows. The soil shall be firm around each block and then the entire sodded
area shall be carefully rolled with a heavy, hand roller developing fifteen (15) to twenty-five
(25) pounds per square inch compression. Hand tamping may be required on terraces.
b. Block Sodding.
At locations on the Drawings or where directed, sod blocks shall be carefully placed on the
prepared areas. The sod shall be so placed that the entire designated area shall be
covered, and any voids left in the block sodding shall be filled with additional sod and
tamped. The entire sodded area shall be rolled and tamped to form a thoroughly compact
solid mass. Surfaces of block sod, which, in the opinion of the Engineer, may slide due to
the height or slope of the surface or nature of the soil, shall,. upon direction of the
Engineer, be pegged with wooden pegs driven through the sod block to the firm earth,
sufficiently close to hold the block sod firmly in place.
When necessary, the sodded areas shall be smoothed after planting has been completed
and shaped to conform to the cross-section previously provided and existing at the time
sodding operations were begun. Any excess dirt from planting operations shall be spread
uniformly over the adjacent areas or disposed of as directed by the Engineer so that the
completed surface will present a sightly appearance .
The sodded areas shall be thoroughly watered immediately after they are planted and
shall be subsequently watered at such times and in a manner and quantity directed by the
Engineer until completion and final acceptance of the project by the City of Fort Worth.
3. SEEDING
DESCRIPTION: "Seeding" will consist of preparing ground, providing and planting seed or a
mixture of seed of the kind specified along and across such areas as may be designated on
the Drawings and in accordance with these Specifications.
MATERIALS:
11129/04 SC-33
PART D -SPECIAL CONDITIONS
a. General. All seed used must carry a Texas Testing Seed label showing purity and
germination , name, type of seed, and that the seed meets all requirements of the Texas
Seed Law. Seed furnished shall be of the previous season's crop and the date of analysis
shown on each tag shall be within nine (9) months of time of delivery to the project. Each
variety of seed shall be furnished and delivered in separate bags or containers. A sample
of each variety of seed shall be furnished for analysis and testing when directed by the
Engineer.
The specified seed shall equal or exceed the following percentages of Purity
germination :
Common Name Purity Germination
Common Bermuda Grass 95% 90%
Annual Rye Grass 95% 95%
Tall Fescue 95% 90%
Western Wheatgrass 95% 90%
Buffalo Grass Varieties
Top Gun 95% 90%
Cody 95% 90%
Table 120.2.(2)a.
URBAN AREA WARM-SEASON SEEDING RATE (lbs .); Pure Live Seed {PLS)
Dates
Feb 1
to
May 1
Mixture for Clay or Tight Soils
(Eastern Sections)
Bermudag rass 40
Buffalograss 60
(Western Sections)
Buffalograss 80
Bermudagrass 20
Total: 100 Total : 100
Table, 120.2.(2)b
Mixture for
Sandy Soils
(All Sections)
Bermudagrass 60
Buffalograss 40
Total: 100
TEMPORARY COOL-SEASON SEEDING RA TE; (lb.) Pure Live Seed (PLS)
Dates (All Sections)
Aug 15 Tall Fescue 50
to Western Wheatgrass 50
May 1 Annual Rye 50
Total: 100
and
CONSTRUCTION METHODS : After the designated areas have been completed to the lines,
grades, and cross-sections shown on the Drawings and as provided for in other items of this
Contract, seeding of the type specified shall be performed in accordance with the
requirements hereinafter described.
a . Watering . Seeded areas shall be watered as directed by the Engineer so as to prevent
washing of the slopes or dislodgment of the seed .
b. Finishing. Where applicable , the shoulders , slopes , and ditches shall be smoothed after
seed bed preparation has been completed and shaped to conform to the cross-section
previously provided and existing at the time planting operations were begun .
11/29/04 SC-34
PART D -SPECIAL CONDITIONS
BROADCAST SEEDING : The seed or seed mixture in the quantity specified shall be uniformly
distributed over the areas shown on the Drawings and where directed. If the sowing of seed
is by hand, rather than by mechanical methods, the seed shall be sown in two directions at
right angles to each other. Seed and fertilizer shall be distributed at the same time provided
the specified uniform rate of application for both is obtained . "Finishing" as specified in
Section D-45, Construction Methods , is not applicable since no seed bed preparation is
required.
DISCED SEEDING: Soil over the area shown on the Drawings as directed to be seeded shall
be loosened to a minimum depth of three (3) inches and all particles in the seed bed shall be
reduced to less than one (1) inch in diameter or they shall be removed. The area shall then
be finished to line and grade as specified under "Finishing" in Section D-45 , Construction
Methods .
The seed , or seed mixture, specified shall then be planted at the rate required and the
application shall be made uniformly . If the sowing of seed is by hand rather than by
mechanical methods, seed shall be raked or harrowed into the soil to a depth of
approximately one-eight (1/8) inch. The planted area shall be rolled with a corrugated roller of
the "Cultipacker" type. All rolling of the slope areas shall be on the contour.
ASPHALT MULCH SEEDING: The soil over the area shown on the Drawings, or as directed
to be seeded , shall be loosened to the minimum depth of three (3) inches and all particles in
the seed bed shall be reduced to less than one (1) inch in diameter, or they shall be removed.
The area shall then be finished to line and grade as specified under "Finishing" in Section D-
45, Construction Methods.
Water shall then be applied to the cultivated area of the seed bed until a minimum depth of six
(6) inches is thoroughly moistened .
After the watering, when the ground has become sufficiently dry to be loose and pliable, the
seed, or seed mixture specified , shall then be planted at the rate required and the application
shall be made uniformly. If the sowing of seed is by hand, rather than mechanical methods,
the seed shall be sown in two directions at right angles to each other . Seed and fertilizer may
be distributed at the same time, provided the specified uniform rate of application for both is
obtained. After planting, the seed shall be raked or harrowed into the soil to a depth of
approximately one-quarter (1/4) inch . The planted surface area and giving a smooth surface
without ruts or tracks . In between the time compacting is completed and the asphalt is
applied , the planted area shall be watered sufficiently to assure uniform moisture from the
surface to a minimum of six (6) inches in depth.
The application of asphalt shall follow the last watering as rapidly as possible . Asphalt shall
be of the type and grade as shown on the Drawings and shall conform to the requirements of
the item 300, "Asphalts , Oils and Emuls ions". If the type of asphalt to be used is not shown
on the Drawings , or if Drawings are not included, then MS-2 shall be used. Applications of the
asphalt shall be at a rate of three-tenths (0.3) gallons per square yard. It shall be applied to
the area in such a manner so that a complete film is obtained and the finished surface shall be
comparatively smooth .
RE-SEEDING OF AREAS PLANTED WITH COOL SEASONS SPECIES : Areas where
temporary cool season species have been planted may be replanted beginning February 1
with warm season species as listed in Table 120 .2(2)a . The re-seeding will be achieved in the
following manner. The cool .season species shall be mowed down to a height of one (1) inch
11129/04 SC-35
PART D -SPECIAL CONDITIONS
to insure that slit-seeding equipment will be able to cut through the turf and achieve adequate
soil penetration.
* Slit-seeding, is achieved through the use of an implement which cuts a furrow (slit) in the soil
and places the seed i n the sli t which is then pressed close with a cult packer wheel.
4. HYDROMULCH SEEDING:
If hydro mulch seeding is provided, seed mix shall have 95% purity of Bermuda grass and
have a germination rate of 90%. Contractor shall ensure that the grass establishes.
5. CONSTRUCTION WITHIN PARK AREAS
TURF RESTORATION OF PARK AREAS : FERTILIZER
DESCRIPTION : "Fertilizer" will consist of providing and distributing fertilizer over such areas
as are designated on the Drawings and in accordance with these Specifications.
MATERIALS : All fertilizer used shall be delivered in bags or containers clearly labeled
showing the analysis. The fertilizer is subject to testing by the City of Fort Worth in
accordance with the Texas Fertilizer Law . A pelleted or granulated fertilizer shall be used with
an analysis of 16-20-0 or 16-5-8 or having the analysis shown on the Drawings . The figures
in the analysis represent the percent of nitrogen , phosphoric acid, and potash nutrients
respectively as determined by the methods of the Association of Official Agricultural Chemists .
In the event it is necessary to substitute a fertilizer of a different analysis, it shall be a pelleted
or granulated fertilizer with a lower concentration. Total amount of nutrients furnished and
applied per acre shall equal or exceed that specified for each nutrient.
CONSTRUCTION METHODS: When an item for fertilizer is included in the Drawings and
proposal, pelleted or granulated fertilizer shall be applied uniformly over the area specified to
be fertilized and in the manner directed for the particular item of work . Fertilizer shall be dry
and in good physical condition . Fertilizer that is powdered to caked will be rejected.
Distribution of fertilizer as a particular item of work shall meet the approval of the Engineer.
Unless otherwise indicated on the Drawings, fertilizer shall be applied uniformly at the
average rate of three hund red (300) pounds per acre for all types of "Sodding" and four
hundred (400) pounds per acre for all types of "Seeding".
MEASUREMENT: Topsoil secured from borrow sources will be measured by the square yard
in place on the project site. Measurement will be made only on topsoils secured from borrow
sources .
Acceptable material for "Seeding" will be measured by the linear foot, complete in place .
Acceptable material for "Sodding" will be measured by the linear foot, complete in place .
Acceptable material for "Fertilizer" shall be subsidiary to the price of sodding or seeding.
PAYMENT: All work performed as ordered and measured shall be subsidiary to the contract
unless and otherwise noted in the plans and bid documents to be paid for at the unit price bid
for each item of work. Its price shall be full compensation for excavating (except as noted
11129/04 SC-36
-
PART D -SPECIAL CONDITIONS
below), loading, hauling, placing and furnishing all labor, equipment, tools, supplies , and
incidentals necessary to complete work.
All labor, equipment , tools and incidentals necessary to supply , transport, stockpile and place
topsoil or salvage topsoil as specified shall be included in "Seeding" or "Sodding " bid items
and will not be paid for directly. ·
"Spot sodding" or "block sodding" as the case may be, will be paid for at the contract unit
price per square yard, complete in place, as provided in the proposal and contract. The
contract unit price shall be the total compensation for furnishing and placing all sod ; for all
rolling and tamping; for all watering ; for disposal of all surplus materials; and for all materials,
labor, equipment, tools and incidentals necessary to complete the work, all in accordance with
the Drawings and these Specifications.
The work performed and materials furnished and measured as provided under "Measurement"
shall be paid for at the unit price for "Seeding", or "Sodding", of the type specified, as the case
may be, which price shall each be full compensation for furnishing all materials and for
performing all operations necessary to complete the work accepted as follows :
Fertilizer material and application will not be measured or paid for directly, but is considered
subsidiary to Sodding and Seeding .
D-46 CONFINED SPACE ENTRY PROGRAM
It shall be the responsibility of the contractor to implement and maintain a variable "CONFINED
SPACE ENTRY PROGRAM" which must meet OSHA requirements for all its employees and
subcontractors at all times during construction. All active sewer manholes , regardless of depth,
are defined by OSHA, as "permit required confined spaces ". Contractors shall submit an
acceptable "CONFINED SPACE ENTRY PROGRAM " for all applicable manholes and maintain an
active file for these manholes . The cost of complying with this program shall be subsidiary to the
pay items involving work in confined spaces.
D-47 SUBSTANTIAL COMPLETION INSPECTION/FINAL INSPECTION
7. Prior to the final inspection being conducted for the project, the contractor shall contact the
city inspector in writing when the entire project or a designated portion of the project is
substantially complete.
8. The inspector along with appropriate City staff and the City's consultant shall make an
inspection of the substantially completed work and prepare and submit to the contractor a
list of items needing to be completed or corrected.
9. The contractor shall take immediate steps to rectify the listed deficiencies and notify the
owner in writing when all the items have been completed or corrected .
10. Payment for substantial completion inspection as well as final inspection shall be
subsidiary to the project price. Contractor shall still be required to address all other
deficiencies , which are discovered at the time of final inspection .
11. Final inspection shall be in conformance with general condition item "CS-5.18 Final
Inspection " of PART C -GENERAL CONDITIONS.
11/29/04 SC-37
PART D -SPECIAL CONDITIONS
D-48 EXCAVATION NEAR TREES (WHERE IDENTIFIED ON THE PLANS)
1. The Contractor shall be responsible for taking measures to minimize damage to tree
limbs, tree trunks, and tree roots at each work site. All such measures shall be considered
as incidental work included in the Contract Unit Price bid for applicable pipe or structure
installation except for short tunneling/tree augering.
2. Any and all trees located within the equipment operating area at each work site shall, at
the direction of the Engineer, be protected by erecting a "snow fence" along the drip line or
edge of the tree root system between tree and the construction area .
3. Contractor shall inspect each work site in advance and arrange to have any tree limbs
pruned that might be damaged by equipment operations. The Engineer shall be notified at
least 24 hours prior to any tree trimming work. No trimming work will be permitted within
private property without written permission of the Owner.
4. Nothing shall be stored over the tree root system within the drip line area of any tree .
5. Before excavation (off the roadway) within the drip line area of any tree, the earth shall be
sawcut for a minimum depth of 2 feet.
6. At designated locations shown on the drawings, the "short tunnel" method using Class 51
D.I. pipe shall be utilized.
7. Except in areas where clearing is allowed, all trees up to 8" in diameter damaged during
construction shall be removed and replaced with the same type and diameter tree at the
contractor's expense.
8. Contractor shall employ a qualified landscaper for all the work required for tree care to
ensure utilization of the best agricultural practices and procedures.
9. Short tunneling shall consist of power augering or hand excavation. The tunnel diameter
shall not be larger than 1-1 /2 times the outside pipe diameter. Voids remaining after pipe
installation shall be pressure grouted.
D-49 CONCRETE ENCASEMENT OF SEWER PIPE
Concrete encasement of sewers shall be paid for at the Contract Unit Price per linear foot of
concrete encasement as measured in place along the centerline of the pipe for each pipe
diameter indicated. The Contract Unit Price shall include all costs associated with installation and
reinforcement of the concrete encasement.
D-50 CLAY DAM
Clay dam construction shall be performed in accordance with the Wastewater Clay Dam
Construction, figure in the Drawings in these Specifications, at locations indicated on the
Drawings or as directed by the City. Clay dams shall be keyed into undisturbed soil . to make an
impervious barrier to reduce groundwater percolation through the pipeline trench . Construction
material shall consist of compacted bentonite clay or 2 :27 concrete. Payment for work such as
forming, placing and finishing shall be subsidiary to the price bid for pipe installation.
11/29/04 SC-38
PART D -SPECIAL CONDITIONS
D-51 EXPLORATORY EXCAVATION (D-HOLE)
The Contractor shall be responsible for verifying the locations of all existing utilities prior to
construction, in accordance with item D-6. At locations identified on the drawings , contractor shall
conduct an exploratory excavation (D-Hole ), to locate and verify the location and elevation of the
existing underground utility where it may be in potential conflict with a proposed facility alignment.
The exploratory excavation shall be conducted prior to construction of the entire project only
at locations denoted on the plans or as directed by the engineer. Contractor shall submit a report
of findings (including surveyed elevations of existing conflicting utilities) to the City prior to the
start of construction of the entire project. If the contractor determines an existing utility is in
conflict with the proposed facil ity, the contractor shall contact the engineer immediately for
appropriate design modifications.
The contractor shall make the necessary repairs at the exploratory excavation (D-Hole) to obtain
a safe and proper driving surface to ensure the safety of the general public and to meet the
approval of the City inspector. The contractor shall be liable for any and all damages incurred
due to the exploratory excavation (D-Hole).
Payment shall not be made for verification of existing utilities per item D-6. Payment for
exploratory excavation (D-Hole), at locations identified on the plans or as directed by the
Engineer, shall include full compensation for all materials, excavation, surface restoration , field
surveys, and all incidentals necessary to complete the work, shall be the unit price bid. No
payment shall be made for exploratory excavation(s) conducted after construction has begun .
D-52 INSTALLATION OF WATER FACILITIES
11/29/04
52.1 Polyvinyl Chloride (PVC) Water Pipe
POLYVINYL Chloride Plastic Water Pipe and fittings on this Project shall be in accordance
with the material standard contained in the General Contract Documents . Payment for work
such as backfill, bedding , blocking, detectable tapes and all other associated appurtenant
required, shall be included in the linear foot price bid of the appropriate BID ITEM(S).
52.2 Blocking
Concrete blocking on this Project will necessarily be required as shown on the Plans and
shall be installed in accordance with the General Contract Documents. All valves shall have
concrete blocking provided for supporting. No separate payment will be made for any of the
work involved for the item and all costs incurred will be considered to be included in the
linear foot bid price of the pipe or the bid price of the valve .
52.3 Type of Casing Pipe
1. WATER:
The casing pipe for open cut and bored or tunneled section shall be AWWA C-200
Fabricated Electrically Welded Steel Water Pipe, and shall conform to the provisions of
E1-15, E1-5 and E1-9 in Material Specifications of General Contract Documents and
Specifications for Water Department Projects . The steel casing pipe shall be supplied as
follows :
For the inside and outside of casing pipe, coal-tar protective coating in accordance with
the requirements of Sec. 2.2 and related sections in AWWA C-203.
Touch-up after field welds shall provide coating equal to those specified above.
C. Minimum thickness for casing pipe used shall be 0.375 inch.
SC-39
11/29/04
PART D -SPECIAL CONDITIONS
.Stainless Steel Casing Spacers (centering style) such as manufactured by Cascade
Waterworks Manufacturing Company or an approved equal shall be used on all non-
concrete pipes when installed in casing . Installation shall be as recommended by the
Manufacturer.
2. SEWER:
Boring used on this project shall be in accordance with the material standard E1-15 and
Construction standard E2 -15 as per Fig . 110 of the General Contract Documents .
3. PAYMENT:
Payment for all materials, labor, equipment, excavation, concrete grout, backfill , and
incidental work shall be included in the unit price bid per foot.
52.4 Tie-Ins
The Contractor shall be re~ponsible for making tie-ins to the existing water mains. It shall
be the responsibility of the Contractor to verify the exact location and elevation of the
existing line tie-ins . And any differences in locations and elevation of existing line tie-ins
between the contract drawings and what may be encountered in the field shall be
considered as incidental to construction . The cost of making tie-ins to existing water or
sanitary sewer mains shall be included in the linear foot bid price of the pipe .
52.5 Connection of Existing Mains
The Contractor shall determine the exact location , elevation , configuration and angulation
of existing water or sanitary sewer lines prior to manufacturing of the connecting piece.
Any differences in locations, elevation, configuration, and or angulation of existing lines
between the contract drawings and what may be encountered in the said work shall be
considered as incidental to construction. Where it is required to shut down existing mains
in order to make proposed connections, such down time shall be coordinated with the
Engineer, and all efforts shall be made to keep this down time to a minimum. In case of
shutting down an existing main, the Contractor shall notify the Manager, Construction
Services, Phone 871-7813, at least 48-hours prior to the required shut down time. The
Contractor's attention is directed to Paragraph CS-5.15 INTERRUPTION OF SERVICE,
Page C5-5(5), PART C -GENERAL CONDITIONS OF THE WATER DEPARTMENT
GENERAL CONTRACT DOCUMENTS AND GENERAL SPECIFICATIONS. The
Contractor shall notify the customer both personally and in writing as to the location, time,
and schedule of the service interruption .
The cost of removing any existing concrete blocking shall be included in the cost of
connection. Unless bid separately all cost incurred shall be included in the linear foot
price bid for the appropriate pipe size.
52.6 Valve Cut-Ins
It may be necessary to cut-in gate valves to isolate the water main from which the
extension and/or replacement is to be connected . This may require closing valves in other
lines and putting consumers out of service for that period of time necessary to cut in the
new valve; the work must be expedited to the utmost and all such cut-ins must be
coordinated with the engineer in charge of inspection. All consumers shall be individually
advised prior to the shut out and advised of the approximate length of time they may be
without service .
Payment for work such as backfill , bedding, fittings, blocking and all other associated
appurtenants required, sh all be included in the price of the appropriate bid items.
SC-40
PART D -SPECIAL CONDlTIONS
52. 7 Water Services
The relocation, replacement, or reconnection of water services will be required as shown
on the plans, and/or as described in these Special Contract Documents in addition to
those located in the field and identified by the Engineer.
All service's shall be constructed by the contractor utilizing approved factory manufactured
tap saddles (when required) and corporation stops, type K copper water tubing, curb stops
with lock wings, meter boxes, and if required approved manufactured
service branches . All materials used shall be as specified in the Material Standards (E1-
17 & E 1-18) contained in the General Contract Documents .
All water services to be replaced shall be installed at a minimum depth of 36 inches below
final grade.
All existing 3/4-inch water service lines which are to be replaced shall be replaced with 1-
inch Type K copper, 1-inch diameter tap saddle when required, and 1-inch corporation
from the main line to the meter box .
All services which are to be replaced or relocated shall be installed with the service main
tap and service line being in line with the service meter unless otherwise directed by the
Engineer.
A minimum of 24 hours advance notice shall be given when service interruption will be
required as specified in Section C5-5.15 INTERRUPTION OF SERVICE .
All water service meters shall be removed, tagged, and collected by the contractor for
pickup by the Water Department for reconditioning or replacement. After installation of the
water service in the proposed location and receipt of a meter from the project inspector the
contractor shall install the meter. The meter box shall be reset as necessary to be flush
with existing ground or as otherwise directed by the Engineer. All such work on the
outlet side of the service meter shall be performed by a licensed plumber.
1. WATER SERVICE REPLACEMENTS: Water service replacement or relocation is
required when the existing service is lead or is too shallow to avoid breakage during street
reconstruction. The contractor shall replace the existing service line with Type K copper
from the main to the meter, curb stop with lock wings, and corporation stop.
Payment for all work and materials such as backfill, fittings, type K copper tubing, curb
stop with lock wings , service line adjustment, and any relocation of up to 12-inches from
center line existing meter location to center line proposed meter location shall be included
in the Linear Foot price bid for Copper Service Line from Main to five (5) feet behind
Meter. Any vertical adjustment of customer service line within the 5 foot area shall be
subsidiary to the service installation .
Payment for all work and materials such as tap saddle (if required), corporation stops, and
fittings shall be included in the price bid for Service Taps to Main.
1. WATER SERVICE RECONNECTION : Water service reconnection is required when the
existing service is copper and at adequate depth to avoid breakage during street
reconstruction. The contractor shall adjust the exist~ng water service line as required for
reconnection and furnish a new tap with corporation stop . The contractor will be paid for
11129/04 SC-41
PART D -SPECIAL CONDITIONS
one (1) Service Tap to Main for each service reconnected plus for any copper service line
used in excess of five (5) feet from Main to five (5) feet behind the Meter.
2. WATER SERVICE METER AND METER BOX RELOCATIONS: When the replacement
and relocation of a water service and meter box is required and the location of the meter
and meter box is moved more than twelve (12) inches, as measured from the center line
of the existing meter to location to the center line of the proposed meter location, separate
payment will be allowed for the relocation of service meter and meter box . Centerline is
defined by a line extended from the service tap through the meter. Only relocations made
perpendicular to this centerline will be paid for separately. Relocations made along the
centerline will be paid of in feet of copper service line .
When relocation of service meter and meter box is required, payment for all work and
materials such as backfill, fittings, five (5) feet of type K copper service and all materials,
labor, and equipment used by and for the licensed plumber shall be included in the price
bid for the service meter relocation. All other costs will be included in other appropriate
bid item(s).
This item will also be used to pay for all service meter and meter box relocations as
required by the Engineer when the service line is not being replaced . Adjustment of only
the meter box and customer service line within 5 feet distance behind the meter will not
justify separate payment at any time. Locations with multiple service branches will be paid
for as one service meter and meter box relocation .
4. NEW SERVICE: When new services are required the contractor shall install tap saddle
(when required), corporation stop, type K copper service line, curb stop with lock wings,
and meter box. Reinforced plastic meter boxes with cast iron lid shall be provided for all 2
inch water meters or smaller. The reinforced plastic water meter boxes shall comply with
section E1-18A-Reinforced Plastic Water Meter Boxes .
Payment for all work and materials such as backfill, fittings, type K copper tubing, and curb
stop with lock wings shall be included in the Linear Foot price bid for Service Line from
Main to Meter five (5) feet behind the meter.
Payment for all work and materials such as tap saddle, corporation stops, and fittings shall
be included in the price bid for Service Taps to Mains.
Payment for all work and materials such as furnishing and setting new meter box shall be
included in the price bid for furnish and set meter box.
1. MULTIPLE SERVICE BRANCHES: When multiple service branches are required the
contractor shall furnish approved factory manufactured branches .
Payment for multiple service branches will include furnishing and installing the multiple
service branch only and all other cost will be included in other appropriate bid item(s).
2. MULTIPLE STREET SERVICE LINES TO SINGLE SERVICE METER: Any multiple
service lines with taps servicing a single service meter encountered during construction
shall be replaced with one service line that is applicable for the size of the existing service
meter and approved by the Engineer.
Payment shall be made at the unit bid price in the appropriate bid item(s).
11/29104 SC-42
PART D -SPECIAL CONDITIONS
52.8 2-lnch Temporary Service Line
A. The 2-inch temporary service main and 3/4-inch service lines shall be installed to provide
temporary water service to all buildings that will necessarily be required to have severed
water service during said work. The contractor shall be responsible for coordinating the
schedule of the temporary service connections and permanent service reconnections with
the building owners and the Engineer in order that the work be performed in an
expeditious manner. Severed water service must be reconnected within 2 hours of
discontinuance of service.
A 2-inch tapping saddle and 2-inch corporation stop or 2-inch gate valve with an
appropriate fire hydrant adapter fitting shall be required at the temporary service point of
connection to the City water supply. The 2-inch temporary service main and 3/4-inch
service lines shall be installed in accordance to the attached figures 1, 2 and 3. 2"
temporary service line shall be cleaned and sterilized by using chlorine gas or chlorinated
lime (HTH) prior to installation .
The out-of-service meters shall be removed, tagged and collected by the Contractor for
delivery to the Water Department Meter Shop for reconditioning or replacement. Upon
restoring permanent service, the Contractor shall re-install the meters at the correct
location. The meter box shall be reset as necessary to be flush with the existing ground or
as otherwise directed by the Engineer.
The temporary service layout shall have a minimum available flow rate of 5 GPM at a
dynamic pressure of 35 PSI per service tap. This criteria shall be used by the Contractor
to determine the length of temporary service allowed, number of service taps and number
of feed points.
When the temporary service is required for more than one location the 2-inch temporary
service pipes, 3/4-inch service lines and the 2-inch meter shall be moved to the next
successive project location .
Payment for work such as fittings, 3/4-inch service lines, asphalt, barricades, all service
connections, removal of temporary services and all other associated appurtenants
required, shall be included in the appropriate bid item.
B. In order to accurately measure the amount of water used during construction, the
Contractor will install a fire hydrant meter for all temporary service lines. Water used
during construction for flushing new mains that cannot be metered from a hydrant will be
estimated as accurately as possible . At the pre-construction conference the contractor will
advise the inspector of the number of meters that will be needed along with the locations
where they will be used. The inspector will deliver the hydrant meters to the locations.
After installation, the contractor will take full responsibility for the meters until such time as
the contractor returns those meters to the inspector. Any damage to the meters will be the
sole responsibility of the contractor. The Water Department Meter Shop will evaluate the
condition of the meters upon return and if repairs are needed the contractor will receive an
invoice for those repairs. The issued meter is for this specific project and location only.
Any water that the contractor may need for personal use will require a separate hydrant
meter obtained by the Contractor, at its cost, from the Water Department.
11129/04
52.9 Purging and Sterilization of Water Lines
Before being placed into service all newly constructed water lines shall be purged and
sterilized in accordance with E2-24 of the General Contract Documents and Specifications
SC-43
11129/04
PART D -SPECIAL CONDITIONS
except as modified herein. The City will provide all water for INITIAL cleaning and
sterilization of water lines. All materials for construction of the project, including
appropriately sized "pipe cleaning pigs", chlorine gas or chlorinated lime (HTH) shall be
furnished by the Contractor. Chlorinated lime (HTH) shall be used in sufficient quantities
to provide a chlorine residual of fifty (50) PPM. The residual of free chlorine shall be
measured after 24 hours and shall not be less than 10 parts per million of free chlorine.
Chlorinated water shall be disposed of in the sanitary sewer system . Should a sanitary
sewer not be available , chlorinated water shall be "de-chlorinated" prior to disposal. The
line may not be placed in service until two successive sets of samples, taken 24 hours
apart, have met the established standards of purity.
Purging and sterilization of the water lines shall be considered as incidental to the project
and all costs incurred will be considered to be included in the linear foot bid price of the
pipe.
52.10 Work Near Pressure Plane Boundaries
Contractor shall take note that the Vo'.ater line to be replaced under this contract may cross
or may be in close proximity to an existing pressure plane boundary. Care shall be taken
to ensure all "pressure plane" valves installed are installed closed and no cross
connections are made between pressure planes
52.11 Water Sample Station
GENERAL:
All water sampling station installations will be per attached Figure 34 or as required in
large water meter vaults as per Figure 33 unless otherwise directed by the Engineer.
The appropriate water sampling station will be furnished to the Contractor free of charge;
however, the Contractor will be required to pick up this item at the Field Operations
Warehouse.
PAYMENT FOR FIGURE 34 INSTALLATIONS: Payment for all work and materials
necessary for the installation of the 3/4-inch type K copper service line will be shall be
included in the price bid for copper Service Line from Main to Meter.
Payment for all work and materials necessary for the installation tap saddle (if required),
corporation stops, and fittings shall be included in the price bid for Service Taps to Main.
Payment for all work and materials necessary for the installation of the sampling station,
concrete support block, curb stop, fittings, and an incidental 5-feet of type K copper
service line which are required to provide a complete and functional water sampling
station shall be included in the price bid for Water Sample Stations.
PAYMENT FOR FIGURE 33 INSTALLATIONS: Payment for all work and materials
necessary for the installa tion tap saddle , gate valve, and fittings shall be included in the
price bid for Service Taps to Main.
Payment for all work and materials necessary for the installation of the sampling station,
modification to the vault, fittings, and all type K copper service line which are required to
provide a complete and functional water sampling station shall be included in the price bid
for Water Sample Stations.
SC-44
PART D -SPECIAL CONDITIONS
52.12 Ductile Iron and Gray Iron Fittings
Reference Part E2 Construction Specifications, Section E2-7 Installing Cast Iron Pipe ,
fittings , and Specials, Sub section E2-7.11 Cast Iron Fittings:
E2-7.11 DUCTILE-IRON AND GRAY-IRON FITTINGS : All ductile-iron and gray-iron
fittings shall be furnished .with cement mortar lining as stated in Section E 1-7. The price
bid per ton of fittings shall be payment in full for all fittings, joint accessories, polyethylene
wrapping, horizontal concrete blocking, vertical tie-down concrete blocking, and concrete
cradle necessary for construction as designed.
All ductile-iron and gray-iron fittings, valves and specials shall be wrapped with
polyethylene wrapping conforming to Material Specification E1-13 and Construction
Specification E2-13. Wrapping shall precede horizontal concrete blocking, vertical tie-
down concrete blocking , and concrete cradle. Payment for the polyethylene wrapping,
horizontal concrete blocking , vertical tie-down concrete blocking, and concrete cradle shall
be included in bid items for vales and fittings and no other payments will be allowed.
D-53 SPRINKLING FOR DUST CONTROL
All applicable provisions of Standard Specifications Item 200, "Sprinkling for Dust Control" shall
apply. However, no direct payment will be made for this item and it shall be considered to this
contract.
D-54 DEWATERING
The Contractor shall be responsible for determining the method of dewatering operation for the
water or sewage flows from the existing mains and ground water. The Contractor shall be
responsible for damage of any nature resulting from the dewatering operations.
The DISCHARGE from any dewatering operation shall be conducted as approved by the
Engineer. Ground water shall not be discharged into sanitary sewers.
Dewatering shall be considered as incidental to a construction and all costs incurred will be
considered to be included in the project price .
D-55 TRENCH EXCAVATION ON DEEP TRENCHES
Contractor to prevent any water flowing into open trench during construction. Contractor shall not
leave excavated trench open overnight. Contractor shall fill any trench the same day of
excavation . No extra payment shall be allowed for this special condition.
D-56 TREE PRUNING
A. REFERENCES : National Arborist Association's "Pruning Standards for Shade Trees ".
B. ROOT PRUNING EQUIPMENT
1. Vibratory Knife
2. Vermeer V-1550RC Root Pruner
C. NATURAL RESOURCES PROTECTION FENCE
3. Steel "T' = Bar stakes, 6 feet long.
11129104 SC-45
PART D -SPECIAL CONDITIONS
4. Smooth Horse-Wire : 14-1/2 gauge (medium gauge) or 12 gauge (heavy gauge).
5 . Surveyor's Plastic Flagging : "Tundra" weight , International fluorescent orange or red
color.
6 . Comb ination Fence: Commercially manufactured combination soil separator fabric on
wire mesh backing as shown on the Drawings.
D. ROOT PRUNING
7. Survey and stake loc ation of root pruning trenches as shown on drawings.
8 . Using the approved specified equipment, make a cut a minimum of 36 inches deep in
order to minimize damage to the undisturbed root zone.
9. Backfill and compact the trench immediately after trenching.
10 . Place a 3-foot wide by 4-inch deep cover of mulch over the trench as required by the
Engineer.
11 . Within 24 hours , pru ne flush with ground and backfill any exposed roots due to
construction activity . Cover with wood chips of mulch in order to equalize soil
temperature and minimize water loss due to evaporation.
12. Limit any grading work within conservation areas to 3-inch maximum cut or fill , with no
roots over 1-inch diameter being cut unless cut by hand or cut by specified methods,
equipment and protect ion.
E. MULCHING : Apply 2-inches to 4-inches of wood chips from trimming or clearing
operation on areas designated by the Engineer.
F. Tree Pruning shall be considered subsidiary to the project contract price .
D-57 TREE REMOVAL
Trees to be removed shall be removed using applicab le methods, including stump and root ball
removal, loading, hauling and dumping . Extra caution shall be taken to not disrupt existing
utilities both overhead and buried . The Contractor shall immediately repair or replace any
damage to utilities and private property including, but not limited to, water and sewer services,
pavement, fences, walls, sprinkler system piping , etc ., at no cost to the Owner. All costs for tree
removal, including temporary service costs, shall be consi'dered subsidiary to the project contract
price and no add itional payment will be allowed .
D-58 TEST HOLES
The matter of subsurface exploration to ascertain the nature of the soils, including the amount of
rock , if any, through which this pipeline installation is to be made is the responsibility of any and
all prospective bidders, and any bidder on this project shall submit his bid under this condition.
Whether prospective bidders perform this subsurface exploration jointly or independently, and
whether they make such determination by the use of test holes or other means , shall be left to the
discretion of such prospective bidders .
If test borings have been made and are provided for bidder's information, at the locations shown
on the logs of borings in the appendix of this specification, it is expressly declared that neither the
11129104 SC-46
PART D -SPECIAL CONDITIONS
City nor the Engineer guarantees the accuracy for the information or that the material
encountered in excavations is the same , either in character, location , or elevation, as shown on
the boring logs . It shall be the responsibility of the bidder to make such subsurface investigations,
as he deems necessary to determine the nature of the material to be excavated. The Contractor
assumes all responsibility for interpretation of these records and for making and maintaining the
required excavation and of doing other work affected by the geology of the site.
The cost of all rock removal and other associated appurtenances , if required , shall be included in
the linear foot bid price of the pipe .
D-59 PUBLIC NOTIFICATION PRIOR TO BEGINNING CONSTRUCTION AND
NOTIFICATION OF TEMPORARY WATER SERVICE INTERRUPTION DURING
CONSTRUCTION
Prior to beginning construction on any block in the project, the contractor shall , on a block by
block basis, prepare and deliver a notice or flyer of the pending construction to the front door of
each residence or business that will be impacted by construction. The notice shall be prepared as
follows:
The notification notice or flyer shall be posted seven (7) days prior to beginning any construction
activity on each block in the project area. The flyer shall be prepared on the Contractor's
letterhead and shall include the following information : Name of Project, DOE No ., Scope of
Project (i.e. type of construction activity), actual construction duration within the block, the name
of the contractor's foreman and his phone number, the name of the City's inspector and his phone
number and the City's after-hours phone number. A sample of the 'pre-construction notification '
flyer is attached .
The contractor shall submit a schedule showing the construction start and finish time for each
block of the project to the inspector. In addition , a copy of the flyer shall be delivered to the City
Inspector for his review prior to being distributed . The contractor will not be allowed to begin
construction on any block until the flyer is delivered to all residents of the block.
In the event it becomes necessary to temporarily shut down water service to residents or
businesses during construction , the contractor shall prepare and deliver a notice or flyer of the
pending interruption to the front door of each affected resident. The notice shall be prepared as
follows :
The notification or flyer shall be posted twenty-four (24) prior to the temporary interruption. The
flyer shall be prepared on the contractor's letterhead and shall include the following information:
Name of the project, DOE number, the date of the interruption of service, the period the
interruption will take place, the name of the contractor's foreman and his phone number and the
name of the City's inspector and his phone number. A sample of the temporary water service
interruption notification is attached.
A copy of the temporary interruption notification shall be delivered to the i nspector for his review
prior to being distributed . The contractor shall not be permitted to proceed with interruption of
water service until the flyer has been delivered to all affected residents and businesses.
Electronic versions of the sample flyers can be obtained from the Construction office at (817) 871 -
8306.
All work involved with the notification flyers shall be considered subsidiary to the contract price
and no additional compensation shall be made.
11129/04 SC-47
PART D -SPECIAL CONDITIONS
D-60 TRAFFIC BUTTONS
The removal and replacement of traffic buttons is the responsibility of the contractor and shall be
considered a subsidiary item . In the event that the contractor prefers for the Signals , Signs and
Markings Division (SSMD) of the Transportation/Public Works Department to install the markings,
the contractor shall contact SSMD at (817) 871-8770 and shall reimburse SSMD for all costs
incurred , both labor and material. No additional compensation shall be made to the contractor for
this reimbursement.
D-61 SANITARY SEWER SERVICE CLEANOUTS
Whenever a sanitary sewer service line is installed or replaced, the Contractor shall install a two-
way service cleanout as shown in the attached detail. Cleanouts are to be installed out of high
traffic areas such as driveways, streets, sidewalks , etc. whenever possible . When it is not
possible, the cleanout stack and cap shall be cast iron.
Payment for all work and materials necessary for the installation of the two-way service cleanout
which are required to provide a complete and functional sanitary sewer cleanout shall be included
in the price bid for Sanitary Sewer Service Cleanouts .
D-62 TEMPORARY PAVEMENT REPAIR
The Contractor shall provide a t emporary pavement repair immediately after trench backfill and
compaction using a minimum of 2-inches of hot mix asphalt over a minimum of 6-inches of
compacted flex base. The exis ting asphalt shall be saw cut to provide a uniform edge and the
entire width and length of the temporary repair shall be rolled with a steel asphalt roller to provide
smooth rideability on the stree t as well as provide a smooth transition between the existing
pavement and the temporary repair. Cost of saw cutting shall be subsidiary to the temporary
pavement repair pay item.
The contractor shall be responsible for maintaining the temporary pavement until the paving
contractor has mobilized . The paving contractor shall assume maintenance responsibility upon
such mobilization. No additional compensation shall be made for maintaining the temporary
pavement.
D-63 CONSTRUCTION STAKES
The City, through its Surveyor or agent, will provide to the Contractor construction stakes or other
customary method of markings as may be found consistent with professional practice,
establishing line and grades for roadway and utility construction, and centerlines and benchmarks
for bridgework. These stakes shall be set sufficiently in advance to avoid delay whenever
practical. One set of stakes shall be set for all utility construction (water, sanitary sewer, drainage
etc.), and one set of excavation/or stabilization stakes, and one set of stakes for curb and
gutter/or paving . It shall be the sole responsibility of the Contractor to preserve, maintain, transfer,
etc., all stakes furnished until completion of the construction phase of the project for which they
were furnished .
If the City or its agent determines that a sufficient number of stakes or markings provided by the
City, have been lost, destroyed , or disturbed, to prevent the proper prosecution and control of the
work contracted for in the Contract Documents, it shall be the Contractor's responsibility, at the
Contractor's sole expense, to have such stakes replaced by an individual registered by the Texas
Board of Professional Land Surveyor as a Registered Land Surveyor. No claims for delay due to
lack of replacement of construction stakes will be accepted , and time will continue to be charged
in accordance with the Contract Documents .
11129104 SC-48
=
--
PART D -SPECIAL CONDITIONS
D-64 EASEMENTS AND PERMITS
The performance of this contract requires certain temporary construction, right-of-entry
agreements, and/or permits to perform work on private property .
The City has attempted to obtain the temporary construction and/or right-of-entry agreements for
properties where construction activity is necessary on City owned facilities, such as sewer lines or
manholes. For locations where the City was unable to obtain the easement or right-of-entry, it
shall be the Contractor's responsibility to obtain the agreement prior to beginning work on subject
property. This shall be subsidiary to the contract. The agreements, which the City has obtained,
are available to the Contractor for review by contacting the plans desk at the Department of
Engineering, City of Fort Worth. Also, it shall be the responsibility of the Contractor to obtain
written permission from property owners to perform such work as cleanout repair and sewer
service replacement on private property. Contractor shall adhere to all requirements of
Paragraph C6-6.10 of the General Contract Documents. The Contractor's attention is directed to
the agreement terms along with any special conditions that may have been imposed on these
agreements, by the property owners .
The easements and/or private property shall be cleaned up after use and restored to its original
condition or better. In event additional work room is required by the Contractor, it shall be the
Contractor's responsibility to obtain written permission from the property owners involved for the
use of additional property required . No additional payment will be allowed for this item.
The City has obtained the necessary documentation for railroad and/or highway permits required
for construction of this project. The Contractor shall be responsible for thoroughly reviewing,
understar:idirtg anq complying with all provisions of such permits, including obtaining the requisite
insurance, and shall pay any and all costs associated with or required by the permit(s). It is the
Contractor's responsibility to provide the required flagmen and/or provide payment to the
appropriate railroad/agency for all flagmen during construction in railroad/agency right-of-way. For
railroad permits, any and all railroad insurance costs and any other incidental costs necessary to
meet the conditions associated with permit(s) compliance, including payment for flagmen, shall be
subsidiary to the bid item price for boring under the railroad. No additional payment will be
allowed for !his it~m.
D-65 PRE-CONSTRUCTION NEIGHBORHOOD MEETING
After the pre-construction conference has been held but before construction is allowed to begin
on this project a public meeting will be held at a location to be determined by the Engineer. The
contractor, inspector, and project manager shall meet with all affected residents and present the
projected schedule, including construction start date, and answer any construction related
questions. Every effort will be made to schedule the neighborhood meeting within the two weeks
following the pre-construction conference but in no case will construction be allowed to begin
until this meeting is held.
D-66 WAGE RATES
C,2 m1:1liance with and Enforfg_rn ent of-Preyal ling Wage Laws
Duty to pay Prevailing Wage Rates.
The contractor shall comply with all req1,.1ireme'nts of Chapter 2258, Texas Government Code
(Chapter 2258), including \he payment of 11ot less than th~ rates determineq ·by the City Council of
t_he City of Fort Worth to be the prevailing wage rates ii) accordance yvith Chapter ~258. Such
ereyailin_g WJ!9e rates. are included in these c611tr~ct dodtments.
11129/04 SC-49
PART D -SPECIAL CONDITIONS
Practices and Erosion Control Manual for Construction Activities (BMP Manual). This manual can
be obtained through the Internet at www.dfwstormwater.com/runoff.html. Not all of the structural
controls discussed in the BMP Manual will necessarily apply to this project. Best Management
Practices are construction management techniques that, if properly utilized, can minimize the
need for physical controls and possible reduce costs . The methods of control shall result in
minimum sediment retention of not less than 70%.
NOTICE OF INTENT (NOi): If the project will result in a total land disturbance equal to or greater
than 5 acres , the contractor shall sign at the pre-construction meeting a TCEQ Notice of Intent
(NOi) form prepared by the engineer. It serves as a notification to the TCEQ of construction
activity as well as a commitment that the contractor understands the requirements of the permit
for storm water discharges from construction activities and that measures will be taken to
implement and maintain storm water pollution prevention at the site. The NOi shall be submitted
to the TCEQ at least 48 hours prior to the contractor moving on site and shall include the required
$100 application fee.
The NOi shall be mailed to:
Texas Commission on Environmental Quality
Storm Water & General Permits Team; MC-228
P .O . Box 13087
Austin, TX 78711-3087
A copy of the NOi shall be sent to :
City of Fort Worth
Department of Environmental Management
5000 MLK Freeway
Fort Worth, TX 76119
NOTICE OF TERMINATION (NOT): For all sites that qualify as Large Construction Activity, the
contractor shall sign, prior to final payment, a TCEQ Notice of Termination (NOT) form prepared
by the engineer. It serves as a notice that the site is no longer subject to the requirement of the
permit.
The NOT should be mailed to:
Texas Commission on Environmental Quality
Storm Water & General Permits Team; MC-228
P.O . Box 13087
Austin, TX 78711-3087
STORM WATER POLLUTION PREVENTION PLAN (SWPPP): A document consisting of an
erosion control and toxic waste management plan and a narrative defining site parameters and
techniques to be employed to reduce the release of sediment and pollution from the construction
site. Five of the project SWPPP's are available for viewing at the plans desk of the Department of
Engineering. The selected Contractor shall be provided with three copies of the SWPPP after
award of contract, along with unbounded copies of all forms to be submitted to the Texas
Commission on Environmental Quality.
LARGE CONSTRUCTION ACTIVITY-DISTURBED AREA EQUAL TO OR GREATER THAN 5
ACRES: A Notice of Intent (NOi) form shall be completed and submitted to the TCEQ including
payment of the TCEQ required fee. A SWPPP that meets all TCEQ requirements prepared by the
Engineer shall be prepared and implemented at least 48 hours before the commencement of
construction activities. The SWPPP shall be incorporated into in the contract documents. The
11129/04 SC-52
PART D -SPECIAL CONDITIONS
contractor shall submit a schedule for implementation of the SWPPP. Deviations from the plan
must be submitted to the engineer for approval. The SWPPP is not warranted to meet all the
conditions of the permit since the actual construction activities may vary from those anticipated
during the preparation of the SWPPP. Modifications may be required to fully conform to the
requirements of the Permit. The contractor must keep a copy of the most current SWPPP at the
construction site. Any alterations to the SWPPP proposed by the contractor must be prepared and
submitted by the contractor to the engineer for review and approval. A Notice of Termination
(NOT) form shall be submitted within 30 days after final stabilization has been achieved on all
portions of the site that is the responsibility of the permittee, or, when another permitted operator
assumes control over all areas of the site that have not been finally stabilized .
SMALL CONSTRUCTION ACTIVITY -DISTURBED AREA EQUAL TO OR GREATER THAN
ONE ACRE BUT LESS THAN FIVE ACRES : Submission of a NOi form is not required. However,
a TCEQ Site Notice form must be completed and posted at the site . A copy of the completed Site
Notice must be sent to the City of Fort Worth Department of Environmental Management at the
address listed above. A SWPPP, prepared as described above, shall be implemented at least 48
hours before the commencement of construction activities . The SWPPP must include
descriptions of control measures necessary to prevent and control soil erosion, sedimentation and
water pollution and will be included in the contract documents. The control measures shall be
installed and maintained throughout the construction to assure effective and continuous water
pollution control. The controls may include, but not be limited to, silt fences, straw bale dikes, rock
berms, diversion dikes, interceptor swales, sediment traps and basins, pipe slope drain, inlet
protection, stabilized construction entrances, seeding, sodding, mulching, soil retention blankets,
or other structural or non-structural storm water pollution controls. The method of control shall
result in a minimum sediment retention of 70% as defined by the NCTCOG "BMP Manual."
Deviations from the proposed control measures must be submitted to the engineer for approval.
PAYMENT FOR SWPPP IMPLEMENTATION: Payment shall be made per lump sum as shown
on the proposal as full compensation for all items contained in the project SWPPP.
D-69 COORDINATION WITH THE CITY'S REPRESENTATIVE FOR OPERATIONS OF
EXISTING WATER SYSTEMS
It is the Contractor's responsibility to coordinate any event that will require connecting to or the
operation of an existing City water line system with the City's representative. The Contractor may
obtain a hydrant water meter from the Water Department for use during the life of named project.
In the event the Contractor requires that a water valve on an existing live system be turned off
and on to accommodate the construction of the project, the Contractor must coordinate this
activity through the appropriate City representative. The Contractor shall not operate water line
valves of existing water system. Failure to comply will render the Contractor in violation of Texas
Penal Code Title 7, Chapter 28 .03 (Criminal Mischief) and the Contractor will be prosecuted to the
full extent of the law. In addition, the Contractor will assume all liabilities and responsibilities as a
result of these actions.
D-70 ADDITIONAL SUBMITTALS FOR CONTRACT AWARD
The City reserves the right to require any pre-qualified contractor who is the apparent low
bidder(s) for a project to submit such additional information as the City, in sole discretion may
require, including but not limited to manpower and equipment records, information about key
personnel to be assigned to the project, and construction schedule, to assist the City in evaluating
and assessing the ability of the apparent low bidder(s) to deliver a quality product and
successfully complete projects for the amount bid within the stipulated time frame. Based upon
the City's assessment of the submitted information, a recommendation regarding the award of a
11129/04 SC-53
PART D -SPECIAL CONDITIONS
contract will be made to the City Council. Failure to submit the additional information if requested
may be grounds for rejecting the apparent low bidder as non-responsive . Affected contractors will
be notified in writing of a recommendation to the City Council.
D-71 EARLY WARNING SYSTEM FOR CONSTRUCTION
Time is of the essence in the completion of this contract. In order to insure that the contractor is
responsive when notified of unsatisfactory performance and/or of failure to maintain the contract
schedule, the following process shall be applicable:
The work progress on all construction projects will be closely monitored. On a bi-monthly basis
the percentage of work completed will be compared to the percentage of time charged to the
contract. If the amount of work performed by the contractor is less than the percentage of time
allowed by 20% or more ( examp le : 10% of the work completed in 30% of the stated contract time
as may be amended by change order), the following proactive measures will be taken:
1. A letter will be mailed to the contractor by certified mail, return receipt requested
demanding that, within 10 days from the date that the letter is received, it provide
sufficient equipment, materials and labor to ensure completion of the work within the
contract time . In the event the contractor receives such a letter, the contractor shall
provide to the City an updated schedule showing how the project will be completed
within the contract time .
2. The Project Manager and the Directors of the Department of Engineering, Water
Department, and Department of Transportation and Public Works will be made aware
of the situation . If necessary, the City Manager's Office and the appropriate city council
members may also be informed .
3. Any notice that may , in the City's sole discretion, be required to be provided to
interested individuals will distributed by the Engineering Department's Public
Information Officer.
4. Upon receipt of the contractor's response, the appropriate City departments and
directors will be notified. The Engineering Department's Public Information Officer will,
if necessary, then forward updated notices to the interested individuals.
5 . If the contractor fails to provide an acceptable schedule or fails to perform satisfactorily
a second time prior to the completion of the contract, the bonding company will be
notified appropriately.
D-72 AIR POLLUTION WATCH DAYS
The Contractor shall be required to observe the following guidelines relating to working on City
construction sites on days designated as "AIR POLLUTION WATCH DAYS". Typically, the
OZONE SEASON, within the Metroplex area , runs from May 1, through OCTOBER 31, with 6 :00
a .m. -10 :00 a.m. being critical BECAUSE EMISSIONS FROM THIS TIME PERIOD HAVE
ENOUGH TIME TO BAKE IN THE HOT ATMOSPHERE THAT LEADS TO EARLY AFTERNOON -
OZONE FORMATION ..
The Texas Commission on Environmental Quality (TCEQ), in coordination with the National
Weather Service, will issue the Air Pollution Watch by 3:00 p.m. on the afternoon prior to the
WATCH day. On designated Air Pollution Watch Days, the Contractor shall bear the
responsibility of being aware that such days have been designated Air Pollution Watch Days and
11/29104 SC-54
PART D -SPECIAL CONDITIONS
as such shall not begin work until 10:00 a .m. whenever construction phasing requires the use of
motorized equipment for periods in excess of 1 hour. However, the Contractor may begin work
prior to 10 :00 a .m. if use of motorized equipment is less than 1 hour, or if equipment is new and
certified by EPA as "Low Emitting ", or equipment burns Ultra Low Sulfur Diesel (ULSD), diesel
emulsions, or alternative fuels such as CNG.
If the Contractor is unable to perform continuous work for a period of at least seven hours
between the hours of 7:00 a.m . -6:00 p.m., on a designated Air Pollution Watch Day , that day will
be considered as a weather day and added onto the allowable weather days of a given month .
D-73 FEE FOR STREET USE PERMITS AND RE-INSPECTIONS
A fee for street use permits is in effect. In addition, a separate fee for re-inspections for parkway
construction , such as driveways, sidewalks, etc., will be required . The fees are as follows:
1. The street permit fee is $50.00 per permit with payment due at the time of permit
application. ,
2 . A re-inspection fee of $25 .00 will be assessed when work for which an inspection
called for is incomplete . Payment is due prior to the City performing re-inspection.
Payment by the contractor for all street use permits and re-inspections shall be considered
subsidiary to the contract cost and no additional compensation shall be made.
11129/04 SC-55
PART D -SPECIAL CONDITIONS
."'; -Jf :p·: ' . ,/ ' .. City of Fort Worth ·. . . · \~~}; . ·?r-/t ;:;·: . ' .. ;•,,,:
Highway (Heavy) Construction 'I,~(1,t i • ~. ; :.:: '.!, ,. ~;,{;.~'J:"I i Prevailing Wage Rates For 2006 ; ' •' Classifications Hrly Rts Classifications Hrly Rts
Air Tool Operator $10 .06 Scraper Operator $11 .42 I
Asphalt Raker $11.01 Servicer $12 .32 --.
Asphalt Shoveler $8.80 Sl ip Form Machine Operator $12 .33 .
Asphalt Distributor Operator $13 .99 Spreader Box Operator $10.92 I
Asphalt Paving Machine Operator $12 .78 Tractor operator, Crawler Type $12 .60 -
Batching Plant Weigher $14.15 Tractor operator , Pneumatic $12 .91 l
Broom or Sweeper Operator $9 .88 Traveling Mixer Operator $12.03 l,
Bulldozer operator $13 .22 Truck Driver-Single Axle (Light) $10 .91
Carpenter (Rough) $12 .80 Truck Driver-Single Axle (Heavy) $11 .47 I
Concrete Finisher-Paving $12 .85 Truck Driver-Tandem Axle Semi-Trailer $11 .75 ,J..
Concrete Finisher -Structures $13 .27 Truck Driver-Lowboy/Float $14.93
Concrete Paving Curbing Mach . Oper. $12.00 Truck Driver-Transit Mix $12 .08 i
Concrete Paving Fin ishing Mach . Oper. $13 .63 Wagon Drill , Boring Machine , Post Hole Driller $14 .00 ;tii,.
Concrete Paving Joint Sealer Oper. $12 .50 Welder $13 .57
Concrete Paving Saw Oper. $13 .56 Work Zone Barricade Servicer $10 .09 I
Concrete Paving Spreader Oper. $14 .50 -
Concrete Rubber $10 .61
Crane, Clamshell , Backhoe, Derrick , Dragline , Shovel $14 .12
Electrician $18.12
Flagger $8.43
Form Builder-Structures $11 .63
Form Setter-Paving & Curbs $11 .83
Foundation Drill Operator, Crawler Mounted $13 .67
Foundation Drill Operator, Truck Mounted $16 .30
Front End Loader $12 .62
Laborer-Common $9.18
Laborer-Utility $10 .65
Mechanic $16 .97 -Milling Machine Operator, Fine Grade $11 .83
Mixer Operator $11 .58
Motor Grader Operator (Fine Grade) $15 .20
Motor Grader Operator, Rough Oile r $14 .50
Painter, Structures $13 .17
Pavement Marking Machine Oper. $10 .04
Pipe Layer $11 .04 -Roller, Steel Wheel Plant-Mix Pavements $11 .28
Roller, Steel Wheel Other Flatwhee l or Tamping $10 .92
Roller, Pneumatic, Self-Propelled Sc raper $11 .07
Reinforcing Steel Setter (Paving) $14.86
Reinforcing Steel Setter (Structure) $16 .29
11/29104 SC-56
Date: ____ _
FORT WORTH
DOE NO. XX.XX
Project Name:
NOTICE OF TEMPORARY WATER SERVICE
INTERRUPTION
DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR
WATER SERVICE WILL BE INTERRUPTED ON ---------
BETWEENTHEHOURSOF _______ AND _____ ~
IF YOU HAVE QUESTIONS ABOUT THIS SHUT-OUT, PLEASE CALL:
MR. AT __________ _
(CONTRACTORS S_UPERINTENDENT) (TELEPHONE NUMBER)
OR
MR. ____________ AT __________ _
(CITY INSPECTOR) (TELEPHONE NUMBER)
THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE.
THANK YOU,
____________ CONTRACTOR .
i
C:
e
u
s
a
.n
11
y
0
T
A
H
p
A
D
1N e
s
H
A
p
a
T
0
H
PART D -SPECIAL CONDITIONS
~ DEMOLITION/ RENOVATION
~ NOTIFICATION FORM
T D H
NOTIFICATION# __ ---------
TEXAS OEPARTME.NT OF HEALTH
NOTE: CIRCLE ITEMS THAT ARE AMENDED
t) Abii!ement Contractor:~-------...... --_______ TDH Licen5e Nvrnber. _______ _ .Address : ____________ Cit;y : ____________ State : Zfp: ____ ~
Offic8 PhoM Number: ~~--------Job Site PhOne Numbct :.~-~----------
Site supervisor: _ TOH Ucense N1J1rnber: --------------
S:ite SUpcrvisor : TOH Ucen-se Number: ___ ~----------
Trained On-Site NESHAP lndividual : ______ -_______ Certification Date: ______ _
l"il\.
Demolition Con l rac tor: __________ ~ __ omce Phone Number......._ . .....___ __________ _
Ad d'ress ; Cily: S1a1e ; ___ -Zip; ___ _
2) Project Consul1an t oc Operator: ________________ TOH LiCE!ns8 Number:. _____ _: Mailing Add ress : _________________________________ _
City: Slate: _____ Zip,: _____ Office Phone Number:...__._ _____ _
3) FacllityOwner. ___________________________________ .,..
Attontion : ___________________________________ _
Ma ili ng Add ress : __ ~--------------------,--------------
. City: --S1ate : Zip : Owner Phone Number( ) _
••Noto: Tho htvoir:o for tho notification fee wlll be &ent to the owner of the bullcflng and the blllll\!I ~CfdNtU for thl> Invoice will be
obtained (rem tl'to-lnformotion tMt Is provided In this section_
4) Description or Faci[ity Name:. ________ -:------------------=-----Physical Ad dress ; ____________ CounlY-City: Zip ; ___ _
Facility Phone Numner FacilJty Cont..ict Person: ___ =-----------.
Descrip ti on of Area.rRoom Nurnbe.r: ____ ~~----------------------
Prior Use; _________ --,-_____ F.lJ!UtB Us.e:. _________ ~===-----
Age o f Building/Facility: Size: Number of Fioor5; Sdlool {K • 12): o YES n NO
5) Type of Work: O Demolition o 1Renovatlon {Abatement) o An.nual Cons.alidated
Work wiU be during : Ll Day D Evenlflg D Ni~f\l :: Pt"lasM Project .
Description of work schedule: ________________ =-------------
6) Is this a PUblic Building? D YES D NO Federal Facility? D YES O NO Industrial Site? D YES O NO
D NESHAP~Only Facility? D YES D NO Is Bllilding/Facility OCCUpied? tJ YES a NO
L
11/29/04
V
I
0
1 1
a
ti
0
n
?
D
y
E
s
G
N
7) No1ification Type CHECK ONLY ONE
o Original (10 Wo rking Days} _ Cancella1ion D Amendment D Emergency/Ordered
If this is an amendment , which amendmen1 number Is thls?_ (Enclosic copy of original and/or last amendment)
If en emergency, vmo did you talk wltn at TDH? l;mergency#:_· ~-----
Date aod Hour of EmtJtgency (HH/MMIDD.IYY)~: -------
Dasctiptio!'I of ttie su(Jden, unexpected event and explooarion or how the event caused unsafe condition5 or Would cau i
equ ipment damage {computets, machi nery, etc·---------------------~--
B) Desctiplion of procedures to be followed In the eveot that U'tlexpected asbestos is found or previooi,.1$):,0 rtQfl•friable
asbestos material becomes ctumbled. iJ)ulvetizad. or redU'¢ed to powder ;----------------
9) Was ari Asbes tos survey performed? o YES D NO Date:. I I TOH lnspec•l)f License No: ____ _
Analylical Method ; D PLM D TEM D Assumed 'rDH Labor{llQry l.ice~ No ; ,......,.-----
(for TAI-IPA (put:llic building) projects : an assvmption must be mad'e by a TOH Licensed Inspector)
10) Descrlpjjon of planned <femoliliOn or cenov.ation work, type of material, e:nd method(s) to be used . .._·-------
11} Doscription of wQr~ practices and engineertng controls 10 be used to prevent emissions Of asbestos at the
demolifionJrenovanon : _____ ~-------------------------
SC-58
11/29/04
PART D -SPECIAL CONDITIONS
t2} ALL applicable IIBms in tJ'8' following table must be, completed : IF NO ASBESTOS PRESENT CHECK HERE:
Approxlm11te amo u nt of Check unit of measurement
Asbestos-Containing Building Material .......,. __ -As_. _b,...e ... $ ... ..,s ________ .___,,.._......,._--1
Type
Pipes Surface Area
RACM lo be rernoved
RACM NOT remo_\'e51 __
Interior Cate l non.fria ble removed
Exlef'iot Cale o I non-friable remo"ed
Cate r non •friable NOT removed
lnte.rioLCat ·o II non-ftiabl'.e removed
Exterior CateA II non-friable removed
Cate II non-frlable_ N_OT removad
RACM Off-Facility Component
13) Waste Transporter Name: -----~---------TOH License Number.------Addtcss : ___________ Cify : ______ =.--Stale : _ Zip: ___ _
Contact Person : _ Phooa Number: ~~--------
14) waste Disposal Site Name:. _______ """"'.""."----------~,------,=-----
Address ·._-,-----,-------=~~~-City: _________ State: ___ Zip : ___ _
Telephone : TNRCC Permit Number:--------
15) For structurally unsound facllllles , attach a copy of demormon order and identify G<lvemme11tal Official below: Name: Registration No: ____________ _
Tille· ·
Da1e of order (MM/00/W) Date order to beg in (MM/00/YY) f I
16) Scheduled Dates of Asbestos Abatement (MM/DOIYY} Start: __ _,l'--___,f'---Complete: -~/'--___,-
17) SCheduled Dates Demolition/Renovation (MM/OD/YY} Slart: f J Complete :_~/ __ /~---
.,. Note: If the start dale on this. notiflc:.lltlo!'I c~n not bo mot. th111 TDH Regional or Local Program office Mlist be contsctsd by
phone prior to the start data. Failure to do so hr avtolatl<1n tr1 accordancoto TAHPA. SOc:tlon .295.61.
I hereby cer1ifythat all information I.have provided Is cooect, complete. at u:1 trua to the bast Ofmy knowledge . I sckn0'""1edge
that I am responsible for all aspects of tha notificcltion forrp, including, but not limi!i!lil, content and submlss fon dates. Th8
maximum penelty is $10 ,000 per day per violation.
(Signelute of Building Owner/ Operator
or Delegated Consultant/Conli'actor)
MAIL TO :
.. Faxos aro not a.cceptod"
(Printed Name) (Date)
ASBESTOS NOTIFICATION SECTION
TOXIC SUBSTANCES CONTROL DIVISION
TEXAS DEPARTMENT OF HEALTH
PO BOX 143538
AUSTIN. TX 78714-3538
PH : 512-834-6600, 1-800·572-5548
(TeleptiOf'le)
(Fax Number)
"Faxes arc-not accttpted"
Farm APB#5, dated 07/2<J/02. Replaces TOH form dated 07113/01. For assistance in complftling form, coll 1-80().572-5548
----------'···----·-----
SC-59
PART DA
DA-1
DA-2
DA-3
DA-4
DA-5
DA-6
DA-7
DA-8
DA-9
DA-10
DA-11
DA-12
DA-13
DA-1.4
DA-15
DA-16
DA-17
DA-18
DA-19
DA-20
DA-21
DA-22
DA-23
DA-24
DA-2.5
DA-26
DA-27
DA-28
DA-29
DA-30
DA-31
DA-32
DA-33
DA-34
DA-35
DA-36
DA-37
DA-38
DA-39
DA-40
DA-41
DA-42
DA-43
DA-44
DA-45
DA-46
DA-47
DA-48
DA-49
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
AWARD OF CONTRACT FOR PROJECTS WITH MULTIPLE UNITS ................... OMIT
PIPELINE REHABILITATION CURED-IN-PLACE PIPE ......................................... OMIT
PIPE ENLARGEMENT SYSTEM ............................................................................. OMIT
FOLD AND FORM PIPE ........................................................................................... OMIT
SLIPLINING ............................................................................................................... OMIT
PIPE INSTALLED BY OTHER THAN OPEN CUT .......................................................... 4
TYPE OF CASING PIPE .................................................................................................. 7
SERVICE LINE POINT REPAIR/ CLEANOUT REPAIR ....................... : ................. OMIT
PROTECTIVE MANHOLE COATING FOR CORROSION PROTECTION ..................... 8
MANHOLE REHABILITATION ................................................................................. OMIT
SURFACE PREPARATION FOR MANHOLE REHABILITATION ................................ 10
INTERIOR MANHOLE COATING -MICROSILICATE MORTAR SYSTEM ............ OMIT
INTERIOR MANHOLE COATING -QUADEX SYSTEM .......................................... OMIT
INTERIOR MANHOLE COATING -SPRAY WALL SYSTEM ....................................... 11
INTERIOR MANHOLE COATING -RAVEN LINING SYSTEM ..................................... 14
INTERIOR MANHOLE COATING; PERMACAST SYSTEM WITH EPOXY LINEROMIT
INTERIOR MANHOLE COATING-STRONG-SEAL-SYSTEM ................................. OMIT
RIGID FIBERGLASS MANHOLE LINERS ............................................................... OMIT
PVC LINED CONCRETE WALL RECONSTRUCTI.ON ............................................ OMIT
PRESSURE GROUTING .......................................................................................... OMIT
VACUUM TESTI.NG OF REHABILITATED MANHOLES ........................................ OMIT
FIBERGLASS MANHOLES ..................................................................................... OMIT
LOCATION AND EXPOSURE OF MANHOLES AND WATER VALVES ................ OMIT
REPLACEMENT OF CONCRETE CURB AND GUTTER. ....................................... OMIT
REPLACEMENT OF 6" CONCRETE DRIVEWAYS . ., ............................................. OMIT
REPLACEMENT OF H.M.A.C. PAVEMENT AND BASE ........................................ OMIT
GRADED CRUSHED STONES ................................................................................ OMIT
WEDGE MILLING 2" TO O" DEPTH 5.0' WIDE ............... , ....................................... OMIT
BUTT JOINTS -MILLED ...................... .' ................................................................... OMIT
2" H.M.A.C. SURFACE COURSE {TYPE "D" MIX) ................................................. OMIT
REPLACEMENT OF 7" CONCRETE VALLEY GUTTER ........................................ OMIT
NEW 7" CONCRETE VALLEY GUTTER ................................................................. OMIT
NEW 4" STANDARD WHEELCHAIR RAMP ........................................................... OMIT
8" PAVEMENT PULVERIZATION ............................................................................ OMIT
REINFORCED CONCRETE PAVEMENT OR BASE (UTILITY CUT} ...................... OMIT
RAISE.D PAVEMENT MARKERS ............................................................................ OMIT
POTENTIALLY PETROLEUM CONTAMINATED MATERIAL HANDLING ................. 17
LOADING, TRANSPORTATION, AND DISPOSAL OF CONTAMINATED SOIL. ........ 21
ROCK RIPRAP -GROUT -FILTER FABRIC ............................................................... 22.
CONCRETE RIPRAP ............................................................................................... OMIT
CONCRETE CYLINDER PIPE AND FITTINGS ....................................................... OMIT
CONCRETE PIPE FITTINGS AND SPECIALS ........................................................ OMIT
UNCLASSIFIED STREET EXCAVATION ................................................................ OMIT
6" PERFORATED PIPE SUBDRAIN ....................................................................... OMIT
REPLACEMENT OF 4 11 CONCRETE SIDEWALKS ..................................................... 25
RECOMMENDED SEQUENCE OF CONSTRUCTION ............................................ OMIT
PAVEMENT REPAIR IN PARKING AREA ................................................................... 26
EASEMENTS AND PERMITS ....................................................................................... 26
HIGHWAY REQUIREMENTS ........................................................................................ 26
ASC-1
DA-50
DA-51
DA-52
DA-53
DA-54
DA-55
DA-56
DA-57
DA-58
DA-59
DA-60
DA-61
DA-62
DA-63
DA-64
DA-65
DA-66
DA-67
DA-68
DA-69
DA-70
DA-71
DA-72
DA-73
DA-74
DA-75
DA-76
DA-77
DA-78
DA-79
DA-80
DA-81
DA-82
DA-83
DA-84
DA-85
DA-86
DA-87
DA-88
DA-89
DA-90
DA-91
DA-92
DA-93
DA-94
DA-95
DA-96
DA-97
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
CONCRETE ENCASEMENT ......................................................... · ................................ 26
CONNECTION TO EXISTING STRUCTURES .............................................................. 27
TURBO METER WITH VAULT AND BYPASS INSTALLATION ............................. OMIT
OPEN FIRE LINE INSTALLATIONS ........................................................................ OMIT
WATER SAMPLE STATION .................................................................................... OMIT
CURB ON CONCRETE PAVEMENT ....................................................................... OMIT
SHOP DRAWINGS ........................................................................................................ 27
COST BREAKDOWN .................................................................................................... 28
STANDARD STREET SPECIFiCATIONS H.M.A.C. OVERLAY .............................. OMIT
H.M.A.C. MORE THAN 9 INCHES DEEP ................................................................ OMIT
ASPHALT DRIVEWAY REPAIR .............................................................................. OMIT
TOP SOIL ................................................................................................................. OMIT
WATER METER AND METER BOX RELOCATION AND ADJUSTMENT ............. OMIT
BID QUANTITIES .......................................................................................................... 28
WORK 1.N HIGHWAY RIGHT OF WAY ......................................................................... 28
CRUSHED LIMESTONE (FLEX-BASE) ................................................................... OMIT
OPTION TO RENEW ................................................................................................ OMIT
NON-EXCLUSIVE CONTRACT ............................................................................... OMIT
CONCRETE. VALLEY GUTIER ............................................................................... OMIT
TRAFFIC BUTIONS ................................................................................................ OMIT
PAVEMENT STRIPING ................................................................................................. 29
H.M.A.C. TESTING PROCEDURES ........................................................................ OMIT
SPECIFICATION REFERENCES .................................................................................. 29
RELOCATION OF SPRINKLER SYSTEM BACK-FLOW PREVENTER/CONTROL
VALVE AND BOX ..................................................................................................... OMIT
RESILIENT-SEATED GATE VALVES .......................................................................... 29
EMERGENCY SITUATION, JOB MOVE-IN ............................................................. OMIT
1 %" & 2" COPPER SERVICES ................................ : .............................................. OMIT
SCOPE OF WORK (UTIL. CUT) .............................................................................. OMIT
CONTRACTOR'S RESPONSIBILTY (UTIL. CUT} ................................................... OMIT
CONTRACT TIME (UTIL. CUT).. .............................................................................. OMIT
REQUIRED CREW PERSONNEL & EQUIPMENT (UTIL. CUT) ............................. OMIT
TIME ALLOWED FOR UTILITY CUTS (UTIL. CUT}.. .............................................. OMIT
LIQUIDATED DAMAGES (UTIL. CUT) .................................................................... OMIT
PAVING REPAIR EDGES (UTIL. CUT) ................................................................... OMIT
TRENCH BACKFILL (UTIL. CUT) ........................................................................... OMIT
CLEAN-UP (UTIL. CUT) ........................................................................................... OMIT
PROPERTY ACCESS (UTIL. CUT) ............................................ : ............................. OMIT
SUBMISSION OF BIDS (UTIL. CUT) ....................................................................... OMIT
STANDARD BASE REPAIR FOR UNIT I (UTIL. CUT).. .......................................... OMIT
CONCRETE BASE REPAIR FOR UNIT II & UNIT Ill (UTIL. CUT) .......................... OMIT
2" TO 9" H.M.A.C. PAVEMENT (UTIL. CUT) .......................................................... OMIT
ADJUST WATER VALVE BOXES, MANHOLES, AND VAULTS (UTIL. CUT) ....... OMIT
MAINTENANCE BOND (UTIL. CUT) ....................................................................... OMIT
BRICK PAVEMENT (UTIL. CUT) ............................................................................. OMIT
LIME STABILIZED SUBGRADE {UTIL. CUT) ......................................................... OMIT
CEMENT STABILIZED SUBGRADE (UTIL. CUT} ................................................... OMIT
REPAIR OF STORM DRAI.N\ STRUCTURES (UTIL. CUT) ..................................... OMIT
"QUICK-SET" CONCRETE (UTIL. CUT) ....................... '. ......................................... OMIT
ASC-2
DA-98
DA-99
DA-100
DA-101
DA-1.02
DA-103
DA-104
DA-105
DA-106
DA-107
DA-108
DA-109
DA-110
DA-1.11
DA-112
DA-113
DA-11.4
DA-115
DA-116
DA-117
DA-118
DA-119
DA-120
DA-121
DA-122
DA-123
DA-124
DA-125
DA-126
DA-1.27
DA-128
DA-129
DA-130
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
UTILITY ADJUSTMENT (UTIL. CUT) ...................................................................... OMIT
STANDARD CONCRETE SIDEWALK AND WHEELCHAIR RAMPS (UTIL. CUT) OMIT
LIMITS OF CONCRETE PAVEMENT REPAIR (UTIL. CUT) .................................. OMIT
CONCRETE CURB AND GUTTER (UTIL. cun ..................................................... OMIT
PAYMENT (UTIL. CUT) ........................................................................................... OMIT
DEHOLES (MISC. EXT.) .......................................................................................... OMIT
CONSTRUCTION LIMITATIONS (MISC. EXT.) ...................................................... OMIT
PRESSURE CLEANING AND TESTING (MISC. EXT.) .......................................... OMIT
BID QUANTITIES (MISC. EXT.) .............................................................................. OMIT
LIFE OF CONTRACT (MISC. EXT.) ........................................................................ OMIT
FLOWABLE FILL (MISC. EXT.) ................................................................................... 30
BRICK PAVEMENT REPAIR (MISC. REPL.) .......................................................... OMIT
DETERMINATION AND INITIATION OF WORK (MISC. REPL.) ............................ OMIT
WORK ORDER COMPLETION TIME (MISC. REPL.) ............................................. OMIT
MOVE IN CHARGES (MISC . REPL.) ....................................................................... OMIT
PROJECT SIGNS (MISC. REPL.) ............................................................................ OMIT
LIQUIDATED DAMAGES (MISC. REPL.) ............................................................... OMIT
TRENCH SAFETY SYSTEM DESIGN (MISC. REPL.) ............................................ OMIT
FIELD OFFICE ......................................................................................................... OMIT
TRAFFIC CONTROL PLAN .......................................................................................... 31
COORDINATION OF WORK WITH CONTRACTOR FOR OTHER UNITS ............. OMIT
ABANDON EXISTING PIPE LINE ................................................................................ 31
ABANDON EXISTING SANITARY SEWER MANHOLE .............................................. 31
SUBSURFACE EXPLORATION ................................................................................... 32
DUCTILE IRON PIPE .................................................................................................... 32
CONCRETE PRESSURE PIPE, BAR-WRAPPED STEEL CYLINDER TYPE ............. 39
FIBERGLASS SEWER PIPE -GRAVITY SERVICE ................................................... .49
SANITARY SEWER AND WATER LINE MARKERS ................................................... 53
REPLACEMENT OF TREES ........................................................................................ 54
PIPELINES CROSSING HI.GHWAYS, STREETS AND RAILROADS BY BORING,
TUNNELING OR OPEN CUT ......................................................................................... 55
GATE VALVE.S ............................................................................................................. 63
AIR RELEASENACUUM VALVES .............................................................................. 66
JUNCTION SANITARY SEWER MANHOLE ................................................................ 69
ASC-3
PART DA -ADDITIONAL SPECIAL CONDITIONS
DA-1 OMIT
DA-2 OMIT
DA-3 OMIT
DA-4 OMIT
DA-5 OMIT
DA-6 PIPE INSTALLED BY OTHER THAN OPEN CUT
A. GENERAL:
1. Furnish materials and necessary accessories, with strengths, thickness, coatings,
and fittings indicated, specified and/or necessary to complete the work.
2. AH excavation shall provide an open area conforming to the outside diameter of the
casing and/or carrier conduit. The excavation shall be to an alignment and grade
which will allow the carrier conduit to be installed to proper line and grade as
shown on the Plans and as established in the Specifications.
3 . Work shall be performed in accordance with the requirements of the City of Fort
Worth Water Department, the Texas Department of Transportation, or railroad
company, as applicable .
B. MATERIALS:
1. Casing Pipe: Casing pipe shall be steel conforming to ANSI B36.10 and the
fallowing:
a. Field Strength: 35,000 psi minimum.
b. Wall thickness: 0.375 in. minimum (0.5 for railroad crossings).
c. Diameter: As shown on the drawings (minimum size requirements).
d . Joints: Continuous circumferential weld in accordance with AWS D1 .1.
2. Carrier Pipe in Casing: Carrier pipe shall be as shown on drawings and as
specified in the General Contract Documents.
3. Sewer Pipe without Casing Pipe: Shall be minimum Class 51 ductile iron pipe, or
as designated on t he plans.
4. Grout: Grout shall be Portland Cement grout of min . 2000 psi compressive
strength at 28 days. Proportioned not less than 1 cu. ft. of cement to 3 cu . ft. of
fine sand with sufficient water added to provide free flowing thick slurry.
C. EXECUTION
1.
11/02/04
Where sewer pipe is required to be installed under railroad embankments or under
highways, streets or other facilities in other than open cut, construction shall be
performed in such a manner so as to not interfere with the operation of the railroad,
ASC-4
-
-
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
street, highway, or other facility, and so as not to weaken or damage any
embankment or structure . During construction operations, barricades and lights ta
safeguard traffic and pedestrians shall be furnished and maintained, until such time
as the backfill has been completed and then shall be removed from the site.
2. Pits and Trenches:
a. If the grade of the pipe at the end is below the ground surface, suitable pits
or trenches shall be excavated for the purpose of conducting the jacking or
tunneling operations and for placing end joints of the pipe. Wherever end
trenches are cut in the sides of the embankment or beyond it , such work
shall be sheeted securely and braced in a manner to prevent earth from
caving in .
b. The location of the pit shall meet the approval of the Engineer.
c. The pits of trenches excavated to facilitate these operations shall be
backfilled immediately after the casing and carrier pipe installation has
been completed.
3. Boring and Jacking Steel Casing Pipe: Steel casing pipe shall be installed by
boring hole with the earth auger and simultaneously jacking pipe into place.
a. The boring shall proceed from a pit provided for the boring equipment and
workmen. The holes are to be bored mechanically. The boring shall be
done using a pilot hale. By this method an approximate 2-inch hole shall
be bored the entire length of the crossing and shall be checked for line and
grade on the opposite end of the bore from the work pit. Thi.s pilot hale
shall serve as the centerline of the larger diameter hole to be bored. Other
methods of maintaining line and grade an the casing may be approved if
acceptable ta the Engineer. Excavated material shall be placed near the
top of the working pit and disposed of as required. The use of water or
other fluids in connection with the baring operation will be permitted only to
the extent required to lubricate cuttings. Jetting or sluicing will not be
permitted.
b. In unconsolidated sail formations, a gel-forming colloidal drilling fluid
consisting of at least 10 percent of high grade carefully processed bentonite
may be used to consolidate cuttings of the bit, seal the walls of the hole,
and furnish lubrication for subsequent removal of cuttings and installation of
the pipe immediately thereafter.
c. Allowable variation from the line and grade shall be as specified under
paragraph A.2. All voids between bore and outside of casing shall be
pressure grouted.
4. Installation of Carrier Pipe in Casing:
a. Sanitary sewer pipe located within the encasement pipe shall be supported
by "skids" or "bands" to prevent the pipe and bells from snagging on the
inside of the casing, and to keep the installed line from resting on the bells.
ASC-5
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
b. All skids shall be treated ~ith a wood preservative. Skids should extend for
the full length of the pipe with the exception of the bell area and spigot area
necessary for assembly unless otherwise specified .
c. The Contractor shall prevent over-belling the pipe while installing it through
the casing. A method of restricting the movement between the assembled
bell and sp igot where applicable shall be provided.
d. At all bored, jacked, or tunneled installations, the annular space between
the carrier pipe and casing shall be filled with grout. Care must be taken
that not too much water is forced into the casing so as not to float the pipe.
The backfill material will not be required unless specified on the plans and
specified by the Engineer.
e. Closure of the casing after the pipe has been installed shall be plugged at
the ends of the casing as shown on the drawings or as required by the
Engineer.
5. Boring and Jacking Ductile Iron Pipe without Casing Pipe:
a . As indicated on drawings and as required and directed by the Engineer
sewer shall be constructed of bore and jacked ductile iron pipe.
b. When a casing pipe is not designated on the drawings, the contractor shall
provide a casing pipe if necessary to achieve line and grade. Casing pipe
shall be provided at no additional cost and shall be subsidiary to the cost
bid for installation By Other than Open Cut.
c . Bore and jack in accordance with paragraph C.3. above.
d . Short length of sewer consisting of a single pipe section may be installed by
jacking without a bore hole if permitted by the Engineer and in soft soil
layer. All voids outside of installed pipe shall be pressure grouted.
6. Tunneling: Where the characteristics of the soil, the size of the proposed pipe, or
the use of monolithic sewer would make the use of tunneling more satisfactory
than jacking or boring, or when shown on the plans, a tunneling method may be
used , with the approval of the Engineer or railroad/highway officials.
a .
b.
When tunneling is permitted, the lining of the tunnel shall be of sufficient
strength of support the overburden. The Contractor shall submit the
proposed liner method to the EngineE:?r for approval. The tunnel liner
design shall bear the seal of a licensed professional engineer in the State
of Texas. Approval by the Engineer shall not relieve the Contractor of the
responsibility for the adequacy of the liner method .
The space between the tunnel liner and the limits of excavation shall be
pressure g routed or mud-jacked .
ASC-6
PART DA -ADDITIONAL SPECIAL CONDITIONS
c. Access hales for placing concrete shall be space at maximum intervals of
10 feet.
D. MEASUREMENT AND PAYMENT: lnstaHation of pipe by other than open cut will be
measured by the linear foot of pipe , complete in place. Such measurement will be made
between the ends af the pipe along the central axis as installed . The work performed and
materials furnished as prescribed by this item will be paid for at the Contract Unit Price bid
per linear foot for Pipe Installed by Other Than Open Cut of the type, size, and class of
pipe specified as shown on plans. The furnishing of all materials, pipe, liner materials
required for installation, for all preparation, hauling and installing of same, and for all labor,
tools, equipment and incidentals necessary to complete the work, including excavation,
backfilling and disposal of surplus material shall be included in the Contract Unit Price as
shown in the Bid Proposal. Payment shall not include pavement replacement, which if
required, shall be paid separately.
DA-7 TYPE OF CASING PIPE
A. WATER:
The casing pipe for open cut and bored or tunneled section shall be AWWA C-200
Fabricated Electrically Welded Steel Water Pipe, and shall conform to the provisions of
E1-15, E1-5 and E1-9 in Material Specifications of General Contract Documents and
Specifications far Water Department Projects . The steel casing pipe shall be supplied as
follows:
1. Far the inside and outside of casing pipe, coal-tar protective coating in accordance
with the requirements of Sec. 2.2 and related sections in AWWA C-203.
2 . Touch-up after field welds shall provide coating equal to those. specified above.
3 . Minimum thickness for casing pipe used shall be 0.375 inch (0.5 for railroad
crossings).
Casing Spacers (centering style) such as manufactured by Cascade Waterworks
Manufacturing Company , Advanced Products and Systems, Inc., or an approved equal
shall be used an all non-concrete pipes when installed in cas.ing . Installation shall be as
recommended by the manufacturer.
B. SEWER:
Boring used on this project shall be in accordance with the material standard E1-15 and
Construction standard E2-15 as per Fig. 110 of the General Contract Documents.
C. PAYMENT:
Payment for all materials, labor, equipment, excavation, concrete grout, backfill, and
incidental work shall be included in the unit price bid per foot.
DA-8 OMIT
11/02/04 ASC-7
PART DA -ADDITIONAL SPECIAL CONDITIONS
DA-9 PROTECTIVE MANHOLE COATING FOR CORROSION PROTECTION
A. GENERAL:
1. Scope: This section governs all work, materials and testing required for the
application of interior protective coating . Structures designated to receive interior
coating are listed on the construction drawings. The structures are to be coated,
includi_ng interior wall, top and bench surfaces. Protective coating for corrosion
protection shall meet the requirements of this Specification (and items DA-14 and
DA-15) and the Manufacturers recommendations and specifications.
2. Description: The Contractor shall be responsible for the furnishing of all labor,
supervision, materials, equipment, and testing required for the completion of
protective coating of structures in accordance with manufacturer's
recommendations .
3. Manufacturer's Recommendations: Materials and procedures utilized for the lining
process shall be in strict accordance with manufacturer's recommendations.
4 . Corrosion Protection: Corrosion protection may be required on all structures
where high turbulence or high H2S content is expected.
B. MATERIALS:
11/02/04
1. Scope: This section governs the materials required far completion of protective
coating of designat ed structures.
2. Protective Coating: The protective coating shall be a proprietary two component,
100 percent solids, rigid polyurethane system designated as Spray Wall as
manufactured by Sprayroq, Inc. or a two-part epoxy resin system using 100% solids
based epoxy binder with fibrous and flake fillers, is manufactured by Raven Lining
systems and designated as Raven 405.
3. Specialty Cement (lf required for leveling or filling): The specialty cement-based
coating material shall be either Quadex QM-1s as manufactured by Quadex, Inc. or
Reliner MSP as manufactured by Standard Cement Materials.
4 . Material Identification:· The protective coating material sprayed onto the surface of
the structure shall be a urethane or epoxy resin system formulated for the
application to a sanitary sewer environment. The spray system shall exhibit the
minimum physical properties as follows:
5.
Property
Tensile Strength
Flexural Stress
Flexural Modulus
Standard
ASTM D-638
ASTM D-790
ASTM D-790
Long Term Value
5,000 psi
10,000 psi
550,000 psi
Mixing and Handling: Mixing and Handling of specialty cement material and
protective coating material, which may be toxic under certain conditions shall be in
ASC-8
-
-
PART DA -ADDITIONAL SPECIAL CONDITIONS
accordance with the recommendations of the manufacturer and in such a manner
as to minimize hazard to personnel. It is the responsibility of the Contractor to
provide appropriate protective measures to ensure that materials are under control
at all times and are not available to unauthorized personnel or animals. All
equipment shall be subject to the approval of the Engineer. Only personnel
thoroughly familiar with the handling of the coating material shall perform the spray
coating operations and coating installations.
C . EXECUTION :
11/02104
1. General: Protective coating shall not be installed until the structure is complete
and in place .
2. Preliminary Repairs:
a . All foreign materials shall be removed from the interior of the structure
using high pressure water spray (3500 psi to 4000 psi at spray tip).
b . All unsealed lifting holes, unsealed step holes, and voids larger than
approximately one-half (1/2) inch in thickness shall be filled with patching
compound as recommended by the material supplier for this application.
c. After all repairs have been completed, remove all loose material.
3. Protective Coating:
a. The protective coating shall be applied to the structure from the bottom of
the frame to the bench, down to the top of the trough. The top of the
structure shall also be coated.
b. The protective coating shall be installed in accordance with the
manufacturer's recommendations and the following procedure .
1)
2)
3)
4)
5)
The surface shall be thoroughly cleaned of all foreign materials and
matter.
Place covers over the invert to prevent extraneous material from
entering the sewers.
If required for filling or leveling, apply specialty cement product to
provide a smooth surface for the coasting material.
Spray the urethane or epoxy onto the structure wall and
bench/trough to a minimum uniform thickness of 125 mils (0.125
inches). Thickness to be verifiable through the use of methods
acceptable to the Engineer. After the walls are coated, the wooden
bench covers shall be removed .
The final application shall have a minimum of three (3) hours cure
time or be set hard to the touch, before being subjected to active
flow.
ASC-9
PART DA -ADDITIONAL SPECIAL CONDITIONS
6) No applications shall be made to frozen surfaces or if freezing is
expected to occur inside the structure within 24 hours after
application .
4 . Testing of Rehabilitated Manholes : Testing of rehabilitated manholes for
water tightness shall be performed by the Contractor after operations are
complete in accordance with the Section D-36 -VACUUM TESTING OF
SANITARY SEWER MANHOLES .
D. MEASUREMENT AND PAYMENT: Payment shall be based on the Contract Unit Price
Bid per vertical foot, measured from the bottom of the frame to the top of the bench . The
Contract Unit Price shall be payment in full for performing the work and for furnishing all
labor, supervision, materials, equipment and material testing required to complete the
work. Pressure grouting , if necessary to stop active infiltration prior to application of the
protective coating , shall be included in the above unit price. Grouting of the pipe seals.
bench and trough, and lower portion of a particular structure , if required by the Engineer,
shall be paid for sep~rate ly, as specified in Section DA-10, MANHOLE REHABILITATION.
DA-10 OMIT
DA-11 SURFACE PREPARATION FOR MANHOLE REHABILITATION
A. GENERAL: This item shall govern the preparation of surfaces for manhole rehabilitation.
B. CLEANING:
11/02104
1. Covers (screens) shall be placed over the pipe inverts to prevent extraneous material
from entering the sewer system.
2. All concrete that is not sound or has been damaged by chemical exposure shall be
removed from the manhole . Loose and protruding brick, mortar and concrete shall
be removed using a masonry hammer and chisel and/or scrapers. Existing roots and
manhole steps shall be removed by cutting them flush with the wall of the manhole.
3. All contaminates including but not limited to: oi.ls, grease, waxes, form release, curing
compounds, efflorescence, sealers, salts, incompatible existing coatings, and all
other contaminants shall be removed.
4.
5.
Surfaces to receive protective coating shall be cleaned and abraded to produce a
sound concrete/brick surface with adequate profile and porosity to provide a strong
bond between the protective coating and the substrate. All foreign materials shall be
removed from the manhole interior using high pressure water spray (3500 psi to
4000 psi). Cleaning equipment shall have a pressure gauge that indicates the water
pressure being used.
Detergent water cleaning, muriatic acid, and hot water blasting shall be used, if
necessary, to remove dirt, oils, grease, and other matter which may prevent a good
bond of sealing material to the manhole surface. A mild chlorine solution (household
ASC-10
-
PART DA -ADDITIONAL SPECIAL CONDITIONS
bleach) may be used to neutralize the surface to diminish microbiological bacteria
growth prior to final rinse and coating .
C. PRELIMINARY REPAIRS
1. All unsealed lifting holes , unsealed step holes, voids larger than approximately one-
half (1/2) inch in thickness shall be filled with patching compound at least one hour
(1) prior to application of the first spray coat.
2. Active leaks shall be stopped using City approved products specifically for that
purpose and according to manufacturer's recommendation. Some leaks may require
grouting to stop the inflow. Grouting shall be performed in accordance with City
specifications and Section DA-20 -PRESSURE GROUTING.
3. Bench area shall be built up if required to provide a uniform slope from the
circumferences to the manhole trough. City approved cementitious patching
compounds or epoxy grout as recommended by manufacture shall be used.
4 . After all repairs have been completed , all loose material shall be removed from the
manhole. Contractor shall insure no material is allowed to enter the sewer system .
5 . Contractor shall ensure the manhole is clear of all detergents and cleaners and that
all active infiltration has been stopped prior to application of protective manhole
coatings for rehabilitation .
D. INSPECTION
Applicator shall carefully inspect all surfaces prior to application of protective coating and
shall notify Owner of any noticeable disparity in the surface wh ich may interfere with the
proper performance of the repa ir mortar and protective coating.
E. MEASUREMENT AND PAYMENT
Payment for Surface Preparation shall be considered subsidiary to the cost for Interior
Manhole Coating or Protective Manhole Coating for Corrosion Protection .
DA-12 OMIT
DA-13 OMIT
DA-14 INTERIOR MANHOLE COATING -SPRAY WALL SYSTEM
A. GENERAL
11/02104
1. Scope
This section governs all work, materials and testing required for the application of
interior manhole coating. Manholes designated for interior coating are listed on the
Manhole Rehabilitation Schedule. Interior manhole coating shall meet the
requirements of this Section or of Section DA-12 , DA-13 , DA-15, DA-16 or DA-17.
ASC-11
PART DA -ADDITIONAL SPECIAL CONDITIONS
2. Description
The Contractor shall be responsible for the furnishing of all labor, superv1s1on,
materials, equipment, and testing required far the completion of interior coating of
manholes in accordance with the Contract Documents.
3. Manufacturer's Recommendations
Materials , mixture ratios, and procedures utilized for the coating process shall be in
accordance with manufacturer's recommendations . ·
4 . Manholes
Manholes to be coated are of brick, block, or concrete construction. All manholes
shall have a minimum of one-half (1/2) inch specialty cement-based coating material
(Quadex QM-1s or Reliner MSP) sprayed or toweled on coating over the original
interior surface . ·
B. MATERIALS
11/02104
1. Scape
This section governs the materials required for completion of interior coating of
manholes.
2 . Interior Coating
The interior coating shall be a proprietary two component, 100 percent solids, rigid
polyurethane system designated as Spray Wall as manufactured by Sprayroq , Inc.
3. Specialty Cement
The specialty cement-based coating material shall be either Quadex QM-1 s as
manufactured by Quadex, Inc. or Reliner MSP as manufactured by Standard Cement
Materials.
4. Material Identification
The interior manhole coating material sprayed onto the surface of the manhole shall
be a urethane resin system formulated for the application to a sanitary sewer
environment. The spray system shall exhibit the physical properties as follows :
Property
Tensile Strength
Flexural Stress
Flexural Modulus
5. Mixing and Handling
Standard
ASTM D-638
ASTM D-790
ASTM D-790
Long Term Value
5,000 psi
10,000 ps i
550,000 psi
Mixing and handling of specialty cement material and interior coating material , which
may be toxic under certain conditions shall be in accordance with the
ASC-12
PART DA -ADDITIONAL SPECIAL CONDITIONS
recommendations of the manufacturer and in such a manner as to minimize hazard
to personnel. It is the responsibility of the Contractor to provide appropriate
protective measures to ensure that materials are under control at all times and are
not available to unauthorized personnel or animals. All equipment shall be subject to
the approval of the Engineer. Only personnel thoroughly familiar with the handling of
the coating material shall perform the spray coating operations and coating
installations.
C. EXECUTION
11/02104
1. General
Manhole coating shall not be installed until sealing of manhole frame and grade
adjustments, or partial manhole replacement when required for the manhole per the
Manhole Rehabilitation Schedule, are complete.
2. Temperature
Normal interior coating operation shall be performed at temperatures of 40°F or
greater. No application shall be made when freezing is expected within 24 hours.
3. Interior Manhole Coating
1.
a . The interior coating shall be applied to the manhole from the bottom of the
frame to the bench, down to the top of the trough.
b. The interior coating shall be installed in accordance with the manufacturer's
recommendations and the following procedure.
1) The surface shall be thoroughly cleaned of all foreign materials and
matter. Cleaning shal.1 be accomplished by using high pressure water
spray (minimum 3500 psi at spray tip}, cleaning with muriatic acid,
degreaser, or other solvents as needed in order to remove any film or
residue on the surface.
2) Place covers over the invert to prevent extraneous material from
entering the sewers.
3) Apply a minimum of one-half (1/2} inch specialty cement product
(Quadex QM-1s or Reliner MSP) smooth surface for the urethane
coating material.
4) Spray the urethane onto the manhole wall and bench/trough with a
minimum thickness of 125 mils (0.125 inches). Thickness to be
verifiable through the use of methods acceptable to the Engineer.
5) Coat trough area with specialty cement product (Quadex QM-1s or
Reliner MSP}.
Testing of Rehabilitated Manholes
ASC-13
PART DA -ADDITIONAL SPECIAL CONDITIONS
a. Testing of rehabilitated manholes for water tightness shall be performed by
the Contractor after operations are complete in accordance with Section DA-
21.
D. MEASUREMENT AND PAYMENT
Payment shall be based on the Contract Unit Price per vertical foot, measured from the
bottom of the frame to the top of the bench. The Contract Unit Price shall be payment in full
for performing the work and for furnishing all labor, supervision, materials, equipment and
material testing required to complete the work. Grouting, if necessary, shall be included in
the above unit price. Grouting of the pipe seals, bench and trough, and lower portion of a
particular manhole, if required by Manhole Rehabilitation Work Schedule or required to be
done by the Engineer, shall be paid for separately at the Contract Unit Price.
DA-15 INTERIOR MANHOLE COATING -RAVEN LINING SYSTEM
A. GENERAL
1. Scope
This section governs all work, materials and testing required for the application of
interior manhole coating. Manholes designated for interior coating are listed of the
Manhole Rehabilitation Schedule, listed in Section I. Interior manhole coating shall
meet the requirements of this Section, or of Section DA-12, DA-13, DA-14, DA-16 or
DA-17.
2. Description
The Contractor shall be responsible for the furnishing of all labor, superv1s1on,
materials, equipment, and testing required for the completion of interior coating of
manholes in accordance with the Contract Documents.
3. Manufacturer's Recommendations
Materials, mixture ratios, and procedures utilized for the coating process shall be in
accordance with manufacturer's recommendations.
4. Manholes
Manholes to be coated are of brick,. block, or concrete construction . All manholes
shall have a minimum of one-half (1/2) specialty cement-based coating material
(Quadex QM-1s or Reliner MSP} sprayed or toweled on coating over the original
interior surface.
B. MATERIALS
1. Scope
This section governs the materials required for completion of interior coating of manholes.
2. Interior Coating
11/02104 ASC-14
PART DA -ADDITIONAL SPECIAL CONDITIONS
Raven Ultra High-Build epoxy Coating, a two-part epoxy resin system using 100%
solids based epoxy binder with fibrous and flake fillers, is manufactured by Raven
Lining systems and designated as Raven 405.
3. Specialty Cement
The specialty cement-based coating material shall be either Quadex QM-1 s as
manufactured by Quadex, Inc . or Reliner MSP as manufactured by Standard Cement
Materials .
4. Material Identification
Contractors will completely identify the types of grout, mortar, sealant, and/or root
control chemicals proposed and provide case histories of successful use or defend
the choice of grouting materials based on chemical and physical properties, ease of
application, and expected performance. These grouting materials shall be
compatible with Raven 405 interior coating. The contractor shall be responsible for
getting approval from Raven Lining systems and/or the grout manufacturers for the
use of these grouting materials.
5. Mixing and Handling
Mixing and handling of interior coating, which may be toxic under certain conditions
shall be in accordance with the recommendations of the manufacturer and in such a
manner as to minimize hazard to personnel. It is the responsibility of the Contractor
to provide appropriate protective measures to ensure that materials are under control
at all times and are not available to unauthorized personnel or animals. All
equipment shall be subject ta the approval of the Engineer. Coating shall be
performed only by certified applicators approved by the manufacturers.
C. EXECUTION
11/02104
1. General
Manhole coating shall not be performed until sealing of manhole from frame and
grade adjustments, partial manhole replacement, manhole grouting or sewer
replacement/repairs are complete.
2 . Temperatures
Normal interior coating operation shall be performed at temperatures of 40°F or
greater. No application shall be made when freezing is expected within 24 hours.
3. Interior Manhole Coating
a. Manholes scheduled far interior coating are shown on the Manhole
Rehabilitation Schedule. The interior coating shall be applied ta the manhole
from the bottom of the manhole frame to the bench/trough, including the
bench/trough.
ASC-15
PART DA -ADDITIONAL SPECIAL CONDITIONS
b. The interior coating shall be installed in accordance with the manufacturer's
recommendations and the following procedure. .
1) The surface preparation shall comply with the requirements of Section
DA-11, SURFACE PREPARATION FOR MANHOLE
RESTORATION.
2) Apply a minimum of one-half (1/2) inch specialty cement-based
product (Quadex QM-1s or Reliner MSP) smooth surface for the
ure thane coating material.
3) The surface prior to application may be damp but shall not have
noticeable free water droplets seeping or running water. Material
shall be spray applied per manufacturer's recommendations with a
minimum thickness of 125 mils (0.125 inch).
4) After the walls are coated, the wooden bench covers shall be
removed and the bench sprayed to the same average and minimum
thickness as required for the walls.
5) The final application shall have a minimum of three (3) hours cure
time or be set hard to the touch, before being subjected to active flow.
6) No applications shall be made to frozen surfaces or if freezing is
expected to occur in side the manhole within 24 hours after
application.
4 . Testing of Rehabilitated Manholes
a. After the epoxy liner has set (hard to touch), all visible pinholes shall be
repaired. Repairs shall be made by lightly abrading the surface and brushing
the lining material over the area. All blisters and evidence of uneven cover
shall be repaired according ta the manufacturer's recommendations. Spot
check of coating thickness may be made by Owner's Representative, and the
contractor shall repair these areas as required, at no additional cast ta the
Owner.
b. Testing of rehabilitated manholes for water tightness shall be performed by
the Contractor after operations are complete in accordance with Section DA-
21 -VACUUM TESTING OF REHABILITATED MANHOLES.
D. MEASUREMENT AND PAYMENT
Payment shall be based on the Contract Unit Price per vertical foot, measured from the
. bottom of the frame to the top of the bench . The Contract Unit Price shall be payment in full
for · performing the work and for furnishing all labor, supervision, materials, equipment all
testing necessary to complete the work. Payment for grouting of pipe seals, bench and
trough and manhole walls shall be based on the Contract Unit Price for each manhole
actually grouted.
11/02104 ASC-16
PART DA -ADDITIONAL SPECIAL CONDITIONS
DA-16 OMIT
DA-17 OMIT
DA-18 OMIT
DA-19 OMIT
DA-20 OMIT
DA-21 OMIT
DA-22 OMIT
DA-23 OMIT
DA-24 OMIT
DA-25 OMIT
DA-26 OMIT
DA-27 OMIT
DA-28 OMIT
DA-29 OMIT
DA-30 OMIT
DA-31 OMIT
DA-32 OMIT
DA-33 OMIT
DA-34 OMIT
DA-35 OMIT
DA-36 OMIT
DA-37 POTENTIALLY PETROLEUM CONTAMINATED MATERIAL HANDLING
A. GENERAL :
11/02104
Where known by the design engineer, the locations of potentially petroleum contaminated
material (soil) that may be encountered during excavation and/or construction activities will
be shown on the plans. For all 1.ocations where material is excavated and suspected of
being contaminated with petroleum products, whether known or not, these special conditions
are to be followed. The contractor is also to follow all applicable Federal. State and Local
regulations when handling known or suspect contaminated materials (soils).
1. WORK INCLUDED
a . Excavation, stockpiling and testing of Potentially Petroleum Contaminated Material.
b. Removal, testing, and disposal of petroleum contaminated groundwater.
c. Obtaining and paying for required permits.
d. Hiring of qualified environmental professional consultant(s). Contractor will be
required to submit the environmental consultant's experience and qualifications to
the City prior to beginning work in areas of Potentially Petroleum Contaminated
Material.
e. Hiring of qualified environmental sampling professionals that will collect and submit
samples to the applicable City of Fort Worth testing laboratory. The City of Fort
Worth's Department of Environmental Management for coordination of laboratory
testing. ·
ASC-17
PART DA -ADDITIONAL SPECIAL CONDITIONS
2. REFERENCES
a. All applicable OSHA regulatory requirements.
b. All applicable Env ironmental Protection Agency (EPA) regulatory requirements .
c. All applicable State of Texas regulatory requirements .
d. All applicable City of Fort Worth (City) regulatory requirements .
e. All applicable NIOSH standards.
f. All applicable TNRCC requ irements .
3. SUBMITIALS
a. The contractor shall prepare and submit to the City 's Department of Environmental
Management, Senior Specialist in Compliance, plans for handling Potentially
Petroleum Contaminated Material (PPCM) not less than 30 days prior to
commencing excavation.
b. The Contractor shall take necessary precautions while performing this project.
Contractor shall not commence PPCM work (1) Contractor's submittal for dealing
with PPCM is reviewed by the City and (2) the plans (i.e., drawing and description)
for discharging any treated liquid into the storm sewer or sanitary sewer are reviewed
by the City (3) and acceptable stockpile area is identified by the Contractor.
c. Contractor shall submit the name of his proposed qualified environmental
professional cons ultant(s) and proposed PPCM Handling Plan to the City. The
PPCM Handling Plan shall include the detailed sequence of construction including
proposed excavation and handling methods, proposed carriers for contaminated
materials, waste disposal site, and a list of any permits that may be required for
PPCM handling or contaminated materials disposal. The above data must be
compiled and arra nged in a format that is acceptable to the Texas Natural Resource
Conservation Commission (TNRCC}.
d. Contractor shall submit actual limits of PPCM excavation , as prepared by his
qualified environmental consultant(s) and testing lab .
e. Contractor shall submit for review the proposed carrier pipe material to be used with
the actual limits of PPCM excavation, including pipe gasket and carrier pipe coating
or liner.
B. PRODUCTS :
1. PIPE GASKET MATERIAL. Materials used within the actual limits of PPCM excavation,
including pipe gaskets , shall be resistant to petroleum hydrocarbon deterioration.
C. EXECUTION:
1. POTENTIALLY PETROLEUM CONTAMINATED AREAS
11/02/04 ASC-18
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
a. Areas suspected of having petroleum contaminated material (soils) are shown in on
the engineering drawings .
b. In areas other than those noted on the plans and where potentially petroleum
contaminated materials are either detected or suspected , the City of Fort Worth and
the Engineer should be notified immediately and the work should proceed in
accordance with this section.
2. SCREENING POTENTIALLY PETROLEUM CONTAMINATED AREAS
a. Care should be taken during all excavation and dewatering activities to identify areas
potentially contaminated by petroleum .
b. When a petroleum odor is encountered during excavation or when there is visual
evidence of potentially petroleum contaminated soil , the Contractor shall notify the
Engineer without delay.
c . The Contractor shall have retained the services of an environmental consultant who
shall be present at the site to screen suspect soil with a photo-ionization detector
(PIO) or a flame ionization detector (FID). A read ing of 20 ppm above ambient
conditions or greater on PIO or FID tested soil sample will be considered potentially
petroleum contaminated. The soul sample should be a recent sample from the
excavation face . The sample should be stored in a laboratory supplied glass jar with
a teflon gasket lined lid . The City of Fort Warth Department of Environmental
Management will be notified prior to all sample collection and submittal to the current
testing laboratory identified by the City . The PIO or FID tests should be performed in
a confined location. Soils producing a reading of less than 20 ppm above ambient
will not be considered potentially petroleum contaminated . The PIO or FID shall be
calibrated according ta manufactures instructions.
d. Water encountered during excavation or dewatering shall be considered to be
potentially contaminated if there is a visible she.en, a hydrocarbon odor, adjacent sail
that appears visually to be contaminated by hydrocarbons or at any time the
Contractor has reason to believe that hydrocarbon contamination may have
occurred. The Contractor shall immediately notify the City and the TNRCC whenever
contaminated water is encountered .
e. The Contractor . shall contact the City whenever contamination from any source is
suspected .
3. HANDLING POTENTIALLY PETROLEUM CONTAMINATED SOIL (PPCS)
a. Contractor shall coordinate with the City to determine a suitable location for the
stockpiling of contaminated soil. The following procedure shall be followed in
preparing the chosen site:
1. Provide a diked enclosure large enough ta hold all material and prevent runoff.
2. The diked area shall be lined with 20-30 mils plastic to prevent seepage into the
existing soil.
3. At the end of each work day, Contractor shall completely cover stockpile with 20
mil plastic. During the day , the Contractor shall keep the stockpile covered , as
necessary, to prevent release of contaminated materials due to rain or wind.
ASC-19
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
4 . Sampling and evaluation of materials will be pe.rformed at the Contractor's
expense. (The City of Fort Worth will provide laboratory services)
b. PPCS shall be handled , tested, observing all standard chain-of-custody procedures
and sampling preservation and analyses shall conform to published and recognized
standards .
c. The stockpiled PPCS shall be sampled and tested every 50 cubic yards for Total
Petroleum Hydrocarbons (TPH) (TX1005) and Benzene , Toulene, Ethylbenzene and
Xylene (BTEX) (EPA 8020). All test results will be forwarded to the City of Fort
Worth Department of Environmental Management.
d. Contam inated soil identified by test results will be disposed of according to DA-36,
Loading , Transportation , and Disposal of Contaminated Soil.
e . It is the intent of the City of Fort Worth that uncontaminated soils be utilized as
backfill material, if the soils also meet the Type C or B backfill classifications.
4 . HANDLING POTENTIALLY PETROLEUM CONTAMINATED WATER (PPCW)
a. Water pumped from the excavation or from dewatering activities that has an oily
sheen , a hydrocarbon odor, or is otherwise suspect , shall be considered potentially
petroleum contaminated.
b. PPCW shall be handled , tested, and discharged in accordance w ith the TNRCC's
appropriate state regulation . PPCW shall be tested no later than 15 days prior to
extraction . PPCW shall, if necessary, be treated in an appropriately sized oil/water
separator, air strip per or GAC canisters . Contractor shall have his testing laboratory
determine that the oil/water separator treated discharge is within the limits
established by the TNRCC 's regulations before being allowed to discharge
(discharge to san itary sewer). Contractor shall be responsible for furnishing the
effluent test reports to the City.
c . Alternatively, the Contractor may dispose of contaminated water, after appropriate
pretreatment, into the sanitary sewer collection system . It shall be the responsibility
of the Contractor to obtain the necessary permit(s) and to perform all testing required
by the City of Fort Worth Pretreatment Services Division .
d. All treated water shall be discharged into a Contractor supplied Frac Tank , sampled,
and analyzed befo re discharge into the sewer system.
e. The product that is recovered shall be disposed of in accordance with all applicable
regulations . Any phase separate product recovered from the oil/water separator and
air stripper shall be transported in accordance with Department of Transportation
rules and regulat ions for flammable products. When transporting product for
disposal, transportation shall also be performed by a licensed carrier. The
Contractor is responsible for proper manifesting of the material from the site to the
waste disposal facility. Completed Manifests shall be returned to the City
Department of Environmental Management within 90 days of shipment.
ASC-20
PART DA -ADDITIONAL SPECIAL CONDITIONS
5. HANDLING VAPOR CONCENTRATIONS
a. In order to maintain safe working conditions, the vapor concentrations should not
exceed 20 percent of the Lower Explosive Limit (LEL). During construction,
measures should be taken to maintain LEL levels below 20 percent in all working
areas.
b. To monitor vapor levels and oxygen levels a combustible gas indicator (CGI) with a
LEU02 meter should continuously operate in the working area. The CGI should be
properly calibrated and should have an alarm that sounds if 20 percent LEL is
reached. Monitoring data from the GCI should be recorded periodically to determine
if ventilation or other methods are effective. In the event local health and safety
agencies require more stringent monitoring, the local regulations must be
implemented.
D. MEASUREMENT AND PAYMENT:
Payment for handling PPCS, PPCW and Vapor Concentrations, obtaining and paying for
any permits required, hiring the services of a qualified professional environmental
consultant(s), environmental issues, stockpiling and all issues included and incidental to this
section will be full compensation for all labor, equipment, materials, and supervision.
Measurement and Payment for this section will be per linear foot of trench excavated where
the excavated material is handled as a contaminated material. No separate payment will be
made for handling of contaminated water, vapor concentrations, sampling, stockpiling, etc.
DA-38 LOADING, TRANSPORTATION, AND DISPOSAL OF CONTAMINATED SOIL
A. GENERAL:
This item has been established for the loading, transportation and disposal of contaminated
soils in a State of Texas approved disposal site (landfill) to handle special wastes
(petroleum contaminated soils). A bid item has been established in the proposal for the
proper loading, transportation and disposal of the material to a designated site and the
quantity established is the engineer's best estimate of the quantity that may be removed.
This quantity may vary depending upon actual conditions and testing results. The unit
price bid will not be increased regardless of the actual amount of material disposed and
may be decreased if a larger volume of material, than that listed in the bid proposal,
results in a unit cost reduction for disposal.
B. WASTE MANIFESTS:
11/02104
Any and all nan-hazardous liquid and petroleum substance waste removed from the site
of generation and transported for treatment and/or disposal must be accompanied by a
waste shipment record/manifest detailing required generator, transported, destination
and waste description information. These results may not be uniform throughout the
entire site. For all petroleum substance waste, the waste shipment record utilized shall
be the TNRCC PETROLEUM-SUBSTANCE WASTE AFFIDAVIT (Form TWC-0332).
The Contractor shall be responsible for obtaining, originating and maintaining manifests
in accordance with federal and state laws. The Contractor shall sign the manifests forms
as Independent Contractor to the Owner. AUTHORIZATION OF PAYMENT FOR
REMOVAL TRANSPORT AND TREATMENT / DISPOSAL OF WASTES IN
ASC-21
PART DA -ADDITIONAL SPECIAL CONDITIONS
CONTINGENT UPON RECEIPT BY THE ENGINEER OF FULLY COMPLETED AND
SIGNED MANIFEST FORMS that are in agreement with regard to the type and amount
of waste removed from the site and received by the treatment/disposal facility. The
Contractor shall immediately resolve any manifest discrepancies. Completed Manifests
shall be returned to the City Department of Environmental Management within 90 days of
shipment.
C. MEASUREMENT AND PAYMENT :
Payment for this item shall be made per in place cubic yard of contaminated sails that
are loaded, transported and disposed of in an approved special disposal site. No
separate payment will be made for loading, transportation and disposal of contaminated
ground waters collected; these costs considered subsidiary to DA-37, POTENTIALLY
PETROLEUM CONTAMINATED MATERIAL HANDLING. The proposed landfill shall be
included in the Contractor's bid submittal and approved by the City of Fort Warth
Department of Environmental Management prior to contract award. Contractor shall be
responsible for all landfill costs, including , but not limited to landfill fees, transportation
costs and landfill operator requested analytical testing and waste characterization.
DA-39 ROCK RIPRAP -GROUT-FILTER FABRIC
A. GENERAL:
1. General Conditions, Supplemental Conditions, applicable requirements of Division 1 -
General Requirements and the North Central Texas Council of Governments
(NCTCOG) Standard Specifications, are hereby made a part of this section.
2. This item shall govern for the installation of rock riprap of the various sizes shown on
the plans.
B. DESIGN CRITERIA:
1. The toe of the riprap revetment shall be entrenched in stable channel bottoms. If the
channel bottom is not stable, the design shall incorporate other requirements needed
to stabilize the revetment toe.
2. The channel side slope shall be as shown on the drawings.
3. Engineering filter fabric material shall be placed underneath the riprap.
4. Riprap shall extend up the bank to an elevation where vegetation will provide
adequate protection. See cross sections.
C. PRODUCT:
11/02104
1. RIPRAP MATERIAL: Stone for riprap shall be durable and of a suitable quality to
insure permanence in the structure. It shall be free from cracks, seams and other
defects that would tend to increase deterioration. Rock shall be reasonably well
graded between the following prescribed limits:
Sieve Size
ASC-22
-
PART DA -ADDITIONAL SPECIAL CONDITIONS
24"
Riprap
18"
Riprap
(Square Mesh)
24inch
18inch
12inch
6inch
Sieve Size
(Square Mesh)
18 inch
12inch
6inch
3inch
Percent Passing
100
80-90
45-55
0-20
Percent Passing
100
60-85
15-45
0-15
2. RIPRAP WEI.GHT : Weight of rock shall be one hundred fifty five pounds per solid
cubic foot (min.) calculated from the bulk specific gravity (saturated surface dry).
3. FILTER FABRIC BLANKET:
Approved Manufacturer: • Supac -Heavy Grade BNP (UV)
• Trevira 011/280
• Amoco 4553
• or Equal Heavy Grade
4 . RIPRAP GROUTING
a. FINE AGGREGATE: Fine aggregate for grouting mix shall consist of natural sand,
manufactured sand, or a combination of natural and manufactured sands. The
grading and uniformity of the fine aggregate shall conform to the following
requirements as delivered to the mixers:
Sieve Designation, U.S.
Standard Square Mesh
3/8 in. (9.5 mm)
No. 4 (4.75 mm)
No. 8 (2.36 mm)
No . 16 (1.18 mm)
No. 30 (600 um)
No. 50 (300 um)
No. 100 (150 um)
Permissible Limits
Percent by Weight, Passing
100
95-100
80-95
55-75
30-60
12-30
2-10
D. EXECUTION :
11/02104
1. CONSTRUCTION:
a . The channel side slope and the toe excavation shall be prepared ta the required
lines and grades.
b. Filter fabric and riprap shall be placed in succession to the required thicknesses
and elevations. Riprap shall be hand placed around structures to prevent damage
to the structures .
ASC-23
PART DA -ADDITIONAL SPECIAL CONDITIONS
2. INSTALLATION OF THE FILTER FABRIC (GEOTEXTILE): The geotextile shall be
placed in the manner and at the locations shown on the drawings . At the time of
installation, the geotextile shall be rejected if it has defects, rips , holes, flaws ,
deterioration or damage incurred during manufacture, transportation or storage. The
surface to receive the geotextile shall be prepared to a relatively smooth condition free
of obstructions , depressions, debris , and soft or low density pockets of material.
Erosion features such as rills , gullies , etc . must be graded out of the surface before
geotextile placement. The geotextile shall be placed with the long dimension
perpendicular to the centerline of the channel and laid smooth and free of tension,
stress , folds, wrinkles, or creases . The strips shall be placed to provide a minimum
width of 24-inches of overlap for each joint. Temporary pinning of the textile to help
hold it in place until the rock riprap is placed . The temporary pins shall be removed as
the riprap is placed to relieve high tensile stress which may occur during placement of
material on the geotextile . The specified placement procedure requires that the length
of the geotextile be greater than the actual slope length. The Contractor shall adjust
the actual length of the geotextile used based on initial installation experience . The
geotextile shall be protected at all times during construction from contamination by
surface runoff and any geotextile so contaminated shall be removed and replaced with
uncontaminated geotextile. Any geotextile damaged during its installation or during
placement of riprap shall be replaced by the Contractor at no cost to the Owner. The
work shall be scheduled so that the covering of the geotextile with a layer of the
specified material is accomplished within seven (7) calendar days after placement of
the geotextile . Failure to comply shall require replacement of geotextile. The
geotextile shall be protected from damage prior to and during the placement of rock
riprap . Before placement of gabion units , the Contractor shall demonstrate that the
placement technique will prevent damage to the geotextile . In no case shall any type
of equipment be. allowed on the unprotected geotextile .
3. RIPRAP PLACEMENT: Stone for riprap shall be placed on the filter fabric blanket in
such a manner as to produce a reasonably well graded mass of rock with the minimum
practicable percentage of voids and shall be constructed within the specified tolerance
to the lines and grades shown on the drawings. Then intent of these specifications is
to require placement of riprap to the thickness shown and to allow isolated stones to
extend as much as six inches above grade . Riprap shall be placed to its full course
thickness at one operation and in such a manner as to avoid displacing the fabric. The
larger stones shall be well distributed and the entire mass of stones in their final
position shall conform to the gradation specified hereinbefore. The finished riprap
shall be free from objectionable pockets of small stones and clusters of larger stones.
The desired distribution of the various sizes of stones throughout the mass shall be
obtained by selective loading of the material at the quarry or other source, by
controlled dumping of successive loads during final placing, or by other methods of
placement which will produce the specified results. Rearranging of individual stones,
by mechanical equipment or by hand will be required to the extent necessary to obtain
a reasonably well graded distribution of stone specified above. The Contractor shall
maintain the riprap protection until accepted. Any material displaced by any cause
shall be replaced at his erosion to the lines and grades shown on the Drawings.
4. GROUT PLACEMENT: Grout shall be composed of cement, water and air-entraining
admixture and sand mixed in the proportions of 1 part of Portland cement to 3 parts of
sand, sufficient water to produce a workable mixture, and that amount of admixture
which will entrain sufficient air to produce durable grout, as determined by the
11102104 ASC-24
PART DA -ADDITIONAL SPECIAL CONDITIONS
ENGINEER. Sand for grouting shall conform to the requirements of paragraph : FINE
AGGREGATE. The grout shall be mixed in a concrete mixer in the manner specified for
concrete except that the time of mixing shall be increased to that necessary to produce a
mixture having a consistency such as to permit gravity flow into the interstices of the
riprap with the help of limited spading and brooming. The grout shall be used in the work
within a period of one (1} hour after mixing. Retempering of ground will not be permitted.
Riprap shall not be grouted when the ambient temperature is below 35 degree F. or
above 95 degrees F. unless approved by the ENGINEER in writing; nor when the grout,
without special protection, is likely to be subjected to freezing temperatures before final
set has occurred. Prior to grouting, all surfaces of riprap shall be wetted. The riprap
shall be grouted in successive longitudinal strips, approximately 10 feet in width,
commencing at the lowest strip and working up the slope. Grout shall be brought to the
place of final deposit by approved means, and in no case will grout be permitted to flow
on the rip rapped surface a distance in excess of 10 feet. Immediately after dumping the
batch of grout, it shall be distributed over the surface of the strip by the use of brooms
and the grout worked into place between stones with suitable spades, trowels, or
vibrating equipment. As a final operation, the grout shall be removed from the top
surfaces of the upper stones and from pockets and depressions in the surface of the
stone protection. After completion of any strip as specified, no workman or any load
shall be permitted on the grouted surface for a period of at least 24 hours. The grouted
surface shall be protected from rain, flowing water, and mechanical injury. The surface
of all grouted riprap shall be cured by keeping the surface continuously wet for a period
of not less than 7 days.
E. MEASUREMENT AND PAYMENT
1. FILTER FABRIC: Filter fabric will be measured by the square yard for material used
including that required at toes and thickened edges of riprap. Payment for filter fabric
will be made at the contract unit price per square yard which includes all plant, labor,
material, and all installation costs in-place, complete.
2 . STONE RIPRAP: Stone (rock) riprap will be measured by the cubic yard using actual
plan dimensions. Payment for riprap will be made at the contract unit price per cubic
yard which includes all plant, labor, material, and installation costs in-place, complete.
3. GROUT: Grout for rock riprap will be measured by the square yard using actual plan
dimensions. Payment for grout will be made at the contract unit price per square yard
which includes all plant, labor, material, and installation casts in-place, complete.
DA-40 OMIT
DA-41 OMIT
DA-42 OMIT
DA-43 OMIT
DA-44 OMIT
DA-45 REPLACEMENT OF 4" CONCRETE SIDEWALKS
This item shall include the removal and replacement of existing concrete sidewalk due to failure or
in situation where curb and gutter is replaced to adjust grades to eliminate ponding water with
11/02104 ASC-25
PART DA -ADDITIONAL SPECIAL CONDITIONS
same day haul-off of the removed material to a suitable dumpsite. For specifications governing
this item see Item No . 104 "Removing Old Concrete ", and Item No. 504 "Concrete Sidewalk and
Driveways".
The unit price bid per square yard shall be full compensation for all labor, material, equipment,
supplies, and incidentals necessary to complete the removal and replacement work .
DA-46 OMIT
DA-47 PAVEMENT REPAIR IN PARKING AREA
The unit price bid under appropriate BID ITEM(S) of the Proposal shall cover all cost for providing
pavement repair equal to or superior in composition, thickness, etc., to existing pavement. All
required paving cuts shall be made with a concrete saw in a true and straight line on both sides of
the trench , a minimum of twelve (12) inches outside the trench walls. The trench shall be
backfilled and the top nine (9) inches shall be filled with crushed limestone base material,
compacted and level with the finished adjacent surface. This finished grade shall be maintained
in a serviceable condition until the paving has been replaced.
DA-48 EASEMENTS AND PERMITS
Easements and permits , both temporary and permanent, have been secured for this project at
this time and made a part thereto . Any easements and/or permits, both temporary and
permanent, which have not been obtained by the time of publication, shall be secured before
construction starts. No work is to be done in areas requiring easements and/or permits until the
necessary easements are obta ined. The Contractor's attention is directed to the easement
description and permit requirements, as contained herein, along with any special conditions that
may have been imposed an these easements and permits .
Where the pipeline crosses privately owned property, the easements and construction areas are
shown on the plans. The easements shall be cleaned up after use and restored to their original
conditions or better. In the event additional work room or access is required by the
Contractor, it shall be the Contractor's responsibility to obtain written permission from the
property owners involved for the use of additional property required. No additional payment
will be allowed for this item.
DA-49 HIGHWAY REQUIREMENTS
The Texas Department of Transportation requirements pertaining to the construction of this
project are enclosed herein and made part of these specifications.
DA-50 CONCRETE ENCASEMENT
Concrete encasement shall be Class E (1500 psi) concrete and for sewer line encasements shall
conform to Fig. 113 ; for water line encasements it shall conform to Fig. 20 of the General Contract
Documents. Requirements for such encasement are specified in Sections E1-20 and E2-20 of
the General Contract Documents .
11/02104 ASC-26
PART DA -ADDITIONAL SPECIAL CONDITIONS
Payment for work such as forming , placing, and finishing including all labor, tools , equipment and
material necessary to complete the work shall be included in the linear foot price bid for Concrete
Encasement.
DA-51 CONNECTION TO EXISTING STRUCTURES
AU connections between proposed and existing facilities shall consist of a watertight seal.
Concrete used in the connection shall be Class A (3000 psi) concrete and meet the requirements
of Section E1-20 and E2-20 of the General Contract Documents . Prior to concrete placement , a
gasket, RAM-Nek or approved equal shall be installed around penetrating pipe .
Payment for such work as connecting to existing facilities including all labor, tools , equipment,
and material necessary to complete the work shall be included in the linear foot price of the
appropriate pipe BID ITEM .
DA-52 OMIT
DA-53 OMIT
DA-54 OMIT
DA-55 OMIT
DA-56 SHOP DRAWINGS
1. Submit seven (7) copies of shop drawings, layouts , manufacturer's data and material
schedules as may be required by the Engineer for his review . Submittals may be checked by and
stamped with the approval of the Contractor and identified as the Engineer may require. Such
review by the Engineer shall include checking for general conformance with the design concept of
the project and general compliance with information given in the General Contract Documents.
Indicated actions by the Engineer, which may result from his review, shall not constitute
concurrence with any deviation from the plans and specifications unless such deviations are
specifically identified by the method described below, and further shall not relieve the Contractor
of responsibility for errors or omiss ions in the subm itted data. Processed shop drawing submittals
are not change orders . The purpose of submittals by the Contractor is to demonstrate that the
Contractor understands the design concept, and that he demonstrates his understanding by
indicating which equipment and materials he intends to furnish and install, and by detailing the
fabrication and installation methods he intends to use. If deviations, discrepancies or conflicts
between submittals and the design drawings and/or specifications are discovered, either pr ior to
or after submittals are processed, the design drawings and specifications shall govern. The
Contractor shall be responsible far dimensions which are to be confirmed and correlated at the
job site, fabrication processes and techniques of constriction, coordination of his work with that of
other trades and satisfactory performance his work. The Contractor shall check and verify all
measurements and review submittals prior to being subm itted , and sign or initial a statement
included with the submittal, which signifies compliance with plans and specifications and
dimensions suitable for the application . Any deviation from the specified cr iteria shall be
expressly stated in writing in the submittal. Three (3) copies of the approved submittals shall be
retained by the Contractor until completion of the project and presented to the City in bound form .
2 . Shop drawings shall be submitted for the following items prior to installation:
List the require.ct submittals here
11/02/04 ASC-27
PART DA -ADDITIONAL SPECIAL CONDITIONS
Additional shop drawing requirements are described in some of the material specifications .
3. Address for Submittals -The s ubmittals shall be addressed to the Project Manager:
Liam Conlon
City of Fo rt Worth
1000 Thro c kmorton
Fort Worth , TX 76102
DA-57 COST BREAKDOWN
In order to establish a basis upon which partial payments to the Contractor may be authorized,
immediately after execution of the contract the Contractor shall furnish a detailed cost breakdown
of his contract price arranged and itemized to meet the approval of the Engineer.
DA-58 OMIT
DA-59 OMIT
DA-60 OMIT
DA-61 .0MIT
DA-62 OMIT
DA-63 BID QUANTITIES
Bid quantities of the various items in the proposal are for comparison only and may not reflect the
actual quantities. There is no lim it to which a bid item can be increased or decreased .
Contractor shall not be entitled to renegotiation of unit prices regardless of the final measured
quantities . To the extent that C4-4.3 conflicts with this provision, this provision controls . No claim
will be considered for lost or anticipated profits based upon differences in estimated quantities
versus actual quantities.
In particular, the Contractor shall be aware that it is the City's intention that the quantities in Unit I
be used on an "emergency" basis only.
Total quantities given in the bid proposal may not reflect actual quantities; however, they are
given for the purpose of bidding and awarding the contract. A contract in the amount of $200,000
(see Options to Renew) shall be awarded with final payment based on actual measured quantities
and the unit price bid in this proposal. Moreover, there is to be not limit on the variation between
the estimated quantities shown and actual quantities performed.
It is understood and agreed that the scope of work contemplated in this contract is that which is
designated by the City bit will in not case exceed $200,000 (see Options to Renew) including all
change orders .
DA-64 WORK IN HIGHWAY RIGHT OF WAY
When the Engineer directs the Contractor to perform work in the right-of-way which is under the
jurisd iction of the Texas Department of Transportation (Tex-Dot), the Contractor shall obtain
11/02/04 ASC-28
PART DA -ADDITIONAL SPECIAL CONDITIONS
approval from the Texas Department of Transportation prior to commencing any work therein . AU
work performed in the Tex-Dot right-of-way shall be performed in compliance with and subject to
approval from the Texas Department of Transportation and Item E2-29.1 "Construction Within
Highway Right-of-Way'' of the General Contract Documents and Specifications, effective July 1,
1978, as amended.
DA-65 OMIT
DA-66 OMIT
DA-67 OMIT
DA-68 OMIT
DA-69 OMIT
DA-70 PAVEMENT STRIPING
Pavement striping, whenever and wherever encountered, shall be replaced to match the existing
striping or as directed by the Engineer. Materials used shall be of 420 Type intersection grade
tape (in 18-inch width) such as Stamark as manufactured by 3M company or approved equal.
The unit price bid for this item shall be full compensation for all materials , labor, equipment and
incidentals necessary to complete the work.
DA-71 OMIT
DA-72 SPECIFICATION REFERENCES
When reference is made in these specifications to a particular ASTM , AWWA, ANSI or other
specification , it shall be understood that the latest revision of such specification , prior to the date
of these general specifications or revisions thereof, shall apply.
DA-73 OMIT
DA-74 RESILIENT-SEATED GATE VALVES
Any resilient-seated gate valves supplied for this contract shall conform to Material Standard
E1-26 , STANDARD SPECIFICATIONS FOR RESILIENT-SEATED GATE VALVES, with the
exception of size requirements in sections E-26 .1. All resilient-seated gate valves shall be
mechanical joints and be approved on the City of Fort Worth Standard Product List.
DA-75 OMIT
DA-76 OMIT
DA-77 OMIT
DA-78 OMIT
DA-79 OMIT
DA-80 OMIT
DA-81 OMIT
DA-82 OMIT
DA-83 OMIT
DA-84 OMIT
DA-85 OMIT
DA-86 OMIT
11/02104 ASC-29
PART DA -ADDITIONAL SPECIAL CONDITIONS
DA-87 OMIT
DA-88 OMIT
DA-89 OMIT
DA-90 OMIT
DA-91 OMIT
DA-92 OMIT
DA-93 OMIT
DA-94 OMIT
DA-95 OMIT
DA-96 OMIT
DA-97 OMIT
DA-98 OMIT
DA-99 OMIT
DA-100 OMIT
DA-101 OMIT
DA-102 OMIT
DA-103 OMIT
DA-104 OMIT
DA-105 OMIT
DA-106 OMIT
DA-107 OMIT
DA-108 FLOWABLE FILL (MISC. EXT.)
1. Description :
The flowable fill material shall be delivered to the site , free flowing and self-leveling and shall
have a consistency enabling it to fill all voids without tamping, vibrating or compacting.
The flowable fill material shall ha ve an in place density of not less than 95 and not more than 115
lbs./cu . ft., with a maximum twenty-eight (28) day compression strength of not less than 60 and
not more than 85 PSI allowing t he material to be removed with hand tools such as picks and
shovels. The height of free fall of the flowable fill shall not exceed four (4) feet.
2 . Material Specifications:
Flowable fill shall consist of:
a . An appropriate amount of Portland Cement meeting ASTM C-150 (w ith other add itives as
necessary).
b. Aggregates meeting ASTM C-33
c. Sand or fine aggregates as per City of Ft. Worth Standard Specifications far Street and Storm
Drain Construction Item 406
d . Flyash, Class C or F, meeting ASTM C-618
e. Admixtures
11/02104
1. Mineral admixture s will be pozzolanic
2. Chem ical admixtures shall be in liquid or powder form used in standard ready -mix
concrete products unless specifically des igned for flowable fill . Permissible types of
admixtures are :
ASC-30
DA-109
DA-110
DA-111
DA-112
DA-113
DA-114
DA-115
DA-116
DA-117
PART DA -ADDITIONAL SPECIAL CONDITIONS
OMIT
OMIT
OMIT
OMIT
OMIT
OMIT
OMIT
OMIT
a. High air generators, as manufactured by Grace Construction Products
or approved equal, which are specifically designed for flowable fill to
lower unit weights, reduce shrinkage and subsidence, and control
compressive strength.
b. Air entraining admixtures conforming to ASTM C-260 .
c. High range water reducers conforming to ASTM C-494 Type F or G.
d. Accelerating admixtures conforming to ASTM C-494, Type C.
1. Non-chloride, non-corrosive accelerators used where metals
are present in concrete or embedded members.
2. Calcium chloride
TRAFFIC CONTROL PLAN
Traffic control shall be in accordance with item D-8 of the Special Conditions with the exception of
the Contractor providing the traffic control plan. A traffic control plan has been prepared and is
included in the project plans. All other requirements of 0-8 shall apply.
DA-118 OMIT
DA-119 ABANDON EXISTING PIPE LINE
This item shall consist of filling existing sanitary sewer pipe to be abandoned with cement slurry
as designated in the construction plans. Concrete slurry material shall be in accordance with the
requirements of the Texas Department of Transportation.
Payment for this item shall be per linear foot of pipe filled with cement slurry . This cost shall
include all labor, material, and equipment associated with filling existing sanitary sewer pipe with
concrete slurry.
DA-120 ABANDON EXISTING SANITARY SEWER MANHOLE
Manholes to be abandoned in place shall have all pipes entering or exiting the structure plugged
with lean concrete. Manhole top or cone section shall be removed to the top of the full barrel
diameter section, or to a point not less than 18-inches below final grade. The structure shall then
be backfilled using flowable fill, per item DA-108. Surface restoration shall be compatible with
surrounding service surface. Payment for work involved in backfilling, plugging of pipe(s) and all
other appurtenances required, shall be included in the bid item.
11/02104 ASC-31
PART DA -ADDITIONAL SPECIAL CONDITIONS
DA-121 SUBSURFACE EXPLORATION
Any data, which has or may be provided on subsurface conditions, is not intended as a
representation or warranty of accuracy or continuity between soil strata. It is expressly understood
that neither the Owner nor the Engineer wil.l be responsible for interpretations or conclusions
drawn there from by the Contractor. Data is made available for convenience of the Contractor.
Subsurface exploration , to ascertain the nature of the soils at the project site, including the
amount of rock, if any , is to be the responsibility of any and all prospective bidders.
Whether prospective bidders perform this subsurface exploration jointly or independently, it shall
be left to the discretion of such prospective bidders . Subsurface exploration shall not be
attempted without the approval of the Owner.
The Geotechnical Boring Logs have been included in these specifications.
DA-122 DUCTILE IRON PIPE
A. GENERAL
1. SCOPE OF WORK
Furnish all labor, material, tools, equipment and incidentals required and install
buried ductile iron pipe and fittings complete as shown on the Drawings and as
specified herein.
2. QUALITY ASSURANCE
a. Manufacturer: Finished pipe shall be the product of one (1) manufacturer.
Pipe manufacturing operations (pipe, fittings , lining, and coating) shall be
performed at one (1) location.
b. Reference Standards:
1) ANSI/AWWA C104/A21.4 -American National Standard for cement
-Mortar Lining for Ductile-Iron Pipe and Fittings for water.
2) ANSI/AWWA C105/A21 .5 -American National Standard for
Polyethylene Encasement.
. 3) ANSI/AWWA C110/A21.10 -American National Standard for Ductile
Iron and Grey Iron Fittings, 3-inch through 48 inches for water and
other liquids.
4) ANSI/AWWA C111/A21.11 -American Nationai Standard for
Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings .
5) ANSI/AWWA C115/A21.15,7 American National Standard for
. Flanged Ductile-Iron Pipe with Ductile-Iron or Gray-Iron Threaded
Flanges.
11102104 ASC-32
..
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
6) ANSI/AWWA C150/A21.50 ,8 American National Standard for the
Thickness Design of Ductile-Iron Pipe .
7) ANSI/AWWA C151/A21.51 ,9 American National Standard for the
Ductile-Iron Pipe, Centrifugally Cast , for Water or Other Liquids.
8) ANSI/AWWA C153/A21 .53 , "Ductile-Iron Compact Fittings For
Water Service"
9) ANSI/AWWA C600 , 11 Installation of Ductile-Iron Water Mains and
Their Appurtenances .
10) AWWA M-41 Ductile-Iron Pipe and Fittings.
3 . SUBMITTALS
Submittals shall be in accordance with the Special Specifications and shall include
the following:
a . Prior to the fabrication of the pipe, submit Record Data of fabrication and
laying drawings to the Owner for review of general conformance to contract
documents. Record Data shall include a complete description of the pipe
offered , including cuts, tabulated layout, design calculations, thrust
calculations, and pertinent design data. Record Data shall incorporate any
changes necessary to avoid confl icts with existing utilities and structures.
The laying schedule shall show pipe class , class coding , station limits and
transition stations for various pipe classes. Details for the design and
fabrication of all fittings and specials and provisions for thrust shall be
included. Submittal shall be sealed by a Licensed Professional Engineer in
the State of Texas .
b . Submittal for painting exterior pipe to include recommendation for
preparation, application and storage.
c. Prior to delivery of the pipe to the project site , the manufacturer shall
furnish an affidavit certifying that all pipe , fittings, and specials, and other
products and materials furnished, comply with this specification . If
requested by the OWNER, the manufacturer shall submit certified reports
of all testing .
4. DELIVERY AND STORAGE
a. Delivery and Storage shall be in accordance with ANSI/AWWA C600 and
AWWA M41 .
ASC-33
PART DA -ADDITIONAL SPECIAL CONDITIONS
B. PRODUCTS
11/02104
1. DUCTILE IRON PIPE:
g.
h.
i.
a. Pipe shall be in accordance with NCTCOG 2.12 .8, AWWA C110, AWWA
C111, AWWA C115, AWWA C150, and AWWA C151. All pipe shall meet
the requirements of NSF 61.
b . Flexible Restrained Push on Joints (FRPJ) shall be U .S. Pipe -TR-Flex,
American -Flex-Ring, or approved equal.
c. All pipe shall be cement mortar coated in accordance with ANSI/AWWA
C104.
d . All buried pipe shall be polyethylene encased in accordance with AWWA
C105 .
e. As a minimum standard, the following pressure classes shall apply :
f.
Diameter Pipe (inch)
3" through 12"
14" -20"
24"
30"-64"
Min. Pressure Class (PSI)
350 psi
250 psi
250 psi
250 psi
Engineer shall verify that pressure class specified meets the minimum
design requirements contained within these provisions . When requested,
pipe design calculations shall be submitted to the City. Ductile iron pipe
shall be designed in accordance with the latest revision of ANSI/AWWA
C150/A21.50 for a minimum 150 psi (or project requirements, whichever is
greater) rated working pressure plus a 100 . psi surge allowance; a 2 to 1
factor of safety on the sum of the working pressure plus surge pressure;
Type 4 lay i ng condition, and a minimum depth of cover of 12 feet. Type 4
laying conditions are as defined in ANSI/AWWA C150/A21.50.
Mechanica l thrust restraint may be done only for make-up pieces where
push on joints are not applicable. Retainer glands shall be Series 1100
Megalugs by EBAA Iron for ductile iron pipe mechanical joints, Series
2000PV Mechanical Joint Restraint Glands by EBAA Iron for PVC pipe
mechanica l joints, and Series 1500 Ductile Iron Retainers for PVC pipe
push-on joints.
Ductile iron pipe shall have nominal lay lengths of 18 or 20 feet.
Dimensions and tolerances of each nominal pipe size shall be in
accordance with ANSI/AWWA C151/A21.
Pipe marki ngs shall meet the minimum requirements of ANSI/AWWA
C151/A21, latest revision. Minimum pipe markings shall be as follows:
ASC-34
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
1) "DI" or "DUCTILE" shall be cast or metal stamped on each pipe
2) Weight, pressure class, and nominal thickness of each pipe
3) Year and country pipe was cast
4) Manufacturer's mark
j. Iron used in the manufacture of pipe for these specifications shall have:
1) Minimum tensile strength -60,000 psi
2) Minimum yield strength -42 ,000 psi
3) Minimum elongation -10%
2. DUCTILE IRON PIPE JOINTS :
a. General -Comply with ANSI/AWWA C111/A21 .11, latest revision.
1) Push-On Joints
2) Mechanical Joints
3) Restrained Joints
4) Flanged Joints-AWWAC115/A21.15, ANSI B16.1 , Class 125
b. All rubber joint gaskets utilized on ductile-iron pipe shall be in conformance
with ANSI/AWWA C111/A21.11, latest revision.
c. Bolts and Nuts: Bolts and nuts for mechanical joints or flanged ends shall
be of a high strength corrosion resistant low-carbon steel in accordance
with ANSI/AWWA C111/A21.11, ANSI/AWWA C115/A21.15, and ASTM
A307, "Standard Specification for Carbon Steel Bolts and Nuts." For
mechanical joints, bolts and nuts shall be coated with a ceramic-filled,
baked on fluorocarbon resin. Coated bolts and nuts shall be prepared
"near white" or "white" when coated to manufacturer's recommended
thickness by a certified applicator. Coating shall be of Xylan® as
manufactured by Whitford Corporation, or approved equal. Coating shall
conform to the performance requirements of ASTM B 117, "Salt Spray Test"
and shall include, if required, a certificate of conformance;
3. DUCTILE IRON PIPE COATINGS:
a.
b.
C.
All ductile iron pipe shall have an asphaltic coating, minimum of 1 mil thick,
on the pipe exterior, unless otherwise specified.
Pipes shall have an interior cement mortar lining applied in accordance with
ANSI/AWWA C104/A21.04, or latest revision .
Pipe and fittings exposed to view in the finished work shall not receive the
standard asphaltic coat on the outside surfaces, but shall be shop-coated
with rust inhibitive primer. Primer shall have a minimum dry film thickness
of 4 mils and be certified in accordance with ANSI/NSF 61.
ASC-35
PART DA -ADDITIONAL SPECIAL CONDITIONS
d . All buried ductile iron pipe shall be polyethylene encased , unless otherwise
specified . Encasement for buried pipe shall be 8 mil linear low density
(LLD) polyethylene or 4 mil high density · cross-laminated (HDCL)
polyethylene encasement conforming to AWWA C105/A21.5 . Polyethylene
film must be marked as follows:
1) Manufacturer's name or trademark
2) Year of manufacturer
3) ANSI/AWWA C105/A21 .5
4) Mi nimum film thickness and material type
5) Applicable range of nominal diameter size(s).
6) Warning-Corrosion Protection-Repair Any Damage
e . For gravity sewer applications , all ductile iron pipe shall have an approved
corrosion resistant coating applied to the interior. Interior coating shall be
pre-approved by Fort Worth Water Department Standard Product
Committee for application in wastewater environment. Coating shall be-
Protecto 401 or approved equal.
4 . DUCTILE IRON PIPE FITTINGS:
a . Joints: Fittings shall have flanged, mechanical, restrained , push-on joints
or any combination of these. Joints must be manufactured in accordance
with the above referenced standards. Unless specified otherwise on the
plans or in the project specifications, fittings will be provided for installation
as follows :
b . Pressure Rating : Unless specified otherwise, the rated working pressures
for fittings are as follows :
Ductile Iron Compact Fittings (AWWA C153/A21.53)
Nominal Size (in)
3"-24"
30 "-48"
54 " -64"
Pressure Rating (PSI)
350 PSI
250 PSI
250 PSI
Ductile-Iron Full Body Fittings (AWWA C11 O/A21.10)
Nominal Size (in) Pressure Rating (PSI)
3" -24 " 350 PSI
30 " -48 " 250 PSI
11102104 ASC-36
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
C.
d .
e .
f .
g.
h .
i.
j.
Dimensions and Thickness : Fittings and joints shall conform to the
thickness and dimensions shown in the various standards referenced under
Section 1.02.B.
Flange : Unless specified otherwise, the bolt circle and the bolt-holes shall
match those of ANSI B16.1 Class 125. All screwed-on flanges shall be
ductile iron . Field fabrication of flanges shall be prohibited, unless
approved otherwise .
Gland: Glands shall be manufactured of ductile iron conforming to ASTM
A536. Restraining devices shall be of ductile iron. Dimensions of the gland
shall be such that it can be used with the standardized joint bell and tee-
head bolts conforming to ANSI/AWWA C153/A21 .53 .
Bolts and Nuts: Bolts and nuts for mechanical joints or flanged ends shall
be of a high strength corrosion resistant low-alloy steel in accordance with
ANSI/AWWA C111/A21.11 and ASTM A307, "Standard Specification for
Carbon Steel Bolts and Nuts". For mechanical joints , the bolts and nuts
shall be coated with a ceramic-filled , baked on fluorocarbon resin . Coated
bolts and nuts shall be prepared "near white " or "white" when coated to
manufacturer's recommended thickness by a certified applicator. Coating
shall be Xylan®, as manufactured by Whitford Corporation, or approved
equal. Coating shall conform to the performance requirements of ASTM
B 117, "Salt Spray Test" and shall include, if required, a certificate of
conformance.
Accessories : Unless otherwise specified, gaskets , glands, bolts, and nuts
shall be furnished with mechanical joints , and gaskets and lubricant shall
be furnished with push-on joints ; all in sufficient quantity for assembly of
each joint.
Outside Coating: All ductile fittings shall have an asphaltic or fusion
bonded epoxy coating. Asphaltic coatings shall be a minimum of 1 mil
thickness , on the pipe exterior, unless otherwise specified. Fusion bonded
exterior coatings shall comply with ANSI/AWWA C116/A21 .16, shall have a
minimum dry film thickness of 4 mils, and be certified in accordance with
ANSI/NSF 61 .
Interior Lining: All ductile iron fittings are to be furnished with a cement-
mortar lining of standard thickness as defined in referenced ANSI/AWWA
C104/A21.4 and given a seal coat of asphaltic material, unless otherwise
specified. Fusion bonded interior coatings shall comply with ANSI/AWWA
C116/A21.16, shall have a minimum dry film thickness of 4 mils, and be
certified in accordance with ANSI/NSF 61 .
Polyethylene Encasement: All ductile iron fittings shall be polyethylene
encased, unless otherwise specified. Encasement for buried fittings shall
be 8 mil linear low density (LLD) polyethylene or 4 mil high density cross-
laminated (HDCL} polyethylene encasement conforming to AWWA
C105/A21.5 . Polyethylene film must be marked as follows :
ASC-37
PART DA -ADDITIONAL SPECIAL CONDITIONS
1) Manufacturer's name or trademark
2) Year of manufacturer
3) ANSI/AWWA C105/A21.5
4) Minimum film thickness and material type
5) Applicable range of nominal diameter size(s).
6) Warning -Corrosion Protection -Repair Any Damage
k. Marking: Fitting marking shall meet the requirements of ANSI/AWWA
C110/A21 .10 or ANSI/AWWA C153/A21.53 shall have distinctively cast on
them the following information :
1) C-153 or C-110, depending on which type of fitting provided.
2) Pressure Rating
3) Nominal diameter of openings
4) Manufacturer's identification
5) Country where cast
6) Number of degrees or fraction of the circle on all bends
7) Letters "DI" or "DUCTILE" cast on them.
C. EXECUTION
11/02104
1. GENERAL:
a . Install, pipe, fittings, and appurtenances as special in accordance with
AWWA M41 and AWWA C600.
b. All pipe shall be mechanically restrained at fittings and within the calculated
restraint areas, or as shown on the drawings.
c. Polyethylene encasement shall be installed in accordance with AWWA
C105 and AWWA M41, Method A or B. Method C will not be allowed.
d . Where indicated, paint shall be applied per manufacturer's
recommendations .
e .
f.
Ductile iron pipe shall be manufactured in accordance with the latest
revision of ANSI/AWWA C151/A21.51 . Each pipe shall be subjected to a
hydrostatic test of not less than 500 psi for a duration of at least 10
seconds .
The manufacturer shall take adequate measures during pipe production to
assure compliance with ANSI/AWWA C151/A21.51 by performing quality-
control tests and maintaining results to those tests as outlined in section 5,
"Verification" of that standard.
ASC-38
PART DA -ADDITIONAL SPECIAL CONDITIONS
g. The City of Fort Worth may, at its own cost, subject random lengths of pipe
for testing by an independent laboratory for compliance with this
specification. Any visible defects or failure to meet the quality standards
herein will be grounds for rejecting the entire order.
h. The Contractor shall, upon request by City, furnish manufacturer's certified
test reports that indicate that each run of pipe furnished has met
specifications, that all inspections have been made, and that all tests have
been performed in accordance with ANSI/AWWA C151/A21.51.
i. The Contractor shall, upon request by City, furnish manufacturer's certified
test reports stating that all fittings furnished meet the requirements of
applicable Standards and Specifications. Test reports must be provided to
the Engineer before construction commences.
DA-123 CONCRETE PRESSURE PIPE, BAR-WRAPPED STEEL CYLINDER TYPE
A. GENERAL
11/02104
1. SUMMARY
a . Furnish labor, materials, equipment and incidentals necessary to install bar-
wrapped concrete cylinder pipe and fittings, and specials, including
connections and appurtenances as shown on the drawings and specified
herein.
b. Cathodic protection details and spacing requirements are shown in the
drawings and in the cathodic protection section of the specifications.
2. QUALITY ASSURANCE
a. Manufacturer: Finished pipe shall be the product of one (1) manufacturer.
Pipe manufacturing operations (pipe, fittings, lining, and coating) shall be
performed at one ( 1 ) location.
b. Factory Testing:
1) The OWNER reserves the option to have an independent testing
laboratory, at the OWNER's expense, inspect pipe and fittings at the
pipe manufacturer's plant. The OWNER's testing laboratory and
ENGINEER shall have free access to the manufacturer's plant. The
pipe manufacturer shall notify the OWNER, in writing, at least two
(2) weeks ahead of pipe fabrication as to start of fabrication and
fabricating schedule so that the OWNER can advise the
manufacturer as to OWNER's decision regarding tests to be
performed by an independent testing laboratory. In event the
OWNER elects to retain an independent testing laboratory to make
material tests and weld tests, it is the intent that the tests be limited
to one ( 1) spot testing of each category unless the tests do not
show compliance with the standard. If these tests do not show
ASC-39
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
compliance, the OWNER reserves the right to have the laboratory
make additional tests and observations.
2) The OWNER may require the manufacturer to furnish mill test
certificates on reinforcing steel or wire , steel plate, and cement.
The manufacturer shall perform the tests described in AWWA C303 ,
for all pipe, fittings, and specials, except that the following
absorption test shall supersede the requirements of the applicable
portion of AWWA C303 .
3) Absorption Test. A water absorption test shall be performed on
samples of cured mortar coating taken from each working shift. The
mortar coating samples shall have been cured in the same manner
as the pipe . A test value shall consist of the average of a minimum
of three samples taken from the same working shift. The test
method shall be in accordance with ASTM C497, Method A . The
average absorption value for any test shall not exceed 9 percent
and no individual sample shall have an absorption exceeding 11
percent. Tests for each working shift shall be performed on a daily
basis until conformance to the absorption requirements has been
established by 10 consecutive passing test results, at which time
test ing may be performed on a weekly basis for each working shift.
Da ily testing shall be resumed for each working shift with failing
absorption test results and shall be maintained until conformance to
the absorption requirements is re-established by 10, consecutive
passing test results.
4) The cost of all tests specified are subsidiary to the cost of the pipe
and will not be paid for separately.
c . Manufactu rer's Technician for pipe installation:
During the construction period, the Pipe Manufacturer shall furnish the
services of a factory trained, qualified, job experienced technician to advise
and instruct as necessary in pipe laying and pipe jointing. The technician
shall assist and advise the Contractor in his pipe laying operations and
shall instruct construction personnel in proper joint assembly and joint
inspection procedures. The technician is not required to be on-site full
time; however, the technician shall be regularly on-site during the first two
weeks of pipe laying and thereafter as requested by the Engineer, Owner,
or Contractor.
3. SUBMITIALS
Submittals shall be in accordance with the Special Conditions and shall include the
following:
a . Prior to the fabrication of the pipe, submit Record Data of fabrication and
laying drawings to the OWNER for review of general conformance to
contract documents . Record Data shall include a complete description of
the pipe offered, including cuts, tabulated layout, design calculations, joint
ASC-40
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS -
restraint and thrust calculations , and pertinent design data . Record Data
shall reference stationing on the plan profile sheets and shall incorporate
changes necessary to avoid conflicts with existing utilities and structures .
Deta ils for the design and fabrication of all fittings and specials and
provisions for thrust shall be included . Subm ittal shall be sealed by a
Licensed Professional ENGINEER in the State of Texas .
b . Prior to delivery of the pipe to the project site, the manufacturer shall
furnish an affidavit certifying that all pipe, fittings, and specials , and other
products and materials furnished, comply with this specification . If
requested by the OWNER, the manufacturer shall submit certified reports
of all testing required by AWWA C303 .
4 . STANDARDS
Except as modified or supplemented herein, pretension concrete cylinder pipe
shall conform to the applicable requirements of the following standard
specifications , latest edition .
a. AWWA C303 "Concrete Pressure Pipe -Bar-Wrapped Steel Cylinder
Type"
b. AWWA M9 Manual : "Concrete Pressure Pipe"
c . ASTM A33 "Standard Specification for Concrete Aggregates"
d . ASTM A635 "Standard Specification for Steel, Sheet and Strip, Carbon ,
Hot Rolled, Structural Quality"
e . ASTM C144 "Specification for Aggregate for Masonry Mortar"
f . ASTM C150 "Specification for Portland Cement"
g. ASTM C497 "Methods of Testing Concrete Pipe"
h. NCTCOG Item 2.12.5(a) through (d) and (h)
5. DELIVERY AND STORAGE
a. Packing:
1) The pipe shall be prepared for shipment to afford maximum
protection from normal hazard of transportation and allow pipe to
reach project site in an undamaged condition. Pipe damaged in
shipment shall not be delivered to the project site unless such
damaged pipe is properly repaired .
2) After the completed pipe . and fittings have been removed from the
final cure at the manufacturing plant, the pipe lining shall be
protected from drying by means of plastic end covers banded to the
pipe ends. Covers shall be maintained over the pipe ends at all
ASC-41
· PART DA -ADDITIONAL SPECIAL CONDITIONS
tim es until ready to be placed in the trench. Moisture shall be
ma intained inside the pipe by periodic addition of water as
necessary .
3) Pipes shall be carefully supported during shipment and storage.
Each length of pipe , fitting, or special shall be internally supported
and braced with stulls to maintain a true circular shape . Internal
supports shall consist of timber or steel stulls firmly wedged and
secured so that the stulls remain in place during handling . Pipe
sh all be rotated so that one (1) of the stulls is vertical during
storage, shipment and installation. Stulls shall not be removed from
pipe until backfill operations are complete (excluding final cleanup),
unl ess it can be demonstrated to the OWNER's satisfaction that
removal of the stulls will not adversely affect the pipe installation .
Pipe, fittings , and specials shall be separated so that they do not
bear against each other in transit. Store pipe on padded skids,
sa nd or dirt berms , tires , or other suitable means to protect the pipe
from damage .
4) In addition, deliver , handle, and store pipe in accordance with the
ma nufacturer's recommendations to protect coating systems .
b . Marking for Identification : Each joint of pipe and each fitting shall have
plainly ma rked on one end the class for which it is designed, the date of
manufactu rer, and the identification number that matches shop drawing
records . The top centerline shall be marked on all specials .
B. PRODUCTS
11/02104
1. MATERIALS
2.
a . Cement: Cement for use in concrete and mortar shall be Type I or II
Portland Cement. .
b . Aggregates : Aggregates for concrete lining and coating shall conform to
ASTM C-33 .
c . Sand: Sand used for inside and outside joints shall be of silica base,
conforming to ASTM C-144 .
d . Special Coating : Pipe to be installed in casing shall have two built-up
mortar rings, each approximately 2 feet long and slightly higher than the
pipe b~II. to prevent the pipe from being supported by the pipe bell. Built-
up mortar rings are to be applied at the quarter points of the pipe section .
e. Bushes , Couplings and Plugs : Where outlets or taps are threaded, furnish
and install brass reducing bushings in larger steel half couplings for the
outlet size indicated. Threaded plugs shall be brass .
MIXES; CEMENT MORTAR
ASC-42
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
Cement mortar used for pouring joints shall consist of one (1) part Portland
Cement to two (2) parts clean , fine , sharp silica sand, mixed with water . No
manufactured sand shall be permitted . Exterior joint mortar shall be mixed to the
consistency of thick cream . Interior joint mortar shall be mixed with as little water
as possible so that the mortar is very stiff, but workable. Cement shall be ASTM
C150, Type I or Type II. Sand shall conform to ASTM C144 . Cement mortar used
for patching shall be mixed as per cement mortar for inside joints.
3 . MANUFACTURED PRODUCTS
a . Pipe:
1) General: Pipe, bends , and special fittings shall be designed ,
manufactured, and tested in accordance with the applicable
requirements of AWWA C303 and AWWA M9, and the special
requirements of this specification. Pipe shall be certified by the
National Sanitation Foundation Standard 61 for use with potable
water.
2) Pipe Design Criteria : Sizes and pressure classes (working
pressure) shall be as specified . For the purposes of pipe design ,
working pressure plus transient pressure shall be as indicated
below. Fittings, specials and connections shall be of the same or
greater pressure class as the associated pipe. Pipe and fittings
shall be clearly marked with the pressure class and piece number to
permit easy identification in the field. Pipe design shall be based on
trench conditions and design pressure class specified. Pipe shall
be designed according to the methods indicated in AWWA C303
and AWWA Manual M9 for trench construction, using the following
parameters:
i.) Unit Weight of Fill (w) = 130 pcf
ii.) Live Load = AASHTO H-20 truck for unpaved conditions or
Cooper E-80 for railroad conditions
iii.) Trench Depth = .As indicated
iv .) Coefficient Ku' = 0 .150
v .) Trench Width (Bd) as indicated
vi.) Bedding Conditions = As indicated
vi i.) Pressure Class = 150 psi min . working pressure
viii.) Surge Allowance= 100 psi minimum , where : Total Pressure
(including surge) = 150 psi + 100 psi = 250 psi.
x.) Deflection Lag Factor= 1.0
xi.) Soil Reaction Modulus, E' < 1,000
Trench depths indicated shall be verified after existing utilities are
located . Vertical alignment changes required because of existing
utility or other conflicts shall be accommodated by an appropriate
ASC-43
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
change in pipe design depth . In no case shall pipe be installed
deeper than its design allows .
3) Provisions for Thrust:
i.) Thrusts at bends , tees, plugs, or other fittings shall be
resisted by restra ined joints . Thrust at bends adjacent to
casing pipe shall be restrained by we lding joints through
casing and for a sufficient distance each side of casing. The
distance for thrust restraint shown on the plans is the
minimum restraint and does not relieve the manufacturer
from calculating the restraint needs as specified herein. In
no case shall the restrained distance be less than indicated
on the plans . If the manufacturer calculates the need for
additional restraint, no additional compensation will be
allowed . No thrust restraint contribution shall be allowed for
the welded length of pipe within the casing, unless casing is
filled with grout.
ii.) Restrained joints shall be used for a sufficient distance from
each side of the bend, tee, plug , or other fitting to resist
thrust which will be developed at the design pressure of the
pipe. For the purpose of thrust restraint , design pressure
shall be 1 .5 times pressure class (working pressure), or
equal to the test pressure , or working pressure plus the
surge allowance , whichever is greater. Restrained joints
shall consist of welded joints . In areas where restrained
joints are used for thrust restraint , the pipe shall have
adequate cylinder thickness to transmit the thrust forces .
iii.) The length of pipe with welded joints to resist thrust forces
shall be determined by the pipe manufacturer in accordance
with AWWA Manual M9 and the following:
iv.)
a) The weight of earth (We) shall be calculated as the
weight of the projected soil prism above the pipe.
b) Soil density = 110 pcf (maximum value to be used).
c) Coefficient of friction = 0.25 (maximum value to be
used).
The above applies to unsaturated soil conditions . In
locations where ground water is encountered, the soil
density shall be reduced to its buoyant weight for the backfill
below the water table , and the coefficient of friction shall be
reduced to 0 .25.
Thrust collars will only be permitted for temporary plugs.
Thrust collars may not be used for any other application,
unless approved in writing by the ENGINEER.
ASC-44
PART DA -ADDITIONAL SPECIAL CONDITIONS
4) Inside Diameter: The inside diameter, of the cement mortar lining
shall be the Nominal diameter specified .
b . Joint Wrappers : Similar and equal to those manufactured by Mar-Mac
Manufacturing Company.
c. Insulated Connections: Insulated connection shall be in accordance with
Section 15640 included in the Appendix. Where insulated connections are
indicated , furnish dielectric insulation gaskets , sleeves , and plastic washers
as indicated . Insulating flange kits are to be installed on all flanged outlets
of the main line pipe and on both flanges of each main line valve.
d. Flexible Joint Couplings: Dresser Style 38, Smith-Blair Style 411 , or
approved equal.
e . Pipe Ends: The standard pipe end shall include steel joint ring and a
continuous solid rubber ring gasket as per AWWA Manual M-9.
f . Flanges : Flanges shall conform to AWWA C207 with laying dimensions
and drilling in accordance with ANSI B 16 .1, Class 125. Flanges shall be
Flange Class E with a minimum working pressure of 275 psi for areas
designated with 225 psi test pressure. In no case shall the working or test
pressure of the pipe exceed the working pressure of the flange . Drilling
shall match class of valves or appurtenances which are attached. Nuts and
bolts shall conform to ASTM A307, Grade B. Nuts and bolts shall conform
to AWWA C207.
C. EXECUTION
11/02/04
1. Installation
a. General:
1) Install pipe, fittings, specials, and appurtenances as specified
herein, as specified in AWWA Manual M9 , and in accordance with
the pipe manufacturer's recommendations .
2) Lay pipe to the lines and grades as indicated.
2. Pipe Handling:
3.
a. Haul and distribute pipe, fittings at the project site . Handle piping with care
to avoid damage. Before lowering into the trench , inspect each joint of
pipe, and reject or repair any damaged pipe.
b. Keep the pipe clean during and after the laying operation and free of sticks,
dirt, animals, and trash, and at the close of each operating day, effectively
seal the open end of the pipe using a gasketed night cap.
Pipe Jointing:
ASC-45
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
a. General :
b.
C.
1) Thoroughly clean the bell and spigot rings before laying each joint of
pipe by brushing and wiping. If any damage to the protective
coating on the metal has occurred, repair the damage before laying
the pipe. Lubricate the gasket and the inside surface of the bell with
an approved lubricant (flax soap) which will facilitate the telescoping
of the joint. Tightly fit together sections of pipe and exercise care to
secure true alignment and grade. When a joint of pipe is being laid,
place the gasket on the spigot ring and enter the spigot end of the
pipe into the bell of the adjoining pipe and force into position. The
inside joint space between ends of the pipe sections shall have an
opening within the tolerances as recommended by the pipe
manufacturer. No "blocking up" of pipe or joints will be permitted,
and if the pipe is not uniformly supported or the joint not made up
properly, remove the joint and properly prepare the trench. After
joining, check the position of the gasket with a feeler gauge. If the
gasket is out of position, disassemble the joint and repeat the joint
laying procedure.
2) For interior welded joints, complete backfilling before welding. For
exterior field-welded joints, provide adequate working room under
and beside the pipe.
Exterior Joints: Make the exterior joint by placing a joint wrapper around
the pipe and secure in place with two (2) metal straps. The wrapper shall
be 9" inches wide for pipe 36" and larger, and 7" wide for smaller pipe,
hemmed on each side. The wrapper shall be fiberglass reinforced or
burlap clo t h, with lengths encircling the pipe, leaving enough opening
between ends to allow the mortar to be poured inside the wrapper into the
joint. Fill the joint with mortar from one side in one (1) continuous operation
until the grout has flowed entirely around the pipe. During the filling of the
joint, pat or manipulate the sides of the wrapper to settle the mortar and
expel any entrapped air. Leave wrappers in place undisturbed until the
mortar has set-up.
Interior Joints: Upon completion of backfilling of the pipe trench, fill the
inside joint recess with a stiff cement mortar. Prior to placing of mortar,
clean out dirt or trash which has collected in the joint, and moisten the
concrete surfaces of the joint space by spraying or brushing with a wet
brush. Ram or pack the stiff mortar into the joint space and take extreme
care to insure that no voids remain in the joint space. After the joint has
been filled, level the surfaces of the joint mortar with the interior surfaces of
the pipe with a steel trowel so that the surface is smooth. Interior joints of
pipe smaller than 21" shall have the bottom of the bell buttered with mortar,
prior to inserting the spigot, such that when the spigot is pushed into
position it will extrude surplus mortar from the joint. The surplus mortar
shall be struck off flush with the inside of the pipe by pulling a filled burlap
bag or an inflated ball through the pipe with a rope.
ASC-46
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
d . Welded Joints:
1)
2)
3)
4)
5)
6)
7)
8)
9)
Weld joints in accordance with the AWWA Manual M9. Contractor
shall provide adequate ventilation for welders and for Owner's
representative to observe welds . Unless otherwise specified , welds
shall be full circle fillet welds.
Adequate provisions for reducing temperature stresses shall be the
responsibility of the Contractor.
After the pipe have been joined and properly aligned and prior to the
start of the welding procedure , the spigot and bell shall be made
essentially concentric by shimming or tacking to obtain clearance
tolerance around the periphery of the joint. In no case shall the
clearance tolerance be permitted to accumulate.
Furnish labor, equipment, tools and supplies, including shielded
type welding rod. Protect welding rod from any deterioration prior to
its use. If any portion of a box or carton is damaged, reject the
entire box or carton.
In all hand welding , the metal shall be deposited in successive
layers. For hand welds, not more than 1/8" of metal shall be
deposited in each pass. Each pass except the final one, whether in
butt or fillet welds, shall be thoroughly bobbed or peened to relieve
shrinkage stresses and to remove dirt, slag, or flux before the
succeeding bead is applied . Each pass shall be thoroughly fused
into the plates at each side of the welding groove or fillet and shall
not be permitted to pile up in the center of the weld. Undercutting
along the side shall not be permitted.
Welds shall be free from pin holes, non-metallic inclusions, air
pockets, undercutting and/or any other defects.
If the ends of the pipe are laminated , split or damaged to the extent
that satisfactory welding contact cannot be obtained, remove the
pipe from the line.
Furnish each welder employed with a steel stencil for marking the
welds, so that the work of each welder may be identified. Have
each welder stencil the pipe adjacent to the weld with the stencil
assigned to him. In the event any welder leaves the job, his stencil
shall be voided and not duplicated if another welder is employed.
Use only competent , skilled and qualified workmen. Each welder
employed by the Contractor shall be required to satisfactorily pass a
welding test in accordance with AWWA C206 before being allowed
to weld on the line.
ASC-47
PART DA -ADDITIONAL SPECIAL CONDITIONS
10) After each welder has qualified in the preliminary tests referred to
above , inspections shall be made of joints in the line . Any welder
making defective welds shall not be allowed to continue to weld .
11) Dye penetrant tests in accordance with ASTM E 165, or magnetic
particle test shall be performed by the Contractor under the
supervision and inspection of the Owner's Representative or an
independent testing laboratory , on all full welded joints . Welds that
are defective will be replaced or repaired, whichever is deemed
necessary by the Engineer, at the Contractor's expense .
12) If the Contractor d isagrees with the Engineer's interpretation of
we ld i ng tests , test sections may be cut from the joint for physical
testing . The Contractor shall bear the expense of repairing the joint,
regardless of the results of physical testing. The procedure for
repair i ng the joint shall be approved by the Engineer before
proceeding .
e. Protection of Exposed Metal:
1) Protect exposed ferrous metal by a minimum of one ( 1 ") inch
coating of cement mortar as previously specified for inside joints
unless otherwise specified. Exposed· large flat surfaces such as
flanges , bolts , caulked joints, threaded outlets, closures, etc ., shall
ha ve coating reinforced with galvanized wire mesh .
2) Thoroughly clean and wet the surface receiving a cement mortar
coating with water just prior to placing the cement mortar coating.
After placing , take care to prevent cement mortar from drying out
too rapidly by covering with damp earth or burlap. Cement mortar
coating shall not be applied during freezing weather.
f . Patching:
1) Excessive field-patching of lining or coating shall not be permitted .
Pa tching of lining or coating will be allowed where area to be
repaired does not exceed 100 square inches and has no
dimensions greater than 12". In general, there shall not be more
than one patch on either the lining or the coating of any one joint of
pipe .
2) Wherever necessary to patch the pipe, make patch with cement
mortar as previously specified for interior joints. Do not install
patched pipe until the patch has been properly and adequately
cured and approved for laying by the OWNER. Promptly remove
rejected pipe from the site.
D. FIELD QUALITY CONTROL
1. Hydrostatic and Leakage Tests
11 /02/04 ASC-48
PART DA -ADDITIONAL SPECIAL CONDITIONS
a . Furnish all necessary equipment and labor for carrying out a pressure test
on the pipelines . The procedures and method for carrying out the pressure
tests shall be approved by the Engineer.
b . Make any taps and furnish all necessary caps , plugs, bulkheads, etc ., as
required in conjunction with testing portions of the pipe . Furnish test
pumps , gauges , meters and any other equipment required in conjunction
with carrying out the tests. Hydrostatic pressure and leakage tests shall
conform to AWWA M9.
c. All pipelines shall be subjected to hydrostatic pressure as indicated in
2 .03.A .2 at the lowest points of the section being tested and this pressure
maintained for at least one hour. The amount of leakage which will be
permitted shall be in accordance with AWWA C600.
d . Lines which fail to meet the requirements of the test shall be repaired and
retested as necessary until test requirements are met. Defective materials ,
pipes , valves, and accessories shall be removed and replaced .
e . The Owner will supply at no cost to the Contractor a maximum quantity of
water for testing purposes equal to 11 O· percent of the volume of the
pipeline . The Contractor shall furnish and install the necessary connections
which may be required to transport the water to the pipe being tested.
Additional water required will be provided at the Owner's standard rates for
the volume required .
DA-124 Fiberglass Sewer Pipe -Gravity Service
A. GENERAL
11/02/04
1. Section Includes
a . Fiberglass Reinforced Polymer Mortar Pipe.
2 . References
a. ASTM D3262 -Standard Specification for "Fiberglass " (Glass-Fiber-
Reinforced Thermosetting-Resin) Sewer Pipe.
b. ASTM D4161 -Standard Specification for "Fiberglass" (Glass-Fiber-
Reinforced Thermosetting-Resin) Pipe Joints Using Flexible Elastomeric
Seals .
c. ASTM D2412 -Standard Test Method for Determination of External Loading
Charact~ristics of Plastic Pipe by Parallel-Plate Loading.
3 . Specifications
The specifications contained herein govern , unless otherwise agreed upon between
purchaser and supplier.
ASC-49
PART DA -ADDITIONAL SPECIAL CONDITIONS
4. Submittals
Contractor shall submit load and pipe calculations confirming selected pipe behavior.
Load calculations shall include, but not limited to, buckling resistance, pipe
deflection, pipe wall strain cracking and wall crushing load. All design calculations
shall be sealed by a Licensed Engineer of the State of Texas .
a. Product da ta submittals to include the following are as a minimum :
b . Details of the proposed pipe .
c. Details of proposed manholes .
d . Properties, strengths, etc. of the pipe.
e. Joint detail drawing , including maximum interior joint gap opening, in the
deflected position and in the straight alignment.
f. Instructions on storage, handling, transportation, and pipe installation.
g . Standard catalog sheets.
h. Gasket type and composition showing ability to withstand the chemicals
and conditions within sanitary sewers .
i. Pipe laying schedule.
j. Connections to all proposed structures including water stop.
B. PRODUCTS
1. Materials
a.
b.
C.
d .
e.
11/02104
Resin Systems: The manufacturer shall use only polyester resin systems
with a proven history of performance in this particular application. The
historical data shall have been acquired from a composite material of
similar construction and composition as the proposed product.
Glass Reinforcements: The reinforcing glass fibers used to manufacture
the components shall be of highest quality commercial grade E-glass
filaments with binder and sizing compatible with impregnating resins.
Silica Sand: Sand shall be minimum 98% silica with a maximum moisture
content of 0.2%.
Additives : Resin additives , such as curing agents, pigments, dyes fillers,
thixotropic agents, etc., when used, shall not detrimentally affect the
performance of the product.
Elastomeric Gaskets: Gaskets shall be supplied by approved gasket
manufactu rers and be suitable for the service intended.
ASC-50
PART DA -ADDITIONAL SPECIAL CONDITIONS
2. Manufacture and Construction
a. Pipes : Manufacture pipe to result in a dense, non-porous , corrosion-
resistant, consistent composite structure .
b. Joints: Unless otherwise specified, the pipe shall be field connected with
fiberglass sleeve couplings that utilize elastomeric sealing gaskets made of
EPDM rubber compound as the sole means to maintain joint water
tightness. The joints must meet the performance requirements of ASTM
D4161. Joints at tie-ins, when needed may utilize fiberglass, gasket-sealed
closure couplings.
c. Fittings: Flanges, elbows, reducers, tees, wyes, laterals and other fittings
shall be capable of withstanding all operating conditions when installed.
They may be contact molded or manufactured from mitered sections of pipe
joined by glass-fiber-reinforced overlays . Properly protected standard
ductile iron , fusion-bonded epoxy coated steel and stainless steel fittings
may also be used .
3. Dimensions
4.
a . Diameters: The actual outside diameter (18" to 48") of the pipes shall be in
accordance with ASTM D3262. For other diameters, OD's shall be per
manufacturer's literature.
b. Lengths : Pipe shall be supplied in nominal lengths of 20 feet. Actual laying
length shall be nominal +1, -4 inches . At least 90% of the total footage of
each size and class of pipe, excluding special order lengths, shall be
furnished in nominal length sections.
C.
d.
Testing
a.
b.
Wall Thickness: The minimum wall thickness shall be the stated design
thickness.
End Squareness: Pipe ends shall be square to the pipe axis with a
maximum tolerance of 1/8".
Pipes: Pipes shall be manufactured and tested in accordance with ASTM
D3262 .
Joints: Coupling Joints shall meet the requirements of ASTM D4161.
Stiffness: Minimum pipe stiffness when tested in accordance with ASTM
D2412 shall normally be 72 psi for SH-121 Part 1 and 46 psi for SH-121
Parts 5 and 7A. In no case will the stiffness be less than SN72 for SH-121
Part 1 and 46 psi for SH-121 Parts 5 and 7A.
5. Customer Inspection
11102104 ASC-51
PART DA -ADDITIONAL SPECIAL CONDITIONS
a. The owner or other designated representative shall be entitled to inspect
pipes or witness the pipe manufacturing .
b . Manufacturers Notification to Customer: Should the Owner request to see
specific pi pes during any phase of the manufacturing process, the
manufacture must provide the Owner with adequate advance notice of
. when and where the production of those pipes will take place .
6 . Packaging, Handling, Shipping
a. Packaging , handling , and shipping shall be done in accordance with the
manufacturer 's instructions .
C . EXECUTION
11 /02104
1. Installation
a. Burial : The bedding and burial of pipe and fittings shall be in accordance
with the project plans and specifications and the manufacturers
requirements (Section 13 A of the product brochure).
b. Pipe Handl ing : Use textile slings , other suitable materials or a forklift . Use
of chains or cables is not recommended .
c. Jointing :
1) Clean ends of pipe and coupling components .
2) Apply joint lubricant to pipe ends and elastomeric seals of coupling.
Use only lubricants approved by the pipe manufacturer.
3) Use suitable equipment and end protection to push or pull the pipes
together.
4) Do not exceed forces recommended by the manufacturer for
coup ling pipe.
5) Join pipes in straight alignment then deflect to required angle. Do
not allow the deflection angle to exceed the deflection permitted by
the manufacturer.
d) Field Testing
1) Infiltration / Exfiltration Test: Maximum allowable leakage shall be
per local specification requirements.
2) Low Pressure Air Test: Each reach may be tested with air pressure
(max 5 psi). The system passes the test if the pressure drop due to
leakage through the pipe or pipe joints is less than or equal to the
spec ified amount over the prescribed time period.
ASC-52
PART DA -ADDITIONAL SPECIAL CONDITIONS
3) Individual Joint Testing : For pipes large enough to enter, individual
joints may be pressure tested with a portable tester to 5 psi max . with
air or water in lieu of line infiltration, exfiltration or air testing.
2 . Deflection: Maximum allowable long-term deflection is 5% of the initial diameter.
D. MEASUREMENT AND PAYMENT
The measurement of sewer pipe for payment purposes will be the horizontally measured
length of the line from center of fitting or manhole to center of fitting or manhole, or end of
pipe without deduction for intermediate fittings or manhole.
Payment will be made at the applicable unit price bid in the proposal as it corresponds in
size and depth of the constructed facility. Such payment shall include furnishings and
installing sewer pipe, and crushed limestone bedding and embedment, backfill and/or
flowable fill backfill.
OA-125 SANITARY SEWER ANO WATER LINE MARKERS
A. GENERAL
These work described in this specification includes supplying and placing markers for
sanitary sewer lines and water lines .
B. MATERIALS
1. Buried Markers -Buried markers shall be Omni Marker balls as manufactured by
Tempo or approved equal (www.tempo-textron .com). Markers for water lines shall
be blue . Markers for sanitary sewer lines shall be green .
2. Surface Markers -Surface markers shall be COTTMark Cable and Pipe Warning
System as manufactured by COTT Manufacturing Co. or approved equal
(www.cottmfg .com). Markers for water lines shall have a blue warning sign. Markers
for sanitary sewer lines shall have a green warning sign. Marker posts shall be 4-
inch diameter PVC.
C. EXECUTION
1. GENERAL
a. Buried markers shall be placed at a depth of three-feet below natural
ground surface and directly above the feature they are marking.
b. Surface markers shall be a minimum of six-feet in length and shall be
buried a minimum of two-feet , with a minimum of four-feet above ground.
The warning sign for all surface markers shall be 21-inches (not including
post cap). Surface markers shall be placed as follows :
i. Buried Features: Surface markers shall be placed directly above a
buried feature .
11102104 ASC-53
PART DA -ADDITIONAL SPECIAL CONDITIONS
ii. Above-Ground Features: Surface markers shall be placed a
maximum of two (2) feet away from an above-ground feature.
2. PLACEMENT
a. Water Lines 16-inches and Above
Buried markers shall be placed at all horizontal and vertical bends, all
horizontal points of curvature, tangency, and reverse curvature, horizontal
tees (excluding fire hydrant taps), cleanout wyes, blowoff valves, end-of-line
plugs, and at other locations as shown on the plans or as deemed
appropriate by the ENGINEER.
Surface markers shall be placed at each right-of-way line (or end of casing
pipe) of major highway crossings, railroad crossings, crossings with major
utilities such as high pressure gas lines and fiber-optic lines, and at other
locations as shown on the plans or as deemed appropriate by the
ENGINEER.
b . Water Lines 12-inches and Below
Buried markers shall be placed at the end-of-line cap on all dead-end stub
outs.
Surface markers shall not be utilized for water lines 12-inches and under.
c. Sanitary Sewer Lines, All Sizes
Buried markers shall be placed at all horizontal points of curvature,
tangency and reverse curvature if no manhole is present, and at .all stub
outs.
Surface markers shall be placed at each right-of-way line (or end of casing
pipe) of major highway crossings, railroad ~rossings, crossings with major
utilities such as high pressure gas lines and fiber-optic lines, and at other
locations as shown on the plans or as deemed appropriate by the
ENGINEER.
D. MEASURMENT AND PAYMENT
The cost of buried and surface sanitary sewer and water markers is subsidiary work and
the cost of same shall be included in the unit price bid for pipe complete in place as bid in
the proposal, and no other compensation will be allowed .
DA-126 REPLACEMENT OF TREES
Replacement trees shall consist of 3" caliper container grown Live Oak (Qurcus Virginiana) trees,
10-12" in height. Measurement and payment for replacing any trees that are removed shall be on
a per each basis and shall cover all cost for complete replacement of the existing tree(s) in
accordance with the City of Fort Worth Tree Ordinance. Included shall be all excavation, backfill,
11/02104 ASC-54
PART DA -ADDITIONAL SPECIAL CONDITIONS
watering , materials , labor, and equipment necessary in accordance with the City of Fort Worth
Tree Ordinance . A copy of the City of Fort Worth Tree Ordinance is included in the Appendix .
DA-127 PIPELINES CROSSING HIGHWAYS, STREETS AND RAILROADS BY BORING,
TUNNELING OR OPEN CUT
A. GENERAL
11/02/04
1. WORK INCLUDED
Furnish labor, materials, equipment and incidentals necessary to install pipe
casings or tunnel liners by boring , tunneling or open cut as specified . This section
sets forth the requirements for utility lines crossing roadways or railroads using
bore, tunneling, or open cut.
2. QUALITY ASSURANCE
a . DESIGN CRITERIA
1) TUNNEL LINER PLATE
The tunnel liner plate shall be designed by the Manufacturer in
accordance with the methods and criteria as specified in AASHTO
Standard Specifications for Highway Bridges, Section 16 . Soil
parameters shall be determined by the Tunnel Liner Plate
Manufacturer. The tunnel liner plate shall be designed to allow a
maximum deflection of 3%. The thickness of the tunnel liner plate
specified herein is the minimum acceptable and shall be increased
as necessary to obtain adequate joint strength , stiffness , buckling
strength, and resistance to deflection.
ASC-55
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
2) CASING INSULATORS
Casing insulators shall be designed by the Manufacturer to
adequately support and electrically isolate the carrier pipe within the
casing pipe under all conditions . Number and location of spacing
insu lators shall be determined by the Manufacturer to protect carrier
pipe from damages. One insulator shall be placed within 2' of ends
of casing.
b. INSTALLER'S QUALIFICATIONS
Installation shall be by a competent, experienced contractor or sub-
contractor. The installation contractor shall have a satisfactory experience
record of at least five (5) years engaged in similar work of equal scope.
c. PERFORMANCE REQUIREMENTS
Lateral or vertical variation in the final position of the pipe casing or tunnel
liner from the line and grade established by the engineer shall be permitted
only to the extent of 1" in 1 O', provided that such variation shall be regular
and only in the direction that will not detrimentally affect the function of the
carrier pipe, or clearances from other underground utilities or structures.
Any additional cost caused by this variation shall be the responsibility of the
Contractor.
3. SU BM ITT ALS
Submittals shall include:
a . Installer's Qualifications
b. Shop drawings of the tunnel liner plate and fasteners from the tunnel liner
plate manufacturer. Shop drawings shall include calculations for the design
of the tunnel liner plate sealed by a Licensed Engineer in the State of
Texas. Shop drawings are for record purposes only and will not be
reviewed or approved by the Engineer.
4. STANDARDS
AWWAC-206
AWWAC-210
AASHTO M-190
AASHTO
ASTM A-36
ASTM A-123
"Field Welding of Steel Water Pipe"
"Liquid Epoxy Coating Systems for the Interior and Exterior
of Steel Water Pipelines"
"Bituminous Coated Corrugated Metal Culvert Pipe and Pipe
Arches"
Standard Specifications for Highway Bridges, 1989.
"Structural Steel"
"Zinc (Hot Dipped Galvanized) Coatings on Iron and Steel
ASC-56
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
Products"
ASTM A-135
ASTM A-139
ASTM A-153
ASTM A-307
ASTM A-449
ASTM A-569
"Electric -Resistance -Welded Steel Pipe"
"Electric -Fusion (Arc) -Welded Steel Pipe"
"Zinc Coating (Hot Dip) on Iron and Steel Hardware"
"Carbon Steel Bolts and Studs , 60 ,000 PSI Tens i le "
"Quenched and Tempered Steel Bdlts and Studs "
"Steel , Carbon, Hot-Rolled Sheet and Strip , Commercial
Quality "
ASTM A-570 "Hot Rolled Carbon Steel Sheet and Strip , Structural
Quality "
ASTM C-76
ASTM D-4254
"Reinforced Concrete Culvert , Storm Drain, and Sewer Pipe"
"Test Methods for Minimum Index Density of Soils and
Calculation of Relative Density"
5. · DELIVERY AND STORAGE
a . · The Contractor shall store tunnel liner plate in accordance with
manufacturer's recommendations. Any liner plate that appears to have
been damaged in the opinion of the Owner's representative shall be
removed from the project and replaced with a new piece .
6. JOB CONDITIONS ; PERMITS AND EASEMENT REQUIREMENTS
a .
b .
C.
Where the work is in the public right-of-way or ra ilroad company right-of-
way, the Owner will secure the appropriate permits or .easements. The
Contractor shall observe regulations and instructions of the right-of-way
Owner as to the methods of performing the work and take precautions for
the safety of the property and the public . Negotiations and coordination
with the rig~t-of-way Owner shall be carried on by the Contractor, not less
than five (5) days prior to the time of his intentions to begin work on the
rig ht-of-way.
Comply with the requirements of the permit and/or easement, a copy of
which is included in the Appendix. The work within the Texas Department
of Transportation (TxDOT) Right-of-Way shall comply with TxDOT
specifications. If required by the Right-of-Way Owner, obtain Protective
Liability Insurance in the amount required by the particular company or
other insurance as is specified in the permit at no cost to the Owner.
Acquire a permit, agreement, or work order from the right-of-way Owner as
is required .
Construction along roads and railroads shall be performed in such manner
that the excavated material be kept off the roads and railroads at all times,
ASC-57
PART DA -ADDITIONAL SPECIAL CONDITIONS
as well as, all operating equipment. Construction shall not interfere with the
operations of the roads and railroads .
d. Barricades , warning signs, and flagmen, when necessary and specified,
shall be provided by the Contractor.
e. No blasting shall be allowed. Existing pipelines are to be protected . The
Contractor shall verify location and elevation of any pipe lines and
telephone cable before proceeding with the construction and plan his
construction so as to avoid damage to the existing pipe lines or telephone
cables. Verification of location of existing utilities shall be the complete
responsibil ity of the Contractor.
7 . OPTIONS
a. CASING MATERIAL: Unless specified otherwise, the Contractor may use
steel pipe or tunnel liner plate where bore and/or tunnel as specified .
Unless specified otherwise, the Contractor shall use steel pipe where open
cut casing is specified. The material specification for casing pipe and
tunnel line r are the minimum acceptable. The Contractor shall be fully
responsible to insure the materials used are of sufficient strength for the
installation method chosen and the soil conditions encountered .
b. BORE AND TUNNEL METHODS: Unless specified otherwise, the
Contractor may use jacking, tunneling for the installation method of casing
material. Tunnel liner plate shall not be used where bore or jack methods
are used. The Contractor shall be fully responsible to insure the methods
used are adequate for the protection of workers, pipe, property, and the
public. Provide a finished product as required .
8 . GUARANTEES [Not Used]
B . PRODUCTS
11/02104
1. MA TE RIALS
a. STEEL PIPE: Steel casing pipe shall have a minimum yield strength of
35 ,000 psi. Casing shall meet ASTM A36, ASTM A570, ASTM A 135,
ASTM A 139, or approved equal. Pipe shall be coated and lined in
accordance with AWWA C210 or approved equal. Pipe joints shall be
we lded in accordance with AWWA C206. After pipe is welded, coating and
lining shall be repaired. Unless specified otherwise, the minimum wall
thickness of steel casing pipe shall be as follows:
ASC-58
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
Casing Diameter Wall Thickness
42" 0 .562"
54" 0.719"
b. TUNNEL LINER PLATES: Corrugated metal tunnel liner plates shall be
galvanized made from steel sheets conforming to the requirements of
ASTM A-569. Material to be galvanized shall be zinc coated in accordance
with ASTM A-123, except that the zinc shall be applied at a rate of 2.0 oz.
per square foot on each side. Tunnel liner plates and fasteners shall
comply with the requirements of MSHTO Standard Specifications for
Highway Bridges, 1989 . Liner plates shall be punched for bolting on both
longitudinal and circumferential seams, fabricated to permit complete
erection from the inside of the tunnel. Bolts and nuts shall be galvanized to
conform to ASTM. Where groundwater is encountered , gasketed liner
plates shall be used .
2 . MIXES
a.
b.
A-153: Plates shall be of uniform fabrication and those intended for one
size tunnel shall be interchangeable. Welding of tunnel liner plate shall not
be allowed. The material used for the construction of these plates shall be
new, unused, and suitable for the purpose intended. Workmanship shall be
first class in every respect. Minimum thickness of tunnel liner plate shall be
as follows:
Project Tunnel Diameter Minimum Thickness
SH-121 Part 5 Water 48 " - 2 Flanged 14 gage
48" - 4 Flanged 12 gage
SH-121 Part 5 Sewer 48" - 2 Flanged 12 gage
48" -4 Flanged 12 gage
CEMENT MORTAR: Consisting of one ( 1) part cement to two (2) parts
clean sand w ith sufficient water to make a thick workable mix.
PRESSURE GROUT MIX: Comprised of 1 cubic foot of cement and 3.5
cubic feet of clean fine sand with sufficient water added to provide a free
flowing thick slurry. If desired to maintain solids in the mixture in
ASC-59
PART DA -ADDITIONAL SPECIAL CONDITIONS
suspension, one cubic foot of commercial grade bentonite may be added to
each 12 to 15 cubic feet of the slurry.
c. CELLULAR GROUT MIX: The cellular grout shall be a low-density, non-
shrink grout composed of Type II Portland cement, water, and a pre-formed
foam. The cellular grout shall have the following characteristics:
1) Minimum 28-day Compressive Strength = 1000 psi
2) · Slurry (Wet) Density = 95 to 105 pct
3) Cement= Type II, per ASTM C150
4) Water = Potable
5) Foam = Per ASTM C869
6) Water/Cement Ratio = 0.50 to 0.55
3. FABRICATIONS [Not Used]
4 . MANUFACTURED PRODUCTS
a. TUNNEL LINER: Manufactured by Contech Construction Products, Inc .. ,,
American Commercial Inc., or approved equal.
b. CASING INSULATORS : Casing insulators may be used in lieu of rails and
rollers. Casing insulators shall be used for this project. In lieu of casing
insulators, steel rails and rollers may be considered as an acceptable
substitute. However, the Contractor must submit a design for the rail and .
roller installation as well as documentation to justify the substitution as an
acceptable installation, in lieu of casing insulators. Use casing insulators
for any type of carrier pipe. Insulators shall consist of pre-manufactured
stainless steel bands with plastic lining and plastic runners. Insulators shall
fit snug over the carrier pipe and position the carrier pipe approximately in
the center of the casing pipe, to provide adequate clearance between the
carrier pipe bell and the casing pipe. Fasteners for insulators shall be
stainless steel or cadmium-plated. Insulators shall be as manufactured by
Cascade Waterworks Manufacturing Company or Advanced Products and
Systems, Inc. or approved equal.
c . MORTAR BANDS: Concrete cylinder pipe and mortar coated steel pipe
may have thickened outside mortar bands in lieu of casing insulators .
Mortar bands shall be properly position the pipe within the casing or tunnel
liner.
C. EXECUTION
1. PREPARATION [Not Used]
2. GENERAL CONSTRUCTION PROCEDURES
11/02/04 ASC-60
11/02104
PART DA -ADDITIONAL SPECIAL CONDITIONS
a . EXCAVATION AND BACKFILL OF ACCESS PITS
1) Do not allow excav.ation over the limits of the bore or tunnel as
specified. Trench walls of access pits adjacent to the bore or tunnel
face shall be truly vertical. Shore the trench walls as necessary to
protect workmen, the public, structures, roadways, and other
improvements.
2) Excavations within the right-of-way and not under surfacing shall be
backfilled, with type B backfill, and consolidated by tamping in 6"
horizontal layers to 95% of maximum density as measured by ASTM
D-698. Surplus material shall be removed from the right-of-way and
the excavation finished to original grades. Backfill pits immediately
after the installation of the carrier pipe is completed. If carrier pipe is
not installed immediately after casing pipe installation, the Right-of-
Way Owner may require the access pits be temporarily backfilled
until installation of carrier pipe.
b . INSTALLING CARRIER PIPE IN CASINGS
1)
2)
3)
4)
5)
Pipe to be installed within the casing or tunnel liner shall meet the
requirements for this type of pipe as specified. Where indicated,
place, align, and anchor guide rails and/or casing insulators inside
the casing. If guide rails are used, place cement mortar on both
sides of the rails.
Pull or skid pipe into place inside the casing. Lubricants such as flax
soap or drilling mud may be used to ease pipe installation. Do not
use petroleum products, oil or grease for this purpose. If guide rails
are used, install pipe and hold down jacks after installation of carrier
pipe .
After installation of the carrier pipe, mortar inside and outside of the
joints as applicable. Verify electrical discontinuity between the
carrier pipe and tunnel liner. If continuity exists, remedy the short
prior to applying cellular grout.
After carrier pipe installation is complete, if hold down jacks or casing
spacers are used, seal or plug the ends of the casing .
After carrier pipe installation is complete, the annular space between
the carrier pipe and tunnel liner or casing shall be completely filled
with cellular grout. The Contractor shall take precautions to prevent
flotation of the carrier pipe are not required to be mortared if flex-
protex is used. Exterior joint coating (heat shrink sleeves) is required
for polyurethane coated pipe. Provide necessary bulkheads as
recommended by the cellular grout supplier. If pressure is used to
apply grout, verify the maximum allowable pressure with the carrier
pipe manufacturer, and do not exceed this pressure.
ASC-61
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
c . FREE-AIR SYSTEM
If required by OSHA standards, free-air systems shall be installed and
maintained .
d . INSTALLATION OF PRESSURE GROUT MIX
1) Install pressure grout mix in the void space between the outside of
the casing pipe or tunnel liner and the excavation. For bore or jacks
with casing pipe, install pressure grout mix immediately upon
completion of setting casing pipe. For tunnel liner plate, install
pressure grout mix at the end of each work day or more often as
conditions warrant.
2) Unless specified otherwise, install pressure grouting through grout
fittings for the casing pipe or tunnel liner plate 48" in diameter or
larger. Grout fittings shall be fabricated into casing pipe and tunnel
liner plate at a maximum spacing of 6'. Remove and plug grout
fittings after pressure grouting.
3) Install pressure grout from the low end for all crossings where grout
fittings are not used. Seal the low end and pressure grout until grout
is extruded from the opposite end.
3. CROSSINGS INSTALLED BY BORING
a.
b.
C.
Perform the boring from the low or downstream end unless specified
otherwise. Bore the holes mechanically and use a pilot hole. By this
method, an approximate 2" pilot hole shall be bored the entire length of the
crossing and shall be checked for line and grade. This pilot hole shall
serve as the centerline of the larger diameter hole to be bored . Place
excavated material near the top of the working pit and dispose of material
as required. The use of water or other fluids in connection with the boring
operation will be permitted only to the extent to lubricate cuttings. Jetting
shall not be permitted.
In unconsolidated soil formations, a · gel-forming colloidal drilling fluid
consisting of at least 10% of high grade carefully processed bentonite may
be used to consolidate cuttings of the bit, seal the walls of the hole, and
furnish lub rication for subsequent removal of cuttings and installation of the
pipe immediately thereafter.
In locations where the soil formation is other than consolidated rock, insert
the casing pipe simultaneously with the boring operation. This requirement
applies to all bored holes of 18" or greater in diameter. For smaller
diameter bored holes, it is desirable that the casing be installed as the
boring progresses, but because of differences in soil formations, the time
for inserting the casing shall be the Contractor's responsibility. In the event
that caving sand or water bearing materials are encountered, insert the
casing pipe simultaneously with the boring operation regardless of the
diameter of the bored hole . In all cases, the security and integrity of the
ASC-62
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
roadway is the primary concern. The Contractor shall be held fully
responsible for the continued integrity of the structure of the roadway being
crossed, whether or not a casing pipe is inserted simultaneously with the
boring operation .
4 . CROSSINGS INSTALLED BY TUNNELING AND JACKING
a. Jack the pipe from the low or downstream end, unless specified otherwise.
Provide heavy duty jacks suitable for forcing the pipe through the
embankment. In operating jacks, apply even pressure to the jacks used.
Provide a suitable jacking head and bracing between jacks so that pressure
will be applied to the pipe uniformly around the ring of the pipe. Provide a
suitable jacking frame or back stop. Set the pipe to be jacked on guides,
properly braced together, to support the section of the pipe and to direct it
in the proper line and grade. Place the whole jacking assembly so as to
line up with the direction and grade of the pipe. In general, excavate
embankment material just ahead of the pipe and material removed through
the pipe . Force the pipe through the embankment with jacks into the space
provided.
b. The excavation for the underside of the pipe, for at least 1/3 of the
circumference of the pipe, shall conform to the contour and grade of the
pipe. Provide a clearance of not more than 2" for the upper half of the pipe .
This clearance shall be tapered off to zero at the point where the
excavation conforms to the contour of the pipe . Extend the distance of the
excavation beyond the end of the pipe depending on the character of the
material, but do not exceed 2' in any case. Decrease the distance if the
character of the material being excavated makes it desirable to keep the
advance excavation closer to the end of the pipe .
c. If desired, use a cutting edge of steel plate around the head end of the pipe
extending a short distance beyond the end of the pipe with inside angles or
lugs to keep the cutting edge from slipping back onto pipe.
d. When jacking of pipe has begun, carry on the operation without interruption
to prevent the pipe from becoming firmly set in the embankment. Remove
and replace any pipe damaged in the jacking operations . The Contractor
shall absorb the entire expense .
5. CROSSINGS INSTALLED WITH TUNNEL LINER PLATE
a.
b.
Install the tunnel liner plates to the limits indicated and as specified in
AASHTO Standards Specifications for Highway Bridges, Section 11-26,
Construction Tunnels Using Steel Tunnel Liner Plates. Assemble steel
liner plates into circumferential rings. Liner plates shall be of the type to
permit segments to be installed completely from inside the tunnel or bore.
Accurately maintain the face of the excavation inside the tunnel so as to
allow the absolute minimum of void space outside the liner plate. Maintain
a maximum of 1/2" tolerance between the outside of the liner plate and the
ASC-63
PART DA -ADDITIONAL SPECIAL CONDITIONS
excavation wherever possible . The tunnel diameter shall not be greater
than 2" larger than the liner 0.0.
c. Liner plate installation shall proceed as closely as possible behind the
excavation. Excavation shall at no time be more than 6" ahead of the
required space to install an individual tunnel liner plate . Use breast plates,
poling boards or other suitable devices to maintain accurate excavation
with the minimum of unsupported excavation at any time. Tunnel liner plate
shall not be allowed to deflect vertically during installation.
6. CROSSINGS WITH CASING INSTALLED BY OPEN CUT
a . This article covers the requirements for the construction of crossings where
pipe casing is required for installation by the open cut method. Excavation,
backfill, and embedment of casing pipe shall be as specified in the
construction plans. All other requirements shall be as specified herein .
DA-128 GATE VALVES
A . GENERAL
11/02104
1. SCOPE OF WOR K
a . Furnish all labor, materials, equipment and incidentals required to
completely install and put into operation resilient seated gate valves and
actuator as specified herein and shown on the drawings .
· 2. QUALITY ASSURANCE
a. References :
1) American Water Works Association (AWWA)
AWWA C509 Resilient seated gate valve for water supply service.
2) American Society for Testing and Materials (ASTM)
ASTM A48 Gray Iron Castings
ASTM A 126 Gray Iron Castings for Valves, Flanges, and Pipe
Fittings
ASTM A436 Austenitic Gray Iron Castings
ASTM A536 Ductile Iron Castings .
b. Unit Responsibility and Coordination :
The Contractor shall cause all equipment specified under this section to be
furnished by the valve manufacturer who shall be responsible for the
adequacy and compatibility of all valve components including the actuator.
Any component of each complete unit not provided by the valve
manufacturer shall be designed, fabricated, testing, and installed by
factory-authorized representatives experienced in the design and
ASC-64
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
manufacture of the valve equipment. This requirement , however, shall not
be construed as relieving the Contractor of the overall responsibility for this
portion of the work.
3. ENVIRONMENTAL CONDITIONS
The equipment to be provided under this section shall be suitable for installation
and operation either inside vault structure or directly buried for a gate valve .
4 . SUBMITTALS
a . Submittals required after award of contract and prior to installation:
1) Technical bulletins and brochures on resilient seated gate valves .
b . Submittals required prior to final walk through:
1) Operation and Maintenance Manual.
5. SPARE PARTS AND TOOLS
a. Furnish one set of special tools required for the proper servicing of all
equipment supplied under these Specifications, packed in a suitable steel
tool chest with a lock.
6. SHIPPING INSTRUCTIONS
a. All parts shall be properly protected so that no damage or deterioration will
occur during a prolonged delay from the time of shipment until installation is
completed and the units and equipment are ready for operation .
b . All equipment and parts must be properly protected against any damage
during a prolonged period at the site.
c. The finished surfaces of all exposed flanges shall be protected by wooden
blank flanges, strongly built and securely bolted thereto.
d . Finished iron or steel surfaces not painted shall be properly protected to
prevent rust and corrosion.
e. Storage and · Protection: Take special care to prevent plastic and similar
brittle items from being directly exposed to the sun, or exposed to extremes
in temperature, preventing any deformation .
7. WARRANTY
a. The equipment shall be warranted to be free from defects in workmanship,
design and materials. If any part of the equipment should fail during the
warranty period, it shall be replaced and the unit(s) restored to service at no
expense to the Owner. Warranty shall be for a period of two years and
begin on the Date of Acceptance.
ASC-65
PART DA -ADDITIONAL SPECIAL CONDITIONS
8. PRODUCTS
11/02104
1. RESILIENT SEATED GATE VALVES
a. Resilient seated gate valves 4" through 48" shall meet or exceed the latest
revisions of AWWA C509 and shall meet or exceed the requirements of this
specification. All valve components in contact with potable water shall
conform to the requirements of ANSI/NSF Standard 61. All valve materials
for components in contact with potable water shall be resistant to
chloramines.
b . Valve body shall be ductile iron per ASTM A536. Flanged ends shall be
furnished in accordance with ANSI/AWWA C115/A21.15. Standard Flanged
Drilling. Mechanical Joints shall be furnished with outlets which conform to
ANSI/AWWA C111 /A21.11 mechanical joint requirements.
c. The disc shall be constructed of ductile iron fully encapsulated in rubber.
No iron shall be exposed on the disc.
d. Hex head bolt, and hex nut shall be Steel ASTM A307 Gr. 8, Zinc Plate per
ASTM 8633 , SC3 for non-buried service (4" through 12" valves). Hex head
bolt and hex nut shall be 304 or 316 Stainless Steel for buried service (all
sizes) and for valves 16-inch through 30-inch (non-buried service).
e. T-8olts shall be high strength low alloy Cor-Ten or approved equal.
f . Resilient seated gate valves shall be US Pipe, Clow, American Flow -
Control, Mueller, or equal for size 4" through 48". Valves 16" and larger
shall be contained within a vault as shown on the plans.
g . Gate valves in buried service shall be provided with polyethylene
encasement in accordance with AWWA C105 .
h . Resilient seated gate valves for buried service shall be furnished with a
square 2" operating nut. The valve box shall be Mueller H-10360 or
Engineer approved equal.
i. In all non -buried service, handwheel operators shall be furnished , unless
otherwise specified .
j. Resilient seated gate valves shall be non-rising stem type unless otherwise
specified.
k. Resilient seated gate valves used as part of Air Release Valve assembly
shall be non-rising stem with enclosed miter gearing and a fusion bonded
epoxy body.
I. All resilient seated gate valves shall be provided to open in clockwise
direction .
ASC-66
J
PART DA -ADDITIONAL SPECIAL CONDITIONS
C. EXECUTION
1. INSTALLATION
a. All resilient seated gate valves shall be installed in accordance with the
instructions of the manufacturer and as shown on the drawings .
DA-129 AIR RELEASENACUUM VALVES
A . GENERAL
11/02104
1. SCOPE OF WORK:
a. Furnish all labor, materials, equipment and incidentals required to
completely install and put into operation, air release/ air vacuum valves as
specified herein and shown on the drawings .
2 . SYSTEM DESCRIPTION
a. The arrangement shown on the drawings is based upon the best
information available to the Engineer at the time of design and is not
intended to show exact dimensions to any specific equipment unless
otherwise shown or specified. Therefore, it may be anticipated that the
structural supports, foundations, and connected piping shown, in part or in
whole , may have to be changed in order to accommodate the equipment
furnished. No additional payment will be made for such changes. All
necessary calculations and drawings for any related redesign shall be
submitted to the Engineer for his approval prior to beginning the work.
b . The valve shall be designed to operate with the following working
conditions without damage to the valve.
C.
Water Type
Working Pressure Range
Test Pressure Range
Surge Pressure
Flow Range
Raw Water
10 psi -150 psi
225 psi
100 psi
0 MGD-56 MGD
The air release/air vacuum valve shall operate satisfactorily over the
complete operating range shown. The equipment to be provided under this
section shall be suitable for installation and operation at elevations from
about 560-590 feet above sea level inside a vault structure. Outside
ambient temperatures range between O and 110 degrees F, and reported
water temperatures vary between 50 and 105 degrees F. Relative humidity
is expected to range between 5 and 100 percent. The valve shall be
capable of being submerged periodically.
ASC-67
11/02/04
PART DA -ADDITIONAL SPECIAL CONDITIONS
The valve shall be the product of a manufacturer regularly engaged in the
manufact ure of Air release/air vacuum valves having similar service and
size. The valves covered by the specifications are intended to be standard
equipmen t of that has proven ability. Only the following manufacturers and
models are acceptable .
Manufacturers
Vent-0-Mat RBX Anti-shock
ARI D-060-C HF NS
d . All other valves will be considered a substitution, and will be required to
submit a substitution request. The Engineer shall be the sole judge of the
acceptabil ity of any substitution requested . If the substitution request is
found to be unacceptable by the Engineer then the contractor shall provide
the listed equipment at no additional expense to the owner. The Contractor
shall be responsible for any delays as a result of a substitution request.
e . The listing above does not imply that the manufacturer's standard product
is acceptable . The successful manufacturer will be required to conform to
all specifications .
3 . SUBMITTALS
a. Submittals required after award of contract and prior to installation:
1) Technical bulletins and brochures on air release valves.
b . Submittals required prior to final walk through :
1) Operation and Maintenance Manual.
4 . SHIPPING INSTRUCTIONS
a.
b .
C.
d .
All parts shall be properly protected so that no damage or deterioration will
occur during a prolonged delay from the time of shipment until installation is
completed and the units and equipment are ready for operation.
All equipment and parts must be properly protected against any damage
during a prolonged period at the site.
Finished iron or steel surfaces not painted sha,11 be properly protected to
prevent rust and corrosion.
Storage and Protection: Take special care to prevent plastic and similar
brittle items from being directly exposed to the sun, or exposed to extremes
in temperature , preventing any deformation .
ASC-68
PART DA -ADDITIONAL SPECIAL CONDITIONS
5 . WARRANTY:
a . The equipment shall be warranted to be free from defects in workmanship,
design and materials. If any part of the equipment should fail during the
warranty period , it shall be replaced and the unit(s) restored to service at no
expense to the Owner. Warranty shall be for a period of two years and
begin on the Date of Acceptance.
B. PRODUCTS
1. AIR RELEASE/AIR VACUUM VALVE
a. The air vacuum valve shall achieve the following functions :
1) High volume discharge during pipeline filling
2) High volume intake through the large orifice
3) Pressurized air discharge
4) Surge Dampening -Controlled discharge rates
b. The valve shall have an integral surge alleviation mechanism which shall
operate automatically to limit transient pressure rise or shock induced by
closure due to high velocity air discharge or the subsequent rejoining of the
separated water columns. The limitation of the pressure rise shall be
·achieved by decelerating the approaching water prior to valve closure.
c . Materials
1) All internal parts shall be a non-corroding material such as stainless
steel or High density polyethylene.
2) The valve body shall be constructed of stainless steel or ductile iron
and equipped with intake and discharge flanges . Intake/Discharge
orifice area shall be equal to the nominal size of the valve. The valve
shall perform as intended with no deformation, leaking or damage of
any kind for the pressure ranges indicated . ·
C. EXECUTION
1. All air release valves shall be installed in accordance with the instructions of the
manufacturer and as shown on the drawings.
DA-130 JUNCTION SANITARY SEWER MANHOLE
This item shall consist of the construction of a new junction sanitary sewer manhole connecting
existing sanitary sewer line to the proposed san itary sewer line at locations as designated in the
construction plans. Excavation and backfill, furnishing and installation of materials, labor, and
equipment shall be included in the unit bid item price. Item shall be constructed in conformance
with Item 444 and detailed drawings included in the construction plans.
11/02104 ASC-69
PART DA -ADDITIONAL SPECIAL CONDITIONS
MEASUREMENT AND PAYMENT -Measurement and payment for junction sanitary sewer
manhole shall include appurtenant work including excavation through flowable fill backfill to
provide for the structure complete in place as designed for the project. Payment shall be per
each at the contract unit price bid,. which shall include all labor, material, and equipment
necessary for complete installation of structure.
11/02104 ASC-70
"""
PARTE
SECTION E SPECIFICATIONS
(January 1, 1978)
All mate ri als , construction methods and procedures used in this project shall confo rm t o
Sections E1, E2 , and E2A of the Fort Worth Water Department General Co ntract
Documents and General Specifications, together with any additional ma te ri al
specification(s}, construction(s) or later revision(s). (See revisions listed on this sheet.)
Sect ions E 1, E2 and E2A of the Fort Worth Water Department General Contract Documents
and General Specifications are hereby made a part of this contract document by referen ce
for all purposes, the same as if copies verbatim herein, and such Sections are filed and kept
in the office of the City Secretary of the City of Fort Worth as an official record of the City of
Fort Worth.
INDEX
E1 MATERIAL SPECIFICATIONS
E2 CONSTRUCTION SPECIFICATIONS
E2A GENERAL DESIGN DETAILS
Revisions as of April 20, 1981 , follow :
E1-2.4
E2-2 .11
Backfill : (Correct minimum compaction requirement to 95% Proctor de nsi ty
and correct P.I. values as follows:
c. Additional backfill requirements when approved for use in stree ts :
1. Type 'B' Backfill
(c) Maximum plastic index (Pl) shall be§..
2. Type 'C' Backfill
(a) Material meeting requirements and having a Pl of§. or
less shall be considered as suitable for compactio n by
jetting .
(b) Material meeting requirements and having a Pl of~ or
more shall be considered for use only with mechanical
compact ion.
Trench Backfill : (Correct Minimum compaction requirement wherever it
appears in this section to 95% Proctor density except for paragraph a.1
where the "95% modified Proctor density" shall remain unchanged .)
E-1
SECTION E100 -MATERIAL SPECIFICATIONS
MATERIAL SPECIFICATIONS
January 1, 1978 (Added 5/13/90)
E100-4 WATERTIGHT MANHOLE INSERTS
E 100-4 .1 GENERAL: This standard covers the furnishing and installation of watertight
gasketed manhole inserts in the Fort Worth sanitary sewer collection system.
E100-4 .2 MATERIALS AND DESIGN :
a. The manhole insert shall be of corrosion-proof high density polyethelene that meets
or exceed the requirements of ASTM 01248 , Category 5, Type Ill.
b. The minimum thickness of the manhole insert shall be 1/8".
c. The manhole insert shall have a gasket that provides positive seal in wet or dry
conditions . The gasket shall be made of closed cell neoprene rubber and meet the
requirement of ASTM 01056, or equal.
d. The manhole insert shall have a strap for removing the insert. The strap shall be
made of minimum 1" wide woven polypropylene or nylon webbing, with the ends
treated to prevent unraveling. Stainless steel hardware shall be used to securely
attach strap to the insert.
e. The manhole insert shall have one or more vent holes or valves to release gasses
and allow water inflow at a rate no greater than 1 O gallons per 24 hours .
E100-4.3 INSTALLATION :
a. The manhole frame shall be cleaned of all dirt and debris before placing the manhole
insert of the rim.
b. The manhole insert shall be fully seated around the manhole frame rim to retard
water from seeping between the cover and the manhole frame rim.
E-2
PARTF
ACORQ .. CERTIFICATE OF LIABILITY INSURANCE I
DATE (MM/DDIYYYY)
06/18/200 7
PRODUCE ~ (817)457-6700 FAX (817)457-7246 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFO fiMATION
THE SWEENEY COMPANY ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
1121 E. Loop 820 South HOLDER. THIS CERTIFICATE DOES NOT AMEND , EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW .
PO Box 8720
Fort Worth , TX 76124-0720 INSURERS AFFORDING COVERAGE NAIC#
INSURED Conatser Construction TX, LP INSURER A: Bituminous Casualty Corp IH IX
P.O.Box 15448 IN SURE R B: Bituminous Fire & Marine Ins Co A+ IX
Fort Worth, TX 76119 IN SURER C :
INSURERD:
INSURER E:
COVERAGES
THE POLICIES OF INSURANCE LISTED BE LOW HAVE BEEN ISSUED TO THE IN SURED NAMED ABO VE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT . TERM OR COND ITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERT IFICATE MAY BE ISSUED OR
MAY PERTAIN , THE INSURANCE AFFORDED BY TH E POLICI ES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXC LUSIONS AND CO NDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLA IMS .
1rJ: ~0.,9;/ TYPE OF INSURANCE POLICY NUMBER PJl_}i~Y-~_FFEC .!!.V.E pgk'f/1~~[\If~!9iN LIMITS
GENERAL LIABILITY CLP 3 231 053 08/01/2006 08/01/2007 EACH OCCURRENCE $ 1,000,000 -DAMAGE TO RENTED X COMMERC IAL G ENERAL LIABILITY "=-$ 100,000
1 CLAIMS MAD E 0 OCCUR MED EX P (Any one person) $ 5,000
A X CONTRACTUAL, xcu PERSONAL & A DV INJURY $ 1,000,000
X INDEP CONTRACTORS GENERAL AGGREGATE $ 2 ,000,000 -
G EN'L AGGREGATE LIMIT APPLIES PER : PRODUCTS -COMP/OP AGG $ 2,000,000 I rxl PRO-POLICY J ECT nLOC
AUTOMO BILE LIABILITY CAP 3 506 658 08/01/2006 08/01/2007 COMBINED SI NGLE LIMIT -$ X A NY AUTO (Ea acci dent) 1,000,000
X ALL OWNED AUTOS BODILY INJURY -$ X SCHEDULED AUTOS (Per person)
B X HIRED AUTOS BODILY INJURY -$ X NO N-OWNED A UTOS (Per accident)
-
-PROPERTY DAMAGE $ (Per accident)
GARAGE LIABILITY AUTO ONLY -EA ACCIDENT $ Fl ANYAUTO OTHER THAN EAACC $
AUTO ONLY: AGG $
EXCESS/UMBRELLA LIABILITY CUP 2 578 762 08/01/2006 08/01/2007 EACH OCCURREN C E $ 5,000,000 0 OCCUR D CLAIMS MADE UMBRELLA AGGREGATE $ 5,000,000
A $
~ DEDUCTIBLE $
RETENTION $ 10,00C $
WORKERS COMPENSATION AND WC 3 231 052 08/01/2006 08/01/2007 x I we STATU-I T()RV I "AIT<a IOJ,tt·
EMPLOYERS' LIABILITY 1 ,000,000 A ANY PROPRIETOR/PARTNER/EXECUTIVE E.L. EACH ACC IDENT $
O F FICER/MEMBER EXCLU DED? E.L. D ISEASE -EA EMPLOYEE $ 1,000,000
If yes . describe unde r 1,000,000 SPEC IAL PROVISIONS below E.L. D ISEASE -POLI CY LIMIT $
OTHER
DESCRIPTION OF OPERATIONS/ LOCATIONS/ VEHICLES/ EXCLUSIONS ADDED BY ENDORSEMENT/ SPECIAL PROVISIONS
WATER & SANITARY SEWER RELOCATION TO SERVE SH 121T SOUTHWEST PARKWAY , BELLAIRE DR, IH 20, OVERTON RIDGE
P264-603170020483 & P274-703170020483; IN THE CITY OF FT WORTH. CERT HOLDER NAMED ADLN INSURED EXCEPT
PN WORKERS COMP WITH COMMERCIAL LIAB BEING PRIMARY & NON -CONTRIBUTORY WITH WAIVER OF
SUBROGATION ALL POLICIES AS REQUIRED BY WRITTEN CONTRACT. 30 DAY CAN( NOTICE
~MENDED TO 10 DAY FOR NON-PAY OF PREMIUM
CERTIFICATE HOLDER
CITY OF FORT WORTH
1000 THROCKMORTON ST
FT WORTH, TX 76102
25 (2001/08)
CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EX PIRATION DATE THEREOF, THE ISSUING INSURER WILL ~X~ MAIL
_lQ_ DAYS WRIITEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,
~~Xll(K~~KX«MilC!Xt)@tXiXi~:ou,oon:xx
M~~X!llM~~~IMXXXX~KM~x~~xxxxxxxx
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED , the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certi ficate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED , subject to the terms and co nditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement (s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affi rm ativel y or negatively amend , extend or alter the coverage afforded by the policies listed thereon .
ACORD 25 (2001/08)
CERTIFICATE OF INSURANCE
TO : CITY OF FORT WORTH Date~
NAME OF PROJECT:
PROJECT NUMBER:
Water and Sa nita ry Sewer Relocations for SH -121T (S ou thwest Parkway), Parts 1, 5
and 7A
P264-603170020483/P274 -703170020483
IS TO CERTIFY THAT: Conatser Construction TX, LP
is, at the date of this certificate, Insured by this Company with respect to the business operations hereinafter described , for
the type of insurance and accordance with provisions of the standard policies used by this Company, and further
hereinafter described . Exce ptions to standard policy noted on reverse side hereof.
TYPE OF INSURANCE
Policy Effective Expires Limits of Liability
Worker 's Compensation
Comp rehen sive General Bodil y Injury:
Liability Insurance (Public Ea. Occurrence : $
Liability) Property Damage :
Ea. Occurrence: $
Blasting Ea . Occurrence : $
Co llapse of Building or
structures adjacent to Ea. Occurrence : $ ---
excavations
Damage to Underground
Utilities Ea. Occurrence : $
Builder 's Risk
Comprehensive Bodil y Injury :
Automo bile Liability Ea. Person : $
Ea . Occurrence : $
Property Damage :
Ea . Occurrence: $
Bodily Injury :
Contractual Liability Ea . Occurrence : $
Property Damage :
Ea . Occurrence: $
Other
Locat ions covered :-----------------------------------
Description of operations covered:-----------------------------
The above policies either in the bod y thereof or by appropriate endorsement provided that they may not be changed or
canceled by the insurer in less than five (5) days after the insured has received written notice of such change/or
cancellati on .
Where applicable local laws o r re gulations require more than five (5) days actual notice of change or cancellation to be
ass ured , the above policies contain such special requirements , either in the body thereof or by appropriate endorsement
thereto attached .
The C ity, its officers , employees and servants shall be endorsed as an additional insured on Co ntracto r's insurance polici es
exce pt ing employer's liability insurance coverage under Co ntractor 's worker 's compensation insurance policy.
A enc Insurance Co .: ___________ _
Fort Worth Agent By _________________ _
Add ress _________________ _ Title ________________ _
'
VENDORCOMPLIANCETOSTATELAW
The 1985 Session of the Texas Legislature passed House Bill 620 relative to the award of contracts to
non-resident bidders. The law , that in order to be awarded a contract as low bidder, non-resident
bidders ( out-of-state contractors whose corporate offices or principal place of business are outside of
the state of Texas) bid projects for construction, improvements, supplies or services in Texas at an
amount lower than the lowest Texas resident bidder by the same amount that a Texas resident bidder
would be required to underbid a non-resident bidder in the order to obtain a comparable contract in
the state in which the non-resident's principle place of business is located. The appropriate blanks in
Section A must be filled out by all out-of-state or non-resident bidders in order for your bid to meet
specification s. The failure of out-of-state or non-resident contractor 's to do so will autom atically
disqualify that bidder. Resident bidders must check the box in Section B.
A. Non-resident vendors in ______ (give state), our principal place of busi ne ss , are
required to be percent lower than resident bidders by state law . A copy
of the statute is attached.
Non-resident vendors in ______ (give state), or principal place of business , are not
required to underbid resident bidders.
B . Our principal place of business or corporate offices are in the State of Texas. [$1
BIDDER:
Company
City ' State Zip
TIDS FORM MUST BE RETURNED WITH YOUR QUOTATION
F-3
CONTRACTOR COMPLIANCE WITH
WORKERS ' COMPENSATION LAW
Pursuant to V.T.C.A Labor Code Section 406 .096 (2000), as amended, Contracto r certifies that it provides
wo rkers ' compensation insurance coverage for a ll its e mplo yees emplo ye d on city of Fort Worth Department of
Eng ineerin g No . 5504 and City of Fort Worth Proj ect Number P264-603170020483/P274-703170020483
Date
ST A TE OF TEXAS §
COUNTY OF TARRANT §
BEFORE ME, the undersigned authority, on th is day personally appeared MllYK. B<,p~'.:. ,
known to me be the person whose name is s ub scribed to the foregoing instrument, and acknowledged to me that he
executed the same as the act and deed of Conatser Construction TX, LP the purpose and consideration therein
expressed an d in the capacity there in stated.
GIVEN UN DER MY HAND AND SEAL OF OFFICE thi s day of <M\:\.t . 2007 .
SYDNEY JONES
Notary Public, State of Texas
My Co m missi on Exp ires
May 09 , 2010
the State of Texas
I.
!
I
Bo nd No : 022020 9 49
PERFORMANCE BOND
THE ST ATE OF TEXAS §
KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
. . . Liberty Mu..tual
That we (1) Conatser Construction TX, LP as Prmc1pal herem, and (2) Insurarl.ce Canpany ,
a corporation organized under the Jaws of the State of (3) MA , and who is
authorized to issue surety bonds in the State of Texas, Surety herein , are held and firmly bound unto the City of Fort
Worth , a municipal corporation located in Tarrant and Denton Counties, Texas, Obligee herein, in the sum of:
Three Million One Hundred Eighty-four Thousand Nine Hundred Thirty-eight and no/100 ......................... ..
Dollars ($3,184,938.00) for the payment of which sum we bind ourselves, our heirs , executors, administrators ,
successors and assigns, jointly and severally, firmly by these present.
JUN 19 2007
WHEREAS, Principal has entered into a certain written contract with the Obligee dated the __ of
______ 2_0_0_7 a copy of which is hereto attached and made a part hereof for all purposes , for the construction
of:
Water and Sanitary Sewer Relocations for SH-121T (Southwest Parkway), Parts I, 5 and 7A
NOW THEREFORE, the condition of this obligation is such, if the said Principal shall faithfully perform
the work in accordance with the plans, specifications, and contract documents and shall fully indemnify and hold
harmless the Obligee from all costs and damages which Obligee may suffer by reason of Principal's default, and
reimburse and repay Obligee for all outlay and expense that Obligee may incur in making good such default, then
this obligation shall be void; otherwise, to remain in full force and effect.
PROVIDED, HOWEVER, that this bond is executed pursuant to Chapter 2253 of the Texas Government
Code , as amended, and all liabilities on this bond shall be determined in accordance with the provisions of such
statute, to the same extent as if it were copied at length herein.
IN WITNESS WHEREOF, the duly authorized representatives o f the Principal and the Surety have
executed this instrument.
SIGNED AND SEALED this_ day of UN 1 g 20072007.
ATTEST:
(Principal) Secretary
(SEAL)
ATTEST:
Secretary
Fort Worth, TX 76119
Liberty Mutual Insurance Canpany
Surety ~ :~~-
(Attorney-in-fact)
Address: j 75 Berkeley Street
Boston, MA 02117
Telephone Number: 972. 233. 9588
Carolyn Maples
NOTE:
(1) Correct name of Principal (Contractor).
(2) Correct name of Surety.
(3) State of incorporation of Surety
Telephone riumber of surety must be stated . In addition, an original copy of Power of Attorney shall
be attached to Bond by the Attorney-in-Fact.
The date of the bond shall not be prior to date of Contract.
Bond No: 02202094 9
PAYMENT BOND
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS :
COUNTY OF TARRANT §
That we (1) Conatser Construction TX, LPas Principal herein, and (2) Liberty Mutual Insurance
Company a corporation organized and existing
under the laws of the State of (3) MA , as surety, are held and firmly bound unto the City of Fort Worth , a
municipal corporation located in Tarrant and Denton Counties, Texas, Obligee herein, in the amount of Three
Million One Hundred Eighty-four Thousand Nine Hundred Thirty-eight and no/100 ........................... Dollars
($3,184,938.00) for the payment whereof, the said Principal and Surety bind themselves and their heirs, executors ,
adll)inistrators, successors and assigns, jointly and severally, firmly by these presents :
WHEREAS : the Principal has entered into a certain written contract with the Obligee dat~tt~ ~ifaqPJf
-----A.D . , 2007, which contract is hereby referred to and made a part hereof as if fully and to the same
ex tent as if copied at length, for the following project:
Water and Sanitary Sewer Relocations for SH-121T (Southwest Parkway), Parts 1, 5 and 7A
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the s;:iid Principal
shaU faithfully make payment to each and every claimant (as defined in Chapter 2253, Texas Government Code, as
amended) supplying labor or materials in the prosecution of the work under the contract, then this obligation shall be
void; otherwise, to remain in full force and effect. .
PROVIDED, HOWEVER, that this bond is executed pursuant to Chapter 2253 of the Texas Government
Code, as amended, and all liabilities on this bond shall . be determined in accordance with the provisions of said
sta tute , to the same extent as if it were copied at length herein. ·
IN WITNESS WHEREOF, the duly authorized representatives of the Principal and the Surety have
executed this instrument.
. JUN 1 9 2007 SIGNED AND SEALED this __ day of , 1007.
ATIEST:
(Principal) Secretary
(SEAL)
ATIEST:
Secretary
(SEAL)
Vice President of Conatser ManageIEnt
Title: Group, Inc., GP
PO Box 15448
Fort Worth, TX 76119
Name: Glenna S. Davis
Attorney in Fact
~~
Address: 175 Berkeley Street
Boston MA 02117
Carolyn Maples
NOTE :
Telephone Number: 972.233.9588
1. Correct name of Principal (Contractor).
2 . Correct name of Surety.
3. State of incorporation of Surety .
Telephone number of surety must be stated . In addition, an original copy of Power of Attorney
shall be attached to Bond by the Attorney-in-Fact.
The date of bond shall not be prior to date of Contract.
Bond No: 022020949
MAINTENANCE BOND
THE STATE OF TEXAS §
COUNTY OF TARRANT §
KNOW ALL MEN BY THESE PRESENTS: Liberty Mutual
That Conatser Construction TX, LP(Contractor), as principal, and Insurance Canpany , a
corporation organized under the laws of the State of MA , (Surety), do hereby acknowledge themselves to be
held and bound to pay unto the City of Fort Worth, a Municipal Corporation chartered by virtue of Constitution and
laws of the State of Texas, ("City") in Tarrant County, Texas the sum of Three Million One Hundred Eighty-four
Thousand Nine Hundred Thirty-eight and no/100 ..................... , ..... Dollars ($3,184,938.00) lawful money of the
United States, for payment of which sum well and truly be made unto said City and its successors, said Contractor
and Surety do hereby bind themselves, their heirs, executors, administrators, assigns and successors, jointly and
severally.
This obligation is conditioned, however; that, . JIJN 7
WHEREAS, said Contractor has entered into a written Contract with the City of Fort Worth, dated the 9 (00?
__ day of 2007 copy of which is hereto attached and made a part hereof, the performance of the
following described public improvements:
Water and Sanitary Sewer Relocations for SH-121T (Southwest Parkway), Parts l, 5 and 7A
the same being referred to herein and in said contract as the Work and being designated as project P264-
603170020483/P274-703170020483and said contract, including all of the specifications, conditions, addenda,
change orders and written instruments referred to therein as Contract Documents being incorporated herein and
made a part hereof, and,
WHEREAS, in said Contract, Contractor binds itself to use such materials and to so construct the work that
it will remain in good repair and condition for and during a period of after the date of Two (2) Years after the date
of the final acceptance of the work by the City; and
WHEREAS, said Contractor binds itself to maintain said work in good repair and condition for said term of
Two (2) Years; and,
WHEREAS, said Contractor binds itself to repair or reconstruct the work in whole or in part at any time
within said period, if in the opinion of the Director of the Water Department of the City of Fort Worth, it be
necessary; and,
WHEREAS, said Contractor binds itself, upon receiving notice of the need therefore to repair or
reconstruct said work as herein provided.
NOW THEREFORE, if said Contractor shall keep and perform its said agreement to maintain, repair or
reconstruct said work in accordance with all the terms and conditions of said Contract, these_presents shall be null
and void , and have no force or effect. Otherwise this Bond shall be and remain in full force and effect, and the City
shall have and recover from the Contractor and Surety damages in the premises prescribed by said Contract.
This obligation shall be continuing one and successive recoveries may be had hereon for successive
breaches until the full amount hereof is exhausted .
IN WITNESS WHEREOF, this instrument is executed in !_counterparts, each one of which shall be
deemed an original, this __ day of A.D. 2007.
JUN 1 9 2007
ATTEST:
(SEAL)
Secretary
ATTEST:
(SEAL)
Secretary
Managem=mt Group, Inc., GP
Liberty Mutual Insurance Ccxnpany
Name: GJ enna S. Davis
Title: Attorney-:in-Fact
175 Berkeley Street
Boston, MA 02117
Address
Tel No: 972.233.9588
2133668
THIS POWER OF ATTORNEY IS NOT VALID UNLESS IT IS PRINTED ON RED BACKGROUND.
This Power of Attorney limits the acts of those named herein, and they have no authority to bind the Company except in the manner and to
the extent herein stated .
LIBERTY MUTUAL INSURANCE COMPANY
BOSTON,MASSACHUSETTS
POWER OF ATTORNEY
KNOW ALL PERSONS BY THESE PRESENTS: That Liberty Mutual Insurance Company (the "Company"), a Massachusetts stock insurance
company , pursuant to and by authority of the By-law and Authorization hereinafter set forth, does hereby name, constitute and appoint
MICHAEL A. DELABANO, GREG A. WILKERSON, GLENNA S. DAVIS, CATHY VINSON, CAROLYN MAPLES, ALL OF THE
CITY OF FORT WORTH, STATE OF TEXAS ......................................................................................................................... .
, each individually if there be more than one named , its true and lawful attorney-in-fact to make , execute , seal , acknowledge and deliver, for and on its
behalf as surety and as its act and deed, anv and all undertakings, bonds, recognizances and other .surety obligations in the penal sum not exceeding
TWENTY FIVE MILLION AND OQ/100**'***************** DOLLARS($ 25,000,000.00***** ) each, and the
execution of such undertakings, bonds, recognizances and other surety obligations , in pursuance of these presents , shall be as binding upon the
Company as if they had been duly signed by the president and attested by the secretary of the Company in their own proper persons .
That this power is made and executed pursuant to and by authority of the following By-law and Authorization :
ARTICLE XIII -Execution of Contracts: Section 5 . Surety Bonds and Undertakings .
Any officer of the Company authorized for that purpose in writing by the chairman or the president , and subject to such limitations as the
chairman or the president may prescribe, shall appoint such attorneys-in-fact, as may be necessary to act in behalf of the Company to make ,
execute , seal, acknowledge and deliver as surety any and all undertakings, bonds, recognizances and other surety obligations . Such
attorneys-in-fact, subject to the limitations set forth in the ir respective powers of attorney , shall have full power to bind the Company by their
signature and execution of any such instruments and to attach thereto the seal of the Company. When so executed such instruments shall be
as binding as if signed by the president and attested by the secretary.
By the following instrument the chairman or the president has authorized the officer or other official named therein to appoint attorneys-in-fact:
Pursuant to Article XIII , Section 5 of the By-Laws , Garnet W . Elliott, Assistant Secretary of Liberty Mutual Insurance Company, is hereby
authorized to appoint such attorneys-in-fact as may be necessary to act in behalf of the Company to make , execute , seal , acknowledge and
deliver as surety any and all undertakings , bonds , recognizances and other surety obligations .
That the By-law and the Authorization set forth above are true copies thereof and are now in full force and effect.
IN WITNESS WHEREOF , this Power of Attorney has been subscribed by an authorized officer or official of the Company and the corporate seal of
Liberty Mutual Insurance Company has been affixed thereto in Plymouth Meeting, Pennsylvania this 3rd day of _~M~a~y ________ _
2007
COMMONWEALTH OF PENNSYLVANIA ss
COUNTY OF MONTGOMERY
LIBERTY MUTUAL INSURANCE COMPANY
By~~4f-J2<'~
Garnet W . Elliott , Assistant Secretary
On this~ day of Mav , 2007 , before me , a Notary Public , personally came Garnet W . Elliott , to me known, and acknowledged
that he is an Assistant Secretary of Liberty Mutual Insurance Company ; that he knows the seal of said corporation ; and that he executed the above
Power of Attorney and affixed the corporate seal of Liberty Mutual Insurance Company thereto with the authority and at the direction of said corporation .
first above written .
CERTIFICATE
COMMONWEAi.TH OF PENNSYLVANIA
Nolarial~
Toresa Pastella. Noialy Nlic
~ Twp,, M0/1lgOml!ly Colrlly
My Coo'lmission Expiroo Mar. 28. 2(XX)
By~~
Ter6sa Pastella , Notary Public
I, the undersigned , Assistant ecretary of Liberty Mutual Insurance Company, do hereby certify that the original power of attorney of which the foregoing
is a full , true and correct copy, is in full force and effect on the date of this certificate ; and I do further certify that the officer or official who executed the
said power of attorney is an Assistant Secretary specially authorized by the chairman or the president to appoint attorneys -in -fact as provided in Article
XIII, Section 5 of the By-laws of Liberty Mutual Insurance Company.
This certificate and the above power of attorney may be signed by facsimile or mechanically reproduced signatures under and by authority of the
following vote of the board of directors of Liberty Mutual Insurance Company at a meeting duly called and held on the 12th day of March , 1980.
VOTED that the facsimile or mechanically reproduced signature of any assistant secretary of the company , wherever appearing upon a
certified copy of any power of attorney issued by the company in connection with surety bonds , shall be valid and binding upon the company
with the same force and effect as though manually affixed .
Jl 1~1 1 Q ,nn7 IN TESTIMONY WHEREOF, I have hereunto subscribed my name and affixed the corporate seal of the said company, this day of
>,
cu
"C
ti)
ti)
C1) r:
'iii
:::, .c
>, r: cu
=5 ~ ....
>,Cl)
G>W
Ee
0 Q. =o <(M -·· o"'="
... "C
C1) r: 3: cu
a.o E
cu
.!!!o .r:o -.. _o,
0 r: ~m ~.!
-G)
~.c
G)O =~ e'? ·=~ 'E'? Oo <.>..-
0(0
1-.,!.
~Liberty
~MutuaL
Important Notice
TO OBTAIN INFORMATION ABOUT THIS BOND OR TO MAKE A COMPLAINT:
You may contact the Texas Department of Insurance to obtain information on
companies, coverages, rights or complaints at:
800-252-3439
You may write the Texas Department oflnsurance at:
P. 0. Box 149104
Austin, TX 78714-9104
Your notice of claim against the attached bond may be given to the Surety Company
that issued the bond by sending it to the following address:
. Liberty Mutual Surety
ln.terchange Corporate Center
450 Plymouth Road, Suite 400
Plymouth Meeting, PA 19462-8284
You may contact the claim office by telephone at:
610-832-8240
Premium or Claim Disputes
If you have a dispute concerning a premium, you should contact the agent first. If you
have a dispute concerning a claim, you should contact the company first. If the dispute
is not resolved , you may contact the Texas Department of Insurance.
This notice is for information purposes only and does not become a part of or a condition of the attached
document. It is given to comply with Section 2253. 048, Government Code, and Section 53 . 202 , Property
Code , Effective September 1, 2001
PART G -CONTRACT
THE ST A TE OF TEXAS §
COUNTY OFT ARRANT §
JUN 19 2007
THIS CONTRACT, mad e a nd entered into the __ day of 2007and between the City of
Fort Worth , a home-rule municipal corporation located in Tarrant County, Texas, acting through its City Manager
thereunto duly authorized so to do , Party of the First Part, hereinafter termed "OWNER", and Conatser
Construction TX, LPthe City of Fort Worth County of TARRANT and State of TEXAS , Party of the Second
Part, hereinafter termed "CONTRACTOR".
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned, to
be made and performed by the Party of the First Part (Owner), said Party of the Second Part (Contractor) hereby
agrees with the said party of the First Part (Owner) to commence and complete certain improvements described as
follows :
Water and Sanitary Sewer Relocations for SH-121T (Southwest Parkway), Parts 1, 5 and 7A
And all extra work connected therewith , under the terms as stated in the Contract Documents , and at his (their) own
proper cost and expense to furnish all the materials , supplies , machinery, equipment, tools , superintendent, labor,
bonds , insurance , and other accessories and services necessary to complete the said construction , in accordance with
all the requirements of the Contract Documents, which include all maps , plats , blueprints and other drawings and
printed or written explanatory matter thereof, and the specifications thereof, as prepared by the Engineers employed
by the Owner, each of which has been identified by the endorsement of the Contractor and the Engineers thereon ,
together with the Contractor's Written Proposal and the other parts of the Contract Documents hereto attached ,
including the Fort Worth Water Department General Contractor Documents and General Specifications , all of which
are made a part hereof and collectively and constitute the entire contract.
The Contractor hereby agrees to commence work within ten (10) days after the date written notice to do so
shall have been given to him , and to substantially complete same within the time stated in the proposal.
The Owner agrees to pay the contractor in current funds for the performance of the contract in accordance
with the Proposal submitted therefore , subject to additions and deductions , as provided in the Contract Documents
and all approved modifications thereof, and to make payment on account thereof as provided therein .
IN WITNESS WHEREOF , the Parties to these presents have executed this Contract in ~counterparts in the
year and say first above written .
Marc A. Ott, Assistan City Manager
Conatser Construction TX, LP
PO Box 15448
Fort Worth, TX
A. Douglas Rademaker, P .E . Director
Department of Engineering
ATTEST:
1f\~V\~
City Secretary t -Q.D__Q_l l
(Seal)
WITNESSES :
...
Appendix A
l
I SC~U : 1· • ~·
Fl__, TURE A R B OR L A\/F·-J
z
> cc
r-P ROP OSED SH 1 2 1 z
<
/
cc
CL
LEGEND:
RiG H T OF w ,1:1, Y
J(LLAI~ Dll.
L._
' ....
' ..
I
I •
\
I
I
\
I
I
~-
\
I
I
I
I
I
·-1
~ APPROX . PREVIOUS BORING LOCATIONS
\
\
I
p. p. SO·
B ~ fuF•t:; \ B B ~-2 1
•
I
I
I
I
I
DATE : 03/0 3/06
6120 S. Dairy Ashford Road
Houston, Tens 77072-1010
28 1.933. 7388 Ph
281.933 .7293 Fax
APPROV ED BY :
HE
PREPARED BY :
sv
PLAN OF BORINGS
WATER AND SANITARY RELOCATION -SH 121
PROJECT NO.: DRAWING NO.:
DG -05-26060 PLATE 2E
....
0
(!)
;;
I
-, a..
(!)
I ....
0::
~
.... u.
I
(/)
0
"' 0
"' N
"' 0
(!)
0
(!) z
ix
0
(D ...,
6
(/)
u..
0
(!)
LOG OF BORING
Project: Water & Sanitary Sewer Relocations for SH-121
Boring No .: K Date : 7/14/2005
Groundwater during drilling : ---
Groundwater after drilling : ---
ELEV.
DEPTH,
FEET
SO IL SY MBOLS
SAMPLER S YMBOLS
AND FIELD TEST DATA
Northing: -
Easting : --
SOIUROCK CLASSIFICATION
w
(.'.)> zW
ui ui cno
<(O a_N
>-1-
ui
Zu.
W() oa.
>-
Project No.: DG-05-26060
Elevation :
Station : --
Offset: -
S HEAR STRENGTH, TSF
• • • *
0 .5 1.0 1.5 2.0
-;!!. (j z a:
0 MOISTURE O CONTENT, %
1------'----------+---------------------+----1----lpLAsTIC LIMIT ~ LIQUID LIMIT
-0 10 20 30 40 50 I J 70 80 90
FILL ./
/
./
Stiff ·to ·t1ard · brown ·arid · reddiS.ti · t>rown· CLAY ·(CH) · · -· · · · 119 ~ .--IA
'
//
~5 '\
\
?
-87 ....
~,o
w/sand and gravel
. Tan andgrayLiMESTONE !
d I--
-15
1-20
~25
'-30
'-35
~40
Shear Types : • = Hand Penet. • = Torvane A = Unconf. Comp . * = UU Triaxial
See Plate 2A Through 2E for boring location . PLATE 12
g .__ __________ _
! ~
~ Z §
>~ er:: ~ ...
SCAU: 1· = :)()()'
>-,, .
..._: .. ~,'
7&' • <
'--'
i
~(.S
0''(-c,(>
2
F
Ir 2:J
E
LEGEND:
~ APPROX. BORING LOCATIONS
I I ..,..~1 p,.'v'v
p . s1J11'59 qi>,;i.-f-r1 . I
" I
·-/
I
i-1'<;1.'
I
I e,01) lA.
I
I
. 1011 1,sc1 ..
~-S 1•5 SH ~ 2 1
C;F \:\f /::.~ '( I
I •,o .
. · 1 "'ic. s. s. j!.
~ sj;,,c;
~-21
"'"'4 /-"'
ie::i
' " ~
u510" t<1 ,c• sf.7 ,a
SOUTHY (ST LOOP 820
DATE : 02/20/06
6120 S. Dairy Ashford Road
HoUSU>n, Texas 77072 -1010
281.933. 7388 Ph
lRl.933.7293 Fax
APPROVED BY : PREPARED BY :
HE SV
PLAN OF BORINGS
WATER & SANITARY RELOCATION -SH-121
PROJECT NO.: DRAWING NO.:
DG-05-26060 PLATE 2D
l-o
(!) -:;:
I
--,
CL
(!)
I
I-er
~
1-
lL
I en
0 <D
0
<D
N
"' 0
(!)
0
(!)
~ er
0
CD
=!
0 en
lL
0
(!)
0
LOG OF BORING
Project: Water & Sanitary Sewer Relocations for SH -121
Boring No .: D Date: 1/26/2006
Groundwater during drilling : ---
Groundwater after drilling : ---
ELEV.
DEPTH ,
FEET
SOI L SYMBO LS
SAMPLER SY MBOLS
A ND FIELD TES T DATA
Northing : --
Easting : --
SOIUROCK CLASSIFICATION
w
c.'.l> z W
w in
U) 0
<{0
Q. N
>-1-
iii
Z u. w u oa.
>-
Project No .: DG-05-26060
Elevation :
Station : --
Offset: --
SHEAR STRENG TH , TS F
• • • *
~5 1.0 1.5 2.0
~ci z a:: a MOIS TUR E O CO NTEN T , %
1-----....L_--------i--------------------+---+-~PLASTIC LIM IT 1---i LIQUID LIM IT
-o
'-5
'-10
"'-,) ) ) THO 29/6" & ~ 50/3"
~) )
)\. ) )\.
),
~)
)
~
THO 50/3" &
50/3"
THO 50/2 .5"
& 50/2"
w /limestone 2'-15'
53
~15 THO 50/3" &
50/3 .5"
. Ve ry stiff to hard iight. browri .SANDY C°i.A '((c(_f ........ .
'-20
-25
'-30
'-35
'-4 0
Sh ear Type s :
w/lime stone layers
THO 50/2" &
50/2"
• = Hand Pe net. • = Torvane
See Plate 2A Thro ugh 2E for boring location .
A = Unconf. Comp.
10 20 30 40 50 I J 70 80 90
i
6
\
\
}
111 ) ~ i•
)
0 1-k •Ill
* = UU Tria xial
PLATE 5
_......_ ___________ _
·>· '-I J .
\ ,,, '1..· 1.\ T r '
....
0
0
> I
-, a.
0
I .... -a:
~
I
(/)
0
<O
0
<O
N
"' 0
-0 0
0 z er
0
CD ...,
i5
(/)
lL
0
0
LOG OF BORING
Project: Water & Sanitary Sewer Relocations for SH-121
Boring No .: E Date : 1/25/2006
Groundwater during drilling : ---
Groundwater after drilling : ---
ELEV.
DEPTH ,
FEET
SOIL SY MB OLS
SAMPLER SYMBOLS
ANO FIELD TE ST DATA
Northing : --
Easting : --
SOIUROCK CLASSIFICATION
UJ >-CJ> t: Z':!! en ii5 en Zu. en a UJU
<{ a QQ.
Q.N >-a:
Project No .: DG -0 5-26060
Elevation :
Station: --
Offset: --
SHEAR STRENGTH , TSF
• • • *
0 .5 1.0 1.5 2.0
"#-0 z a MOISTURE O CONTENT. %
1------'---------+--------------------+---+-~PLASTIC LIM IT 1------1 LIQU ID LIMIT
-o
~10
1--15
~20
~25
1--30
1--35
~.o
·.IX THO 18/6" &
17 /6"
. IX THO 50/3'' &
50/2"
I) THO 50/2 .5"
~ &50/2"
= =
= = .....__ THO 50/1.5"
& 50/1 .5"
··Stiff ·to ·t1arcf ·darkg·ray· and ·t>rown · SANDY CLAY · · · · · · · ·
(CL)
w /roots and rocks at 1'
w/limestone 2'-16'
.. Light brown· SHALE .......................................... .
Shear Types : • = Hand Penet. • = Torvane .t.. = Unconf. Comp .
See Plate 2A Through 2E for boring location .
10 20 30 40 50 I O 70 80 90
.89
t-H
121 C
.94
\
* = UU Triax ia l
PLATE 6
S.__ __________ _
~
l-o
('.) ..,
> I
a:
('.)
I
I--a:: ~
1-u.
I en
0
~
~
"' 0 -('.) 0
('.) z
a'.
0 a, ....,
0 en
u.
0
('.)
0
LOG OF BORING
Project: Water & Sanitary Sewer Relocations for SH-121
Boring No .: F Date : 1/25/2006
Groundwater during drilling : ---
Groundwater after drilling : --
ELEV.
DEPTH.
FEET
SOIL SYMBOLS
SAMPLER SYMBOLS
AND FIELD TEST DATA
Northing : --
Easting : --
SOIUROCK CLASSIFICATION
w >-c, > f-
~ ~ ~u. cno wu <(o oa.
a. N >-
°# ci a:
Project No .: OG-05-26060
Elevation :
Station : --
Offset: --
SHEAR STRENGTH , TSF • • • *
0 .5 1.0 1.5 2~
Z 0 MOISTURE O CONTENT, %
1------'-----------!----------------------+---+--PLASTIC LIMIT t------1 LIQUID LIMIT
-o
-5
'-10
>--15
~20
-25
1-30
~35
'-40
Shear Types :
8-12-14
) THO 22/6" &
31/6"'
THO 50/2 .5"'
& 50/2"
THO 50/1 .5"'
& 50/1 .5"'
.. Very .Stiff dark b·rOWri. SANDY CLAY (CL).............. . ...
·. w/roots and limestone ·we~itiie;reci LiMest<:>°N .f . . . . . . . . . . . . . . . . ....... .
Tan and.brown SHALE ................................ .
w/limestone layers
• = Hand Penet. • = Torvane • = Unconf. Comp.
See Plate 2A Through 2E for boring location.
)
)
)
6
)
1
10 20 30 40 50 ! 0 70 80 90
* = UU Triaxial
PLATE 7
....,...._ __________ _ ~ I . I -· :__.:._ .\,.,.: . ..:.'. .. ;
\' '\ '\ I ·\T r,
--,
a.
(.?
I
l-a::
~
1-u.
I
(/)
0
<O
0
<O
N .;,
0
(.?
0
(.? z er
0
al
..J
i5
(/)
u.
0
(.?
0
LOG OF BORING
Project: Water & Sanitary Sewer Relocations for SH-121
Boring No .: G Date : 1/25/2006
Groundwater during drilling : ---
Groundwater after drilling : ---
ELEV.
DEPTH ,
FEET
SOIL SYMBOLS
SAMPLER SY MBOLS
AND FIELD TEST DATA
Northing : -
Easting : -
SOIUROCK CLASSIFICATION
w >-<.? > 1-
~&3 ~u_ enc wu .,:o OCl.
Cl. N >-
~ (j a::
Project No.: DG -05-26060
Elevation :
Station : --
Offset: --
SHEAR STRENGTH , TSF
• • • *
0 .5 1.0 1.5 2.0
Z 0 MOISTURE O CO NTENT. %
1------..,_--------+--------------------+---+----lPLASTIC LIMIT 1---------l LIQUID LIMIT
-o ~
~ ~
) ~
) ) )
)
)
~ )
... 5
~,o
~15
~20
'-25
'-30
~35
-40
Shear Types :
2 1-16-17
8-12-17
THO 5011" &
50/0 .5"
~ THO 50/0.5"
& 50/0 .25"
THO 5010 .5"
&5010"
79
Ver/ stiff redd iS h broWn SANDY CLAY (CL)···········
Clayey sand w/limestone at 8' 39
Tan LIMESTONE
• = Hand Penet. • = Torvane A = Unconf. Comp .
See Plate 2A Through 2E for boring location .
125
10 20 30 40 50 E J 70 80 90
) 1-H
)
J...
V
lo
)
)
.~
,II
* = UU Triaxial
PLATE 8
..,..._ __________ _
SOUTH~E ST LOOP 820
2
PRO
TH CJ r Y 1..f H J 1S
LEGEND:
~ APPROX. BORING LOCATIONS DATE: 02/20/06
6120 S. D&iry Ashford Road
Houstoo. Tc.us 77072-IOlO
28 1.933 . 7388 Ph
28 1.933 .7293 Fax
APPROVED BY:
HE
I tv
10
PREPARED BY:
sv
PLAN OF BORINGS
WATER & SANITARY RELOCATION -SH-121
PROJECT NO .: DRAWING NO.:
DG-05-26060 PLATE 2C
co g
!'.?
M ,_
0
C)
> J:
-,
"-C)
J: ,_
a::
~ ,_
u.
J:
Cl)
0
<D
0
<O
N
"' 0
C)
0
C) z
ii'.
0 a,
..J
6
Cl)
u.
0
C)
0
LOG OF BORING
Project: Water & Sanitary Sewer Relocations for SH-121
Boring No .: H Date: 1/27/2006
Groundwate r during drilling: ---
Groundwater after drilling : ---
ELEV.
DEPTH ,
FEET
SOIL SYMBOLS
SAMPLER SY MBOLS
AND FIELD TE ST DATA
Northing : --
Easting : --
SOIUROCK CLASSIFICATION
w >-c., > 1-z W ii5
ii5 ii5 Z LL mo wu
<(O OCl.
(l_N >-
Project No .: DG-05 -26060
Elevation :
St ati on : -
Offset: --
SHEAR STRENGTH . TSF
• • • *
Q5 1~ 1.5 2 .0
cf!. 0 er
Z 0 MOISTURE O CONTENT. %
l--------'-----------+-------------------+--+---1PLASTIC LIMIT t------l LIQUID LIMIT
-o 7 ~ )
D) >
) ) ~ >
) >
)
>
) >
~5
~,o
'-15
'-20
-25
-30
~40
Shear Types :
--i=1t.L : ii 9ii1 brown si,1rid,i ·day ·ai-id . da,iey ·s{1i ---· · -· · · · · · · · ·
THO 50/0 .25" -Tan anci gray LiMESTONE ·············· ........... ---. -. -
& 5010"
THO 50/0" &
50/0"
THO 50/0" &
50/0"
THO 50/0" &
5010"
76
• = Hand Penet. • = Torvane .A. = Unconf. Comp .
See Pl a te 2A Through 2E for boring location .
10 20 30 40 50 60 70 80 90
I~
\
)
0
* = UU Triaxial
PLATE 9
-''-------------