ORDINANCE ACCEPTING IMPROVEMENTS ON A PORTION OF LOWDEN STREET .
AND PORTIONS OF SUNDRY OTHER STREETS, AVENUES AND PUBLIC PLACES
IN THE CITY OF FORT WORTH, TEXAS; DECLARING THE CONTRACT WITH
GLADE, INC. FOR THE CONSTRUCTION OF SAID
IMPROVEMENTS FULLY COMPLETED AND PERFORMED; DIRECTING THE ISSUANCE,
EXECUTION AND DELIVERY OF CERTIFICATES IN EVIDENCE OF SPECIAL
ASSESSMENTS LEVIED AFTER GIVING EFFECT TO SUNDRY CREDITS HEREIN
AUTHORIZED AND ALLOWED AGAINST SOME OF SAID ASSESSMENTS; DIRECTING
THE CITY SECRETARY TO ENGROSS AND ENROLL THIS ORDINANCE BY COPYING
THE CAPTION OF SAME IN THE MINUTE BOOK OF THE CITY COUNCIL OF
FORT WORTH, TEXAS, AND BY FILING THE COMPLETE ORDINANCE IN APPRO-
PRIATE ORDINANCE RECORDS OF SAID CITY; AND PROVIDING AN EFFECTIVE
DATE.
WHEREAS, the City of Fort Worth, Texas, has heretofore entered into a contract
with GLADE, INC. for the making and construction of certain
street improvements on the hereinafter described portions of streets, avenues and
public places in .stid City, to-vit:
1. LOWDEN STREET From South Grove Street to Pecan Street,
known and designated as Unit 1, Project
No. 104-24000-194.
2. ANNIE STREET From May Street to St. Louis Avenue,
known and designated as Unit 2, Project
No. 104-24000-194.
3. ANNIE STREET From St. Louis Avenue to Galveston Avenue,
known and designated as Unit 3, Project No.
104-24000-194.
4. INGRAM STREET From Lipscomb Street to Travis Street,
known and designated as Unit 4, Project
No. 104-24000-194.
5. WAGGOMAN STREET From Merida Avenue to McCart Avenue,
known and designated as Unit 5, Project No.
104-24000-194.
WHEREAS, by sundry proceedings heretofore passed by the City Council of the
City of Fort Worth, Texas, including Ordinance No. 621888 , a portion of the cost of
said improvements was levied and assessed against the respective properties abutting
on each of the above described portions of streets, avenues�,and public places and against
the real and true owners thereof; and,
WHEREAS, the City Council of the City of Fort Worth, Texas, has, upon review,
found and determined that, in some instances, in order to effect substantial justice
and equality, it is desirable and necessary to grant and issue certain credits against
some one or more of the assessments levied by Ordinance No. 6218 , and
WHEREAS, the street improvements hereinabove mentioned have been completed
upon each of the portions of streets, avenues and public places hereinabove described,
and have been inspected and found to be in complete accordance with the contract therefor;
NOW, THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS, THAT:
I.
The improvements on each of the portions of streets, avenues and public
places hereinabove described be, and they are hereby, accepted; ,and the contract with
reference thereto be, and it is hereby, found and declared fully completed and performed.
II.
The Mayor, be, and he is hereby, directed to issue and execute in the name
of the City, certificates in evidence of the special assessments levied against abutting
property and the owner thereof for such improvements, and the City Secretary is directed
to attest same and impress thereon the corporate seal of the City, all in accordance with
the proceedings relating to such improvements and assessments. The certificates shall be
numbered, shall describe the property against which the assessment has been levied, shall,
where known, state the name or names of the true owners of the respective parcels of pro-
perty assessed and shall be issued in an amount equal to the difference between the
principal amount of the assessment and the amounts of any credit issued thereon. The
numbers of the certificates, with the property descriptions to be shown on'the respective
certificates, together with the names of the owners of said property, the principal amount
of the assessment, the respective credits, if any which are hereby authorized, granted and
allowed against the principal amount ,of some one or more of the assessments heretofore
levied, and the principal amount for which each certificate is to be issued after giving
effect to such credit, if any, are hereby enumerated and itemized as follows:
a -•
III.
When each of the certifiactes has been duly executed as hereinabove provided,
same shall be delivered to the Tax Assessor-Collector as part payment of the contract
price.
IV.
The City Secretary is hereby directed to engross and enroll this ordinance by
copying the caption of same in the Minute Book of the City Council of Fort Worth, Texas,
and by filing the complete ordinance in the appropriate Ordinance Records of said City.
V.
This ordinance shall take effect and be in full force and effect from and after
the date of its passage.
PASSED AND APPROVED THIS ol-S day of 4G�i 19 .
411117
APPROVED AS TO FORM AND LEGALITY:
i
City Attorney
PROJECT NO. 104-24000-194, UNIT 1, LOWDEN STREET FROM SOUTH GROVE STREET TO PECAN STREET, to
be improved with seven-inch thick hot-mix asphaltic concrete pavement on a six-inch thick
lime stabilized subgrade, seven-inch high concrete curb and two-foot wide concrete gutter, so
that the finished roadway will be forty feet wide, and by constructing six-inch thick concrete
driveways and four-foot wide concrete sidewalks where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
BEGINNING AT THE NORTHEAST CORNER OF SOUTH GROVE STREET AND LOWDEN STREET
NORTR SIDE OF STREET RYAN PRUITT ADDITION
Sam Weisblatt 12 7 125' Lot Adjusted to
1900 Rosedale Res. 100' Pavement $1.93 $193.00
100' Curb & Gutter 3.47 347.00
100' Sidewalk 3.60 360.00
85 Sq. Ft. Drivewayl 06 90.10
$ 990.10
Texas Conference of 13 7 165.4' Side Lot Adjusted to
Seventh Day Adventists Comm. 100' Pavement $1.93 $193.00
5225 South Freeway 100' Curb & Gutter 3.47 347.00
100' Sidewalk 3.60 360.00
$ 900.00
PECAN STREET INTERSECTS
SOUTH SIDE OF STREET
Alvin Zidell C 16 165.7' Pavement $9.75 $1,615.58
1318 Davis Bldg. Apt. $1,615.58
Dallas, Texas 75202
Alvin Zidell A 16 125' Pavement $9.75 $1,218.75
1318 DavisBldg. Apt. $1,218.75
Dallas, Texas 75202
TOTAL COST TO PROPERTY OWNERS . . . . . . . . . . . . $ 4,724.43
TOTAL COST TO CITY OF FORT WORTH . . . . . . . . . . 5,686.41
TOTAL CONSTRUCTION COST . . . . . . . . . . . . . . . $100410._84
1.
PROJECT N0. 104-24000-194, UNIT 2, WEST ANNIB STREET PAVING SKIP AT ST. LO IS AVENUE, to be
improved with six-inch thick hot-mix asphaltic concrete pavement on a aix-inch thick lime
stabilized subgrade, .with eight-inch high concrete curb and two-foot wide concrete gutter
so that the finished roadway will be twenty-six feet wide and by constructing six-inch-thick
concrete driveways and four-foot wide concrete sidewalks where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
NORTH SIDE OF STREET TUCKER'S ADDITION
John Hernandez E 10 100' Pavement $3.33 0333.00
512 St. Louis Apt. 100' Curb & Gutter COO 400.00
5' Sidewalk 3.60 18.00
$751.00
ST. LOUIS AVENUE INTERSECTS
SOUTH SIDE OF STREET
REBEKAH LODGE E 15 100' Sidewalk $3.60 $360.00
600 St. Louis `pt. $360.00
TOTAL COST TO PROPERTY OWNERS $1,111.00
TOTAL COST TO CITY OF FORT WORTH 1,301.59
TOTAL CONSTRUCTION COST
2.
PROJECT NO, 104-24000-194, UNIT 3, WEST ANNIE PAVING SKIP AT ST. LOUIS AVENUE, to be
improved with six-inch thick hot-mix asphaltic concrete pavement on a six-inch thick
lime stabilized subgrade, eight-inch high concrete curb and two-foot wide concrete
gutter, so that the finished roadway will be twenty-six feet wide and by constructing
six-inch thick concrete driveways where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
BEGINNING AT THE NORTHWEST CORNER OF LOT E, BLOCK 14
NORTH SIDE OF STREET TUCKER'S ADDITION
Jennie H. Bilderback E 11 105' Existing Facilities No Assessment
515 St. Louis Apt.
C,. H. Martin West 14 85' Pavement $3.33 $283.05
601 St. Louis 85' of Apt. 85' Curb & Gutter 4.00 340.00
E $623.05
G. T. Russell East 14 20' Pavement $5.25 $105.00
209 W. Annie 20' of Comm. 20' Curb & Gutter 4.00 80.00
E $185.00
TOTAL COST TO PROPERTY OWNERS $808.05
TOTAL COST TO CITY OF FORT WORTH 1,444.51
TOTAL CONSTRUCTION COST Y 252.56
3-
PROJECT NO. 104-24000-194, UNIT 4, PAVING SKIPS ON INGRAM STREET BETWEEN LIPSCOMB STREET
TO TRAVIS AVENUE, to be improved with six-inch thick hot-mix asphaltic concrete pavement
on a six-inch thick .lime stabilized subgrade, seven-inch high concrete curb and two-foot
wide concrete gutter, so that the finished roadway will be thirty-feet wide and by con-
structing six-inch thick concrete driveways and four foot wide concrete sidewalks where
specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
NORTH SIDE OF STREET FIELDS-WELCH ADDITION (HENDRICKS SUBDIVISION)
H. C. Stearns 6 D 24 60' Adjusted to
1419 Lipscomb Apt. 45' Pavement $4.06 $182.70
60' Curb & Gutter 3.47 208.20
60' Sidewalk 3.60 216.00
$606.90
Gladys Howard 5 D/24 60' Exisiting*Facilities
6408 Forest Hill Dr. Apt. No Assessment
Emma Alexander 4 D 24 60' Existing Facilities
1117 College Apt. No Assessment
J. R. Morgan 3 D/24 57' Existing Facilities
800 Ingram Apt. No Assessment
TRAVIS AVENUE INTERSECTS
SOUTH SIDE OF STREET
First Assembly of 1 D/24 127' Side Lot Adjusted to
God Church Apt. 100' Pavement $1.93 $193.00
1424 Hemphill 100' Curb & Gutter 3.47 347.00
100' Sidewalk 3.60 360.00
118 Sq. Ft. Drive 1.06 125.06
$1,025.08
G. M. Cole 2 D 24 107' Sidewalk $3.60 $395.20
4312 Clayton Road Apt. $385.20
TOTAL COST TO PROPERTY OWNERS $2,017.18
�• TOTAL COST TO CITY OF FORT WORTH 4,807.22
TOTAL ESTIMATED CONSTRUCTION COST ,�2�►
PROJECT' NO. 104-24000-194, UNIT 5, WAGGOMAN STREET FRCK MERIDA AVENUE TO McCART STREET, to be
improved with seven-inch thick hot-mix asphaltic concrete pavement on a six-inch thick lime
Stabilized subgrade, seven-inch high concrete curb and. two-foot wide concrete gutter, .so
that the finished roadway will be thirty-six feet wide and by constructing six-inch thick
concrete driveways where specified.
BLOCK
OWNER LOT ZONING FRONTAGE . RATE AMOUNT ASSESSMENT
i
BEGINNING AT THE WEST LINE OF LOT 15, BLOCS 4, CARROLL STONE ADDITION
NORTH SIDE OF STREET Gag%& STONE ADDITION
-r
Ralph K. Bell 15 4- 90' Pavement $8.66 $779.40
2612 Waggoman Ind. 90' Curb & Gutter 3.47 312.30
173 Sq. Ft: Drive 1.06 183.38
$1,275.08
Chatley Wilkerson 14 4 90' Pavement $8.66 $779.40
40" Ryan Avenue Apt. 90' Curb & Gutter 3.47 312.30
63 Sq. Ft. Drive 1.06 66.78
$19158.48
Mrs. W. G. Jacobs 13 4 90' Pavement $5.30 $477.00
2606 Waggoman Apt. 90' Curb & Gutter 3.47 312.30
63 Sq. Ft. Drive 1.06 66.78
$ 856.08
Dibrell Truett 12 4 90' Pavement $8.66 $779.40
1155 East Seminary Ind. 90' Curb A Gutter 3.47 312.30
63 Sq. Ft. drive 1.06 66.78
$1,158.48
David D: Miller 11 4__ 90' Pavement $8.66 $779.40
P.O. Box 11431 Ind. 900 Curb & Gutter 3.47 312.30
127 Sq. Ft. Drive 1.06 134.62
$1,226.32
Moreland Warehouse 81, 9, 4� 270! Pavement $8.66 $2,338.20.
Company & 10 Ind. 158' Curb A Gutter 3.47 548.26
252U Waggoman 127 Sq. Ft. Drive 1.06 134.62
' $3,021.08
5-
PROJECT NO, 104-24000-194, UNIT 5. WAGGOMAN STREET FR+dM MERIDA AVENUE TO McCART STREET
CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
NORTH SIDE OF STREET CARROLL STONE ADDITION
Robert Cheek 7 4 91' Pavement $5.30 $482.30
2502 Waggoman Apt. 91' Curb & Gutter 3.47 315.77
IZ7' Sq. Ft. Drive 1.06 134.62
$ 932.69
American Petrofina 6 4 125' Pavement $8.66 $1,082.50
Company Comm, $1,082.50
Box 2159
Dallas, Texas 75221
McCART STREET INTERSECTS
SOUTH SIDE OF -STREET
Knute A. Wilhelms 1 5_ 125' Pavement $8.66 $1,082.50
3778 McCart Comm. $1,082.50
L,, .A. Hackney 24 5 91' Pavement $5.30 $482.30
2509 Waggoman Apt. 91' Curb & Gutter 3.47 315.77
63 Sq. Ft. Drive 1.06 66.78
$ 864.85
Estate of
Mrs. Gustie Harper 23 5 90' Pavement $8.66 $779.40
4932 Gilbert Drive Apt. 90' Curb & Gutter 3.47 312.30
63 Sq. Ft. Drive 1.06 66.78
$1,158.48
James L. Strayhan 22 5 90' Pavement $8.66 $779.40
2540 Rogers Ind. 90' Curb & Gutter 3.47 312.30
63 Sq. Ft. Drive 1.06 66.78
$1,158.48
6.
PROJECT NO. 104-24000-194, UNIT 5, WAGGOMAN STREET FROM MERIDA AVENUE TO McCART STREET
CONTINUED
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
SOUTH SIDE OF STREET CARROLL STONE ADDITION
Ben E. Dyeas & 21 5 90' Pavement $8.66 $779.40
John C. Tucker Ind. 90' Curb & Gutter 3.47 312.30
4833 Collinwood $1,091.70
76107
Mr. and Mrs. J. C. 19 & 5 180' Pavement $8.66 $1,558.80
Collins & Horace G. 20 Ind. 180' Curb & Gutter 3.47 624.60
Anderson $2,183.40
6108 Yosemite Drive
George S. Bohannon 18 5 90' Pavement $8.66 $779.40
3132 Pecan Ind. $ 779.40
Carl Yarborough Co. 17 5 90' Pavement $8.66 $779.40
P.O. Box 11248 Ind. 90' Curb & Gutter 3.47 312.30
3304 S. Freeway 173 Sq. Ft. Drive 1.06 183.38
76110 $1,275.08
0. W. & Jerry 16 5 90' Pavement $8.66 $779.40
Conditt Ind. 90' Curb & Gutter 3.47 312.30
301 Henderson $1,091.70
TOTAL COST TO PROPERTY OWNERS . . . . . . . . . . $21,396.30
TOTAL COST TO CITY OF FORT WORTH . . . . . . . . . 11,258.79
TOTAL ESTIMATED CONSTRUCTION COST . . . . . . . . $32,655.09
7.
PROJECT NO, 104-24000-194, UNIT 6, TRAVIS AVENUE FROM FLINT STREET TO MALTA STREET, to be
improved with six-inch thick hot-mix asphaltic concrete pavement on a six-inch thick lime
stabilized subgrade, seven-inch high concrete curb and eighteen-inch wide concrete gutter,
so that the finished roadway will be thirty-feet wide and by constructing six-inch thick
concrete driveways where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
BEGINNING AT THE SOUTH LINE OF LOT 10, BLOCK 2, BOARD OF TRADE ADDITION
WEST SIDE OF STREET BOARD OF TRADE ADDITION
C. R. Ives 10 2 125' Side Lot Adjusted to
800 Flint Res. 100' Pavement $2.46 $246.00
100' Curb & Gutter 2.94 294.00
85 Sq. Ft. Drive 1.06 90.10
$630.10
0. E. Herron 9 2 125' Side Lot Adjusted to
801 Malta Rees. 100' Pavement $2.46 $246.00
100" Curb & Gutter 2.94 294.00
$540.00
MALTA STREET INTERSECTS
EAST SIDE OF STREET SOUTH SIDE ADDITION
W. A. Morgan 14 3 125' Side Lot Adjusted to
1232 W. Boyce Res. 100' Pavement $2.46 $246.00
100' Curb & Gutter 2.94 294.00
$540.00
Garland W. Winsett 15 3 125' Side Lot Adjusted to
738 Flint Res. 100' Pavement $2.46 $246.00
100' Curb & Gutter 2.94 294.00
85 Sq. Ft. Drive 1.06 90.10
$630.10
TOTAL COST TO PROPERTY OWNERS $2,340.20
TOTAL COST TO CITY OF FORT WORTH 5,061.92
TOTAL ESTIMATED CONSTRUCTION COST IZ,, 2 2
8.
PROJECT N0. 104-24000-194 UNIT 7 -TRAVIS AVENUE FROM MALTA STREET TO BOLT STREET, to be
improved with six-inch thick hot-mix asphaltic concrete pavement on a six-inch thick lime
stabilized subgrade, seven-inch high concrete curb and eighteen-inch wide concrete gutter,
so that the finished roadway will be thirty-feet wide and by constructing six-inch thick
concrete driveways where specified.
BLOCK
OWNER LOT ZONING FRONTAGE RATE AMOUNT ASSESSMENT
BEGINNING AT THE SOUTH LINE OF LOT 10, BLOCK 1, BOARD OF TRADE ADDITION
WEST SIDE OF STREET BOARD OF TRADE ADDITION
Dorothy Walker 10 1 125' Side Lot Adjusted to
2836 Southgate Drive Res. 100' Pavement $2.46 $246.00
100' Curb & Gutter 2.94 294.00
$540.00
Mrs. T. L. Allen 9 1 119' Side Lot Adjusted to
801 Bolt Rea. 100' Pavement $2.46 $246.00
100' Curb & Gutter 2.94 294.00
85 Sq. Ft. Drive 1.06 90.10
$630.10
BOLT STREET INTERSECTS SOUTH SIDE ADDITION
EAST SIDE OF STREET
Mrs. Martha Sue 15 2 122' Side Lot Adjusted to
Davisson Res. 100' Pavement $2.46 $246.00
739 Bolt 100' Curb & Gutter 2.94 294.00
140 Sq. Ft. Drive 1.06 148.40
$688.40
Jacob Farrell 16 2 125' Side Lot Adjusted to
2315 Sanborn Res. 100' Pavement $2.46 $246.00
100' Curb & Gutter 2.94 294.00
85 Sq. Ft. Drive 1.06 90.10
$630.10
TOTAL COST TO PROPERTY OWNERS $2,488.60
TOTAL COST TO CITY OF FORT WORTH 4,593.42
TOTAL ESTIMATED CONSTRUCTION COST 7 0$2.02
9.
6. TRAVIS AVENUE From Flint Street to Malta Street,
known and designated as Unit 6, Project
No. 104-24000-194.
7. TRAVIS AVENUE From Malta Street to Bolt Street, known
and designated as Unit 7, Project No.
104-24000-194.
8. COVERT STREET From Merida Avenue to Sandage Avenue,
known and designated as Unit 8, Project
No. 104-24000-194. The making and con-
struction of street improvements in this
unit only as set out and described in
Ordinance No. 6206, dated Novemeber 24,
1969, with Benefit Hearing set for December
23, 1969, when it was determined by the
City Council to delete this unit from
the contract as provided in Sec. 10, Art.
1105b, of the Revised Civil Statute of
Texas as amended.
9. SANDAGE AVENUE From Covert Street to 380.8 Feet South,
known and designated as Unit 9, Project
No. 104-24000-194. The making and con-
struction of street improvements in this
unit only as set out and described in
Ordinance No. 6206, dated November 24,
1969, with Benefit Hearing set for December
23, 1969, when it was determined by the
City Council to delete this unit from
the contract as provided in Sec. 10, Art.
1105b, of the Revised Civil Statute of
Texas as amended.
10. MERIDA AVENUE From Covert Street to 379.1 Feet South,
known and designated as Unit 10, Project
No. 104-24000-194. The making and con-
struction of street improvements in this
unit only as set out and described in
Ordinance No. 6206, dated November 24,
1969, with Benefit Hearing set for December
23, 1969, when it was determined by the
City Council to delete this unit from
the contract as provided in Sec. 10, Art.
1105b, of the Revised Civil Statute of
Texas as amended.
UNE City of Fort Wortk Texas
%*'WHO Mayor and Council Communication
R.A B.
QRAFiAM� DATE 'Eu�R E sus�EcT: Final Payment, Assessment Paving PAGE
5/25/70
FP-708 at Ten Location on the South Side lor _2
Final Council Action on the project described below is requested.
Project Description
Name: Assessment Paving at 10 Locations on
the South Side, Project No. 104-24000-
194
Contractor: Glade, Inc
Contract Awarded: November 24, 1969 (M&C C-1623)
Work Order Issued: January 9, 1970
Work Order Effective: January 19, 1970
Date of Final Inspection and
Approval: April 22, 1970
Working Time Bid: 95 Working Days
Working Time Used: 28 Working Days
Project Cost and Financing
Original Bid Price: $77,928.00
Change Order No. 1 (M&C C-1623,
11/24/69 - 8,925.00
Revised Bid Price: 69,003.00
Change Order No. 2: (AR, 1-15,
4/9/70) + 1,598.50
Final Bid Price: 70,601.50
Final Contract Cost: $62,766.93
,Partial Payments Previously Made: 3 Amount: $47,105.31
Final Payment Due: $15,661.62
Final Payment to be made from Project Account No. 104-24000-194
Deviation from Bid Price:
The under-run of $7,834.57, was a result of the following:
Item 20. 6" HMAC Pavement at $3.25 per S.Y. , 259 S.Y. of the total
estimated in the contract was not required for project completion
for a savings of $ 841.75
Item 21. 7" HMAC Pavement at $3.80 per S.Y. , 189 S.Y. of the total
estimated in the contract was not required for project completion
for a savings of $ 718.20
Item 24. 6" Metal Pipe Sub-drain at $4..00 per L.F. , 753 L.F. of
the total estimated in the contract was not required for project.
completion for a savings of $3,012.00
$4,571.95
DATE REFERENCE SUBJECT: Final Payment, Assessment Paving PAGE
NUMBER
5/25/70 FP-708 at Ten Locations on the South Side 2_ or Z
The remaining under-run of $3,262.62 occurred because of minor variations
between quantities estimated in the contract documents and quantities actually
measured and used at the job site.
Compliance with Specifications
During testing on this project 10 corings were made on Units 1 and 5 with the
following results:
Exceeds Even with Under Specs but Below
Specs Specs within Tolerance Tolerance
Paving 7 2 1 0
Sub-grade 1 9 0 0
On Units 1 and 5 the average thickness of the HMAC paving is 7.59 inches as
compared to the 7.00 inches specified, and the average thickness of the stab-
ilized sub-grade is 6.01 inches as compared to the 6.00 inches specified.
Seven corings were made on Units 2,3,4,6 and 7 with the following results:
Exceeds Even with Under Specs but Below
Specs Specs within Tolerance Tolerance
Paving 5 0 2 0
Sub-grade 2 5 0 0
On these units the average thickness of the HMAC paving is 6.40 inches as
compared to the 6.00 inches specified, and the average thickness of the lime
stabilized sub-grade is 6.03 inches as compared to the 6.00 inches specified,
Tests made during construction show that materials used were in compliance
with contract specifications.
Recommendations
It is recommended that the project described above be accepted by the adoption
of an ordinance and that final payment of $15,661.62 be authorized to Glade,
Inc.
HDM/mh
SUBMITTED BY: DISPOSIT19N_JW COUNCIL: PROCESSED BY
PPROVED O OTHER (DESC IBE)
Cam_ �3G CI ECRET Y
1 1 DATE
CITY MANAGER 5 _-3 �e,