HomeMy WebLinkAboutContract 36728 AMENDMENT NO. 2
STATE OF TEXAS § CITY SECRETARY CONTRACT NO.
(No M&C Needed)
COUNTY OF TARRANT §
WHEREAS, the City of Fort Worth (City) and Dannenbaum Engineering Corporation,
(Engineer) made and entered into City Secretary Contract No. 31311 (the Contract) which was
authorized by the City Council by M&C C-20483 on the 11 th day of January, 2005; and
WHEREAS, the Contract involves engineering services for the following project:
2004 Capital Improvement Project Drainage Project, Briarhaven-Fieldcrest Drainage
Improvements
Project No. 00086; DOE No. 4895
Water Project No. P253-6021700086
Sewer Project No. P253-7021700086
TPW Project No. C200-2024000086
WHEREAS, it has become necessary to execute Amendment No. 2 to said Contract to
include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their duly-
authorized representatives, enter into the following agreement which amends the Contract:
1.
Article I of the Contract is amended to include the additional engineering services as
specified in a proposal letter dated January 28, 2008, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional services to be performed by Engineer
total $ 24,438.
2.
Article II of the Contract is amended to provide for an increase in the maximum fee to be paid to
Engineer for all work and services performed under the Contract, as amended, so that the total
fee paid by the City for all work and services shall not exceed the sum of $ 173,446.95.
03-1 0-08 P01 14 IN
V� �
�, -'y
3.
All other provisions of the Contract, which are not expressly amended herein, shall remain in full
force and effect.
Executed on this the �� day oft urCh , 2008, in Fort Worth, Tarrant
County, Texas.
APPROVAL RECOMMENDED: APPROVED:
A. Douglas Rademaker, P.E. Fernando Costa
Director,Department of Assistant City Manager(Acting)
Engineering
Dannenbaum Engineering Corporation
ENGINEER l
dQ ATTEST:
Q
By:
Wayne Ahrens, P.E.
Principal y
4000 Fossil Creek Blvd. Marty Hendrix, Ci Secretary
Fort Worth,Texas 76137
NO M&C REQUIRED
APPROVED AS TO FORM AND LEGALITY:
Amy RarWeyl
Assistant City Attorney
p✓f���,�G�!L '15�Vl�WJ
FT. WON, TEX.
DANNENBAUM ENGINEERING CORPORATION "
6421 CAMP BOWIE BLVD„SUITE 400 FORT WORTH,TEXAS 76116-6421 (817)763-8883
January 28, 2008
Mr. Joseph Bergeron, P.E.
City of Fort Worth
1000 Throckmorton Street
Fort Worth, Texas 76102-6311
RE: 2004 Capital Improvements Drainage Project
Briarhaven-Fieldcrest Drainage Improvements
Supplemental Agreement No. 2
Mr. Bergeron:
Per our discussions with Dena Johnson, the City desires to perform a Level `A'
Subsurface Utility Investigation at the intersections of Hulen with Briarhaven and
Fieldcrest. I have engaged a sub-consultant to perform those services. Attached is
Supplemental Agreement No. 2 for the services.
In order the minimize management needs, I have also included other services in the
supplemental. Those services include the easement required due to the alignment
revision at the northeast corner of Hulen and Briarhaven and the costs required for
assistance to the City with easement acquisition and negotiation.
Please advise me of the schedule for presenting this supplement to Mayor and Council so
I can advise my sub-consultants appropriately. If you have any questions or require any
additional information,please do not hesitate to call.
Sincerely,
itwe
Brian D. O'Neill, P.E.
Project Manager
xc: Dena Johnson, P.E.
Carlon Small
GA1210\4095-32\ADM1N\CONTRACT\SA#2\Letter Bergeron 2008-01-28.doc ar,a.
ATTACHMENT "B"
COMPENSATION AND SCHEDULE
2004 CAPITAL IMPROVEMENTS DRAINAGE PROJECT
BRIARHAVEN-FIELDCREST DRAINAGE IMPROVEMENTS
SUPPLEMENTAL AGREEMENT No. 2
PROJECT NO. 00085
I. Compensation:
A. The Engineer shall be compensated a total lump sum fee of$ 24,438.00 as
summarized in Exhibit`13-313". Payment of the total lump sum fee shall
be considered full compensation for the services described in Exhibit"A"
for all labor materials, supplies and equipment necessary to complete the
proj ect.
B. The Engineer shall be paid monthly as described in Exhibit"B-1
Section 1 —Method of Payment.
Each Invoice is to be verified as to its accuracy and compliance with the
terms of this contract by an officer of the Engineer.
II. Schedule:
A. Phases 1 and 2 shall be completed 20 days after the "Notice to Proceed"
letter is issued.
The Scope of Services is outlined in Attachment"A", Exhibit"A".
EXHIBIT "B-1"
(SUPPLEMENTAL TO ATTACHMENT B)
METHOD OF PAYMENT
2004 CAPITAL IMPROVEMENTS DRAINAGE PROJECT
BRIARHAVEN-FIELDCREST DRAINAGE IMPROVEMENTS
SUPPLEMENTAL AGREEMENT No. 2
PROJECT NO. 00085
I. Method of Payment
Partial payment shall be made to the Engineer monthly upon City's approval of an
invoice from the Engineer outlining the estimated current percent complete of the total
project.
The aggregate of such monthly partial fee payments shall not exceed the following:
Until satisfactory completion of Exhibit"A", Conceptual Engineering plan submittal and
approval by the City, a sum not to exceed 30 percent of the total lump sum fee.
Until satisfactory completion of Exhibits"A",Preliminary Construction Plan submittal to
City, a sum not to exceed 60 percent of the total lump sum fee, less previous payments.
Until satisfactory completion of Exhibits"A", Final Construction plan submittal and
approval by the city, a sum not to exceed 90 percent of the total lump sum fee, less
previous payments.
II. Progress Reports
A. The Engineer shall submit to the designated representative of Director of
Department of Engineering monthly progress reports covering all phases of
design by the 151h of every month in the format required by the City.
B. If the Engineer determines in the course of making design drawings and
specifications that the current construction cost estimate will be exceeded,
whether by change in the scope of the project, increased costs or other
conditions,the Engineer shall immediately report such fact to the City's Director
of the Department of Engineering and, if so instructed by Director of the
Engineering Department, shall suspend all work hereunder.
v 6MAE
�, � , f g.
EXHIBIT B-2
(SUPPLEMENT TO ATTACHMENT B)
HOURLY RATE SCHEDULE
2004 CAPITAL IMPROVEMENTS DRAINAGE PROJECT
BRIARHAVEN-FIELDCREST DRAINAGE IMPROVEMENTS
SUPPLEMENTAL AGREEMENT No. 2
Project No. 00085
Employee Classification Rate/Hour
Principal $258.00
Project Manager/Planner $170.00
Senior Engineer/QA-QC $145.00
RPLS $100.00
Project Engineer $110.00
Design Tech. $85.00
CADD Tech. $ 60.00
Clerical $ 58.00
2-Man Survey Crew $100.00
3-Man Survey Crew $120.00
4-Man Survey Crew $150.00
Reimbursables Cost+ 10%
Mileage $0.505 Per Mile
Reproduction work will be at current commercial rates. Subcontractors will be paid for at actual
invoice cost plus ten percent (10%).
4082 Exhibit B-2
�N01TH, TEX,
EXHIBIT "B-3A"
SUMMARY OF TOTAL PROJECT FEES
2004 CAPITAL IMPROVEMENTS DRAINAGE PROJECT
BRIARHAVEN-FIELDCREST DRAINAGE IMPROVEMENTS
SUPPLEMENTAL AGREEMENT No. 2
PROJECT NO. 00085
Exhibit Exhibit Scope of Services Total Fee M/WBE %
A. Design Services $ 24,438.00 $ 1,400.00 5.7
Construction Assistance $ 0.00 $ 0.00 0.0
TOTAL $ 24,438.00 $ 1,400.00 5.7
% of
Proposed M/WBE Sub-Consultants Services Fees Total Fee
ANA Consultants, LLC Field Survey $ 600.00 2.4
ANA Consultants, LLC Easement $ 800.00 3.3
TOTAL $ 1,400.00 5.7
Proposed Non-M/WBE Sub-Consultants
None
J ,t NCNB
CITY MIC-MARY
FT, wi JHI YEN.
EXHIBIT"B-3B"
FEE SUMMARY
2004 CAPITAL IMPROVEMENTS DRAINAGE PROJECT
BRIARHAVEN-FIELDCREST DRAINAGE IMPROVEMENTS
SUPPLEMENTAL AGREEMENT No. 2
PROJECT NO. 00085
***STORM DRAINAGE***
SUBSURFACE UTILITY INVEST. —LEVEL `A' (C-F) $ 19,580.00
DESIGN SURVEY(2 DAYS @ $800/DAY) (ANA) $ 600.00
EASEMENT PREPARATION (ANA) $ 800.00
EASEMENT ACQUISITION ASSISTANCE $ 1,360.00
TOTAL PAVING& STORM DRAINAGE FEE $ 22,340.00
10%FOR SUB ($ 20,980.00) $ 2,098.00
TOTAL FEE 24,438.00
SUMMARY OF TOTAL FEE AND BREAKDOWN OF DESIGN FEE (LESS SURVEY FEE)
A. SUMMARY OF TOTAL FEE
Service Description Water Sewer Paving/Drainage Total
Engineering Services $ 0.00 $ 0.00 $ 23,038.00 $ 23,038.00
Surveying Services $ 0.00 $ 0.00 $ 1,400.00 $ 1,400.00
Total $ 0.00 $ 0.00 $ 24,438.00 $ 24,438.00
B. BREAKDOWN OF WATER, SEWER AND PAVING FEES (LESS SURVEY FEES)
Total Paving/Drainage Fee(less survey fee)Breakdown by Concept, Preliminary and Final
Design
1. Concept(30%)=(Total Drainage Fee—Paving Survey Fee)x(0.3) =$ 23,038.00
2. Preliminary (60%)=(Total Drainage Fee—Paving Survey Fee)x(0.6) =$ 0.00
3. Final(10%)=(Total Drainage Fee—Paving Survey Fee)x(0.1) = $ 0.00
'UIFICJA�l NCO
EXHIBIT"B-3C"
Supplemental Agreement No. 2
Project No. 00085
BREAKDOWN FOR REPRODUCTION FEE AND ADDITIONAL SERVICES FEE
FOR:
ADDITONAL SERVICES FEE TOTAL= $22,340.00
Subsurface Utility Investigation—Level `A' (C-F) _ $19,580.00
Survey for SUE (ANA) _$ 600.00
Easement Preparation(ANA) _$ 800.00
Easement Acquisition Assistance(8 hrs. p.m. x$170/hr. p.m.) _$ 1,360.00
B3C-1