ADVANCE FUNDING AGREEMENT
AMENDMENT#2
THIS AMENDMENT is made by and between the State of Texas, acting through the Texas
Department of Transportation, called the State, and City of Fort Worth, acting by and through its duly
officials, called the Local Government.
WITNESSETH
WHEREAS, the State and the Local Government executed a contract on April 24th of 2007 and
Amendment#1 on July 20th of 2007 to effectuate their agreement to evaluate the railroad crossings
listed to enhance the operation and safety facilities, and construct improvements at certain sites; and,
WHEREAS, it has become necessary to amend that contract;
NOW THEREFORE, in consideration of the premises and of the mutual covenants and agreements
of the parties, the State and the Local Government do agree as follows:
AGREEMENT
1. Description of Amended Items
The original agreement is terminated in its entirety when signed by the last party whose signing
makes this amendment fully executed.
All other provisions of the original contract are unchanged and remain in full force and effect.
2. Signatory Warranty
Each signatory warrants that the signatory has necessary authority to execute this agreement on
behalf of the entity represented.
AFA--AFA Amend Page 1 of 2 D Revised 04/08/11
CSJ#0902-48-688, 0902-48-689
District#02-Fort Worth
Code Chart 64#15000
Project: Live Oak Connector
Federal Highway Administration
CFDA#20.205
Not Research and Development
THIS AGREEMENT IS EXECUTED by the State and the Local Government in duplicate.
THE LOCAL GOVERNMENT: Ci
OP®°°O°0
ATTEST. �o� ° O City of Fort Worth
®°o °
g
C, °
ity, S °
%`°°°°°°°°°°° Assistant City Manager
APPROV A TO FORM AND LEG A APPftqVAL RECOMMENDED
By V By bjj ( J
A467istant City Attorney Doug( W. Wiersig, P.E.
Director
Zt_ Transportation and Public Works
Date:
THE STATE OF TEXAS
ilkThomasiviarrs
Deputy Director of Contract Services
Texas Department of Transportation
Date
AFA—AFA_Amend Page 2 of 2 Revised 04/08/11
M&C Review Page 1 of 4
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA FoRTWORTH
COUNCIL ACTION: Approved on 7/21/2015 - Resolution No. 4490-07-2015 &Ordinance No.
21801-07-2015
REFERENCE 20LIVE OAK CONNECTOR
DATE: 7/21/2015 NO.: C-27383 LOG NAME: IMPROVEMENTS
AGREEMENT
CODE: C TYPE: NON- PUBLIC NO
CONSENT HEARING:
SUBJECT: Adopt Resolution Authorizing Execution of Amendment No. 2 to Terminate the Peach
Street Area Railroad Safety Project Local Project Advance Funding Agreement, as
Amended and Authorizing Execution of the Replacement Live Oak Connector Local
Project Advance Funding Agreement with the Texas Department of Transportation in the
Amount of$3,540,561.00 Which Includes $863,602.00 of City Matching Funds, Provide
for Additional City Funding in the Amount of$800,990.00 for a Total Project Amount of
$4,341,551.00 to Construct the Live Oak Connector in Conjunction with the Tower 55
Project and Subsequently Close Peach Street and East 1st Street at the Union Pacific
Railroad Crossing and Adopt Appropriation Ordinance (COUNCIL DISTRICT 8)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Resolution authorizing the execution of Amendment No. 2 to terminate the
Peach Street area Railroad Safety Project Local Project Advance Funding Agreement, as amended,
(M&C C-21910, City Secretary Contract Nos. 35285 and 35258-A1) and authorizing the execution of a
replacement Local Project Advanced Funding Agreement with the Texas Department of Transportation
in the amount of$3,540,561.00 to which includes an additional $516,114.00 of City Matching Funds to
be added to existing pledged city matching funds in the amount of$347,488.00 to construct the Live
Oak Connector;
2. Authorize the transfer of$445,261.52 from the 1998 CIP Street Improvements Fund; and $95,852.48
from the 2000 C.O. Street Improvements Fund; for a total transfer amount of$541,114.00 to the Grants
Fund for the additional local match and which amount includes additional city funding of$25,000.00
due to the elimination of the BNSF donation.
3. Authorize the acceptance of additional $35,918.00 of Federal funding for the replacement LPAFA;
4. Authorize the acceptance of$160,015.00 of Texas Department of Transportation (TXDOT)
funding for the replacement LPAFA;
5. Adopt the attached Appropriation Ordinance increasing estimated receipts and appropriations in
the amount of$737,047.00 and decrease estimated receipts and appropriations in the amount of
$25,000.00 as a result of elimination of Burlington Northern Santa Fe Railway's donation for a total
appropriation of$712,047.00 in the Grants Fund; and
6. Authorize a payment to Texas Department of Transportation in the amount of$52,068.00 for
Texas Department of Transportation costs, in accordance with the replacement Live Oak Connector
Local Project Advanced Funding Agreement.
DISCUSSION:
As part of the overall Tower 55 Railroad Project, numerous street and railroad grade crossing
http://apps.cfwnet.org/council_packet/mc review.asp?ID=20854&councildate=7/21/2015 1/19/2016
M&C Review Page 2 of 4
improvements have been programed for the area to enhance access and mobility for adjacent land
uses. As part of these overall railroad track improvements, the railroad street grade crossings at
Peach and East First Streets with the Union Pacific Railroad track are scheduled for closure. To
replace these crossings and maintain area mobility Live Oak Street is scheduled for realignment and
will be connected directly into East 4th Street which provides a grade separated route across the
Union Pacific Railroad tracks. The Live Oak Connector project was initially scoped and defined in
2006. Mayor and Council Communication C-21910, which authorized the original Peach Street
Railroad Safety Project Local Advanced Funding Agreement (LPAFA), contained certain outside
funding and expectations which have since changed over time. Therefore, termination of the original
LPAFA has been recommended by TXDOT with which staff agrees.
The replacement Live Oak Connector LPAFA will reallocate and adjust external funding contributions
and reassign some funding previously programmed for construction to the acquisition of right-of-way.
Funding from the old Peach Street Area LPAFA is preserved and will be incorporated into the new
LPAFA along with additional Federal, State and Local monies. The previous Appropriation Ordinance
No. 17334-12-2006 remains valid; however, the $25,000.00 donation from Burlington Northern Santa
Fe Railway will no longer be provided but the $50,000.00 contribution from the Union Pacific Railroad
for closing the at-grade crossings at Peach Street and East First Street remains a part of the project
funding. The additional city funding identified as Independent City Costs in the amount of
$880,990.00 will be funded from the Critical Project Improvements Funds ($254,980.51); the Street
Lights and Signals Improvements Fund ($146,197.49); and the Street Improvements 2008 Fund
($399,812.00).
The following tables summarize the project funding for the old and new LPAFAs as well as a
breakdown of projected project costs.
Project Old Peach Street Area Additional Funds
Funding Replacement Live Oak LPAFA (as amended) (to be Needed for New
Connector LPAFA terminated) LPAFA
Federal F$2,516,944.00 $2,481,026.00 $35,918.00
Funds
V
ate $160,015.00 $0.00 $160,015.00
XDOT)
Local $863,602.00 $347,488.00 $516,114.00
Costs
LPAFA
]$3,540,561.00 $2,828,614.00 $712,047.00
�Total
Project Costs:
New Live
Oak Independent
Connector City Cost
LPAFA
- Federal State Local Total Cost
Engineering F$ 360,000.00 $ $ 40,000.00 $ 63,421.00 $463,421.00
& Env.
Right-of-Way $1,435,285.00 $ $ - $166,715.00 $1,602,000.00
Construction $ 648,429.00 $ 11 $653,871.00 $ 570,854.00 $1,873,154.00
Direct/indirect $ 73,230.00 $160,015.00 $169,731.00�F$ F$402,976.00
Cost
Total Cost $2,516,944.00 $160,015.00 $863,602.00 $800,990.00 $4,341,551.00
Local Funding Elements:
http://apps.cfwnet.org/council_packet/me_review.asp?ID=20854&councildate=7/21/2015 1/19/2016
M&C Review Page 3 of 4
Local Match Previously New Local & Total Local & City
Funding Approved Local Independent City Funding
Source Funding Funding
2004 Bond :$1:981
704.00 $146,197.49 $344,901.49
Funds
City of Fs ,284.0036 $0.00 $36,284.00
Duncanville
TXDOT $37,500.00 $0.00 $37,500.00
Union Pacific $50,000.00 $0.00 $50,000.00
RR
BNSF RR* $25,000.00 $-25,000.00 $0.00
2000 C.O. Sale 11 $0.00 $350,832.99 $350,832.99
Funds 1998 Bond $0.00 $445,261.52 11
$445,261.52
2008 Bond $0.00 $399,812.00 $399,812.00
Funds
Total $347,488.00 $1,317,104.00 $1,664,592.00**
* BNSF Funds are no longer available.
** Includes Staff funding and contingencies.
LPAFA History:
Once the attached Resolution is passed and Amendment No. 2 is executed, the original Peach Street
Railroad Safety Project LPAFA from 2006, as amended, will be terminated. The Resolution also
authorizes the City to enter into the new funding Agreement between TXDOT and the City of Fort
Worth for the Live Oak Connector LPAFA and the eventual closure of Peach Street and East First
Street.
The City of Fort Worth will manage engineering and construction of this project. Construction is
scheduled to begin in the Spring of 2016, with a 12 month duration. Upon completion of the new Live
Oak access connection, the City Council will be asked to formally close Peach Street and East First
Streets at their respective Union Pacific Railroad crossings.
This project is located in COUNCIL DISTRICT 8, Mapsco 63X.
DESCRIPTION AMOUNT M&C APPROVED
City Secretary No. 35258, Local Project $2,904,276.00 C-21910 December
Advance Funding Agreement with the 19, 2006
Texas Department of Transportation and
a Railroad Crossing Closure Agreement
with TXDOT and Union Pacific Railroad
for the Peach Street Area Railroad Safety
Improvement
City Secretary No. 35258-A1, $2,828,514.00* None/Administrative July 20,
Amendment to the Local Project Advance 2007
Funding Agreement with the Texas
Department of Transportation to Adjust
Funding (*Reduction due to State direct
costs having been deleted from the
original Agreement)
City Secretary No. 35258-A2, - Pending -
Amendment to Terminate the Local
Project Advance Funding Agreement with
the Texas Department of Transportation
and a Railroad Crossing Closure
http://apps.cfwnet.org/council packet/me review.asp?ID=2085 4&councildate=7/21/2015 1/19/2016
M&C Review Page 4 of 4
Agreement with TXDOT and Union
Pacific Railroad for the Peach Street Area
Railroad Safety Improvement
Replacement Local Project Advanced $3,540,561.00 Pending -
Funding Agreement with the Texas
Department of Transportation to construct
the Live Oak Connector and
subsequently close Peach Street and
East 1 st Street at Union Pacific Railroad
crossing
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that upon approval of the above
recommendations and adoption of the attached appropriation ordinance, funds will be available in the
current capital budget, as appropriated, of the Grants Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
il
GR76 472115 020302157000 $445,261.52 GR76 5XXXXX 020302157XXX $3,540,561.00
GR76 472116 020302157000 $95,852.48 C115 538070 020115040634 $445,261.52
GR76 541200 020302157000 $712,047.00 C116 538070 020116035569 $95,852.48
5-1
GR76 451995 020302157000 ($25,000.00) GR76 541200 020302157830 $52,068.00
3&5) $35,918.00
GR76 4XXXXX 020302157000
4&5 $160,015.00
GR76 4XXXXX 020302157000
Submitted for City Manager's Office by- Fernando Costa (6122)
Originating Department Head: Douglas W. Wiersig (7801)
Additional Information Contact: Roy Teal (7958)
ATTACHMENTS
20LIVE OAK CONNECTOR IMPROVEMENTS AGREEMENT GR76 A015Rev.docx