HomeMy WebLinkAboutOrdinance 3710 ORDINANCE NO. „ z
AN ORDINANCE REFERRING BIDS FOR THE IMPROM1ENT
OF PORTIONS OF MEEKER BOULEVARD, NORTHWEST TWENTY-
EIGHTH STREET, NORTHWEST LORAINE STREET, AND
NORTHEAST THIRTY-FIRST STREET IN THE CITY OF FORT
WORTH, TEXAS, TO THE PUBLIC WORKS DEPARTMENT FOR
A REPORT THEREON.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS
SECTION 1
That Bids f or the construction of improvements on Meeker Boulevard,
Northwest Twenty Mighth Street, Northwest Loraine Street, and Northeast
Thirty-First Street, in the City of Fort Worth, Texas, having on the loth
day of September 1957 been opened and read and the following persons had
filed for the performance of such work or part thereof, to wit:
1. Texas Bitulithic Company, Fort Worth, Texas
2. General Construction Company, Fort Worth, Texas
that such Bids be and the same are hereby referred to the Public Works
Department, which is directed to cause to be promptly filed with the City
Council a report and recommendation thereon.
SECTION 2
That this Ordinance shall take effect from and after its passage.
APPROVED AS TO FORM:
ASST. CITY ATTORNEY
REPORT OF THE PUBLIC VORKS DEPARTMENT
TO THE HONORABLE MAYOR AND CITY COUNCIL OF THE CITY OF FORT WORTH:
Your Public Works Department, to which was referred the Bids for the
improvement of portions of Meeker Boulevard, Northwest Twenty-Eighth Street,
Northwest Loraine Street, and Northeast Thirty-First Street, hereby respectfully
reports to your Honorable Body that it recommends the acceptance of the Bid of
Texas Bitulithic Company for the performance of said work at and for the follow-
ing prices, to-wit:
ITEM UNIT
N0. DESCRIPTION QUANTITY PRICE AMOUNT
1.1 Unclassified Street Excavation 900 C.Y. $ 1.00 $ 900.00
1.2 Combined 8" Curb & 21 Gutter 1,300 L.F. 2.10 2,730.00
1.10 Standard 51 H.C. Inlet 1 Ea. 220.00 220.00
1.11 Standard 18° H.C.C. Pipe 10 L.F. 5.00 50.00
2.1 Unclassified Street Excavation 1,200 C.Y. 1.50 1,SOO.00
2.2 Combined 8" Curb & 21 Gutter 1,300 L.F. 2.10 2,730.00
3.1 Unclassified Street Excavation 1,000 C.Y. 1.50 1,500.00
3.2 Combined 8" Curb & 29 Gutter 1,300 L.F. 2.10 2,730.00
3.4 Standard 5" Sidewalk 200 S.F. 0.70 114o.p0
8 Removing Existing Sidewalk 200 S.F. 0.30 60.00
.1 Unclassified Street Excavation 1,700 C.Y. 1.00 1,700.00
4.2 Combined 8" Curb & 21 Gutter 1,850 L.F. 2.10 3,985.00
4.3 21 Gutter Only 250 S.F. 0.70 175.00
4.5 Standard Drive Approach 50 S.F. 0.70 35.00
4.6 Remove Existing Curb 250 L.F. 0.50 125.00
4.7 Remove Existing Gutter 250 S.F. 0.30 75.00
4.9 Remove Existing Drive Approach 50 S.F. 0.30 15.00
13 l p Hot Mix Asphaltic Concrete Surf. 8,200 S.Y. 1.00 9,200.00
15 7 e Flexible Base (Orusher-run
Crushed Limestone) 8,200 S.Y. 1.85 15,170.00
TOTAL COST $42,240.00
Respectfully submitted,
PUBLIC WORKS DEPARTMENT
BY
PUBL _ S DIRECTOR
ORDINANCE
No.
Title P P Z
-��?7
Adopted -41
Final Adoption___
Published
-
Filed-L, may of 1 =
City Secretary