NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Lasater Ranch Phase 3
City Project No.: 101341
Improvement Type(s): Water ❑x Sewer ❑x
Original Contract Price: $419,397.25
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $419,397.25
M a r 13, 2020
Contractor Date
President
Title
Moss Utilities, LLC
Company Name
AMW ChiltWil# Mar 13, 2020
Project Inspector Date
Pat-rioK Raa'k4y Mar 16 2020
Patrick Buckley(Mar 16,2020)
Project Manager Date
e s M a r 16,2020
CFA Manager Date
znmq aujd4 Mar 16 2020
Dana Burghdoff(M 16,202 7
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT.WORTH,TX
Notice of Project Completion
Project Name: Lasater Ranch Phase 3
City Project No.: 101341
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Pipe Report: ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety I
Statement of Contract Time
Contract Time: 180 CD Days Charged: 180
Work Start Date: 7/9/2018 Work Complete Date: 3/2/2020
Page 2 of 2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name LASATER RANCH PHASE 3
Contract Limits
Project Type WATER&SEWER
City Project Numbers 101341
DOE Number 1013
Estimate Number I Payment Number I For Period Ending 2/26/2020
CD
City Secretary Contract Number 101341 Contract Time 18(ED
Contract Date 4/7/2018 Days Charged to Date 180
Project Manager NA Contract is 100.00 Complete
Contractor MOSS UTILITIES,LLC
18631 REMBRANDT TERRACE
DALLAS, TX 75287
Inspectors MILLER,W / POWERS
Thursday,March 12,2020 Page 1 of 4
I
City Project Numbers 101341 DOE Number 1013
Contract Name LASATER RANCH PHASE 3 Estimate Number I
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 2/26/2020
Project Funding
UNIT I:WATER IMPROVEMENTS
Item Description of Items Unit Unit Cost
Estimated Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 8"PVC WATER PIPE 3553 LF $24.00 $85,272.00 3553 $85,272.00
2 8"GATE VALVE&BOX 8 EA $1,100.00 $8,800.00 8 $8,800.00
3 CONN.TO EXISTING 4'-12"WATER MAIN 4 EA $2,200.00 $8,800.00 4 $8,800.00
4 FIRE HYDRANT ASSEMBLY 4 EA $3,300.00 $13,200.00 4 $13,200.00
5 1"WATER SERVICE-RESIDENTIAL 93 EA $900.00 $83,700.00 93 $83,700.00
6 1.5"WATER SERVICE 8 EA $1,500.00 $12,000.00 8 $12,000.00
7 TRENCH SAFETY 3553 LF $0.25 $888.25 3553 $888.25
8 DUTICLE IRON FITTINGS W/RESTRAINTS 3 TN $4,000.00 $12,000.00 3 $12,000.00
--------------------------------------
Sub-Total of Previous Unit $224,660.25 $224,660.25
UNIT II:SANTIARY SEWER IMPROVEMENTS
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 8"PVC SEWER 2863 LF $27.00 $77,301.00 2863 $77,301.00
2 8"SEWER W/CSS 190 LF $65.00 $12,350.00 190 $12,350.00
3 4"SEWER SERVICE 79 EA $720.00 $56,880.00 79 $56,880.00
4 4'DIA MANHOLE 9 EA $2,500.00 $22,500.00 9 $22,500.00
5 MANHOLE VACUUM TESTING 9 EA $300.00 $2,700.00 9 $2,700.00
6 EPDXY MANHOLE LINER 9 EA $400.00 $3,600.00 9 $3,600.00
7 TRENCH SAFETY 3053 LF $1.00 $3,053.00 3053 $3,053.00
8 POST-CCTV INSPECTION 3053 LF $1.00 $3,053.00 3053 $3,053.00
9 T EXTRA DEPTH MANHOLE 30 VF $300.00 $9,000.00 30 $9,000.00
10 CONN TO EXISTING 8"SEWER 2 EA $1,300.00 $2,600.00 2 $2,600.00
11 CONN TO EXISTING MANHOLE 1 EA $1,700.00 $1,700.00 1 $t,700.00
--------------------------------------
Sub-Total of Previous Unit $194,737.00 $194,737.00
--------------------------------------
Thursday,March 12,2020 Page 2 of 4
City Project Numbers 101341 DOE Number 1013
Contract Name LASATER RANCH PHASE 3 Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 2/26/2020
Project Funding
Contract Information Summal y
Original Contract Amount $419,397.25
Chanj4e Orders
Total Contract Price $419,397.25
Total Cost of Work Completed $419,397.25
Less %Retained $0.00
Net Earned $419,397.25
Earned This Period $419,397.25
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $419,397.25
Thursday,March 12,2020 Page 3 of 4
City Project Numbers 101341 DOE Number 1013
Contract Name LASATER RANCH PHASE 3 Estimate Number I
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 2/26/2020
Project Funding
Project Manager NA City Secretary Contract Number 101341
Inspectors MILLER,W / POWERS Contract Date 4/7/2018
Contractor MOSS UTILITIES,LLC Contract Time 180 CD
18631 REMBRANDT TERRACE Days Charged to Date 180 CD
DALLAS, TX 75287 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $419,397.25
Less %Retained $0.00
Net Earned $419,397.25
Earned This Period $419,397.25
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $419,397.25
Thursday,March 12,2020 Page 4 of 4
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Lasater Ranch Phase 3
PROJECT NUMBER: 101341
DOE NUMBER: N/A
WATER
PIPE LAID SIZE TYPE OF PIPE LF
3,553 LF 8" PVC 3,553
FIRE HYDRANTS: 6"(4) VALVES(16" OR LARGER)
PIPE ABANDONED SIZE TYPE OF PIPE LF
U
DENSITIES: Yes
NEW SERVICES: 1" Copper 93 EA
1.5" Copper 8 EA
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
2863 L F 8" PVC 2863 L F
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES: Yes
NEW SERVICES: 4" 79 EA
TRANSPORTATION AND PUBLIC WORKS
<` The City of Fort Worth• 1000 Throckmorton Street•Fort Worth,TX 76012-6311
(817)392-7941 •Fax: (817)392-7845
AFFIDAVIT
STATE OF TX
COUNTY OF Tarrant
Before me,the undersigned authority, a notary public in the state
and county aforesaid, on this day personally appeared Shawn Lain, Project
Manager Of Moss Utilities,LLC, known to me to be a credible person,
who being by me duly sworn, upon his oath deposed and said;
That all persons, firms,associations, corporations, or other
organizations furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of
Fort Worth has been paid in full;
That there are no claims pending for personal injury and/or
property damages;
On Contract described as;
Lasater Ranch Phase 3 -Project# 101341
BY "','00"""'oo'��4�
S awn Lain Project Manager
Subscribed and sworn before me on this date J-3-of rkvc h , ado 0.
o Pu 1'
Countyi�,�QS State R
�OSPRYa ii
CHR'ST
9 'ey1 Notary A�blRACHEELE tAZA
F o State
of
Corn fRItV
xpir as
Notary tD @3 g 01-31 Tex2024
� 233,9389
M The Guarantee Company of North America USA
GUARANTEE- One Towne Square, Suite 1470
Southfield, Michigan 48076
Phone: 248-281-0281 Fax: 248-750-0431
www.gcna.com
Bond Number 75159311
OWNER ❑
CONSENT OF SURETY COMPANY ARCHITECT ❑
TO FINAL PAYMENT CONTRACTOR ❑
SURETY ❑
OTHER ❑
PROJECT: Water,Sanitary Sewer,and Storm Drain Improvements for Lasater Ranch Phase 3
(name, address)
TO(Owner
Saginaw 104 Ltd. & City of Fort Worth ARCHITECT'S PROJECT NO.
3045 Lackland Road 200 Texas St. CONTRACT FOR: Water,Sanitary Sewer,and Storm Drain
Fort Worth,TX 76116 Fort Worth,TX 76102 Improvements for Lasater Ranch Phase 3
CONTRACT DATE:
CONTRACTOR: Moss Utilities,LLC 3300 Rock Island Rd.,Irving,TX 75060
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above,the
(here insert name and address of Surety as it appears in the bond).
The Guarantee Company of North America USA One Towne Square#1470 Southfield,M1 48076 , SURETY COMPANY,
on bond of(here insert name and address of Contractor)
Moss Utilities,LLC CONTRACTOR,
Hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not
relieve the Surety Company of any of its obligations to(here insert name and address of Owner)
Saginaw 106,Ltd. &City of Fort Worth OWNERS
As set forth in the said Surety Company's bond.
IN WITNESS WHEREOF,the Surety has hereunto set its hand this 19th day of February 2020
The Guarantee Company of NA America USA
Suret o l'
Signature f Au orized Representative
ATTEST: �� Lloyd Ray Pitts Jr Attorney-In-Fact
(Seal): Melissa Pitts,Bond Secretary Title
The language in this document confirms exactly to the language used in AIA Document G707—Consent of Surety Company to Final Payment.
THE The Guarantee Company of North America USA
GUARANTEE" Southfield,Michigan
POWER OF ATTORNEY
KNOW ALL BY THESE PRESENTS:That THE GUARANTEE COMPANY OF NORTH AMERICA USA,a corporation organized and existing under the
laws of the State of Michigan,having its principal office in Southfield,Michigan,does hereby constitute and appoint
Lloyd Ray Pitts,Jr.,William D.Birdsong
Pitts Fennell and Associates,LLC dba Pitts Birdsong Fennell&Associates
its true and lawful attorney(s)-in-fact to execute, seal and deliver for and on its behalf as surety, any and all bonds and undertakings, contracts of
indemnity and other writings obligatory in the nature thereof,which are or may be allowed,required or permitted by law,statute, rule,regulation,contract
or otherwise.
The execution of such instrument(s)in pursuance of these presents, shall be as binding upon THE GUARANTEE COMPANY OF NORTH AMERICA
USA as fully and amply,to all intents and purposes, as if the same had been duly executed and acknowledged by its regularly elected officers at the
principal office.
The Power of Attorney is executed and may be certified so,and may be revoked, pursuant to and by authority of Article IX,Section 9.03 of the By-Laws
adopted by the Board of Directors of THE GUARANTEE COMPANY OF NORTH AMERICA USA at a meeting held on the 31"day of December,2003.
The President,or any Vice President,acting with any Secretary or Assistant Secretary,shall have power and authority:
1. To appoint Attorney(s)-in-fact, and to authorize them to execute on behalf of the Company, and attach the Seal of the Company thereto,
bonds and undertakings,contracts of indemnity and other writings obligatory in the nature thereof;and
2. To revoke,at any time,any such Attorney-in-fact and revoke the authority given,except as provided below
3. In connection with obligations in favor of the Florida Department of Transportation only,it is agreed that the power and authority hereby given
to the Attorney-in-Fact includes any and all consents for the release of retained percentages and/or final estimates on engineering and
construction contracts required by the State of Florida Department of Transportation. It is fully understood that consenting to the State of
Florida Department of Transportation making payment of the final estimate to the Contractor and/or its assignee,shall not relieve this surety
company of any of its obligations under its bond.
4. In connection with obligations in favor of the Kentucky Department of Highways only,it is agreed that the power and authority hereby given to
the Attorney-in-Fact cannot be modified or revoked unless prior written personal notice of such intent has been given to the Commissioner—
Department of Highways of the Commonwealth of Kentucky at least thirty(30)days prior to the modification or revocation.
Further,this Power of Attorney is signed and sealed by facsimile pursuant to resolution of the Board of Directors of the Company adopted at a meeting
duly called and held on the 6th day of December 2011,of which the following is a true excerpt:
RESOLVED that the signature of any authorized officer and the seal of the Company may be affixed by facsimile to any Power of Attorney or certification
thereof authorizing the execution and delivery of any bond, undertaking, contracts of indemnity and other writings obligatory in the nature thereof, and
such signature and seal when so used shall have the same force and effect as though manually affixed.
a,rirege IN WITNESS WHEREOF,THE GUARANTEE COMPANY OF NORTH AMERICA USA has caused this instrument to be signed and
its corporate seal to be affixed by its authorized officer,this 2nd day of October,2015.
THE GUARANTEE COMPANY OF NORTH AMERICA USA
STATE OF MICHIGAN Stephen C.Ruschak,President&Chief Operating Officer Randall Musselman,Secretary
County of Oakland
On this 2nd day of October, 2015 before me came the individuals who executed the preceding instrument, to me personally known, a:^d being by me
duly sworn,said that each is the herein described and authorized officer of The Guarantee Company of North America USA;that the seal affixed to said
instrument is the Corporate Seal of said Company;that the Corporate Seal and each signature were duly affixed by order of the Board of Directors of
Cynthia A. Takai IN WITNESS WHEREOF,I have hereunto set my hand at The Guarantee
r Notary Public, State of Michigan Company of North America USA offices the day and year above written.
County of Oakland
My Commission Expires February 27,2018 -
.�.••$* Acting in Oakland County
1 �Cliy�•
1,Randall Musselman,Secretary of THE GUARANTEE COMPANY OF NORTH AMERICA USA,do hereby certify that the above and foregoing is a true
and correct copy of a Power of Attorney executed by THE GUARANTEE COMPANY OF NORTH AMERICA USA,which is still in full force and effect.
*GG,
IN WITNESS WHEREOF, I have thereunto set my hand and attached the seal of said Company this 19th day of February 2020
Randall Musselman,Secretary