HomeMy WebLinkAboutContract 37536AMENDMENT NO. 5
STATE OF TEXAS S CITY SECRETARY CONTRACT NO.
(M&C Required)
COUNTY OF TARRANT S
WHEREAS, the City of Fort Worth (City) and CH2M Hill, Inc.,
(Engineer) made and entered into City Secretary Contract No. 28977, (the
Contract) which was authorized by the City Council by M&C C-19675 on the
29th day of July, 2003 and subsequently revised by four previous
amendments, and
WHEREAS, the Contract involves engineering services for the
following project.
Southside II Water Transmission Main from Rolling Hills
Treatment Plant to the Crowley Road/Risinger Road
Intersection.
WHEREAS, it has become necessary to execute Amendment No. 5 to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their
duly authorized representatives, enter into the following agreement which
amends the Contract.
1.
Article I, of the Contract is amended to include the additional
engineering services specified in M&C C-23001, adopted by the City
Council on the 2nd day of September, 2008, and further amplified in a
proposal letter dated July 28, 2008, copies of which are both attached
hereto and incorporated herein. The cost to City for the additional
services to be performed by Engineer total $47,995.00.
2.
Article II, of the Contract is amended to provide for an increase in
the maximum fee to be paid to Engineer for all work and services
performed under the Contract, as amended, so that the total fee paid by
the City for all work and services shall not exceed the sum of
$1,064,294.00. -- - —�
OFFICIAL RECORD
CITY SECRETARY
FT WORTH, TX
3.
A11 other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this
Tarrant County, Texas,
ATTEST
City Secretary
APPROVAL RECOMI�NDED:
the day of , 2008, in Fort Worth,
A. Douglas Rademaker, P.E.
Director, Department of
Engineering
--
Engineer
BY�
Name:Ken
Vice -President
309 W. 7:h Street, Suite 1020
Fort Worth, TX 76102
-2-
�7( , )00\
Contract Authorization
9 1 A j
vats
APPROVED:
Fernando Costa
Assistant City Manager
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
rage 101
DATE: Tuesday, September 02, 2008
LOG NAME: 30AMEND5SSIIWTR
REFERENCE NO.: *`C-23001
SUBJECT:
Authorize Execution of Amendment No. 5 in the Amount of $47,995.00 to City Secretary Contract
No. 28977 with CH2M Hill, Inc., for Southside II Water Transmission Main from Rolling Hills
Treatment Plant to the Crowley Road/Risinger Road Intersection (City Project No. 00303)
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Amendment No. 5 in the
amount of $47,995.00 to City Secretary Contract No. 28977 with CH2M Hill, Inc., to provide for additional
engineering services on the project, thereby increasing the contract amount to $1,063,794.00.
DISCUSSION:
On July 29, 2003, (M&C C-28977) the City Council authorized the City Manager to execute an agreement
with CH2M Hill, Inc., in the amount of $613,449.00 for the design of Southside II Water Transmission Main
from Rolling Hills Treatment Plant to the Crowley Road/Risinger Road intersection.
The project includes design for the installation of a 48 inch water main on Risinger Road from Crowley
Road to Oak Grove Road and a 54 inch water main on Oak Grove Road from Everman Road to the Rolling
Hills Water Treatment Plant.
The agreement was subsequently revised by four previous amendments totaling $402,350.00 as follows;
. Amendment No. 1 (administratively approved by the City Manager on November 4, 2004) in the amount
of $8,700.00, provided for a surge modeling analysis for protection of the water main;
® Amendment No. 2 (M&C C-21177, December
realignment of the 48 and 54 inch water mains in
future Risinger Road and to also avoid conflicts
utilities within the project area;
6, 2005) in the amount of $259,600.00, provided for
order to accommodate the alignment proposed for the
with previously unknown and recently installed private
. Amendment No. 3 (M&C C-22102, May 8, 2007) in the amount of $89,110.00 provided for incorporation
of butterfly valves in lieu of gate valves on the project along with additional survey and easement
preparation on the project; and
. Amendment No. 4 (M&C C-22602, January 8, 2008) in the amount of $44,940.00 provided for the
realignment of a segment of the 54 inch water main this is in direct conflict with an existing AT&T fiber optic
cable.
Amendment No. 5 will provide for redesign of the project plans to avoid conflict with previously unknown
gas mains. The redesign is also necessary to lower the water main at the Rolling Hills Treatment Plant to
►tip://apps.cfwnet.org/council,_packet/Reports/mc print.asp 9/3/200f
Page 2 of
match the elevation of the existing water mains at the plant. In addition, construction assistance will be
provided on the project.
CH2M Hill, Inc., proposes to provide the necessary additional engineering services for a lump sum fee of
$47,995,00. Staff considers this amount to be fair and reasonable.
This project is located in COUNCIL DISTRICTS 6 and 8.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current capital budgets, as appropriated, of the
Water Capital Projects Fund.
TO Fund/Account/Centers
Submitted for City Manager's Office by:
Originating Department Head:
Additional Information Contact:
FROM Fund/Account/Centers
P265 531200 608140030333
Fernando Costa (8476)
A. Douglas Rademaker (6157)
Roberto Sauceda (2387)
$47,995.00
ittp://apps.cfwnat. oz'g/council_packet/Reports/mc_print.asp
9/3/2001
:P
ILL
July 2s, 2oos
Mx. Robexto Sauceda
City of Fort Worth Engineering Department
1000 Throckmorton
Fort Worth, Texas 76102-6311
Subject: Southside II Water Transmission Main
Amendinent No. 5
Dear Mr. Sauceda:
CH2M HILL
309 W 7 h St
Suite 1020
Fort Worth, TX 76102
Tel 817.870.1129
Fax 817.878.5753
The purpose of this Iettex is to request authorization to perform additional services for the
Southside II Water Transmission Main Project as described herein and broken out in detail
in Attachment 1 in the amount of $47,995.00.
Redesign of Pipeline Profiles for Parts 1, 2, 4, and 5
This task includes fees necessary to redesign pipeline profiles for the following Parts:
Part 1-The 54-inch pipe at the Rolling Hills WTP that the Southside line ties into was
installed lower than indicated in the record drawings. A 16-inch water line at the W7I was
also installed lower than anticipated. These unforeseen site conditions resulted in the
redesign of 2,450 LF of 54-inch profile and the reissue of 3 drawings.
Part 2 - A newly installed gas Line required a profile adjustment to avoid a conflict: A
redesign of 1.,645 LF of 54-inch pipe and the reissue of 3 drawings was required to
accommoda to the gas line.
Part 4 - A bust in the construction staking survey resulted in a portion of the 48-inch
Southside lute being installed lower than indicated on tine construction drawings. To bring
the pipe to the correct grade, a redesign of 90 LF of 48-inch profile and the reissue of 1
drawing was required.
Part 5 - A bust in the construction staking survey resulted in a portion. of the 484nch
Southside line being installed lower than indicated on the construction drawings. The
survey bust also resulted in the casing pipe under I-35 being installed lower than called for.
In addition, gas lines were d-holed during construction at the UPRR crossing at STA 61"+-00
that conflicted with the proposed design. To bring the pipe to the correct grade and
accommoda to the gas lines, a redesign of 4,850 LF of 48-filch piping and 483 LF of 12-inch
piping and the reissue of 8 drawings was required.
Amendment No. 5
DULY 28, 2008
Page 2
Additional Submittal and RFI Reviews
The Contract estimated a total of 10 shop drawings reviews and 5 RFI reviews per
construction contract. To date, we have reviewed far in excess of the Contracted amounts
for shop drawings and RFIs as outlh-ied in Attachment 1. We have not included resubmittals
in our quantities of additional submittals that have been reviewed in excess of the estimated
10 per Contract.
A summary of the total project is as foIlows:
Contract
Descri tion
Fee _
Original Contract
Design, bid, and construction services for 43,775 LF of raw
water transmission main.
$6131949
Amendment No. 1
Perform sure analysis.
$8,700
Amendment No. 2
Redesign of 13,600 feet of 48" pipe, redesign of 12,500 feet of
54" pipe, design of an additional 11,200 feet of water
distribution pipe.
$259,600
Amendment No, 3
Revision from 4 parts to 5 parts. Change butterfly valves to gate
valves.
$89,110
_—
Amendment No. 4
Part 2 realignment, revise easements, revise sure analysis,
$44,940
Amendment No, 5
Redesign pipe profiles during construction. Additional
Submittal/RFI reviews.
$47,995
TOTAL PROJECT
$1,0641294
If you have any questions or require additional information, please do not hesitate to
contact me.
Sincerely,
CH2M HILL
Chad M. Simmons, P.E.
Project Manager
Encl.: Attaclunent 1
cc: Mr. Robert Terrell w/encl.
Attachment 1
Southside I I Water Transmission Main
Proposed Fee, Amendment No. 5
ACTIVITY DESCRIPTION
GRADE
HOURS
RATE
LABOR
Profile Redesign (Parts 1, 2, 4 and 5)
Engineering
E5
44
$145.00
$6,380,00
02
18
$70.00
$11260.00
Drafting
T4
88
$120.00
$101560.00
Reproduction Expense
$150.00
Additional Submittal/RFI Reviews
Part 1
Submittals - 30 Additional
E5
15
$145.00
$2,175.00
E3
30
$100400
$3,000.00
02
15
$70.00
$1,050.00
RFIs - 2 Additional
E5
2
$145.00
$290.00
02
1
$70.00
$70.00
Part 2
Submittals - 30 Additional (estimated)
E5
15
$145.00
$2,175.00
E3
30
$100500
$32000.00
02
15
$70.00
$1,050.00
Part 3 - (no additional reviews)
Part 4
Submittals - 30 Additional
E5
15
$145.00
$2,175,00
E3
30
$100.00
$3,000,00
02
15
$70.00
$1,050.00
RFIs - 10 Additional
E5
10
$145,00
$11450.00
02
5
$70.00
$350.0o
Part 5
Submittals - 35 Additional
E5
18
$145600
$2,610.00
E3
35
$100.00
$31500.00
02
18
$70.00
$1,260.00
RFIs - 8 Additional
E5
8
$145.00
$11160.00
02
4
$70,00
$280100
TOTAL AMENDMENT NO. 5 FEE
1
1
$47,995A0
AMMENDMENT NO. 5 SUMMARY
Total CH2M HILL Cost $473995.00
Total Subconsultant Cost $0.00
TOTAL FEE $47,995.00
MIWBE PERCENTAGE 0.0%