WHEREAS, the City of Fort Worth (City) and CH2M Hill, Inc. ,
(Engineer) made and entered into City Secretary Contract No. 35696,
(the Contract) which was authorized by the City Council by M&C C-
22312 on the 14':h day of August, 2007; and
WHEREAS, the Contract involves engineering services for the
following project:
M-244B Emergency Sanitary Sewer Rehabilitation.
WHEREAS, it has become necessary to execute Amendment No. 1 to
said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly authorized representatives, enter into the following
agreement which amends the Contract:
1.
Article I of the Contract is amended to include the additional
engineering services specified in a proposal letter dated March 26,
2008, a copy of which is attached hereto and incorporated herein.
The cost to City for the additional design services to be performed
by Engineer total $-0-. This amendment will not require any
additional funding due to the fact that there are sufficient funds
($38,251.75) available from unutilized scoped items in the original
contract to cover the proposed fee of $24,648.00 for the new scoped
items in Amendment No. 1. The unutilized scoped items will be
replaced with the proposed scoped items to the tune of $24,648.00.
2.
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the total
fee paid by the City for all work and services shall not exceed the
lie of -22. 50.00.
VIM
,� ORIGINAL
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the day of - 2008, in Fort Worth,
Tarrant County, Texas.
ATTEST: , nn
Marty Hendrix
City Secretary
APPROVAL RECOMMENDED: APPROVED:
A�l IMt
A. Douglas Rademaker, P.E. Fernando Costa
Director, Department of Engineering Assistant City Manager
CH2M HILL, Inc.
Engineer
By:
Name:Ken C. Hall, P.E. , Vice President
309 West 7th Street, Suite 1020
Fort Worth, TX 76102
APPROVED AS O FORM GALITY:
Assistant CAy Attorney
] r, j
Wade 8:Associates
6701 Brentwood Stair Road
Suite 10OW
Fort Worth,Texas 76112
ADF&QSSOC I aces Tel 817.451.2820
A CH2M HILL Company
Fax 817.461.2208
March 26, 2008
Mr. Liam Conlon, P.E.
City of Fort Worth Engineering Department
1000 Throckmorton
Fort Worth, Texas 76102-6311
Subject: M-244B Emergency Sanitary Sewer Rehabilitation
City Project No. 00834
Revised Cover Letter for Amendment No. 1
Dear Mr. Conlon:
The purpose of this letter is to request authorization for additional funding to complete the
M-244B Sanitary Sewer Rehabilitation project.as described in the amount of$24,648. The
additional funding is needed to address additional bid phase and construction services. A
detailed breakdown of the additional funding request is attached.
Project History
The M-244B Emergency Sanitary Sewer Rehabilitation project has been successfully
designed,bid and awarded. The City has requested several items from Wade-Hill that
were beyond our original scope and are outlined below.
Request for Additional Funding
The following outlines our request for additional funding.
Address City of Arlington's Comments
The City of Arlington provided a detailed list of concerns that were addressed in
Addendum No. 2. CH2M HILL will formally reply to Arlington with a co-signed letter
from Wade-Hill and the City. The effort involved in addressing the City of Arlington's
concerns was not anticipated nor part of the project's scope.
Address Channel 8 media Inquiry
Channel 8 directly called and requested to interview Chris Brooks, the Wade-Hill project
manager regarding the scope of the project. An actual interview never transpired, but a
days worth of effort was used in discussions with City staff and internal staff in
preparations of a statement,if needed.
Negotiate mitigation Credits
The City has requested CH2M HILL coordinate with the Corps of Engineers for alternative
mitigation bank credits in light of their recent litigation against the Trinity River Mitigation
C:ID000MENTS AND SETTINGSISHOLOLTILOCAL SETTINGSITEMPORARY INTERNET FILESIOLK32MAMENDMENT 1
FINALREV3_LTRHEAD.D0C
Mr. Liam Conlon
March 26,2008
Page 2 of 2
Bank. A mitigation strategy was provided to the City as part of the Pre-Construction
Notification. Coordination and corresponding with multiple banking sources and the
Corps of Engineers is not part of the Contract scope.
Bidding Assistance
The City requested Wade-Hill conform the Contract documents to incorporate items from
the Addendum. Our current scope does not include conformed document preparation.
Assistance ®uiring Construction
Our scoped assistance during construction includes attendance of a pre-construction
conference, participate in a final walk-through and preparation of Record Drawings. The
City has requested we review shop drawings which is out of our scoped services. The
attached breakdown includes the effort for review of Contractor's submittals plus
additional items we believe are necessary to ensure a successful project construction. These
items include responding to Contractor's request for information,review of Contractor's
Change Orders and periodic site visits.
A summary of the total project is as follows:
Contract Description Fee
Original Contract Design, bid, and construction services for M-244B Sanitary Sewer $292,150
Rehabilitation Project
Amendment No. 1 Additional Bidding and Construction Assistance $24,648
TOTAL PROJECT $316,798
Alpha Graphics was used for reproduction services for the conformed Contract documents
in the amount of$624, or 2.5% of the total amendment request.
It should be noted that the original Contract amount is$292,150. Some of the scoped items
for survey(bathemetric survey) and geotechnical(lake borings) services were not
authorized by the City and therefore were not performed and have not been billed. At this
point in the project, it is anticipated these services will not be required. The total amount
for the unperformed services is$38,251.75.
Sincerely,
CH2M HILL
C-i-
Chris Brooks, P.E.
Senior Project Manager
Encl.: Addendum 1 Breakdown
cc: Mr. Robert Terrell w/ encl.
C:0000MENTS AND SETTINGSWOLOLTILOCAL SETTINGSITEMPORARY INTERNET FILESOLK32C1AMENDMENT 1
F I NALRE0_LT RH EAD.DOC
Amondmont Mo. `i
CITY PROJECT MO. 00834
Engineering Services Associated with
M-244B EMERGENCY SANITARY SEWER REPLACEMENT
r1n
ivity Description Labor Category Labor Flours Hourly Rate Total
orporate City of�,rlington's comments Addendum. Formally reply toE6 12 $167.82 $2,014
ington's comments. T3 4 $100.09 $400
SUBTOTAL 16 $2,414
Address Channel 6 Media Inquiry E6 8 $167.82 $1,343
SUBTOTAL 8 $1,343
Conform Contract Plans and Specifications E6 16 $167.82 $2,685
T3 16 $100.09 $1,601
01 4 $72.23 $289
Reproduction Expenses $624
M/WBE Mark-up @ 10% $62
SUBTOTAL 36 $5,261
Negotiate Mitigation Credits E6 14 $167.82 $2,349
SUBTOTAL 14 $2,349
Review Contractor's Shop Drawings E6 30 $167.82 $5,035
(assumes 10 shop drawings aii 4 hrs ea) 01 10 $72.23 $722
SUBTOTAL 40 $5,757
Respond to Contractor's RFI's E6 8 $167.82 $1,343
(assumes 5 @ 2 hrs ea) 01 2 $72.23 $144
SUBTOTAL 10 $1,487
Review Contractor's Change Orders E6 6 $167.82 $1,007
(assumes 2 @ 4 hrs ea) 01 2 $72.23 $144
SUBTOTAL 8 $1,151
Site Visits E6 20 $167.82 $3,356
(assumes 8 weekly site visits @ 4hrs ea) E4 8 $141.28 $1,130
T4 4 $100.09 $400
SUBTOTAL 32 $4,886
TOTAL AMENDMENT NO. 1 $24,648
M/iIIBE Participation $624
MfWBE Participation% 2.5°�