HomeMy WebLinkAboutContract 37228 Amendment No. 3
STATE OF TEXAS § CITY SECRETARY NO.
COUNTY OF TARRANT §
WHEREAS, the City of Fort Worth (City) and Teague Nall and Perkins,
Inc., (Engineer) made and entered into City Secretary Contract No. 34074
(the Contract) which was authorized by the City Council by M&C C-21711 on
the 26th day of September 2006; and
WHEREAS, the Contract involves engineering services for the following
project:
Pavement Reconstruction and Water and Sanitary Sewer
Replacement on Canton Drive (Meadowbrook Blvd. to Craig St.),
Church Street (Louise St. to Handley Dr.), Halbert Street (Craig St. to
Routt St.) and Van Natta Lane (Muse St. to Janice Ln.), 2004 CIP
Contract 48, Project No. 00450, DOE No. 5409
WHEREAS, it has become necessary to execute Amendment No. 3 to
said Contract to include an increased scope of work and revised maximum
fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly authorized representatives, enter into the following agreement
which amends the Contract:
1.
Article I of the Contract is amended to include the revised scope in
engineering services specified in a proposal letter dated February 5, 2008, a
copy of which is attached hereto and incorporated herein. The cost to City
for the additional services to be performed by Engineer total $44,803.00.
2.
Article II of the Contract is amended to provide for an increase in the
maximum fee to be paid to Engineer for all work and services performed
under the Contract, as amended, so that the total fee paid by the City for all
work and services shall not exceed the sum of $329,838.00.
vl�t' �I;t �`1 12,y06-1 9-08 A08:47 MI
1 c
ORIGINAL
Contract Amendment No. 3
Page 1 of 2
,l
3.
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
Executed on this the I I�h day of 2008, in
Fort Worth, Tarrant County, Texas.
APPROVAL RECOMMENDED: APPROVED:
A. Douglas Rademaker, P.E. Fernando Costa
Director, Department of Assistant City Manager
Engineering
Teague Nall and Perkins, Inc. ATTEST:
ENGINEER
By:
Marty Hen ix
Name: Ty Hilton, P.E. City Secretary
Vice President
1100 Macon Street
Fort Worth, Texas 76102 _
Contract �,utho i-ia_ati.on
APPROVED S TO F ND LEGALITY:
Amy R
Assista e Attorney
Contract Amendment No. 3
Page 2of2
Responsive
NO TEAGUE NALL AND PERKINS
Civil Engineering ( Surveying Landscape Architecture 1 Planning
February 5, 2008
Mr. Richard Argomaniz, P.E.
City of Fort Worth
Department of Engineering
1000 Throckmorton
Fort Worth, Texas 76102
Re: 2004 Cip Neighborhood Street Projects Year 4 & 5— Project No. 00450
Contract 48—Street Reconstruction, Water and Sanitary Sewer Replacement
Fee Proposal for Contract Amendment No. 3
TNP No. FTW 06282
Dear Mr.Argomaniz:
Teague Nall and Perkins, Inc. is submitting this fee Amendment to the above referenced contract
based on additional services requested. The following is a brief description and cost for the
additional services provided on this project:
Additional Services to prepare Easement Documents
After preparing plans and after the City's review, it is our recommendation that public open
space easements be prepared and acquired at the intersection of Canton Street and
Meadowbrook Drive. This intersection currently has inadequate sight distance and acquiring
easements will allow for clearing and grading work to alleviate the issue. In addition,
drainage easements are necessary to provide for Inlet and headwall construction and future
maintenance around the inlet and outlet of two culverts on Canton Drive. A small amount of
field survey is also required to complete the easements and design work. The fees shown
include 10% for sub consultant administration.
■ Public Open Space Easements (2 Parcels) $ 1,320
■ Drainage Easements (6 Parcels) $ 3,960
■ Additional Topographic Survey for Culvert Inlet/Outlet $ 2,200
T/PW Subtotal $ 7,480
Water Subtotal $ 0
Sewer Subtotal $ 0
1100 Macon Street Fort Worth,Texas 76102 1 817.336.5773 phone 817.336.2813 fax
www.tnp-online.com
Fort Worth -Dallas Denton
Mr.Richard Argomaniz,PE,February 5,2008,Page 2 of 3
Additional Services for Canton Drive Sewer Modifications
At the direction of the Water Department, we are planning to re-route line L-3209-A to flow
into line L-3203. In addition, line L-3209 will be re-routed to flow down Greenlee Street and
Putnam to the Manhole at the intersection of L-3211 and L-3210. See attached exhibit.
■ Topographic Survey $ 3,080
■ Engineering Design $ 12,708
■ Additional Printing, Submittals, and Coordination $ 800
T/PW Subtotal $ 0
Water Subtotal $ 0
Sewer Subtotal $ 16,588
Additional Services for Church Street Modifications
At the direction of the Transportation/Public Works Department, we will re-design Church
Street to reflect a 23-ft(back-of-curb) pavement width. In addition,we will prepare temporary
construction easements and one right-of-way acquisition document (to allow for a better
alignment across Haynie Street). Our survey crews will also remove right-of-way
monumentation set as a part of the previous acquisition plans. We will also plan for
replacing a short section of sidewalk at the northeast corner of Church Street and Haynie
Street.
■ Right-of-Way Documents (1 Parcel) $ 1,100
■ Temporary Construction Easements (7 Parcels) $ 4,620
■ Engineering Re- Design: $ 7,590
■ Additional Printing, Submittals, Meetings and Coordination $ 2,600
T/PW Subtotal $ 15,910
Water Subtotal $ 0
Sewer Subtotal $ 0
Mr.Richard Argomaniz,PE,February 5,2008,Page 3 of 3
Additional Services for Van Natta at Janice St. Modifications
Repairs and modifications to utilities and streets at the intersection of Van Natta Lane and
Janice Lane have been recently completed by a contractor working for the City. A survey
field crew will be sent to collect horizontal and vertical data on the changes in field
conditions. That data will be incorporated into the plans and designs we are completing.
■ Topographic Survey $ 2,200
■ Engineering Design Update $ 2,425
■ Additional Printing, Submittals, Meetings and Coordination $ 200
T/PW Subtotal $ 2,315
Water Subtotal $ 1,255
Sewer Subtotal $ 1,255
Total Contract Amendment No. 3: $ 44,803
Summary of Contract Fee:
Original Contract Amount: $ 301,145
Amendment No. 1: $ 16,000
Amendment No. 2: ($ 32,110)
Amendment No. 3 $ 44,803
Revised Contract Amount $ 329,838
Work Phase Summary (Includes all Amendments to date)
Work WATER SEWER T/PW Pavin /Draina e
Phase Original Revised Original Revised Original Revised
51 19,251.00 19,823.00 5,035.00 8,687.00 14,414.00 40,770.00
84 - - - - - 17,600.00
31 40,674.00 40,879.00 9,854.00 14,111.00 28,207.00 31,642.00
32 81,347.00 42,491.00 19,706.00 28,221.00 56,414.00 63,283.00
33 13,557.00 7,081.00 3,284.00 4,703.00 9,402.00 10,547.00
Total 154,829.00 110,274.00 1 37,879.001 55,722.00 108,437.00 163,842.00
Thank you for consideration of this contract amendment request. In addition to the fee changes
above, a revised schedule has been attached as a part of this amendment. If you have any
questions, please do not hesitate to call me.
Sincerely,
TEAGUE NAU AND PERKINS, INC.
Mich el ellb um, P.E.
Att: Revised Project Schedule
Copy: Mr. Ty Hilton, PE - TNP
q:\Idt\ftv+06282\dots\contract\_contract amend 03.final.doc
M&C Request Review Page 1 of 2
Fogy T, 1 o
CFWnet City of Fort Worth Employee Intranet 6/4/2008
Staff Action Tracking Council Agenda M&C Employee Directory ACToday Employee Classifieds PRS IT Online Departments
Print M&C
COUNCIL ACTION: Approved on 6/3/2008 -Ord. No. 18123-06-2008
DATE: 6/3/2008 REFERENCE NO.: **C-22833 LOG NAME: 30AMEND3CANTON
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Amendment No. 3 in the Amount of$44,803.00 to City Secretary
Contract No. 34074 with Teague Nall & Perkins, Inc., for Pavement Reconstruction and
Water and Sanitary Sewer Replacements on Canton Drive, Church Street, Halbert Street
and Van Natta Lane (Project No. 00450) and Adopt Appropriation Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the transfer of$19,098.00 from the Water and Sewer Operating Fund to the Water Capital
Projects Fund in the amount of$1,255.00 and the Sewer Capital Projects Fund in the amount of
$17,843.00;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water Capital Projects Fund in the amount of$1,255.00 and the Sewer Capital Projects Fund in the
amount of$17,843.00, from available funds; and
3. Authorize the City Manager to execute Amendment No. 3 in the amount of$44,803.00 to City
Secretary Contract No. 34074 with Teague Nall & Perkins, Inc. to provide additional engineering
services on Canton Drive, Church Street, Halbert Street and Van Natta Lane, thereby increasing the
contract amount to $329,838.00.
DISCUSSION:
The 2004 Capital Improvement Program (CIP) includes funds for pavement reconstruction on Canton
Drive (Meadowbrook Boulevard to Craig Street), Church Street (Louise Street to Handley Drive),
Halbert Street (Craig Street to Routt Street) and Van Natta Lane (Muse Street to Janice Lane).
On September 26, 2006, (M&C C-21711) City Council authorized the City Manager to execute an
engineering agreement with Teague Nall & Perkins, Inc., in the amount of$301,145.00 for the subject
project. The agreement was subsequently revised by two previous amendments totaling a net
reduction of$16,110.00 as follows:
• Amendment No. 1 in the amount of$16,000.00(City Secretary No.34882,February 9,2007)provided additional services for
Geotechnical Analysis and Report that consisted of the investigation of soil conditions at the subject locations and provided
recommendations for the appropriate pavement design for each street.
• Amendment No.2 resulted in a net reduction of$32,110.00(City Secretary No.35350,June 4,2007)in the contract amount. This
amendment deleted the design of a 48-inch water main,the addition of the fee related to administration of sub-consultant services for
the Geotechnical Analysis and Report not included in Amendment No. 1 and the field survey and preparation of documents for right-
of-way easements to widen a portion of Church Street.
Amendment No.3 will provide the following additional services:
• Survey and preparation of documents for acquisition of drainage easements and right-of-way for a portion of Canton Drive
file:HCAE)ocuments and Settings\ArgomaR\My Documents\2004 CIP\CONTRACT 48\M&C Requ... 6/4/2008
M&C Request Review Page 2 of 2
(Meadowbrook Drive to Craig Street)and modification of a portion of Church Street(Louise Street to Haynie Street).
• Survey and design for relocation of an existing sanitary sewer main within the Canton Drive project area.
• Survey and revision to plans for the utilities and street at the intersection of Van Natta Lane and Janice Lane following the completion
of a separate City project at this location.
Teague Nall & Perkins, Inc., proposes to provide the additional engineering services for a lump sum fee
of$44,803.00. City staff considers the fee to be fair and reasonable for the scope of services
proposed.
This project is located in COUNCIL DISTRICT 5, Mapsco 79H, M and 80F, J.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that upon approval of the above recommendations, and the adoption of
the attached appropriation ordinance, funds will be available in the current capital budgets, as
appropriated of the Water Capital Projects Fund, the Sewer Capital Projects Fund and the Street
Improvements Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
1&2) 1 255.00 1)PE45 538070 0609020 $1,255.00
P253 472045 6051700450ZZ
1&2). $17.843.00 1)PE45 538070 0709020 $17.843.00
P258 472045 7051700450ZZ 3)P253 531200 605170045031 $205.00
2)P253 531200 605170045031 $205.00 3)P253 531200 605170045032 $410.00
2)P253 531200 605170045032 $410.00 3)P253 531200 605170045033 $68.00
2)P253 531200 605170045033 $68.00 3)P253 531200 605170045051 $572.00
2)P253 531200 605170045051 $572.00 3)P258 531200 705170045031 $4,257.00
2)P258 531200 705170045031 $4,257.00 3)P258 531200 705170045032 $8,515.00
2)P258 531200 705170045032 $8,515.00 3)P258 531200 705170045033 $1,419.00
2)P258 531200 705170045033 $1,419.00 3)P258 531200 705170045051 $3,652.00
2)P258 531200 705170045151 $3,652.00 3)C200 531200 205400045031 $3,435.00
3)C200 531200 205400045032 $6,869.00
3)C200 531200 205400045033 $1,145.00
3)C200 531200 205400045051 $14,256.00
Submitted for City Manager's Office by; Fernando Costa (8476)
Originating Department Head: A. Douglas Rademaker (6157)
Additional Information Contact: Richard Argomaniz (8653)
ATTACHMENTS
30AMEND3CANTON.doc
30AMEND3CANTON.pdf
file:HC:\Documents and Settings\ArgomaR\My Documents\2004 CIP\CONTRACT 48\M&C Requ... 6/4/2008
6301 N.Beach Street
Wooda�en Fort Worth,Texas 76137
Bank T. 817-489-6500
F: 817-838-0303
June 6, 2008
IRREVOCABLE STANDBY LETTER OF CREDIT NUMBER: 19984
Beneficiary: Applicant:
City of Fort Worth Mercantile Partners L.P.
1000 Throckmorton 3602 N. Sylvania
Fort Worth, TX 76102 Fort Worth, TX 76111
Project No.: 00998 Amount: $77,000.00
Expiration: October 6, 2008
We hereby establish in your favor our Irrevocable Standby Letter of Credit number
19984 which is available with Woodhaven National Bank by payment against
presentation of the original of this Letter of Credit and your drafts at sight drawn on us
accompanied by documents detailed below:
A signed statement from the beneficiary stating that:
"Mercantile Partners L.P. has failed to complete project number 00998 or to make
payment for Northern Crossing West Addition."
We hereby agree with you that the draft(s) drawn under and in compliance with the terms
of this Letter of Credit will be duly honored upon presentation at the above address, Attn:
David Woodle, or by facsimile confirmed by a phone call. When presentation is made by
facsimile the original Letter of Credit is not required.
This Letter of Credit is subject to the International Standby Practices 1998, ICC
Publication No. 590.
If you require any assistance or have any questions regarding this transaction, please call
me.
David Woodle, Sr. Vice President
6301 N.Beach Street
oodaven Fort Worth,Texas 76137
Bank T: 817-489-6500
F: 817-838-0303
June 6, 2008
IRREVOCABLE STANDBY LETTER OF CREDIT NUMBER: 19984
Beneficiary: Applicant:
City of Fort Worth Mercantile Partners L.P.
1000 Throckmorton 3602 N. Sylvania
Fort Worth, TX 76102 Fort Worth, TX 76111
Project No.: 00998 Amount: $77,000.00
Expiration: October 6, 2008
We hereby establish in your favor our Irrevocable Standby Letter of Credit number
19984 which is available with Woodhaven National Bank by payment against
presentation of the original of this Letter of Credit and your drafts at sight drawn on us
accompanied by documents detailed below:
A signed statement from the beneficiary stating that:
"Mercantile Partners L.P. has failed to complete project number 00998 or to make
payment for Northern Crossing West Addition."
We hereby agree with you that the draft(s) drawn under and in compliance with the terms
of this Letter of Credit will be duly honored upon presentation at the above address, Attn:
David Woodle, or by facsimile confirmed by a phone call. When presentation is made by
facsimile the original Letter of Credit is not required.
This Letter of Credit is subject to the International Standby Practices 1998, ICC
Publication No. 590.
If you require any assistance or have any questions regarding this transaction, please call
me.
David Woodle, Sr. Vice President