HomeMy WebLinkAboutIR 8849INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8849
To the Mayor and Members of the City Council Date: June 12, 2007
Page 1 of 3
a SUBJECT: IT Lessons Learned as Applied to Potential ERP Project
..m
Background: On May 29, 2007 (M &C C- 22133), the City Council appropriated funds and authorized
the City Manager to execute a consulting agreement with Salvaggio, Teal & Associates (STA) for the
first phase of the Enterprise Resource Planning Project (ERP). This first phase is a fixed fee contract
which is not to exceed $860,450 and includes a detailed list of milestones and deliverables.
During the Pre - Council discussion, two specific historical initiatives were pointed out as having
significant management problems:
• The Computer -Aided Dispatch system for Fire and Police that began in 1999; and,
• A consulting contract to revamp the IT Solutions Department in 2001.
The intent of this IR is to provide a summary of the lessons learned from these initiatives and to
demonstrate efforts taken to avoid a reoccurrence. Additionally, a matrix is included which outlines the
problems encountered in the past, lessons learned and the changes planned for ERP and future projects.
Any budget variances from the approved plan and contract will be presented to the City Council for
consideration prior to proceeding.
What We Learned: After reviewing these initiatives we have distilled the following critical needs that
contribute to project success:
• Expertise of project team and project management;
• Disciplined project management and governance;
• Clear accountability for the success of the initiative;
• Effective contract controls.
What We Are Doing Differently with ERP: We have incorporated the following elements into our
approach for the project:
• Supplementing the City's functional expertise with that of an outside consultant, experienced in
ERP systems and independent of software, hardware and implementation vendors to assist the
City with ERP requirements definition and product selection.
• Providing an executive sponsor at the appropriate level to control and access resources, resolve
issues and provide direction for delivering the project on time and within scope and budget.
• Following a proven methodology supplemented by generally accepted project management
processes, including a cross functional steering committee that will provide detailed oversight of
project budget, schedule, risks and issues.
• Using a fixed fee approach in phase 1 of the initial contract with STA where a detailed
schedule ties payments to the completion and acceptance of deliverables and milestones.
Moreover, the contract language states, "The City shall have sole discretion to determine
whether a deliverable /milestone is complete prior to acceptance by the City, however,
acceptance will not be unreasonably withheld." Each deliverable and milestone is required to
be accepted by the City and communicated on a signed Milestone Acceptance Document prior
to payment.
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
mltlii
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8849
To the Mayor and Members of the City Council Date: June 12, 2007
Page 2 of 3
°► SUBJECT: IT Lessons Learned as Applied to Potential ERP Project
Following is a chart summarizing past project problems and lessons learned.
1. Undefined and unrealistic budget,
insufficient financial reporting to
compare actual expenditures to plan.
2. Unrealistic schedule.
3. Changes to scope were not properly
estimated and evaluated.
4. Project manager decisions that affected
finances and timeliness were not
monitored; no process for
oversight/accountability.
CAD Proiect
1. Lack of a clearly established
budget and financial oversight
caused cost overruns and
unforeseen charges.
2. Overly optimistic timelines and
inadequate planning led to
unmet expectations and failures
to deliver.
Any changes in scope affect a
project in some manner:
deliverables, time, resources,
cost or quality. Governance
must be in place for any
changes to scope to ensure
proper approvals.
No project manager or single
authority should have sole
control over a project. System
requirements must be published
and reviewed by stakeholders
for completeness prior to
approval. Governance must be
in place for any changes to
scope to ensure proper
approvals. Project Manager and
team members must be held
accountable for deliverables,
timeline and cost.
1. Explicit budget will be reported
and reviewed monthly by the
Steering Committee and accepted
only after the approval of the
Executive Sponsor /ACM.
2. Will do extensive planning to
produce a detailed schedule
listing all the tasks to be included
in the project plan and reviewed
by the Steering Committee.
3. No scope changes will be allowed
without the approval of the
Executive Sponsor /ACM,
Steering Committee and a re-
estimate of the timeline, costs,
end product received or the
resulting quality. City Council
approval is required if items
exceed current appropriation.
4. Weekly meetings will be held
with the Executive Sponsor /ACM
and the Project Management
team. ACMs and Department
Heads will be depended on to
ensure awareness, accountability
and that the best interest of the
City is the primary focus. The
ERP Project will be tracked in the
Capital Project Management
System (CPMS) as one project
account and must have Executive
Sponsor /ACM approval prior to
invoices being submitted for
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8849
rA
p `
To the Mayor and Members of the City Council Date: June 12, 2007
Page 3 of 3
SUBJECT: IT Lessons Learned as Applied to Potential ERP Project
If you have questions, please contact Karen L. Montgomery, Assistant City Manager and Chief Financial Officer at
(817) 392 -6222 or Pete Anderson, Chief Information Officer at (817) 392 -8781.
Charles R. Boswell
City Manager
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
IT Solutions /Contractor
r
2
1.
CIO directed the payment of invoices
1. High -level governance with
1.
ERP project contracts will be managed
from consultants without required
appropriate checks and
by an Executive Sponsor /ACM
documentation of deliverables and
balances, including an
overseeing a Steering Committee
intimidated employees. IT used
Executive Sponsor and Steering
consisting of 4 department directors, 3
existing State contracts for work done
Committee, is mandatory.
assistant directors, ITS Project Manager
by Contractor that lacked controls or
Effective contract controls must
and key members of identified
specified end dates.
be in place.
departments. Budget and deliverables
will be tracked in CPMS and presented
monthly for review.
2.
Prior funding requests for critical
2. All requests need a valid review
2.
A solid business case with cost/ benefit
system upgrades were not approved by
process and proper approval.
analysis will be developed to provide a
management until the situation was dire.
sound basis for review and approval.
CIO allowed Contractor open -ended
This business case will be kept updated
funding with inappropriate checks and
to ensure City Council is appropriately
balances.
advised on funding decisions.
Consultants will be `managed' rather
than be given complete autonomy.
3.
CIO and Contractor pushed changes
3. Every technology
3.
The essentiality of a system will be
forward as necessary, citing `must
implementation must stand on
weighed against the benefits and long
have' technology.
its own merit and not be done on
term costs to the City.
the basis of global statements.
4.
CIO failed to accurately communicate
4. Regular communication about
4.
Status of the ERP Project will be
changes and progress to City Council.
project progress, scope changes
reported to City Council on a regular
and budget variance with the
basis. The Steering Committee will
City Council and the CMO is
review progress and budget monthly.
essential to maintain orderly
The Executive Sponsor /ACM will
checks and balances.
monitor project weekly. The Project
Manager will be dedicated only to ERP
to allow timely reporting and
communication. An intranet website
will maintain project status, meeting
minutes, budget information and
presentations which will provide
transparency for the project.
5.
Did not follow adequate change control
5. A comprehensive change
5.
The ERP project team will follow
procedures. For example, changes were
control process must be in place.
appropriate change control processes,
put into production for a mainframe
conducting unit testing, user acceptance
upgrade without proper testing, causing
tests, parallel testing and system
a network outage.
capacity testing.
If you have questions, please contact Karen L. Montgomery, Assistant City Manager and Chief Financial Officer at
(817) 392 -6222 or Pete Anderson, Chief Information Officer at (817) 392 -8781.
Charles R. Boswell
City Manager
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS