HomeMy WebLinkAboutContract 51447-CO2 RECEIVEA,f ba_.x WORTH City of Fort Worth CSC No:51447-0O2
MAY -5 2020 Change Order Request
CITYOFFORT11VOR Pr*dNamej Village Greek Chlorine Enclosure City Sec No. 51447
CITYSECRETAF, ProjedNo.(3)1 P227156007 070SF30WF80 City Proj.No. CO2273 ,
Project Enclosure of the Gaseous Chtodne and Sulfur Dioodde Slorage Facft
Conhft.l Crescent Consiruclor,Inc. Change Order: U Date: 4/13I2020
Cj(yPr*cAMgr.1 Selavash Mir City inspector: Nathan Gray
Phone Number 817-392-8404 Phone Numbw.1 817-991-0629
Dept. Sewer F$80673,000.00
Contract Time
(Calender days)
Original Contract Amount $8.573.000.00 480
Extras to Dale $65,000.00 70
Credits to Dale
Pending Change Orders(in M&C Process)
Contract Cost to Date $8.638,000.00 $8.638,000.00 550
Amount of Proposed Change Order $0.00 070
Revised Contract Amount $8.638,000.00 $8.638,000.00 620
Original Funds Available for Change Orders $257,000.00 $257,000.00
Remaining Funds Available for this CO $192,000.00 $192,000.00
Additional Funding Of necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS 9d OF ORIGINAL CONTRACT 0.7656
MAXALLOWABLECONTRACTAMOUNT(ORIGINAL CONTRACT COS T+25%) $10,716;250.00
AUSTI CATIQN MAWS FMI ANOPWRD.)9R
1. This Change Order adds time required due to inclement weather.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
In full(both time and money)for all costs arising out of,or incidental to,(he above Change Order.
Crescent Constructor,Inc. Ryan Glanz,P,.E. I Ryan Glanz t.a =-- 0 4/13/2 Ort
Inspector Date PmjectManager Date
Nathan Gray Nathan Gray 04/13/20 Seiavash Mir r� / �2
Director WaterDe t Date E ineer Carol Dale
o T• S, May 4,2020 Matthew Dobbertien,P.E. �Y��---— 4/13/2020
ri to herH rder Ma a 2020
Assistant City Attorney Dale Assistant CityVanager Date
0" &(M,v4,2020) May4,2020 —a radon, 4,20 ay= 2®2t
Council Action IERe uired) JOERECORD
M&C Number I N%A M&C Date Approved :yE,
ARY
FT WORTH,TX
ET
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performanc and reporting requirements.
tl 4 It,
Signature
Tony Sholola
Name of Employee
Assistant Water Director
Title ,COR ,,,,
ATTEST:
Mary J. Kayser5.
City Secretary x.t
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH,TX
Project Rain Days(November 2018 thru March 2020)
Project: C12 Project
NTP Date: 11/20/2018
Month Rain Days CCI Rain Days(FW) Dates
November-18 0 None
December-18 5 12/07,12/26,12/27,12/28(mud),12/31
Janua -19 4 01/02,01/03,01/04(mud),01/11
Februa -19 6 02/07,02/08(coid/mud)02/11,02/12(mud),02/19,02/20(mud)
March-19 4 03/04(cold),03/05(cold),03/13,03/14(mud)
April-19 7 04/08(mud),04/17,04/18,04/19(mud),04/23,04/24,04/25(mud)
May-19 9 05/01,05/02,05/03(mud),O5/08,05/09(mud),05/21,05/22(mud),05/29,05/30(mud)
lune-19 5 06/10(mud),06/17(mud),06/19,06/20(mud),06/24(mud)
July-19 2 07/10,07/11(mud)
August-19 5 08/14,08/15(mud),08/27,08/28(mud),08/30
September-19 0 none
October-19 9 10/10,10/11,10/21,10/22(mud),30/24,10/25(mud),10/29,10/30,10/31(mud)
November-19 3 SS/07,11/08(mud),11/22
December-19 5 12/09(no paint),12/20,12/11(mud),12/16(no paint),12/20(no paint)
01/09(no paint),01/10,01/13(no painl),01/14(no paint),01/15(no paint),01/16,01/17,01/21(no
lanuary-20 13 palnt),01/22,01/23(no paint),01/27(no paint),01/28,01/29(mud)
02/03,02/04(mud),02/05(cold no paint),02/06(cold no paint),2/10,02/11,02/12,02/13(mud),02/18(no
February-20 12 paint),02/19,02/20,02/21(mud)
March-20 11 03/O4,03/O5(mud),03/13,03/16,03/17,03/18,03/19,03/20(mud),03/23(mud),03/30,03/31(mud)
April-20
Ma-20
June-20
July-20
August-20
September-20
Total Rain Days(Work Days)= 100
Rain Day Allowance(Original)_ -30
Rain Day Extension(+Pending)= 70
C12 Substantial Completion(CO41)= 5/23/2020
C12 Substantial Completion(+Pending)= 8/1/2020
Cl2 Final Completion(+Pending)= 9/5/2020
Village Creek Crescent Weather Impact Day Info
Dates: 11/20/18 - 03/31/20
Info shown on attached:
k0range = Holidays/Weekend Days = Weather Impact not counted j
Yellow = Day When Rain >= 0 . 10 inch
= 1 Day (Due to Direct Rain Impact)
Yellow = Day After Rain >=0 . 10 inch
= 1 Day (Due to limited site access or to clean up work areas)
Yellow = Trace Rain/Humidity Day
= 1 Day (Due to not being able to paint or coat work areas)