HomeMy WebLinkAboutContract 38562-A2 AMENDMENT NO. 2
STATE OF TEXAS S CITY SECRETARY CONTRACT NO." a-Ala
(M&C Required)
COUNTY OF TARRANT S
WHEREAS, the City of Fort Worth (City) and Rimley-Horn and
Associates, Inc. , (Engineer) made and entered into City Secretary
Contract No. 38565, (the Contract) which was authorized by the
City Council by M&C C-23518 on the 12th day of May 2009 and
subsequently revised by one previous amendment; and
WHEREAS, the Contract involves engineering services for the
following project:
Water and Sanitary Sewer Main Relocations for the
SH121T Crossing west of the Hulen Street Bridge with
the Union Pacific Railroad Davidson Rail Yard.
WHEREAS, it has become necessary to execute Amendment No. 2
to said Contract to include an increased scope of work au%-- revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement which amends the Contract:
1.
Article I, of the Contract is amended to include the
additional engineering services specified in M&C C-24737, adopted
by the City Council on the 15th day of February 2011, and further
amplified in a proposal letter dated December 15, 2010, copies of
which are both attached hereto and incorporated herein. The cost
to City for the additional services to be performed by Engineer
total $184,400.00.
2 .
Article II, of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $849,765.00.
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
3.
All other provisions of the Contract which are not expressly
amended herein shall remain in full force and effect.
f EXECUTED on this the day of V��.1-L� , 20110,
in Fort Worth, Tarrant County, TexasGA�
47
��o0ooct' op �
y ¢
U
O �
Marty Hendrix
a
City Secretary a 00o 000��� ���,
APPROVAL RECOMMENDED: ROVED:
S. Frank Crumb, P.E. Fernand Costa
Director, Water Department Assistant City Manager
RIMLEY-HORN AND ASSOCIATES, INC. - C--,;,L4-1
Engineer
Contrac' Authorizatioa
a
_ 15 � ti
Date
By:
Name:Glenn A. Gary, P.
Sr. Vice President
801 Cherry Street, Suite 1025
Fort Worth, TX 76102
APPROVED AS TO FORM AND LEGALITY:
Qik 0
Assistant City Attorney
-2- OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Official
CITY COUNCIL AGENDA FORT11
COUNCIL ACTION: Approved on 211612011
DATE: 2/15/2011 REFERENCE **C-24737 LOG NAME: 60WSS121TUPRRA2-KHA
NO..
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Amendment No. 2 in the Amount of$184,400.00 to City Secretary
Contract No. 38565 with Kimley-Horn and Associates, Inc., for Water and Sanitary Sewer
Main Relocations for the State Highway 121T Crossing West of the Hulen Street Bridge
Within the Union Pacific Railroad Davidson Rail Yard (COUNCIL DISTRICTS 3 and 9)
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Amendment No. 2 in
the amount of$184,400.00 to City Secretary Contract No. 38565 with Kimley-Horn and Associates,
Inc., for Water and Sanitary Sewer Main Relocations for the SH121T crossing west of the Hulen
Street Bridge within the Union Pacific Railroad Davidson Rail Yard, thereby increasing the contract
amount to $849,765.00.
DISCUSSION:
On May 12, 2009, (M&C C-23516)the City Council authorized an engineering agreement in the
amount of$585,365.00 with Kimley-Horn and Associates, Inc., for Water and Sanitary Sewer Main
Relocations for the SH121T Crossing west of the Hulen Street Bridge within the Union Pacific
Railroad Davidson Rail Yard.
The agreement was subsequently revised by one previous amendment (M&C C-24048, January 26,
2010) in the amount of$80,000.00 that provided for the relocation of the inaccessible segment of a
48-inch water main that was located within Colonial Park Apartments.
Amendment No. 2 will provide for the following construction assistance services to facilitate timely
construction of the project in order to accommodate NTTA's schedule for SH121T and on-going
improvements within Union Pacific property and will include:
Shop drawing reviews
Construction coordination meetings with City staff and contractors.
Project Management meetings with City staff, Union Pacific and NTTA
Material substitution reviews
A waiver of the M/ BE Ordinance was granted for this amendment due to the fact that no M/WBE
subcontracting opportunities are available on the scope of services proposed to be provided.
The project is located in COUNCIL DISTRICTS 3 and 9.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budgets, as appropriated, of the Water Capital Projects Fund and the Sewer Capital Projects Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
Logname: 604061000I-SJLOUIS Page 1 of 2
P265_531200_703170133231 $22 440.00
P265 _531200__703170133232 $44 880.00
P265 531200 703170133233 $7,480.00
P275 5.31200_703170133231_ $32, 00.8 00
P275 531.200 703170133232 $65,760.00
P275 531200 .703170133233 $10 9960.00
Submitted fo-r City_Manaaer's_Office_bv: Fernando Costa (6122)
Originating Department Head: S. Frank Crumb (8207)
Additional Information Contact: Liam Conlon (6824)
ATTACHMENTS
60WSS121TUPRRA2-KHA MAP.pd_f
Logname: 6040610C01-SJLOUIS Page 2 of 2
Kimley-Horn
and Associates, Inc.
December 15,2010
Sege 950
801 Cherry Street,Unit i t
Fort Worth,Texas
Mr.Liam Conlon 76102
Project Manager
City of Fort Worth Water Department
1000 Throckmorton Street
Fort Worth,TX 76102
Re: Water and Sanitary Sewer Main Relocations for SH121T Crossing West of
the Hulen Street Bridge within the Union Pacific Railroad Davidson Rail
Yard
Additional Services—Amendment No.2
KHA No. 061018062
City Project No.01332
Dear Liam:
The City of Fort Worth(City)has requested Kimley-Hom and Associates,Inc.
(Kimley-Hom)to perform additional services for the construction services for the
Water and Sanitary Sewer Main Relocations for SH121 T Crossing West of the
Hulen Street Bridge within the Union Pacific Railroad Davidson Rail Yard
(UPRR)project. Kimley-Horn has performed or will perform the work outlined
in the following items:
Item 1 (Additional Construction Phase Services)
Perform the additional construction phase services which include:
• Construction Coordination Meetings—Kimley-Hom will conduct and
prepare meeting notes for weekly construction coordination meetings.
Kimlcy-Horn will conduct project management meetings with City staff
twice per month.
• Clarifications and Interpretations,Shop Drawings,Substitutes,and Site
Visits:
1. Clarifications and Interpretations. Kimley-Horn will respond to
reasonable and appropriate Contractor requests for information and
issue necessary clarifications and interpretations of the Contract
Documents to City as appropriate to the orderly completion of
Contractor's work. Any orders authorizing variations from the
Contract Documents will be made by City.
�t
TEL 817 335 6511
FAX 817 335 5070
Kimley-Horn Mr.Liam Conlon,December 15,2010.Page 2
'16� Mori and Associates,Inc.
2. Shop drawings. Kimley-Horn will review and recommend
appropriate action in request to Shop Drawings for the Contractor is
required to submit,but only for conformance with the information
given in the Contract Documents and compatibility with the design
concept of the completed Project as a functioning whole as indicated
in the Contract Documents. Such review and approvals or other
action will not extend to means,methods,techniques,equipment
choice and usage,sequences,schedules,or procedures of
construction or to related safety precautions and programs.
3. Substitutes and"or-equal." Evaluate and determine the acceptability
of substitute or"or-equal"materials and equipment proposed by
Contractor in accordance with the Contract Documents,but subject
to the provisions of applicable standards of state or local government
entities.
4. Site Visits. Kimley-Horn will perform site visits in accordance with
the Engineering Agreement for this project.
• Change Orders—Consultant may recommend Change Orders to Client,
and will review and make recommendations related to Change Orders
submitted or proposed by the Contractor.
• Project Management—Perform project management services including
coordination with City staff,Contractor,Union Pacific Railroad,and
NTTA representatives.
Scope of Services
The scope of services for this amendment is divided into the following tasks:
Item 1 (Additional Construction Phase Services):
$169,000 Kimley-Horn
$ 12,000 Tunneling
$ 2,000 Corrpro
$ 1,40010%Sub Fee
$184,400 Total
(Water$109,600 Sewer$74,800)
• Task 1—Construction Coordination Meetings—Kimley-Horn will
conduct and prepare meeting notes for weekly construction coordination
meetings. Kimley-Horn will conduct project management meetings with
City staff twice per month. $34,400($17,200 water and$17,200 sewer)
,;;P-! Kimley-Horn Mr.Liam Conlon,December 15,2010,Page 3
and Associates,Inc.
• Task 2-Clarifications and Interpretations, Shop Drawings, Substitutes,
and Site Visits. $116,200($73,100 water and$43,100 sewer)
• Task 3-Change Orders-Consultant may recommend Change Orders
to Client,and will review and make recommendations related to Change
Orders submitted or proposed by the Contractor. $21,600($13,600
water and$8,000 sewer)
• Task 4-Project Management-Perform project management services
including coordination with City staff,Contractor,Union Pacific
Railroad,and NTTA representatives. $12,200($6,100 water and$6,100
sewer)
We recommend that the City increase the budget by$184,400 for these
additional services. From the additional services listed above,the recommended
breakdown for water and sewer services is as follows:
Description Water Sewer Total
Item I-Additional Construction $109,600 $74,800 $184,400
Phase Services
Total $109,600 $74,800 $184,400
The following table summarizes the fee per Work Phase
Work Phase Water Fee Sewer Fee Total Fee
31 $32,880 $22,440 $55,320
32 $65,760 $44,880 $110,640
33 $10,960 $7 480 $18,440
Sl 1 $0 1 $0 $0
Total S109,600 $74,800 $184,400
If the City concurs with our requested additional services,the summary of fees
for this project is shown in the table below:
Revised
Contract
Contract/Amendment Water Fee Sewer Fee Survey Fee Total Fee Amount
Original Contract $281,452 $249,513 $54,400 $585,365 $585,365
Amendment No. 1 $49,475 $8,085 $22 440 $80,000 $665,365
Amendment No.2 $109,600 $74,800 $0 $184,400 $849,76S
TOTAL $440,527 $332,398 $76,840 $849,765 1 $849,765
Kimley-Horn Mu Liam Conlon,Occanbu 15.2010.Past 4
11111bimn and Associates,Inc.
M/WBE participation is not planned for these additional services. With the
revised contract amount of$849,765,our total contract M/WBE participation is
projected to be$159,700(18.8%).
We appreciate the opportunity to be of continued service to the City. Please
contact us if we need to provide any further information.
Very truly yours,
KIMLEY-HORN AND ASSOCIATES, INC.
Glenn A.Gary, P.E.
Principal
CTD:ctd
K WTW tAJkiaV619IM6"?NCHA =nolAft d-Mm-md24x dm