NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: PUBLIC SANITARY SEWER IMPROVEMENTS TO SERVE MCPHERSON BLVD
City Project No.: 101684
Improvement Type(s): Water ❑ Sewer
Original Contract Price: $984,760.50
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $984,760.50
May 19,2020
Contractor Date
Project Manager
Title
North Texas Contracting, Inc.
Company Name
lKeilM,XRI-#&I May 19 2020
Kevin Barnes(May 19,202010:38 CDT) Y f
Project Inspector Date
Patrick cki (May 19,20201a:08CDT) May 19,2020
Project Manager Date
Z_a�Z-"t� May 19,2020
CFA Manag r Date
Dana Burghdoff(M 20,202 8:35CDT1 May20,2020
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name: PUBLIC SANITARY SEWER IMPROVEMENTS TO SERVE MCPHERSON
BLVD
City Project No.: 101684
City's Attachments
Final Pay Estimate
Change Order(s): ❑ Yes ® N/A
Pipe Report: ® Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 20 CD Days Charged: 194
Work Start Date: 12/28/2017 Work Complete Date: 7/9/2018
Page 2of2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name PUBLIC SANITARY SEWER IMPROVEMENTS TO SERVE
Contract Limits MCPHERSON BLVD(AT CHISHOLM TRAIL PKWY)
Project Type SEWER
City Project Numbers 101684
DOE Number 1684
Estimate Number 1 Payment Number 1 For Period Ending 5/19/2020
CD
City Secretary Contract Number Contract Time 120D
Contract Date Days Charged to Date 186
Project Manager NA Contract is 100.00 Complete
Contractor NORTH TEXAS CONTRACTING,INC.
P.O.BOX 468
KELLER, TX 76244
Inspectors DICKINSON/ BARNES
Tuesday,May 19,2020 Page 1 of 4
City Project Numbers 101684 DOE Number 1684
Contract Name PUBLIC SANITARY SEWER IMPROVEMENTS TO SERVE Estimate Number 1
Contract Limits MCPHERSON BLVD(AT CHISHOLM TRAIL PKWY) Payment Number 1
Project Type SEWER For Period Ending 5/19/2020
Project Funding
SEWER
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 MOBILIZATION 1 LS $45,000.00 $45,000.00 1 $45,000.00
2 CONSTRUCTION STAKING 1 LS $6,500.00 $6,500.00 1 $6,500.00
3 12"SEWER ABANDONMENT PLUG 7 EA $250.00 $1,750.00 7 $1,750.00
4 SWPPP>1 ACRE 1 LS $20,000.00 $20,000.00 1 $20,000.00
5 LARGE STONE RIPRAP 425 SY $100.00 $42,500.00 425 $42,500.00
6 SMOOTH WIRE FENCE,METAL POSTS 30 LF $50.00 $1,500.00 30 $1,500.00
7 UTILITY SERVICE SURFACE RESTORATION 7200 SY $2.00 $14,400.00 7200 $14,400.00
SEEDING
8 POST-CCTV INSPECTION 4462 LF $1.00 $4,462.00 4462 $4,462.00
9 MANHOLE VACUUM TESTING 14 EA $100.00 $1,400.00 14 $1,400.00
10 TRENCH SAFETY 4462 LF $1.00 $4,462.00 4462 $4,462.00
11 CONCRETE COLLARS 3 EA $1,000.00 $3,000.00 3 $3,000.00
12 TRENCH WATER STOPS 1 EA $300.00 $300.00 1 $300.00
13 CONCRETE ENCASEMENT FOR UTILITY PIPES 2 CY $500.00 $1,000.00 2 $1,000.00
14 24"CASING BY OPEN CUT 20 LF $225.00 $4,500.00 20 $4,500.00
15 24"CASING BY OTHER THAN OPEN CUT 665 LF $600.00 $399,000.00 665 $399,000.00
16 12"SEWER PIPE 58 LF $65.00 $3,770.00 58 $3,770.00
17 15"SEWER PIPE 4404 LF $76.00 $334,704.00 4404 $334,704.00
18 EPDXY MANHOLE LINER 11.25 VF $350.00 $3,937.50 11.25 $3,937.50
19 4'MANHOLE 14 EA $5,000.00 $70,000.00 14 $70,000.00
20 4'EXTRA DEPTH MANHOLE 75.25 VF $300.00 $22,575.00 75.25 $22,575.00
Sub-Total of Previous Unit $984,760.50 $984,760.50
Tuesday,May 19,2020 Page 2 of 4
City Project Numbers 101684 DOE Number 1684
Contract Name PUBLIC SANITARY SEWER IMPROVEMENTS TO SERVE Estimate Number 1
Contract Limits MCPHERSON BLVD(AT CHISHOLM TRAIL PKWY) Payment Number 1
Project Type SEWER For Period Ending 5/19/2020
Project Funding
Contract Information Summary
Original Contract Amount $984,760.50
Change Orders
Total Contract Price $984,760.50
Total Cost of Work Completed $984,760.50
Less %Retained $0.00
Net Earned $984,760.50
Earned This Period $984,760.50
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $984,760.50
Tuesday,May 19,2020 Page 3 of 4
City Project Numbers 101684 DOE Number 1684
Contract Name PUBLIC SANITARY SEWER IMPROVEMENTS TO SERVE Estimate Number 1
Contract Limits MCPHERSON BLVD(AT CHISHOLM TRAIL PKWY) Payment Number 1
Project Type SEWER For Period Ending 5/19/2020
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors DICKINSON/ BARNES Contract Date
Contractor NORTH TEXAS CONTRACTING,INC. Contract Time 120 CD
P.O.BOX 468 Days Charged to Date 186 CD
KELLER, TX 76244 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $984,760.50
Less %Retained $0.00
Net Earned $984,760.50
Earned This Period $984,760.50
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $984,760.50
Tuesday,May 19,2020 Page 4 of 4
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Public Sanitary Sewer Improvements to Serve McPherson BLVD at Chisolm Trail
PROJECT NUMBER: 101684
DOE NUMBER:
WATER
PIPE LAID SIZE TYPE OF PIPE LF
FIRE HYDRANTS: VALVES(16"OR LARGER)
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES:
NEW SERVICES:
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
Sanitary Sewer 12" SDR-26 58
Sanitary Sewer 15" SDR-26 4404
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES: All Densities Passed
NEW SERVICES: