Contract No.
FORT WORTH..) Date Received May 26,2020
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: HARRIS PARKWAY MEDICAL DEVELOPMENT
City Project No.: 101900
Improvement Type(s): Water ® Sewer
Original Contract Price: $189,499.00
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Worst Complete: $189,499.00
May 20 2020
Scott Langham(May 20,202 :28 CDT) Y
Contractor Date
Project Manager
Title
Tri Dal Utilities
Company Name
C044'r 6wrwr, May 20,2020
Cody FKton(May 20,202007:44 CDT)
Project Inspector Date
Gcbbie✓`. wiiiheirn
Debbie J.Willhelm(May 22,202010:26 CDT) May 22,2020
Ppject Manger Date
Laurie Lewis(May
May 22,2020
CFA Manager Date
&I"U' �41�
Dana Burghdoff(M y22,202 :24 CDT) May 22,2020
Asst. City Manager Date --
OFFICIAL RECORD
CM Page 1 of 2
FT. WORTH,TX
Notice of Project Completion
Project Name: HARRIS PARKWAY MEDICAL DEVELOPMENT
City Project No.: 101900
City's Attachments
Final Pay Estimate
Change Order(s): ❑ Yes ® N/A
Pipe Report: ® Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety "
Statement of Contract Time
Contract Time: 90 CD Days Charged: 90
Work Start Date: 1/2/2020 Work Complete Date: 4/30/2020
Page 2of2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name HARRIS PARKWAY MEDICAL DEVELOPMENT
Contract Limits
Project Type WATER&SEWER
City Project Numbers 101900
DOE Number 1900
Estimate Number 1 Payment Number 1 For Period Ending 5/19/2020
CD
City Secretary Contract Number Contract Time 210D
Contract Date Days Charged to Date 210
Project Manager NA Contract is 100.00 Complete
Contractor TRI DAL EXCAVATION&UTILITIES INC
540 COMMERCE ST
SOUTHLAKE, TX 76092
Inspectors OWEN/ HORTON
Tuesday,May 19,2020 Page 1 of 5
City Project Numbers 101900 DOE Number 1900
Contract Name HARRIS PARKWAY MEDICAL DEVELOPMENT Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 5/19/2020
Project Funding
WATER
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 CONSTRUCTION STAKING 1 LS $3,000.00 $3,000.00 1 $3,000.00
2 6"-12"TREE REMOVAL 1 EA $500.00 $500.00 1 $500.00
3 SEEDING 1230 SY $1.00 $1,230.00 1230 $1,230.00
4 TRENCH SAFETY 1110 LF $1.00 $1,110.00 1110 $1,110.00
5 20"CASING BY OTHER THAN OPEN CUT 55 LF $520.00 $28,600.00 55 $28,600.00
6 DUCTILE IRON WATER FITTINGS 0.5 TN $26,000.00 $13,000.00 0.5 $13,000.00
W/RESTRAINT
7 6"PVC WATER PIPE 10 LF $30.00 $300.00 10 $300.00
8 8"PVC WATER PIPE 45 LF $34.00 $1,530.00 45 $1,530.00
9 12"PVC WATER PIPE 1110 LF $54.00 $59,940.00 1110 $59,940.00
10 FIRE HYDRANT 2 EA $4,450.00 $8,900.00 2 $8,900.00
11 CONNECTION TO EXISTING 16"WATER MAIN 1 EA $13,000.00 $13,000.00 1 $13,000.00
12 CONNECTION TO EXISTING 4"-12"WATER 1 EA $7,200.00 $7,200.00 1 $7,200.00
MAIN
13 1"WATER SERVICE 2 EA $2,400.00 $4,800.00 2 $4,800.00
14 2"WATER SERVICE 2 EA $3,500.00 $7,000.00 2 $7,000.00
15 6"GATE VALVE 2 EA $1,250.00 $2,500.00 2 $2,500.00
16 8"GATE VALVE 3 EA $1,650.00 $4,950.00 3 $4,950.00
17 12"GATE VALVE 3 EA $3,000.00 $9,000.00 3 $9,000.00
Sub-Total of Previous Unit $166,560.00 $166,560.00
SEWER
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
1 CONSTRUCTION STAKING 1 LS $550.00 $550.00 1 $550.00
2 REMOVE WALL 235 LF $5.00 $1,175.00 235 $1,175.00
3 REMOVE RIP RAP 1230 SF $1.00 $1,230.00 1230 $1,230.00
4 REMOVE MISC CONC STRUCTURE 1 LS $500.00 $500.00 1 $500.00
5 SEEDING 180 SY $2.00 $360.00 180 $360.00
6 POST CCTV INSPECTION 160 LF $3.00 $480.00 160 $480.00
7 MANHOLE VACUUM TESTING 1 EA $400.00 $400.00 1 $400.00
8 TRENCH SAFETY 160 LF $5.00 $800.00 160 $800.00
Tuesday,May 19,2020 Page 2 of 5
City Project Numbers 101900 DOE Number 1900
Contract Name HARRIS PARKWAY MEDICAL DEVELOPMENT Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 5/19/2020
Project Funding
9 6"SEWER PIPE 5 LF $46.00 $230.00 5 $230.00
10 8"SEWER PIPE 140 LF $67.00 $9,380.00 140 $9,380.00
11 8"SEWER PIPE,CSS BACKFILL 20 LF $95.00 $1,900.00 20 $1,900.00
12 4'MANHOLE 1 EA $4,650.00 $4,650.00 1 $4,650.00
13 4'EXTRA DEPTH MANHOLE 4 VF $321.00 $1,284.00 4 $1,284.00
--------------------------------------
Sub-Total of Previous Unit $22,939.00 $22,939.00
--------------------------------------
Tuesday,May 19,2020 Page 3 of 5
City Project Numbers 101900 DOE Number 1900
Contract Name HARRIS PARKWAY MEDICAL DEVELOPMENT Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 5/19/2020
Project Funding
Contract Information Summary
Original Contract Amount $189,499.00
Change Orders
Total Contract Price $189,499.00
Total Cost of Work Completed $189,499.00
Less %Retained $0.00
Net Earned $189,499.00
Earned This Period $189,499.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $189,499.00
Tuesday,May 19,2020 Page 4 of 5
City Project Numbers 101900 DOE Number 1900
Contract Name HARRIS PARKWAY MEDICAL DEVELOPMENT Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 5/19/2020
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors OATEN/ HORTON Contract Date
Contractor TRI DAL EXCAVATION&UTILITIES INC Contract Time 210 CD
540 COMMERCE ST Days Charged to Date 210 CD
SOUTHLAKE, TX 76092 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $189,499.00
Less %Retained $0.00
Net Earned $189,499.00
Earned This Period $189,499.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $189,499.00
Tuesday,May 19,2020 Page 5 of 5
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Harris Parkway Medical Development
PROJECT NUMBER: 101900
DOE NUMBER: N/A
WATER
PIPE LAID SIZE TYPE OF PIPE LF
C900 12" PVC 1100 LF
C900 8" PVC 45 LF
FIRE HYDRANTS: 2 VALVES(16"OR LARGER) N/A
PIPE ABANDONED SIZE TYPE OF PIPE LF
None.
DENSITIES: YES All Passed
NEW SERVICES: 1" Copper 18 LF
2" Copper 18 LF
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
SDR-26 8" PVC 140 LF
SDR-26 6" PVC 5 LF
PIPE ABANDONED SIZE TYPE OF PIPE LF
None.
DENSITIES: YES All Passed
NEW SERVICES: 6" PVC 5 LF
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth• 1000 Throckmorton Street•Fort Worth,TX 76012-6311
(817) 392-7941 •Fax: (817) 392-7845
AFFIDAVIT
STATE OF Texas
COUNTY OF Tarrant
Before me, the undersigned authority, a notary public in the state
and county aforesaid, on this day personally appeared Scott Langham,
Project Manager Of Tri Dal Utilities, known to me to be a credible person,
who being by me duly sworn, upon his oath deposed and said;
That all persons, firms, associations, corporations, or other
organizations furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of
Foil Worth has been paid in full;
That there are no claims pending for personal injury and/or
property damages;
On Contract described as;
Harris Parkway Medical Development City Project #: 101 900
BY
Scott Langham
Subscribed and sworn before me on this date 19th of May, 2020.
``,�tllllllllfr/r/r�
♦���� t�rr-H err/i
Orj�
�1`R Y pG• e,
Notary ublic - _0 o
Tarrant County, Texas
OF-it
06,06,20%"
rrrr r r r 1 I I 1 I I I t 1 N�1``
CONSENT OF OWNER ❑
SURETY COMPANY ARCHITECT ❑
TO FINAL PAYMENT CONTRACTOR o
AIA DOCUMENT G707 SURETY ❑
OTHER ❑ Bond 4107084150
PROJECT: Public Water.Sanitary Sewer,and Paving Improvements-Harris Parkway Medical Development-6840
Harris Parkway,Fort Worth,TX
TO(Owner): CONTRACT FOR:Construction
City of Fort Worth
1000 Throckmorton Street
Fort Worth,TX 76102 CONTRACT DATE:
CONTRACTOR:
Tri Dal Utilities, Ltd.
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above,the
Travelers Casualty and Surety Company of America
One Tower Square
Hartford,CT 06183 SURETY COMPANY,
on bond of
Tri Dal Utilities,Ltd.
540 Commerce St.
Southlake,TX 76092 CONTRACTOR,
hereby approves of the final payment to the Contractor,and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to
City of Fort Worth
1000 Throckmorton Street
Fort Worth,TX 76102 OWNER,
As set forth in the said Surety Company's bond
IN WITNESS WHEREOF,
the Surety Company has hereunto set its hand this 30th day of April,2020.
Travelers Casualty and Surety Company of America
Surety
Si alure of r111arJ�ed r •enla
Attest:
(.Seal) Eric Lesc , Witness Felix Nave'ar t,►++ r++►.,
Name ;�.• >i13to'k4! F�n cl
r�
AIA DOCUMENT G707•CONSENT OF SURETY COMPANY TO FINAL PAYMENT APRIl. 19701:DITIU '�11 .1
®1970 T1IE AME'RICAN INSTITUTE OF ARCHITEL I'S,1735 NEW YORK AVE.,NW WASI IINGTON,D.C. 24fe4 • .t`
NHINi+Ii Htt,N
TRAVELERS Travelers Casualty and Surety Company of America
Travelers Casualty and Surety Company
St.Paul Fire and Marine Insurance Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS:That Travelers Casualty and Surety Company of America,Travelers Casualty and Surety Company,and St.
Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut(herein collectively called the
"Companies"),and that the Companies do hereby make,constitute and appoint Felix Navejar,of Grapevine,Texas,their true and lawful Attorney-in-
Fact to sign,execute,seal and acknowledge any and all bonds,recognizances,conditional undertakings and other writings obligatory in the nature
thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons,guaranteeing the performance of contracts and executing or
guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
IN WITNESS WHEREOF,the Companies have caused this instrument to be signed,and their corporate seals to be hereto affixed,this 3rd day of February,
2017.
' ' � By:
e HAMR an, aor+rrt Robert L.Raney,Se or Vice President
�t rm
��
State of Connecticut
City of Hartford ss.
On this the 3rd day of February,2017,before me personally appeared Robert L.Raney,who acknowledged himself to be the Senior Vice President of
Travelers Casualty and Surety Company of America,Travelers Casualty and Surety Company,and St. Paul Fire and Marine Insurance Company, and
that he,as such,being authorized so to do,executed the foregoing instrument for the purposes therein contained by signing on behalf of the corporations
by himself as a duly authorized officer.
In Witness Whereof,I hereunto set my hand and official seal.
My Commission expires the 30th day of June,2021 ��j mA• C ��
*�* Mane C.Tetreault,Notary Public
This Power of Attorney is granted under and by the authority of the following \�•�//resolutions adopted by the Boards of Directors of Travelers Casualty and
Surety Company of America,Travelers Casualty and Surety Company,and St.Paul Fire and Marine Insurance Company,which resolutions are now in
full force and effect,reading as follows:
RESOLVED,that the Chairman,the President, any Vice Chairman,any Executive Vice President,any Senior Vice President, any Vice President, any
Second Vice President,the Treasurer,any Assistant Treasurer,the Corporate Secretary or any Assistant Secretary may appoint Attorneys-in-Fact and
Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with
the Company's name and seal with the Company's seal bonds, recognizances,contracts of indemnity, and other writings obligatory in the nature of a
bond,recognizance,or conditional undertaking,and any of said officers or the Board of Directors at any time may remove any such appointee and revoke
the power given him or her;and it is
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice
President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company,provided that each such delegation
is in writing and a copy thereof is filed in the office of the Secretary;and it is
FURTHER RESOLVED,that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional
undertaking shall be valid and binding upon the Company when(a)signed by the President,any Vice Chairman,any Executive Vice President,any Senior
Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant
Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary;or(b)duly executed(under seal,if required)by
one or more Attomeys-in-Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one or more
Company officers pursuant to a written delegation of authority;and it is
FURTHER RESOLVED,that the signature of each of the following officers:President,any Executive Vice President,any Senior Vice President,any Vice
President,any Assistant Vice President,any Secretary,any Assistant Secretary,and the seal of the Company may be affixed by facsimile to any Power
of Attorney or to any certificate relating thereto appointing Resident Vice Presidents,Resident Assistant Secretaries or Attomeys-in-Fact for purposes only
of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof,and any such Power of Attorney or certificate bearing
such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by such facsimile
signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached.
I, Kevin E. Hughes, the undersigned, Assistant Secretary of Travelers Casualty and Surety Company of America, Travelers Casualty and Surety
Company, and St. Paul Fire and Marine Insurance Company,do hereby certify that the above and foregoing is a true and correct copy of the Power of
Attorney executed by said Companies,which remains in full force and effect.
Dated this 30th day of April,2020. ������ ��,SUS fTf�''••,