HomeMy WebLinkAboutOrdinance 24189-05-2020 Ordinance No. 24189-05-2020
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER AND SEWER CAPITAL PROJECTS FUND IN THE AMOUNT OF $659,327.00,
TRANSFERRED FROM AVAILABLE FUNDS IN THE WATER AND SEWER FUND, FOR
THE PURPOSE OF FUNDING THE SANITARY SEWER MAIN M-280-B REHABILITATION
PROJECT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE
CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2019-2020 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of$659,327.00,transferred from available funds in the Water
and Sewer Fund, for the purpose of funding the Sanitary Sewer Main M-280-B Rehabilitation Project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 23835-09-2019 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: PWt
DBlack(May 29,202012:59 CDT) �
Douglas W Black Mary J. Kayser
Sr Assistant City Attorney City Secretary
ADOPTED AND EFFECTIVE: May 5, 2020
OF F®��,'
C;
:Z
MAYOR AND COUNCIL COMMUNICATION MAP
60SSM28OB90I N P2B-SJ LOU IS
PA
E 1ST S_T
V.
i ter'
U)I
.O� 7. ry.. r }. " '�' • yam,�L�_ � ; 'J.�L-� /
� of
Wr
J
. � r
AY PARK p PROJECT '
30
TH
FORTWOR
7 � • y iq a
SL 2020
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 05/05/20 M&C FILE NUMBER: M&C 20-0309
LOG NAME: 60SSM280B90INP2B-SJLOUIS
SUBJECT
Authorize Execution of a Contract with S.J.Louis Construction of Texas, Ltd.,in the Amount of$5,591,888.00 for Sanitary Sewer Main M-280-B
Rehabilitation Project Located in Gateway Park, Provide for Additional Project Costs for a Project Total in the Amount of$6,251,215.00 and Adopt
Appropriation Ordinance(COUNCIL DISTRICT 4)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Appropriation Ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects
Fund in the amount of$659,327.00,transferred from available funds within the Water and Sewer Fund;and
2. Authorize the execution of a contract with S.J.Louis Construction of Texas, Ltd.in the amount of$5,591,888.00 for Sanitary Sewer Main M-
280-B Rehabilitation project located in Gateway Park(City Project No. C01286).
DISCUSSION:
This project will provide for the rehabilitation and replacement of a severely deteriorated 1,430 linear foot segment of sanitary sewer main M-280-
B and related appurtenances located within Gateway Park.
The project was advertised for bid on January 30,2020 and February 6,2020 in the Fort Worth Star-Telegram.On March 5,2020,the following
bids were received:
Bidder I --Amount Time of
Completion
S.J.Louis Construction of Texas, 465 Calendar
Ltd $5,591,888.00 Days
Belt Construction, Inc. $5,999,926.00
Mountain Cascade of Texas,LLC11$6,821,616.0011
Most State Revolving Loans are granted for construction contracts only;as such,additional appropriations of$659,327.00($491,570.00 for
construction staking, project management,material testing and inspection,and$167,757.00 for project contingencies)are needed from the Water
and Sewer Fund.
This project will have no impact on the Water Department's operating budget when completed.Construction is expected to start in July 2020 and
be completed by October 2021.The project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
Appropriations for Sanitary Sewer Main M-280-B Rehabilitation,are as depicted below:
Fund Existing Additional Project Total*
Water&Sewer-6a�pitalAppropriations Appropriations
Projects Fund 56002 11
$123,380.0011
$659,327.00 $782,707.00
1Water/Sewer Bond $750,000.00 $0.00 $750,000.00
2016 Fund 56005
Sewer Capital Legacy $1,852,243.00 $0.00 $1,852,243.00
nd 59607
Water&Sewer Bond
2017 Fund 56013- $0.00 $5,591,888.00 $5,591,888.00
P00100-CWSRF
Series 2017
Project Total $2,725,623.00 $6,251,215.00 $8,976,838.00
*Numbers rounded for presentation purposes.
M/WBE Office-S.J. Louis Construction of Texas, Ltd.is in compliance with the City's BDE Ordinance by committing to seven percent MBE
participation on this project.The City's MBE goal on this project is seven percent.
The project is located in COUNCIL DISTRICT 4.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds will
be available in the Water& Sewer Capital Projects(W&S Capital Projects) Fund. Prior to an expenditure being incurred,the Water
Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by. Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Walter Norwood 5026