HomeMy WebLinkAboutContract 44649-A5 r.
CSC No.44649-A5
2020 AMENDMENT No.5
0 O�YFi
Gv 13V S C�H �Rv TO CITY SECRETARY CONTRACT No. 44649
WHEREAS, the City of Fort Worth (CITY) and Wade Trim, Inc. ,
(ENGINEER) made and entered into City Secretary Contract No. 44649, (the
CONTRACT) which was authorized by M&C C-26320 on the 9th day of July, 2013
in the amount of $ 524, 244 . 00; and
WHEREAS, the CONTRACT was subsequently revised by:Amendment Number 1
in the amount of $47, 710. 00 which was administratively authorized on May
12, 2016, Amendment Number 2 in the amount of $574, 992 . 00 which was
authorized by M&C #C-28254 on June 6, 2017, Amendment Number 3 in the
amount of $836, 860. 00 which was authorized by M&C #C-29087 on May 17,
2019, and Amendment Number 4 in the amount of $77, 415 . 00 which was
administratively approved on December 27, 2019; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Westcliff Drainage Improvements Project; and
WHEREAS, it has become necessary to execute Amendment No. 5 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and
incorporated herein. The cost to City for the additional design services
to be performed by Engineer totals $125, 050. (See Attached Funding
Breakdown Sheet, Page -4-)
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $2,186,271 .
3 .
Westcliff Drainage Improvements Ph.1 CPN C01669
Wade Trim,Inc.
CSN:44649-Amendment No.5 OFFICIAL 4GoOlds 9
CI' SECRETARY
T V0TRH,
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED:
City of Fort Worth ENGINEER
Wade Trim, Inc.
DAhg BU('Ahdof-f
Dana Burghdoff un3,2020 16:41 CDT)
Dana Burghdoff Shawn W. Keough
Interim Assistant City Manager Senior Vice President
DATE: Jun 3, 2020 DATE: May 13, 2020
APPROVAL RECOMMENDED:
William Johnson
Director, Transportation and Public Works Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements .
Mike Bennett(Jun 2,202016:26 CDT)
Mike Bennett
Project Manager
M
OFFICIAL R Cty9 E,
Westcliff Drainage Improvements Ph.1 CPN C01669 CITY SECRETARY
Wade Trim,Inc. p�
CSN:44649-Amendment No.5 FT WORTH,T
1
APPROVED AS TO FORM AND LEGALITY: M&C: 20-0336
a
- Date: 5/19/20
Mack(Jun 3,202010:02CDT) NV lags: aoao-blbag°I
Douglas W. Black
Assistant City Attorney
ATTEST: �R 1
1-fol
Mary J. Kayser
City Secretary 41
Westcliff Drainage Improvements Ph.1 CPN C01669 ®������ �?� °
Wade Trim,Inc. e
REC
CSN:44649-Amendment No.5 CIS' SECRETARY y
4
FT WORTH,;7X
FUNDING BREAKDOWN SHEET
City Secretary No. 44649
Amendment No. 5
Department Fund-Account-Center Amount
TPW 52002-0200431-5330500-001669-0O2830 $125, 050 . 00
Total : $125, 050 . 00
Westcliff Drainage Improvements Ph.1 CPN C01669
Wade Trim,Inc.
CSN:44649-Amendment No.5
WADE
TBPE Firm No. 4
TBPLS Firm No.10194374374
TRIM Wade Trim,Inc.
IN3575 Lone Star Circle,Suite 410•Fort Worth,TX 76177
682.237.7718•www.wadetrim.com
March 19, 2020
City of Fort Worth
Capital Delivery Division/TPW
200 Texas St.
Fort Worth, TX 76102
Attention: Ms. Linda Young, PE, Engineering Manager
Mr. Mike Bennett, PE, Project Manager
Re: Westcliff Drainage Improvements, Phase 1
Proposal for Additional Water and Sewer Design Services
Dear Ms. Young & Mr. Bennett:
As a follow-up to previous conversations which started on January 8, 2020, at a joint project
meeting with the City's Storm Water Division and Water Department, and most recently the
conversation between Andy McCune of our office and Linda Young of the City on March 10,
2020, we are hereby submitting this amendment proposal request for additional water and
sanitary sewer design services for your consideration.
At the January 8, 2020 joint meeting, the Water Department and the Storm Water Division
discussed and confirmed that any required water and sewer relocations necessitated by the
Westcliff Drainage Improvements in Phase 1 would need to be designed through the Storm
Water Division. At the conclusion of that meeting, Wade Trim was asked to prepare a preliminary
concept design for the water and sanitary sewer relocations, as well as a detailed cost estimate
that could be reviewed and used to plan and understand the necessary work as well as provide a
better overall project cost estimate for the City.
As the City is aware, Wade Trim's Amendment No. 3 to City Contract No. 44649 did not include
utility relocation design services and identified these as additional services that were not
included in Wade Trim's existing scope of services. Specifically, language excluding these
services stated: "Plans, specifications, and estimates of additional infrastructure, including but
not limited to water, sanitary sewer, streetlights and signal." It is our understanding that the
Water Department was going to use their own subconsultant (EJES)to complete any water and
sanitary sewer relocation designs.
Please note that Wade Trim acted on the City's direction and delivered a preliminary concept
design and revised cost estimate, including an initial estimate for additional design engineering on
January 17, 2020. These drawings were reviewed with the City's leadership team on February 4,
2020. Since that time, at the encouragement and in cooperation with the City's leadership team,
Wade Trim has continued to perform the following tasks in order to keep the project moving
toward the desired early June out to bid date (or sooner):
• Requested and reviewed available CCTV of the existing sanitary sewers in the vicinity of
the project area, including the outfall area downstream of Trail Lake, along Manderly
Place and along the lateral sanitary sewers that exist in the rear and side yards that
serve the neighborhood.
City of Fort Worth
March 19,2020
Page 2
• Reviewed record drawings and compared them to the CCTV to verify the locations of
sanitary service connections related to homes along the proposed route of the drainage
improvements to ensure feasibility of sewer relocations.
• Reviewed record drawings and the plans prepared by the Water Department consultant
(EJES)to assist and determine where the Church property connects to the City's
sanitary sewer system.
Identified a quote for additional SUE Level A locations based on input and suggestions
provided by the City's Storm Water and Water Department staff. (Please note that we
have reviewed these locations with the Storm Water project management staff, received
their concurrence, updated a few locations, and are authorizing our sub consultant
(RIOS) to begin this work in order to collect this information as soon as possible.)
• Initiated the detailed design of the necessary sanitary sewer and water main relocations
and are planning to re-submit 60% plans to the City on March 20, 2020, including water
and sanitary sewer improvements.
Water and sanitary sewer relocations were not anticipated to be needed when Wade Trim's
project scope and fee for Amendment No. 3 was envisioned just one year ago, based on the
City's desire at that time for the project to be a parallel relief sewer system located in key areas
outside the City right-of-way. Later decisions to eliminate portions of the old drainage system and
place larger box culverts within the City right-of-way have created the need to relocate portions
of the City's water and sanitary sewer system in order to complete the design. Amendment No. 4
negotiations for the redesign of the storm system occurred prior to Wade Trim being aware that
the Storm Water Division would be responsible for the design of necessary relocations.
In the revised table that follows, we have provided an explanation of tasks required and their
proposed budgets. A detailed level-of-effort, consistent with our previously approved Amendments
No. 3 and 4, is attached for reference. Proposed tasks for Amendment No. 5 are shown in blue
highlights on the attached detailed level-of-effort.
Westcliff Phase 1 Proposed
Additional Water&Sewer Design Services (Proposed Amendment No. 5) Budget
Additional Wade Trim Water&Sewer Design Services
Additional project management and coordination with the Water Department $5,400
(Task 1 —Project Management)
Additional coordination with our subconsultant(RIOS) performing the additional $ 1,440
SUE Level A work (Task 2—Concept Design 30%)
Effort for preparation of concept design and detailed cost estimates per City request $24,220
at January 8, 2020 joint meeting 9 (Task 2—Concept Design 30%)
Water&Sewer 30% Review Meeting (Feb 5, 2020)including CCTV review $ 10,400
(Task 2—Concept Design 30%)
60% Design for Outfall Sanitary Sewer(if determined to be necessary) $4,000
60% Design for Manderly Place Sanitary Sewer Relocation $6,060
60% Design for Suffolk Sewer Crossing Box Culvert $2,000
60% Design for Trail Lake/Manderly Place Water Main Relocations $6,060
60% Design for Anita/Suffolk Water Main Relocations $6,060
(Task 3— Preliminary Design (60%)
City of Fort Worth
March 19,2020
Page 3
90%Water System Design (all elements described above) $7,860
90% Sanitary Sewer Design (all elements described above) $7,860
90% Review Meeting with Water Department $3,320
(Task 4— Final Design 90%- 100%)
100%Water and Sanitary System Design—Effort repurposed from previous $0
Amendment No. 4 Authorization—"incorporate water department plans for
additional conflicts"
(Task 4— Final Design 90%- 100%)
Total Wade Trim Additional Water&Sewer Design Services $84,680
Additional Subconsultant Services Related to Water&Sanitary Sewer Design
Additional SUE Level A(RIOS) $ 36,700
Wade Trim— 10% mark-up on Additional Services $3,670
Total Subconsultant Additional Water&Sewer Design Services $40,370
Total Proposed Additional Water&Sewer Design Services Budget $ 125,050
We appreciate the City's consideration of this request. We have attempted to keep this letter
succinct, yet descriptive. Wade Trim is committed to continuing our work to keep this project
moving forward. We are available to answer any questions and ask that the City treat us fairly
as a result of the significant changes to the preliminary alignment that have occurred during this
project. We are proud of our role working with the City on this project and are committed to
helping the City complete it. Thank you for the opportunity to submit this amendment proposal
request.
Very truly yours,
Wade Trim, Inc.
for al
Karen Stafford-Brown, PE Andrew 4J McCune, PE
Senior Project Manager President/Chief Executive Officer
KSB:AJM:ka
FTW 2004-04X
Westcliff Addtl Water Sewer Design Prop Ltr 3-19-20.docx
Enclosure
cc: Mr. Dillon Johns, Deputy Project Manager
Westcliff Amendments No. 3 and No. 4 as Approved Page 1 of
Amendment No. 5 Additional Services Proposal - LOE Breakdown
Submitted on March 19, 2020
WESTCLIFF AMENDMENT No.5(highlighted items) Struct Hyd Civil Tech Tech Sr Tech Proj Sr WT WT
Phase 1 Water&Sewer Improvements Design(0 to 100%)
PE PE PE EIT CADD-GIS Admin Specs Mgr Eng Labor Labor
Activity Name 210 200 180 145 100 75 200 200 250 Hours Cost
1.1 Managing the Team
Internal Project Management 0 0 96 0 0 0 0 160 80 336 $69,280
Pre-Submittal QA/QC of Plans 60/90/100Bid 0 0 24 0 0 0 0 12 12 48 $9,720
Pre-Submittal QA/QC of Specs 60/90/100/Bid 0 0 24 0 0 0 0 12 12 48 $9,720
1.2 Communications and Reporting
Project Kick-Off Meeting 0 0 4 0 0 0 0 4 0 8 $1,520
Monthly Project Update Meefin s/Calls(Design-9 0 0 18 0 0 0 0 14 14 45 $9,315
Weekly Project Update Meefin s/Calls 1 additional call per month 0 0 0 0 0 0 0 4 4 8 $1,800
Monthly Project Update Meetings/Calls Construction-27 0 0 54 0 0 0 0 41 41 1 135 $27,945
Monthly Invoices(Design-9 0 0 45 0 0 0 0 0 0 1 45 $8,100
Monthly Invoices Construction-L71 0 0 135 0 0 0 0 1 0 0 135 $24,300
Monthly MWBEReports(Design-9 0 0 0 0 0 9 0 5 0 14 $1,675
Monthly MWBE Reports Construction-27 0 0 0 0 0 27 0 13 0 40 $4,625
Monthly P6 Schedule Updates 9 0 0 9 0 0 0 0 6 0 15 $2,820
Conduct Plan Review Meetings(60/90/100) 0 0 12 0 0 0 0 12 0 24 $4,560
Coordination Meefin s/Calls w/Water Department 0 0 8 0 0 0 0 8 0 16 $3,040
Ad itiional Coordinaton with Water Department 12 12 24 $5,400
Coordinaton Meetings/Calls w/Streets Division 0 0 8 0 0 0 0 8 0 16 $3,040
Coordination Meefin s/Calls w/Parks Department 0 0 8 0 0 0 0 8 0 16 $3,040
Task 1-Project Management 0 0 445 0 0 36 0 318 174 973 $189,900
2.2-Drainage Computations If Authorized
Step Pool Channel Improvements Layout 0 2 8 0 16 0 0 0 6 32 $4,940
Step Pool Hydraulics 0 8 16 6 0 0 0 2 0 32 $5,750
2.3-Subsurface Utility Engineering
Coordination 0 0 12 0 0 0 0 4 0 16 $2,960
Ad itional Coordinaton 8 8 $1,440
Subconsultant Budget at Bottom
2.4-Water&Sewer Concept Design and Estimating
Effort for Concept Design and Esfimates Jan 8th through 17th 34 30 4 48 15 131 $24,220
Water&Sewer 30%Review Meeting,Preparation&CCTV Review 4 24 16 12 56 $10,400
Task 2-Concept Design 300% 0 10 82 60 20 0 0 70 33 275 $49,710
3.1-Development of Preliminary Design Drawings
Include Plat/Easement Information in Plans 0 0 6 12 0 0 0 0 0 18 $2,820
Include Environmental Assessment Information in Plans 0 0 16 16 0 0 0 0 0 32 $5,200
60%Civil Design-Address City Comments 0 8 60 80 0 0 0 8 16 172 $29,600
60%Civil Design-Add Dimensions from ROW,etc. 0 0 4 12 0 0 0 0 0 16 $2,460
60%Civil Design-Finalize Inlet Calculations 0 24 16 24 0 0 0 2 4 70 $12,560
60%Civil Design-Revise Inlet Lateral designs 11 of 13 changed) 0 4 0 22 12 0 0 2 4 44 $6,590
60%Civil Design-Finalize Calculations Plans Presentation 0 24 12 8 0 0 0 0 4 48 $9,120
60%Civil Design-Add HGL's to Profiles 0 4 12 4 0 0 0 0 2 22 $4,040
60%Civil Design-Outfall Improvements 0 8 12 24 0 0 0 8 8 60 $10,840
60%Civil Design-Update Downstream Assessment 0 1 30 16 1 8 1 0 0 1 0 6 1 4 64 1 $12,240
60%Civil Design-Construction Details 0 0 4 16 0 0 0 0 4 24 $4,040
60%Civil Design-Traffic Control Plan 0 0 2 8 0 0 0 8 0 18 $3,120
60%Civil Design-Detour Plan 0 0 2 8 0 0 0 8 0 18 $3,120
60%Civil Design-Traffic Control Details 0 0 2 8 0 0 0 4 0 14 $2,320
NO 6 Deis n -Outfall Sewer 8 8 2 4 22 $4,000
60 6 Design-Manderl Sewer 8 16 4 6 34 $6,060
CO 6 Design-Suffolk Cross'n 4 4 1 2 11 $2,000
60 6 Deis n-Traillake/Many WM 1 8 16 1 4 6 34 $6,060
60M Design -Anita/Suffok WIVI 8 16 4 6 34 $6,060
60%Structural Des!an_ 30 0 2 20 1 20 0 0 2 2 76 1 $12,460
Additional 60%Structural Design 1 additional junction structures 10 0 1 7 7 0 0 1 1 27 $4,445
60%Specs/Project Manual 16 0 18 22 0 0 5 13 4 78 $14,390
Update OPCC 3 0 6 0 0 0 0 1 1 11 $2,160
Update Project Decision Log 0 0 2 0 0 0 0 0 0 2 $360
3.2-Geotechnical Investigation/Pavement Design
Coordinate Pavement Cores Needed 0 0 2 2 0 0 0 2 1 7 $1,300
Incorporate Data from Cores into Pavement Repair Design 0 1 0 4 6 0 0 1 0 2 0 12 1 $1,990
Full Pavement Replacement Design 0 0 96 0 40 0 0 2 2 140 $22,180
Coordinate w/Streets Division for POL/MOL Recommendations 0 0 1 4 0 1 0 0 0 4 0 8 $1,520
Additional coordination w/Streets Division for Pavement Replacement 0 0 2 0 0 0 2 0 4 $690
3.3-Constructability Review
Schedule&Attend Constructability Review Meeting 0 0 4 0 0 0 0 4 0 8 $1,520
Prepare&Submit Meefin Notes/Minutes/Comments 0 0 4 0 0 0 0 1 1 6 $1,170
3.4-Public Meeting
Prepare Exhibits 0 2 2 6 0 0 0 0 1 11 $1,880
Attend Public Meeting 0 0 5 0 0 0 0 5 0 10 $1,900
3.5-Utility Clearance
Communicate w/City Staff Regarding Potential Issues o 0 4 2 0 0 0 1 2 1 9 v1 i
Westcliff Amendments No. 3 and No. 4 as Approved Page 2of3
Amendment No. 5 Additional Services Proposal - LOE Breakdown
Submitted on March 19, 2020
Create&Upload DWF Files to Buzzsaw 0 0 2 6 0 0 0 0 0 8 $1,230
Task 3-Preliminary Design 600/6 59 104 356 383 79 0 5 102 84 1,172 $203,105
4.1-Pre-Final Design Drawings 90%
90%Civil Design-Address City Comments 0 0 60 80 0 0 0 6 8 154 $25,600
90 6 Water System Desi n 12 20 4 8 44 $7,860
90 a Sewer System Design 12 20 1 4 1 8 1 44 $7,860
90 6 Review Meeting 4 8 4 16 $3,320
90%Structural Design 18 0 0 0 0 0 0 0 0 18 $3,780
Additional 90%Structural Design 6 0 0 0 0 0 0 0 0 6 $1,260
90%Specs/Project Manual 6 0 46 6 0 0 31 31 4 124 $23,810
Check Water Department Plans for Coordination 0 0 16 6 0 0 0 4 4 30 $5,550
Coordinate w/Streets Division for Final Limits 0 0 2 2 0 0 0 2 0 6 $1,050
Update OPCC 0 0 4 0 0 0 0 1 1 6 $1,170
Update Project Decision Log 0 0 2 0 0 0 0 0 1 3 $610
4.2-Final Design Drawings 100%
100%Civil Design-Address City Comments 0 0 30 40 0 0 0 4 8 82 $14,000
10 k Water System Design-effort repurposed from"incorporate water 0 $0
de t plans for additional conflicts"
10 k Sewer System Design-effort repurposed from"incorporate water 0 $0
de t plans for additional conflicts"
100%Structural Design 18 1 0 1 0 0 1 0 0 1 0 1 0 0 1 18 $3,780
Additional 100%Structural Design 6 0 0 0 0 0 0 0 0 6 $1,260
Check Water Department Plans 0 0 16 6 0 0 0 4 4 30 $5,550
Incorporate Water Department Plans 0 0 24 36 0 0 0 16 16 92 $16,740
Incorporate Water Department Plans-additional conflicts 0 0 30 40 0 0 0 14 16 100 $18,000
Coordinate w/Streets Division for Final Limits 0 0 2 2 0 0 0 2 0 6 $1,050
Incorporate Streets Division Specs 0 0 8 16 0 0 0 4 2 30 $5,060
Incorporate Water Department Specs 0 0 24 24 0 0 0 16 4 68 $12,000
100%Specs/Project Manual 6 0 24 24 0 0 16 16 4 90 1 $16,460
Update OPCC 0 0 8 4 0 0 0 2 2 16 $2,920
Update Project Decision Log 0 0 4 0 1 0 0 1 0 0 1 2 6 $1,220
Create&Upload DWF's of All Plans 0 0 2 8 0 0 0 0 0 10 $1,520
Task 4-Final Design 90-1000/6 60 0 330 334 0 0 47 138 96 1,005 $181,430
5.1-Bid Support
Sell Contract Documents and Maintain Plan Holders List 0 0 4 0 0 16 0 8 0 28 $3,520
Log&Answer Bidder's Questions Issue Addenda 4 0 40 0 0 0 0 12 8 64 $12,440
Attend Pre-bid Conference 0 0 4 0 0 0 0 4 0 8 $1,520
Attend Bid Opening 0 0 4 0 0 0 0 4 0 8 $1,520
Tabulate Bids and Recommend Award 0 0 8 4 0 0 0 4 0 16 $2,820
Issue Conformed Contract Documents 0 0 4 4 0 0 0 4 4 16 $3,100
5.2-Final Design Drawings
PDF Drawin s 0 0 12 0 0 0 0 8 0 20 $3,760
DWF Drawings 0 0 8 0 0 0 0 2 0 10 $1,840
DWG Sheet File Drawings Bound 0 0 8 0 0 1 0 0 1 2 0 1 10 $1,840
Task 5-Bid Phase Services 4 0 92 8 0 16 0 48 12 180 $32,360
6.1-Construction Support
Attend Preconstruction Conference 0 0 4 0 0 0 0 0 4 8 $1,720
Attend Public Meeting 0 0 4 0 0 0 0 0 4 8 $1,720
Project Site Visits 0 0 42 0 0 0 0 48 0 90 $17,160
Submittal Review 16 16 28 0 0 0 0 40 8 108 $21,600
Request for Information/Change Order Review 0 0 40 0 0 0 0 40 24 104 $21,200
Final Walk Through and Punch List 0 0 16 0 0 0 0 16 8 40 $8,080
Ph.2B Const.Su pp.Used for Cox McLain+Management 0 0 20 20 0 20 20 18 16 114 $19,600
6.2-Record Drawings
Create Record Drawings from Construction Information 0 0 12 24 0 0 0 0 2 38 $6,140
Create&U load New PDF&DWFs o 1 0 4 8 1 0 0 0 0 1 13 $2,130
Task 6-Construction Phase Services T&M 16 16 170 52 0 20 20 162 67 523 $99,350
7.2-ROW/Easement Preparation&Submittal
Finalize Easement Documents 0 0 2 0 0 0 0 2 2 6 $1,260
Flood lain Easement Documents 0 0 5 0 0 0 0 5 0 10 $1,900
Coordination w/Survey Subconsultant 0 0 2 0 0 0 0 2 0 4 $760
ditional coordination w/Survey Suboonsultant for floodplain easements 0 0 3 0 0 0 0 3 0 6 $1,140
7.3-Temporary Right of Entry
Prepare,Mail,&Obtain Temporary ROE from Landowners 0 0 2 0 0 0 0 2 0 4 $760
7.4-Parks Conversion
Finalize Limits of Conversion Area,Access,etc. 0 0 4 2 0 0 0 2 2 10 $1,910
Coordination w/Survey Subconsultant 0 0 2 0 0 0 0 2 0 4 $760
Prepare Exhibits 0 0 4 8 0 0 0 2 0 14 $2,280
Attend Meetings 0 0 10 0 0 0 0 0 0 10 $1,800
Task 7-ROW Easement 0 0 34 10 0 0 0 20 4 68 $12,570
8.1-Design Surve
Westcliff Amendments No. 3 and No. 4 as Approved Page 3of3
Amendment No. 5 Additional Services Proposal - LOE Breakdown
Submitted on March 19, 2020
Coordination w/Survey Subconsultant 0 0 16 0 0 0 0 12 4 32 $6,280
Task 8-Survey 0 0 16 0 0 0 0 12 4 32 $6,280
9.1-SWPPP
iSWM Construction Plan 0 0 8 12 0 0 0 2 2 24 $4,080
Preliminary iSWM Checklist 0 0 2 0 0 0 0 0 1 3 $610
Final iSWM Checklist 0 0 2 0 0 0 0 0 1 3 $610
9.2-Environmental Services
Coordinate w/Environmental Suboonsultant 0 0 24 0 0 0 0 12 4 40 $7,720
Examine Alternatives 0 8 10 10 0 0 0 2 2 32 $5,750
Prepare Exhibits,Calculations 0 12 20 20 0 0 0 2 2 56 $9,600
Anend Meetings 0 0 8 0 0 0 0 8 0 16 $3,040
Task 9-Permitting 0 20 74 42 0 0 0 26 12 174 $31,610
TOTAL WT Labor Budget 139 150 1599 889 99 72 72 896 486 4402 $806,315
Subconsultant Budgets
RIOS-SUE Survey 2.2.1 $3,700
RIOS-SUE B,C,D 2.2.1 $12,500
Additional SUE Level A RIOS $36,700
RIOS-SUEA 2.2.1 2500
SUE Sub-Consultant Total RIOS $55,400
PK-To oSue 8.1 $10,500
PK-Property Survey 7.2 $14,400
PK-Meets&Bounds for Parks Conversion 7.4 $4,000
PK-Tree Survey 7.4 $2,500
PK-Flood lain easement acquisition exhibits 5 $12,500
PK-Bidding Assistance 5.1.5 and 5.1.6 $10,000
PK-Construction Assistance 6.1.3 and 6.14 10 000
Survey Sub-Consultant Total Pacheco Koch $63,900
Westra-H raulic Computations 3.1 $11,500
Westre-QA/QC&Calculations 3.1&4.1 39 000
Hydrology Sub-Consultant Total estra $51,200
Phase 2B Tunnel Inspection&Construction Phase Services $14,000
Additional Phase 2B Tunnel Inspection&Construction Phase Services 000
Tunnel Inspection&Construction Phase Services Sub-Consultant $18,000
Total Schnabel
AGG-Pavement Cores $3,850
AGG-Soil Type Samples R 295
Geotech Sub-Consultant Total AGG $5,145
Total Sub-Consultant Budget- $193 645
10%Sub Markup-original $14,045
10%Markup on Additional suboonsultant services $1,650
10%Markup on Additional suboonsultant services $3,670
10%Sub Markup $19,365
WT Expense Budget $20,000
Total $1,039,325
Amendment 3 836 860
Amendment 4 $77 415
Amendment 5(Water&Sewer Design Services 125 050
Westcliff Amendment No. 5
Prime and Subconsultants Breakdown
3/19/20
Fee %of Total SBE
Amendment 5 (Water
&Sewer Design
Services) Total $ 125,050 100%
Prime Consultant Wade Trim $ 88,350 71%
Subconsultants The Rios Group, Inc. $ 36,700 29% X*
*Compliance memo issued by City of Fort Worth 4/21/20:
"Compliance with the City's Business Diversity Enterprise (BDE) Ordinance has been achieved
by the following method: Wade Trim&Associates, Inc. is in compliance with the City's BDE
Ordinance by committing to an overall 13% SBE participation on this project exclusive of
amendment No. 5."
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 05/19/20 M&C FILE NUMBER: M&C 20-0336
LOG NAME: 20SW WESTCLIFF STORM DRAIN AMENDMENT#5
SUBJECT
Authorize Execution of Amendment No.5 to City Secretary Contract No.44649,an Engineering Agreement with Wade Trim, Inc.,in the Amount of
$125,050.00 for Additional Engineering Services for the Westcliff Drainage Improvements Project,Thereby Revising the Total Contract Amount to
$2,186,271.00(COUNCIL DISTRICTS 3 and 9)
RECOMMENDATION:
It is recommended that the City Council authorize the execution of Amendment No.5 to City Secretary Contract No.44649,an engineering
agreement with Wade Trim, Inc., in the amount of$125,050.00 for additional engineering services for the Westcliff Drainage Improvements project,
thereby revising the total contract amount to$2,186,271.00(City Project No.C01669).
DISCUSSION:
On July 9,2013,by Mayor&Council Communication(M&C)C-26320,the City Council authorized an Engineering Agreement with Wade Trim,
Inc., in the amount of$524,244.00 for engineering analysis and cost-benefit evaluation of capital improvement alternatives to mitigate flood risks in
the Westcliff neighborhood. The engineering assessment determined that an enlarged pipe system was the most effective alternative to
mitigate the flood risk.
It was decided that a phased approach to construction would be used. TPW Stormwater took advantage of opportunities to partner with
other groups within the City to construct the project in non-linear phases,thus,construction of Phase 2A has been completed and construction of
Phase 2B is underway. It is expected that the construction project for Phase 1 will be awarded in Fall of 2020.
The purpose of the design amendment recommended by this M&C is to identify and resolve any utility conflicts that may exist with the revised pipe
alignment for Phase 1. Previous amendments to the design agreement are as follows:
Contract Description Amount No. Approved
Initial Analysis&Cost benefit evaluation of
Contract phased projects in the Westcliff $524,244.00 C-26320 7/9/2013
CS-44649 Neighborhood and Design of Phase 2A
F
ndment Construction Phase Services for Phase 2A $47,710.00 Administrative 5/12 220161
Amendment Design and Construction Phase Services for
No.2 Phase 2B and Conceptual Design for Phase $574,992.00 C-28254 6/6/2017
1
Amendment Design and Construction Phase Services for �,860.00 C-29087 5/17/2019
No.3 Phase 1
Amendment Design Phase Services for Phase 1 for
No.4 Alternative Pipe Alignment $77,415.00 Administrative 12/24/2019
FNo5
dment Utility Conflict Resolution for Phase 1 L
125,050.00 Pending Pending
EContract:F
$2,186,271.00171
Wade Trim, Inc., proposes to perform the engineering services described for a lump sum fee of$125,050.00. Staff considers the fee to be fair
and reasonable for the scope of services proposed. Authorizations provided with this M&C will result in no additional annual operating impacts to
the Stormwater operating budget.
Funding for this amendment is being provided from the Stormwater Capital Projects Fund.
M/WBE Office:Wade Trim&Associates, Inc.is in compliance with the City's BDE Ordinance by committing to an overall
13%SBE participation on this project exclusive of amendment No.5.
The Westcliff Drainage Improvements project is located in COUNCIL DISTRICTS 3 and 9.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget,as previously appropriated,in the Stormwater Capital
Projects Fund Wescliff Drainage project to support the approval of the above recommendation and execution of the amendment. Prior to any
expenditure being incurred,the Transportation&Public Works Department has the responsibility to validate the availability of funds.
Submitted for City Manager's Office by. Dana Burghdoff 8018
Originating Business Unit Head: William Johnson 7801
Additional Information Contact: Mike Bennett 7891