HomeMy WebLinkAboutOrdinance 24231-06-2020 Ordinance No. 24231-06-2020
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER AND SEWER CAPITAL PROJECTS FUND IN THE AMOUNT OF $606,457.00,
TRANSFERRED FROM AVAILABLE FUNDS IN THE WATER AND SEWER FUND, FOR
THE PURPOSE OF FUNDING THE SANITARY SEWER REHABILITATION, CONTRACT
103 PROJECT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS
ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES
IN CONFLICT HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2019-2020 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of$606,457.00, transferred from available funds in the Water
and Sewer Fund, for the purpose of funding the Sanitary Sewer Rehabilitation, Contract 103 Project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 23835-09-2019 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
0141P�f�
Douglas W Black Mary J. Kayser
Sr Assistant City Attorney City Secretary
ADOPTED AND EFFECTIVE: June 4, 2020
of FO,4y
was
4
MAYOR AND COUNCIL COMMUNICATION MAP
60SSRC103-CRIADO
N r- 'w.Uj
cc I_ W I if pUS T I 2 --� — z
LIJ - ` �+I . �r 4 U]OLE C7
r z I ? -
,.s
1
� _
w E1STST _ j m
� �
> . r. T_
cp
CMEPAULT STLTST_ .CH=VA t- -* 4TH. TJ+ 44THST-J.
�t
I
-
1�
AM
b
y JID .fir '`
"GALVEZ AVE- > G_ALV•EZ XVE ' t-
c:
LrLI
L_j
wbow
71
ElNI AVE ENNIS A►IE _ T, k
L_AALLE ST
r I r J u
L� _FINLEIf$T rrr. y 'uj
FINLEVI T
CI7 Il VAN MORN AVE
VAN HC'R A1�E '
i
J + A •y
i kv UTTMAN ST-'.
�w Fri
- — d4%p SYLVAN( VE Y w
FOuWoRTH
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/02/20 M&C FILE NUMBER: M&C 20-0379
LOG NAME: 60SSRC103-CRIADO
SUBJECT
Authorize the Execution of an Engineering Agreement with Criado&Associates,Inc.,in the Amount of$374,484.00,for the Sanitary Sewer
Rehabilitation Contract 103 Project in the Riverside and Riverside Alliance Neighborhood Areas,and Adopt Appropriation Ordinance(COUNCIL
DISTRICT 8)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the execution of an Engineering Agreement with Criado&Associates,Inc.,in the amount of$374,484.00 for the Sanitary Sewer
Rehabilitation Contract 103 project(City Project No.CO2723);and
2. Adopt the attached Appropriation Ordinance increasing receipts and appropriations in the Water&Sewer Capital Projects(W&S Capital
Projects)Fund in the amount of$606,457.00,transferred from available funds within the Water&Sewer Fund.
DISCUSSION:
This Mayor and Council Communication is to authorize the preparation of plans and specifications for sanitary sewer and water main
replacements on the following streets,alleys and easements located in the Riverside and Riverside Alliance neighborhood areas:
Street From To Scope
S.Retta Street S.Sylvania Avenue Huffman Water/Sewer
Street
Van Horn Avenue S.Retta Street Baurline Water/Sewer
Street
Baurline Street Van Hom Avenue Gibson Water/Sewer
Street
Ennis Street S.Judkins Street Baurline Water/Sewer
Street
LaSalle Street 11S.Sylvania Avenue Retta Street Water/Sewer
12th Street11S.Sylvania Avenue Retta Street Water/Sewer
Easement West of 120 feet West of the S. 460 feet
Sylvania Sylvania Avenue/12th North Sewer
Street intersection
240 feet North of the
Easement East of Riverside 1510 feet East Sewer
Riverside Drive Drive/Huffman Street Northwesterly
intersection
Easement between
Sylvania Avenue 130 feet North of the Galvez Sewer
and Paradise RR tracks Avenue
Street
Easement South of 230 feet East of S. 75 feet East Sewer
Galvez Avenue Judkins Street
Alley between 4th 831 feet
Street and Galvez S.Judkins Street West Sewer
Avenue
Alley between 80 feet South of 400 feet
Paradise Street Chenault Street South Sewer
and Baurline Street _
Alley between f 80 feet South of 450 feet
Chenault Street Chenault Street Ease Sewer
and 4th Street
Alley between S.Judkins
Chenault Street S.Chandler Drive Street Sewer
and 4th Street
Alley between 1 st S.Judkins
Street and N.Chandler Drive Street Sewer
Chenault Street
1st Street N.Chandler Drive N.Judkins Sewer
Street
Easement between
Rouse Street and Grace Avenue Emma Street Sewer
1 st Street
In addition to the contract amount,$231,973.00(Sewer:$152,079.00;Water:$79,894.00)is required for project management,real property
acquisition,utility coordination and material testing.
This project will have no impact on the Water Department's operating budget when completed.Design is expected to start in July 2020 and be
completed by September 2021.The project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
Appropriations for the Sanitary Sewer Replacement Contract 103 project are depicted below:
Fund Existing Additional Project
Appropriations Appropriations Total"
W&S Capital Projects Fund-56002 $0.00 $606,457.00$606,457.00
Project Total $0.00 $606,457.00$606,457.—0
*Numbers rounded for presentation.
MM/BE OFFICE:Criado&Associates, Inc.,is in compliance with the City's BDE Ordinance by committing to 26 percent SBE participation on this
project.The City's SBE goal on this project is 10 percent.
The project is located in COUNCIL DISTRICT 8.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current operating budget of the Water&Sewer fund,and upon approval of the
attached appropriation ordinance,funds will be available in the current capital budget,as appropriated,of the Water&Sewer Capital Projects
(W&S Capital Projects)Fund Sanitary Sewer Rehabilitation Contract 103 project.Prior to any expenditure being incurred,the Water Department
is responsible to validate the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional information Contact: Dena Johnson 7866