WHEREAS, the City of Fort Worth (CITY) and TranSystems Corporation
Consultants (ENGINEER) made and entered into City Secretary Contract No.
38905, (the CONTRACT) in the amount of $368,235.32 which was authorized
by the City Council by M&C C-23498 on the 26th day of May, 2009; and
WHEREAS, the CONTRACT was subsequently revised by Amendment Number 1
in the amount of $30,930.00 administratively authorized by the City on
the 20th day of April, 2010, Amendment Number 2 in the amount of
$180,496.68 authorized by the City Council by M&C C�23498 on the 26th day
of May, 2009; and Amendment #3 in the amount of $87,252.00 authorized by
the City Council by M&C C-24790 on the 22nd day of March 2011;
WHEREAS, the Contract involves engineering services for the following
project:
North Beach Street from Timberland Boulevard to Keller -Hicks Road,
WHEREAS, it has become necessary to execute Amendment No. 4 to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the Contract:
1.
Article I of the Contract is amended to include the additional
engineering services specified in the proposal letter dated November 111
2011, copies of which are attached hereto and incorporated herein. The
cost to City for the additional design services to be performed by
Engineer total $47,126.00.
2.
Article II of the Contract is amended to provide for an increase in
the maximum fee to be paid to Engineer for all work and services
performed under the Contract, as amended, so that the total fee paid by
the City for all work and services shall not exceed the sum of
$714,040.00.
3.
Page -1-
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
EXECUTED on this the 1 day of CJCun ,(V" , 20VL in
Fort Worth, Tarrant County, Texas.
ATTEST:
Ronald P Gonzales U
Assistant City Secretary
APPROVAL RECOMMENDED:
APPROVED:
° Fernando Costa
o Assistant City Manager
3o<<e
Douglas W. Wiersig, P.E.
Director, Transportation/Public Works Department
TRANSYSTEMS CORPORATION CONSULTANTS
ENGINEER
Raul "Pena III , "P . E . C
Senior vice President
AS TO FORM AND LEGALITY:
1 M&C REQUIRED
Page -2-
OFFICIAL RECORD
CITY SECRETARY
FT• WORTH, TX
S�ISt�l11S ,���
AMENDMENT NO. 4
November 11, 2011
Mr. Michael Weiss, P.E.
City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102
TranSystems
[3ank of America Building
500 West 7"' Street
Suite 1100
Fort Worth, TX 76102
Tel 817 339 8950
Fax 817 336 2247
www.transystems.com
RE: Amendment No. 4 —Water and Sanitary Sewer Improvements, Roadway Improvements
North Beach Street — Timberland Blvd to Keller -Hicks Rd
DOE # 6224
City Secretary Contract No. 38905
Qear Mr. Weiss,
TranSystems (TSC) appreciates the opportunity to present this proposal and fee schedule for your
consideration. Specifically, this amendment includes the services to incorporate supplemental contract
documents for water main improvements as indicated herein. This work will be included with and will
augment the design services associated with the original contract. The specific work to be included is as
follows:
WATER DEPARTMENT -WATER IMPROVEMENTS
Evaluation of Existing 2111and 30" Water Mains
TSC will evaluate depth of existing21"and 30" water lines and prepare various
alternatives and cost estimates for water main lowering and relocation. This study
will also include evaluating the conversion of an existing 24" force main into a
potable water main.
Relocation of 21"and 30" Water Mains from Timberline Blvd. to Keller Hicks Rd.
• Plan and profile sheets will be prepared at 1"=40' for both the 21"and 30"
mains. The 21"water main will be lowered and replaced with a 24" water line
for the entire length of project. TranSystems will coordinate with the Water
Department to determine limits of replacement of the 30" water line.
• Bid Items will be determined and quantity takeoffs will be performed for
inclusion into the Beach Street roadway contract as an addendum
• Specifications and related special provisions will be prepared for inclusion
into Beach Street roadway contract as an addendum
• Construction sequencing will be prepared to integrate the water main
construction into the Beach Street paving and drainage improvements
• An addendum will be prepared and issued to contractors to add these water
main improvements into the solicitation for bids that are due on Dec. 01,
2011.
$ 38,326.00
Systems Page 2 of 2
July 29, 2010
• Requests for Information (RFI) related to inclusion of these water lines will be
included in the scope of work.
• Attendance of preconstruction meeting for water main improvements is
included in scope. Of work,
Total Contract Amendment No. 4 4 12
Contract Summary:
Original Contract Fee —Phase 1: $368,235.32
Amendment No. 1: $ 30,930,00 Easements, hydraulic model, and
channel design
Amendment No. 2: $180,496.68 Phase 2 —Bray Birch to Timberland
added to roadway design scope
Amendment No. 3: $ 87,252.00 Local Water and Sewer main
Improvements
Amendment No. 4 47126.00 21' and 30" water line relocation
TOTAL CONTRACT
$714,040.00
This proposal is base on the following conditions::
1. Project will be streamlined by the Water Department with quick review and comments
2. Water Department will work directly with Field Operations and Production to determine shutdowns
and sequencing methods that will be communicated to TranSystems.
3. Water Department will review shop drawings.
4. Bid Plans will be developed by Transystems in the narrow window of time available to meet the
Dec.1 bid date. Water Department will prepare any change order needed to cover changes made
in plans after the bid date.
5. Water Department will perform all water system analysis needed to determine impacts of this
construction to City water systems.
6. This project will not include any special detailing; it is assumed that standard City details are all that
is needed.
7. It is assumed all construction will take place within existing right-of-way.
Thank you for your consideration. Please contact me should you require any additional information.
Sincerely,
TranSystems Corporation Consultants
Raul Pena III, P.E.
Senior Vice President
Copy: Mike Hobbs, Project Manager, TranSystems
Kent Lunski, P.E., TranSystems
G:IFW08105041ProjectMgmtlProposallAmendment 11North Beach Amendmen�1 2010-04-06.doc
Beach Street Water Line towering
TranSystems Corporation Consultants
11-02-2011
Design Services
HOURLY RATE WORK
Estimated Manhours
WORK TASK DESCRIPTION
Project
Manager
250.00
Senior
Enginer
150.00
Design
Engineer
126.00
RPLS
125.00
Survey
Crew
130.00
Senoir
Tech
105.00
Clerical
50.00
Total
Cost
Estimate
$
Special Services
1.
Stud
Alternative and sis
6
20
4,020,00
Vendors and Contractors
6
756.00
Cost Estimates
20
2,520A0
Meetings
4
4
1,504.00
subtotal
81800400
2.
Bid Set Plans
21" Plan and Profiles 7 sheets at 1'=40'
4
12
60
80812,00
30" Plan and Profiles (7 sheets at 1'=40')
4
24
96
14,104,00
Pay Items and Qauntities
12
12
21772400
Construction Sequencing
8
24
5,024,00
Special Provisions and Addendum
2
20
4
3,220.00
City Review, Comments and Meetings
8
8
31008400
sub -total
36,940.00
4.
Construction Assistance
RFIs
8
1,008,06
Preconstruction Meeting
3
378.00
sub -total
1,386.00
Total
of Amendment
47,126.00
This Fee is based on the following items:
1.
Project will be streamlined by Water Department with
quick review and comments
2.
Water Department will work with Field Operations and
Production to determine shutdowns and sequencing
methods
3.
Water Department will review shop drawings
4.
Bid Plans will be developed by Transystems in the
narrow window of time available to meet Dec.1 bid
date. Water Department will prepare any change order
needed to cover finalized plans
5.
Water Department will perform all water system
analysis needed to determine impacts of construction
to the City's Water System distribution.
6.
This project does not include any special detailing; it
Is assumed that standard details are all that is needed.