HomeMy WebLinkAboutContract 39257-CO2FORT WORTH: City of Fort Worth Change Order Request CITY SECRETARY CONTRACT NO. W a�7 �C� Project Namel Paving and Drainage Improvements to Serve Keller Middle School (CFA) City Sec # 39257 Client Project #(s)l City Project No. 01393 DOE 6328 Project Description) CFA project (with TPW participation) for the reconstruction of Old Denton Rd from Prestige Rd to Crawford Farms Is Contractorl Steele & Freeman Change Order # Date 2/9/2012 City Project Mgr.1 Raul Lopez CityInspector Wade Johnson Dept. I Paving I Drainage I Street Lighting I Totals Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date Amount of Pronosed Chanae Order ontract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 1.60% MAXALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $711,789,63 JUSTIFICATION (REASONS) FOR CHANGE ORDER Contract Time 75 0 0 0 II Perforated drains were added north and south of Crawford Farms to eliminate constant groundwater flow over sidewalks within the segment of road added by the City to the Keller ISD CFA project. Cost of change order to be borne by City. Funding already approved as part of CFA Amendment No. 1 of City Contract No. 39257, M&C C-25057. All i i' + �� It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Contractor (Name) Contract Signature D to Steele & Freeman 2,01 Z... pager '�/5ff 'POW WA M&CNumber rll& Date Approved r4� co m 0 DO (D cn cr _v a m rr O [D ❑ D Q � c'a � O CA 7 L CD rr yQ fD I� O N CD 7 cn O fv s w cQ m O CAD 0 v CD 0 c C/) O N O n cfl to cQ n m o � to N N W CT EH CJt CD � CD O O I C" O O Cn O c-� rr v 7q (D a (�D m r m (D r z o 0 N rr v (D N O Ic _ _ O O O c� 0 on A O O n `G � n O N (D = O 0 O o. o c(Di z A 3 � CD D m z � o o w w N � W O m m mCD NMl Q m 0 c� v 00 O CL rD rD r+ 0 N CD N O N c CO O COD O CD CQ CD O CO N 4A fA EH O O O O O O O O O M/WBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0000 Previous Change Orders CO # DATE AMOUNT Total $Q.00 L M M CM O i 1 1 O 1 O J O r r r O O O O M M M 6g 69 69 69 �{} 69 69 69 EA s_ O 0) O C N (L6 > 0 69 (A 69 69 69 69 69 64 69 69 M M M L r r r 1 1 1 G 1 (i C O t� r� 00 OD LL p r r r 69 69 69 69 69 69 69 69 69 L r r r CY 1 t 1 Chi i C6 1 1 1 J r� r ti UI (D CC) CC) L r r r in 64 69 69 69 Vy ER 69 69 69 69 4) O LO � LO to N CY d d 00 4 N 00 4 C r N It(M � co M N 00 d' N N d co N p r N N 69 69 E4EY 6C 69 69 69 69 69 E9 � LO d' � LO (wo CV)o o '> V Oo LO Cl) M U") fti N �O, N CV d 1 �V G9 69 69 69 6 69 69 69 0 �\ .� Lc) ti N LO h O LO (n J U) w , N 0)� t N U , Q U) P, r CO) LO TM t'M o 00 (0 0) w N 00 0) N 'a H a) Lo v E E!i Ef} EA 40 EA Ef! ft} Ei? Efl 6f} C vj _ L c O L ti a) L ^2LO N C i ca ca �N coMca 0 d 0 0 N N m U N Q M M a) �L�.oU N c C: 70 0 -v E U 0 o c � � z a) 0 Q a) L o ca = =0 0 U 0 c S a 0 0 p U o Q'c>a,� S Q `- LLI L o o "-' o (�� N H o U ca U C Q Cc Q o z O aj +i- X O 0 0 � z Z .. c W t j .. E n- o c>i ci Uaa) 0 z Z aim U aa) Q o U C CU W 0 o 0 E ca E U a E o Q- d ui 0 c i 0(n m 0U)c 0 coa70 'rn c o'> c E v o � o �_ o E m o a) -v ammUU6<F— 0 Q UQw 00�Q t FORT WORTH, City of Fort Worth Change Order Request Project Namel Paving and Drainage Improvements to Serve Keller Middle School (CFA) Client Project #(s)l City Project No. 01393 DOE 6328 City Sec # 39257 Project Description, CFA project (with TPW participation) for the reconstruction of Old Denton Rd from Prestige Rd to Crawford Farms Dr. Contractor City Project Mgr. Steele &Freeman Raul Lopez Change Order # Date I zlwzu12 City Inspector Wade Johnson Dept. � Paving � Drainage Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date Street Lighting 4.20 'Amount of Nroposea L;nange uraer Revised Contract Amount $402,326007 $118,153650 $58,074.20 Original Funds Available for Change Orders $2,513.52 $6,608.55 Remaining Funds Available for this CO $0.00 $23354.55 $0.00 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25916) IFICATION FOR CHANGE ORDER Contract Time Totals 431./U 75 767.52 0 0 0 199.22 75 354.55 0 553.77 75 122.07 354.55 1.60% $711,789.63 Perforated drains were added north and south of Crawford Farms to eliminate constant groundwater flow over sidewalks within the segment of road added by the City to the Keller ISD CFA project. Cost of change order to be borne by City. Funding already approved as part of CFA Amendment No. 1 of City Contract No. 39257, M&C C-25057. I It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Contractor (Name) � Contract Signature Date Steele &Freeman { � i l � . � Insp ctor/Inspection Supervisor Date Project Manager/Program Manager Date Assistant Director (Dept) Date bjreGtor, Contr c{ng Department Dept Date Z As'sistant City Attofney Date AssistanCity Manager % Date - - t, Council Action (if required) M&C Number M&C Date Approved T. `( ';�E �) - r D�4 FORT WORTH., Project Name Paving and Client Project City of Fort Worth Change Order Request Improvements to Serve Keller Middle School (CFA) No. 01393 DOE 6328 City Sec # 1 39257 Project Description) CFA project (with TPW participation) for the reconstruction of Oltl Denton Rd from Prestige Rd to Crawford Farms Dr. Contractorl Steele & Freeman Change Order # Date 219/2012 City Project Mgr,l Raul Lopez City Inspector F7Watle Johnson Contract Time Dept. Paving Drainage Street Lighting Totals (CD) Original Contract Amount $399,812.55 $111,544,95 $583074,20 $569,431.70 75 Extras to Date $23513052 $4,254.00 $6,767,52 0 Credits to Date 0 Pending Change Orders (in M&C Process) 0 Contract Cost to Date $402,326.07 $115,798.95 $58,074,20 $576,199022 75 Amount of Proposed Change Order 0.00 2,354.55 0.00 25354.55 0 Revised Contract Amount $402,326007 $118,153,50 $58,074,20 $578,553,77 75 Original Funds Available for Change Orders $2,513,52 $6,608055 1 $9,122007 Remaining Funds Available for this CO $0.00 $2,354.55 $0.00 $2,354,55 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 1.600to MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $711,789.63 JUSTIFICATION (REASONS) FOR CHANGE ORDER Perforated drains were added north and south of Crawford Farms to eliminate constant groundwater flow over sidewalks within the segment of road added by the City to the Keller ISD CFA project. Cost of change order to be borne by City. Funding already approved as part of CFA Amendment No. 1 of City Contract No. 39257, M&C C-250571 i r It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Contractor (Name) Contract Signature Date Steele & Freeman Inspector/Inspection Supervisor Date Project Manager/Program Manager Date -Assistant Director (Dept) Date Director, Contrqcting Department (Dept) Date Assistant City Attorney Date Assistant City Manager Date A4 Council Action if required) M&C Number M&C Date Approved FORT WORTH... City of Fort Worth Change Order Request Project Namel Paving and Drainage Improvements to Serve Keller Middle School (CFA) City Sec # 39257 Client Project #(s)l City Project No. 01393 DOE 6328 Project Description) CFA project (with TPW participation) for the reconstruction of Old Denton Rd from Prestige Rd to Crawford Farms Dr. Contractorl Steele & Freeman Change Order # Date 2/9/2012 City Project Mgr,J Raul Lopez City Inspector Wade Johnson Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) Paving Drainage � Street Lighting CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 259o) � 1US7I1:ICAiI®N (PEAczON4z) FAR CHANCE BRUER Totals 1.60% $711,789,63 Contract Time 75 0 0 0 75 0 75 Perforated drains were added north and south of Crawford Farms to eliminate constant groundwater flow over sidewalks within the segment of road added by the City to the Keller ISD CFA project. Cost of change order to be borne by City. Funding already approved as part of CFA Amendment No. 1 of City Contract No. 39257, M&C C-25057. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Contractor (Name) Contract Signature Date Steele & Freeman Inspector/Inspection Supervisor Date Project Manager/Program Manager Date Assistant Director (Dept) Date Director, Contracting Department (Dept) Date Assistant City Attorney Date Assistant City Manager Date Council Action (if required) M&C Number M&C Date Approved