HomeMy WebLinkAboutContract 38950-A2 (2)Amendment No. 2
STATE OF TEXAS § CITY SECRETARY NO.
(No M&C Needed)
COUNTY OF TARRANT §
WHEREAS, the City of Fort Worth (City) and Dannenbaum Engineering
Corporation (Engineer) made and entered into City Secretary Contract No.
38950 (the Contract) which was authorized by the City Council by M&C &
23658 on the 13th of August, 2009; as amended by Amendment #1 on the
12th of May, 2011 and
WHEREAS, the Contract involves engineering services for the following
project:
2008 Capital Improvements Program Arterial Street Project —
Ray White Road
Project No. 01294
WHEREAS, it has become necessary to execute Amendment No. 2 to
said Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their
duly -authorized representatives, enter into the following agreement which
amends the Contract.
1.
Article I of the Contract is amended to include the additional engineering
services speced in a proposal letter dated March 14, 2011, a copy of which is
attached hereto and incorporated herein. The cost to City for the additional
services to be performed by Engineer total $21,910.00.
2.
Article II of the Contract is amended to provide for an increase in the
maximum fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all work
and services shall not exceed the sum of $258,317.00 e
3, CITY SECRETARY
7M WORTH9 TX
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
09-229u09-P06 0 1 7AK
g:\1210\4463-01\admin\agreement\sa #2\4463-01.cover.amendment 2.doc
Contract Amendment No. 2 09-119009-929028EF
Page 1 of 2
Executed on this the a3 rd
Worth, Tarrant County, Texas.
Marty Hendrix
City Secretary
APPROVAL RECOMMENDED:
GJ `
)ougIcA W. Wiersig, P. .
D i recto r
Transportation and Public Works
Dannenbaum Engineering Corporation
ENGINEER
B C, �.�awtP t E .
Y
Mark C. Lorance, P.E.
North Texas Regional Manager
6421 Camp Bowie Blvd., Suite 400
Fort Worth, Texas 76116
APPROVED AS TO FORM AND LEGALITY:
Doug Bla
Assistant
City Attorney
day of Sp42 ex A"/, 2011, in Fort
APPROVED:
Fernando Costa
Assistant City Manager
g:\1210\4463-OS\admin\agreement\sa #2\4463-Ol.cover.amendment 2.doc
Contract Amendment No. 2
Page 2 of 2
DANNENBAUM ENGINEERING CORPORATION
6421 CAMP BOWIE BLVD., SUITE 400 FORT WORTH, TEXAS 7611U�421 (817) 763-8883
August 22, 2011
Ms. Wilma J. Smith, P.E.
TPW Department
City of Fort Worth
1000 Throckmorton Street
Fort Worth, Texas 76102-6311
RE: Supplemental Agreement No. 2
Ray White Road Paving Improvements
City Project Nos. 01294
Dear Ms. Smith:
We have prepared and are submitting for your review the attachments to Supplemental
Agreement No. 2 to design an enclosed box culvert storm sewer, update the construction plans,
specifications, and estimates, and prepare an easement document. This plan revision will replace
the open channel on the property at the southwest corner of the Ray White Road and Shiver Road
intersection. This supplemental agreement also includes work to prepare, submit, and process a
notification to the United States Army Corps of Engineers (COE) under the rules established by
Nationwide Permit 14.
We have included services from A.N.A. Consultants, L.L.C. to update the storm water pollution
prevention plan and to prepare one easement document. hi addition, we have included services
from Berg -Oliver Associates, Inc., for the work necessary for submitting the notification to the
COE as described above. The above referenced sub -contractors are certified MWBE. For this
amendment, the percentage of the contract being performed by approved M/WBE firms will be
55%. This will result in a 26.6% portion of the overall project agreement that will be performed
by approved M/WBE firms.
If you are in agreement with the attachments for Supplemental Agreement No. 2, our authorized
compensation will increase by $21,910.00. The $216,731.00 original contract amount along with
the amount of $19,676.00 Supplemental Agreement No. 1, both previously authorized will be
increased to $258,317.00. Please do not hesitate to call if you have any questions or require any
additional information.
Sincerely,
mortis S. Caldwell, P.E.
Project Manager
cc: Mark C. Lorance, P.E.
File 4463-01
G:\1210\4463-01\Admin\Agreement\SA #2\I.etter Smith 08-23-201 l.doc
ATTACHMENT "B"
COMPENSATION AND SCHEDULE
RAY WHITE ROAD
PAVING IMPROVEMENTS
SUPPLEMENTAL AGREEMENT NO.2
CITY PROJECT NO, 01294
I. Compensation:
A. The Engineer shall be compensated a total lump sum fee of $21,910.00
as summarized in Exhibit "B-313". Payment of the total lump sum fee
shall be considered full compensation for the services described in Exhibit
"A- I" and Exhibit "A-2" for all labor materials, supplies and equipment
necessary to complete the project.
B. The Engineer shall be paid monthly as described in Exhibit "B-1",
Section 1 — Method of Payment.
Each Invoice is to be verified as to its accuracy and compliance with the
terms of this contract by an officer of the Engineer.
II. Schedule:
A. Phases 1 and 2 shall be completed 180 days after the "Notice to Proceed"
letter is issued.
The Scope of Services is outlined in Attachment "A", Exhibit "A-1" and
Exhibit "A-2".
g:\1210\4463-01\admin\agreement\sa #2\4463-01 attach b 02-24-2011.doc
EXHIBIT "B-1"
(SUPPLEMENTAL TO ATTACHMENT B)
METHOD OF PAYMENT
RAY WHITE ROAD
PAVING IMPROVEMENTS
SUPPLEMENTAL NO.2
CITY PROJECT NO.01294
I. Method of Payment
Partial payment shall be made to the Engineer monthly upon City's approval of an
invoice from the Engineer outlining the estimated current percent complete of the
total project.
The aggregate of such monthly partial fee payments shall not exceed the
following:
Until satisfactory completion of Exhibits "A-1" and "A-2", Conceptual
Engineering plan submittal and approval by the City, a sum not to exceed 30
percent of the total lump sum fee.
Until satisfactory completion of Exhibits "A-1" and "A-2", Preliminary
Construction Plan submittal to City, a sum not to exceed 60 percent of the total
lump sum fee, less previous payments.
Until satisfactory completion of Exhibits 46A-1" and "A-2", Final Construction
plan submittal and approval by the city, a sum not to exceed 90 percent of the
total lump sum fee, less previous payments.
II. Progress Reports
A. The Engineer shall submit to the designated representative of Director of
Department of Engineering monthly progress reports covering all phases
of design by the 15th of every month in the format required by the City.
B. If the Engineer determines in the course of making design drawings and
specifications that the construction cost estimate of $ 63,000.00 (as
estimated on Exhibit 134) will be exceeded, whether by change in the
scope of the project, increased costs or other conditions, the Engineer shall
immediately report such fact to the City's Director of the Department of
Engineering and, if so instructed by Director of the Engineering
Department, shall suspend all work hereunder.
g:\1210\4463-01\admin\agreement\sa #2\4463-01 exhibit b-I 08-23-20] l.doc
EXHIBIT B-2
(SUPPLEMENT TO ATTACHMENT B)
HOURLY RATE SCHEDULE
RAY WHITE ROAD
PAVING IMPROVEMENTS
SUPPLEMENTAL NO.2
CITY PROJECT NO. 01294
Employee Classification
Rate/Hour
Principal $350.00
Project Manager/Planner $190.00
Senior Engineer/QA-QC $190.00
RPLS $120.00
Project Engineer $130.00
Design Tech. $95.00
CADD Tech. $ 75.00
Clerical $ 65.00
2-Man Survey Crew $100.00
3-Man Survey Crew $120.00
4-Man Survey Crew $150.00
Reimbursables Cost + 10%
Mileage $0.55 Per Mile
Reproduction work will be at current comrraercial rates. Subcontractors will be paid for at actual
invoice cost plus ten percent (10%).
g:\1210\4463-01\admin\agreement\sa #2\4463-02 exhibit b-2 08-23-2011.doc
EXHIBIT "15%3A"
SUMMARY OF TOTAL PROJECT FEES
RAY WHITE ROAD
PAVING IMPROVEMENTS
SUPPLEMENTAL NO.2
CITY PROJECT NO. 01294
Exhibit Exhibit Scope of Services Total Fee M/WBE
A-1 Design Pavement Improvements
A-2 Sanitary Sewer Design
A-2 Water Design
TOTAL
$ 21,910.00 $ 12,100.00 55.2
$ 0.00 $ 0.00 0.0
$ 219910.00 $ 12,100.00 55.2
CITY M/WBE GOAL = 22%
% of
Proposed M/WBE Sub -Consultants Services Fees Total Fee
ANA Consultants
ANA Consultants
Berg -Oliver Associates
TOTAL
Update S WPPP
Easement
Nationwide Permit #14
Proposed Non-M/WBE Sub -Consultants
NFATIN
$ 1,100.00 5.0
$ 1,200.00 5.5
$ 9,800.00 44.7
$ 12,100.00 55.2
g:\1210\4463-01\admin\agreement\sa #2\4463-01 exhibit b-3a 08-22-201 I.doc
EXHIBIT "B-3B"
FEE SUMMARY
RAY WHITE ROAD &SHIVER ROAD PAVING IMPROVEA4ENTS
SUPPLEMENTAL NO. 2
CITY PROJECT N0.01294
RAY WHITE ROAD
***PAVING AND STORM DRAINAGE***
OPINION OF PROBABLE CONSTRUCTION COSTS $ 63,000.00
ENGINEERING DESIGN (DEC) $ 8,600.00
SWPPP (ANA) $ 1,100.00
EASEMENT (ANA) $ 1,200.00
NATIONWIDE PERMIT #14 (BERG OLIVER) $ 9,800.00
REPRODUCTION $ -
MYLARPRODUCTION $ -
.PDFPREPARATION $ -
TOTAL PAVING &STORM DRAINAGE $ 20,700.00
10%FOR SUB $ 12,100.00 $ 1,210.00
TOTAL FEE $ 21,910.00
***TOTAL DESIGN COST (WATER, SEWER, PAVING &STORM DRAINAGE)***
WATER DESIGN FEE $ -
SEWER DESIGN FEE $ -
PAVING &STORM DRAINAGE DESIGN FEE $ 21,910.00
GRAND TOTAL $ 21,910.00
G:\1210\4463-01\Admin\Agreement\SA q2\4463-01 EXHIBIT B-3B 02-24-2011.x1s B-3B (1)
EXHIBIT "B-3C"
SUPPLEMENTAL NO, 2
City Project No. 01294
BREAKDOWN FOR REPRODUCTION FEE AND ADDITIONAL SERVICES FEE
FOR:
RAY WHITE ROAD —CITY PROJECT No. 01294:
PAVING AND STORM DRAIN
No additional reproduction and service fees.
G:\1210\4463-01\ADMIN\AGREEMENT\SA #2\4463-01 EXHIBIT B-3C 08-22-2011.DOC
B3C-1
EXHIBIT "15-4"
OPINION OF PROBABLE COST SUMMARY
RAY WHITE ROAD
PAVING IMPROVEMENTS
SUPPLEMENTAL NO.2
CITY PROJECT NO, 01294
RAY WHITE ROAD —CITY PROJECT No. 01294:
Water $ 0.00
Sewer $ 0.00
Paving & Drainage $ 631000000
TOTAL $ 63,000.00
g:\1210\4463-01\admin\agreement\sa #2\4463-01 exhibit b-4 08-22-2011.doc