WHEREAS, the City of Fort Worth (City) and Jacobs Engineering Group, Inc.
("Consultant") made and entered into City Secretary Contract No. 39489 (the Contract) which
was authorized by M&C C-23816 on the 291h day of September 2009
WHEREAS, the Contract involves professional services for the following project:
Citywide Storm Water System GIS Project
WHEREAS, it has become necessary to execute Amendment No.2 to said Contract to
include an increased scope of work and revised maximum fee.
NOW THEREFORE, City and Consultant, acting herein by and through their duly
authorized representatives, enter into the following agreement which amends the Contract:
Article I of the Contract is amended to include the revised scope of services specified in
Attachment A, a copy of which is attached hereto and incorporated herein. The cost to City for
the additional services to be performed by Consultant total $2,123,000.
2.
Article II of the Contract is amended to provide for an increase in the maximum fee to be
paid to Consultant for all work and services performed under the Contract, as amended, so that
the total fee paid by the City for all work and services shall not exceed the sum of $6,193,056.
3.
All other provisions of the Contract, which are not expressly amended herein, shall
remain in full force and effect.
OFFICIAL RECORD
CITY sECRE I An T
1=0RT WORTH, TX
Amendment to
Professional Services Agreement
Page 1 of 2
IN WITNESS THEREOF, the parties hereto have made and executed this Agreement in
multiple originals the day and year first above written, in Fort Worth, Tarrant County, Texas.
CITY OF FORT WORTH:
Fernando Costa
Assistant City Manager
RECOMMENDED:
illiam A.�e�cest'P.E., Director
Transportation and Public Works
APPROVED AS TO FORM
LEGALITY: /
City Attorney
ATTEST:
CONSULTANT:
(
P/ P
Kevin P. Nelson, P.E.
Operations Manager, South Central Region
Cesfit fkCt; Authorization
D a t'e
Marty Hendrix
City Secretary
Date
fy Op000p�� pti
o V Q p
0A0
o �x�
0
o 0Fj
��d
Oo
0��0000�; rLio
Amendment to
Professional Services Agreement
Page 2 of 2
Attachment A
Amendment No. 2
City of Fort Worth Storm Water Management System
Data Collection, Inventory and Mapping
Year 3 Scope of Work
SECTION I -PROJECT DEFINITION
The goal of Year One was to develop the storm water management system asset
inventory and database for the top five priority mapsheds in the City and
implement procedures for expanding and maintaining the database throughout
Years Two, Three, and Four. Year One services was a pilot study to allow the
City and the consultant team the opportunity to judge levels of effort required to
produce the storm water mapping and inventory deliverables that the City needs
as expressed in initial scoping meetings and Version 1.0 of the Quality
Management Plan.
Year Two of the project was developed using the procedures and workflows
defined and approved in Year One, Approximately 37 square miles of mapsheds
were developed for the schematic development task in Year One but the majority
of those mapsheds were not surveyed, rectified, assessed nor integrated into the
City's existing system. By the end of Year Two, schematic development was
anticipated to be completed for all 222 prioritized mapsheds, and field survey
was to be completed for approximately 60 mapsheds.
The scope defined below encompasses the effort anticipated to continue to add
to the GIS inventory through program Year 3, building upon the Year 1 and Year
2 data. The Year 3 scope of work includes survey and data capture; validate and
rectify schematic; limited condition assessment of specific assets; reporting; and
project management. The overall project progress and goals will be reviewed
quarterly, and the goals and scope may be adjusted at the direction of City staff
in working with the consultant team.
Based upon the understood contract budget for the entire program through Year
4, it is not anticipated that all mapsheds will be fully surveyed and rectified.
However, some reduced level of information gathering for the mapsheds that are
not fully inventoried is desired. Therefore, the Year 3 scope anticipates that a
OFFICIAL RECO
coRT w ����j+��R-X
enhanced reconnaissance" and enhanced rectification" approach will be
developed and used on some mapsheds.
It is anticipated that another amendment to the original contract will be
considered in 2011 for the Year 4 program work, which will be similar to this
amendment, to allow the inventory work to continue to September 2012.
SECTION II -BASIC SCOPE OF SERVICES
Task 1600 - Field Survey
The location of each storm water management system asset, as identified and defined in
the QMP for field verification, will be located by conventional survey methods using QMP
survey procedures. Version 1.0 of the Field Survey Manual was developed in Year One
of the project, which specifies the measurements, notes, photographs and occasional
sketches that are to be collected for each asset. If the crews are unable to collect
survey data within an area, the City will be notified and the City will assist in resolving
the issues that prevent the survey.
1. Using the equipment, software and procedures as well as the QC processes
defined in the QMP, survey each storm water management system asset by
priority watershed
a. Load export of the field verified schematic and supporting data on survey
units
b. Following procedures defined in the Survey Field Manual —
i. Capture location of asset
ii. Take measurements and populate attributes
His Take field notes
1. Field observation of condition
iv. Take digital photographs
c. Report issues to the City for assistance in completing survey
2. Upload survey data from survey units
3. Verify that survey attributes meet the standards defined in the QMP
a. Tools, queries and scripts
4. Deliver sub -centimeter survey accuracy data and measurements in ASCII format,
field notes, sketches and photographs in GIS format for City acceptance of the
survey data
The anticipated number of mapsheds to be fully surveyed under the defined budget, and
added to the mapsheds already completed in Years 1 and 2, is 66 mapsheds. This is
based upon costs being experienced for the Year 2 work.
Task 1601 —Enhanced Reconnaissance
An "enhanced reconnaissance" approach will also be developed and implemented under
this task. The goal of this effort will be to collect a reduced level of information from the
full survey approach, allowing all of the mapsheds to have some level of surveyed
information collected. The number of mapsheds that will receive full survey versus the
enhanced reconnaissance level will be determined quarterly, as progress continues to be
measured against the available budget.
The preliminary goal for Year 3 for mapsheds to be completed using this modified
approach is 20 mapsheds.
Task 1700 - Validate and Rectify Schematic
The survey data will be integrated into the geodatabase and the location of the
schematic assets will be adjusted to the surveyed coordinates, as identified and defined
in the QMP.
1. Using the procedures and QA/QC processes defined in the QMP, adjust the asset
locations in the field verified schematic to the survey locations
a. Utilize the geometric network and connectivity rules
2. Calculate intelligent unique ID, defined in QMP, for new features
3. Verify that the features meet the standards defined in the QMP and perform final
QA
a. Generate geometric network and correct connectivity errors
b. Perform network traces and correct flow direction errors
c. Randomly select points (as defined in QMP) to be resurveyed to confirm
accuracy
4. Populate survey attribute fields with actual values while maintaining plan values
5. Verify that attributes meet the standards defined in the QMP
a. Compare plan values to actual values; perform QMP defined data review,
including populating and flagging of missing data using inference tools to
provide a near -model -ready database.
b. Test in InfoWorks/InfoNet model
6. Hyperlink images and survey related data to appropriate asset
7. Deliver geodatabase and InfoWorks/InfoNet model -ready database of the storm
water management system which incorporates the initial schematic, field
reconnaissance improvements, survey data and hyperlinked images in GIS and
InfoWorks/InfoNet format for City acceptance of the storm water management
system for each priority watershed
The anticipated number of mapsheds to be fully rectified under the defined budget, and
added to the mapsheds already completed in Years 1 and 2, is 57 mapsheds. This is
partially based on costs being measured for the Year 2 work.
Task 1701 —Modified Rectification
It is the goal of this- contract and budget to complete schematic rectification far all of thy
prioritized mapsheds that receive full field survey. For those mapsheds where "enhanced
reconnaissance" is used in lieu of full field survey, a "modified rectification" approach will
be developed which will be a reduced level of effort from full rectification. Similar to the
field survey task, the number of mapsheds that will receive full rectification versus the
modified rectification level will be determined quarterly, as progress continues to be
measured against the available budget.
The preliminary goal for Year 3 for mapsheds to be completed using this modified
rectification approach is 10 mapsheds.
Task 1800 -Condition Assessment
During the field verification and survey tasks, assets will be flagged that appear to need
further investigation to determine actual condition. Drainage complaints, maintenance
history and historical knowledge will also be evaluated to determine which assets will be
assessed.
1. Using the methodology defined in the QMP, determine the storm water
management system assets to be assessed
2. Using the equipment, software and procedures as well as the QC processes
defined in the QMP, assess the condition of the specified assets by priority
mapsheds
a. Load export of the geodatabase and supporting data on GPS units
b. Following procedures defined in the Condition Assessment Field Manual —
i. Conduct visual inspection
ii. Conduct CCTV inspection
iii. Conduct pole mounted camera inspection
iv. Confined space entry
v. Take field notes
vi. Take digital photographs
3. Upload condition assessment data from GPS units
4. Verify that the assessment data meets the standards defined in the QMP
a. Tools, queries and scripts
5. Use findings to calculate condition assessment ratings
6. Update geodatabase with calculated rating information
7. Deliver video, photos, and condition assessment report of findings in GIS or a
format compatible with the City Asset Management software for City acceptance
It is the goal of this contract and budget to perform limited and strategic condition
assessment for all of the prioritized mapsheds that are field surveyed. It is anticipated
that there will be needs for more condition assessment information than the current
budget allows. Therefore, condition assessment work will be limited to the agreed -upon
task budget established, and locations of condition assessment work will be reviewed
and confirmed with city staff before the work is started. This will allow the information
collected to be in the most strategic locations in each mapshed.
Task 1900 —Reporting
Quarterly reporting will be performed to allow the City to judge actual budget
requirements necessary to map the City's mapsheds. This budget tracking and reporting
will also allow the City to modify the mapping protocol if it appears that the initial
protocol cannot be performed within the constraints of the City's budget. Following the
production of each report, meetings with the City will be scheduled to review project
status.
Task 2000 —Project Management/Oversight Services
Due to the size, scope and nature of this project, project management services will
include tracking of effort and expenses, review of project progress, scheduling of staff
and subconsultants' staff, quality review and oversight, budget review, communication
with City staff, invoicing, goal review and realignment, and updates to the contract
scope and/or fee, if necessary.
Administrative fees on subconsultants' contracts are included within this task.
Attachment B-1
City of Fort Worth Storm Water Management System
Data Collection, Inventory and Mapping - Year Three
Basis of Compensation
Task
Amendment 2
0100 - Update QMP $0.00
0200 - Geodatabase Requirements (COMPLETED) ---
0300 - Geodatabase Design Scema (COMPLETED) ---
0400 - Data Compilation $0.00
0500 - Data Conversion (NOT USED) ---
0600 - Data Scanning (NOT USED) ---
0700 - Georeferencing $0.00
0800 - Schematic Development W000900 - Maintenance $0.00
0903 - GIS Database Maintenance WOO1000 - Easement Data Compilation $0.00
1100 - Easement Data Scanning (NOT USED) ---
1200 - Georeferencing for Easement Development $0.00
1300 - Easement Development $0.00
1400 - Field Reconnaissance WOO1500 - Evaluation of Easement Layer (NOT USED) ---
1600 - Field Survey $528,000000
1601 - Enhanced Reconaissance $80,000000
1700 - Validate and Rectify Schematic $8557000900
1701 - Modified Rectification $80,000000
1800 - Condition Assessment $200,000,00
1900 - Reporting $4,000600
2000 - Project Management $2101000.00
2100 - Inlet Marker Program Support $0.00
Contingency Account $1661000.00
Subtotal Fee -Amendment 12 $2,123,000.00
Program -to -date Summary
Non-M/WBE Subconsultants $468,500.00
M/WBE Subconsultants $636,500.00
Amendment #2 M/WBE Percentage 30.0%
Subtotal contract
Non-M/WBE Subconsultants
M/WBE Subconsultants
M/WBE Percentage
$7,884,055
$1,714,770
$2,531,240
32.1 %
Exhibit 15-3A
(Supplement to Attachment B)
City of Fort Worth Storm Water Management System
Data Collection, Inventory and Mapping - Year Three
Summary of Total Project Fees
Consulting Firm
Jacobs Engineering Group Inc
NTB Associates, Inc.
InfraMetrix, LLC
DFW Infrastructure, Inc.
Inventive Concepts, Inc.
Franzi Davis, GISP
Surveying and Mapping, Inc.
ANA Consultants, LLC
Gorrondona & Associates, Inc.
Fulton Surveying, Inc.
Prime Responsibility
Survey, Rectify, Condition Assessment, PM
Cel[.y
Pole -Mounted Condition Assessment
CCTV Condition Assessment
GIS
GIS QC
Field Survey and Field Reconnaissance
Field Survey
Field Survey
Field Survey
Total for Professional Services
Task Description
1 Field Survey
2 Rectify Schematic
3 Condition Assessment
4 Reporting
5 Project lv4anagement
Contingency Allowance
Scope of Services
See Attachment A
See Attachment A
See Attachment A
See Attachment A
See Attachment A
Total Fee
$6087000.00
$9351000.00
$2005000,00
$4,000.00
$2107000600
$1669000,00
$21123,000,00
Amount
$1,0181500.00
$357,500.00
$1113000000
$485000,00
$140,000.00
$801000,00
$92,000.00
$923000000
$92,000.00
$921000,00
$2,123,000.00
MWBE Fee
$3681000.00
$2205000.00
$48,000.00
$0.00
$0.00
$636,000.00
Surveying and Mapping, Inc. shall participate in performing portions of Task 1 -Field Survey
ANA Consultants, LLC shall participate in performing portions of Task 1 -Field Survey
Gorrondona & Associates, Inc. shall participate in performing portions of Task 1 - Field Survey
Fulton Surveing, Inc. shall participate in performing portions of Task 1 - Field Survey
Inventive Concepts, Inc. shall participate in performing portions of Task 2 -- Rectify Schematic
Franzi Davis, GISP shall participate in performing the QC review of Task 2 -- Rectify Schematic
Inframetrix, LLC shall participate in performing portions of Task 3 -- Condition Assessment
Non-MWBE Participation Total Fee
NTB Associates, Inc. and InfraMetrix, LLC $�68',500'.00
Percent
48.0%
16.8%
100.0%
Percent
60.5%
23.5%
24.0%
0.0 0
0.0 o
0.0 0
30.0%
Percent
22.1
f� Page 1 of 2
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 9MPUN 1V - Ord. No. 19339-09-2010
DATE: Tuesday, September 14, 2010
LOG NAME: 20SWMGISPROJECT-YR3
REFERENCE NO.: C-24446
SUBJECT:
Authorize the Execution of Amendment No. 2 to City Secretary Contract No. 39489 with Jacobs
Engineering Group, Inc., for Citywide Stormwater System GIS Project, Year Three in the Amount of
$2,123,000.00 for the Transportation and Public Works Department, Increasing Appropriations in the
Stormwater Utility Fund and Decreasing the Unreserved, Undesignated Fund Balance by the Same
Amount and Adopt Supplemental Appropriation Ordinance (ALL COUNCIL DISTRICTS)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached supplemental appropriation ordinance increasing appropriations in the Stormwater
Utility Fund in the amount of $2,123,000.00 and decreasing the unreserved, undesignated fund balance
by the same amount, and
2. Authorize the City Manager to execute an agreement with Jacobs Engineering Group, Inc., in the
amount of $2,123,000.00 for Year Three of the GIS Storm Water mapping project for the Transportation
and Public Works Department, Storm Water Management Division,
DISCUSSION:
The lack of an adequately mapped detailed inventory of the City's storm water system impedes the ability
of staff to respond to maintenance needs and calls from citizens, to plan long-term capital improvements,
and to provide necessary emergency response information for environmental spills which may enter the
storm water system. Developing a detailed inventory and map of the City's storm water assets into GIS
was identified as a high priority when the Storm Water Utility was created. In August 2007, a Request for
Proposal (RFP) was issued and a total of six proposals were received. The top three consultants were
interviewed and Carter and Burgess, Inc., was selected as the most qualified.
Carter and Burgess, Inc., was acquired by Jacobs Engineering Group, Inc. Therefore, on September 29,
���`�y 2009, (M&C C-23816) City Council authorized the City Manager to execute the contract for the Year Two
scope of work with Jacobs Engineering Group, Inc., (City Secretary Contract No. 39489) in the amount of
$3,590,056,00,
On August 24, 2010, City Council authorized the City Manager to execute Amendment No. 1 to the City
Secretary Contract No. 39489 with Jacobs Engineering Group, Inc., in the amount of $480,000.00. This
will bring the total project cost to $7,884,055,
The overall project scope of work includes developing schematic maps based on engineering plans;
performing a detailed location survey of all storm water features including inlets, storm drains, outfalls,
channels, detention ponds, dams and other structures; mapping of drainage easements; and a condition
assessment of selected portions of the underground system. This is Year Three of what is planned to be a
four-year project.
http://apps.cfwnet.org/ecouncil/printmc.asp?id=14033&print=true&DocType=Print 9/24/2010
Page 2 of 2
The scope of the Year Three of the contract was developed with an emphasis on surveying the City's
Storm Water assets and tying this information back to the original plans as well as completing a map of all
known drainage easements since1960.
Jacobs Engineering Group, Inc., proposes to perform the Year Three contract on a time and materials
basis for a not -to -exceed fee of $2,123,000,00, City staff considers this fee to be fair and reasonable for
the scope of services proposed.
Jacobs Engineering Group, Inc., is in compliance with the City's MWWBE Ordinance by committing to 30
percent M/WBE participation. The City's MWBE goal is 29 percent.
This project is located in (ALL COUNCIL DISTRICTS).
FISCAL INFORMATION /CERTIFICATION:
The Financial Management Services Director certifies that upon approval of the above recommendations
and adoption of the attached supplemental appropriation ordinance, funds will be available in the current
operating budget, as appropriated, of the Stormwater Utility Fund. Upon approval the unreserved,
undesignated cash balance of the Stormwater Utility Fund will exceed the minimum reserve as outlined in
the Financial Management Policy Statements,
FUND CENTERS:
TO Fund/Account/Centers
1) PE69 531200 0209204
CERTIFICATIONS:
FROM FundlAccount/Centers
$2,123,000.00 2) PE69 531200 0209204
Submitted for City. Manager's Office by:
Originating Department Head:
Additional Information Contact:
ATTACHMENTS
1. 20SWMGISPROJECTYR3 AO.doc (Public)
2. compliance - yr3.pdf (CFW Internal)
3. fund ingverifcation.pdf (CFW Internal)
Fernando Costa (6122)
William Verkest (7801)
Elizabeth Young (6785)
$2,123,000.00
http://apps.cfwnet.org/ecouncil/printmc.asp?id=14033&print=true&DocType=Print 9/24/2010