HomeMy WebLinkAboutResolution 5252-06-2020 A Resolution
NO. 5252-06-2020
STATEMENT EXPRESSING
OFFICIAL INTENT TO REIMBURSE
EXPENDITURES WITH PROCEEDS OF FUTURE DEBT FOR SANITARY SEWER
M257 UPPER AND MIDDLE VILLAGE CREEK PARALLEL RELIEF MAIN, PART
2B
WHEREAS, the City of Fort Worth, Texas (the "City") is a home-rule
municipality and political subdivision of the State of Texas; and
WHEREAS, the City expects to pay expenditures in connection with the design,
planning, acquisition and construction for the Sanitary Sewer M257 Upper and
Middle Village Creek Parallel Relief Main, Part 2B Project (the "Project") prior to
the issuance of obligations by the City in connection with the financing of the Project
from available funds; and
WHEREAS, the City finds, considers, and declares that the
reimbursement of the City for the payment of such expenditures will be
appropriate and consistent with the lawful objectives of the City and,
as such, chooses to declare its intention, in accordance with the
provisions of Section 1.150-2 of the Treasury Regulations, to reimburse
itself for such payments at such time as it issues obligations to finance
the Project;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FORT WORTH, TEXAS, THAT:
Section 1. The City reasonably expects debt, as one or more series of
obligations, may be issued or incurred by the City with an aggregate maximum
principal amount not to exceed $10,400,000.00 for the purpose of paying the
aggregate costs of the Project.
Section 2. All costs to be reimbursed pursuant hereto will be capital
expenditures. No obligations will be issued by the City in furtherance of this
Statement after a date which is later than IS months after the later of (1) the
date the expenditures are paid or (2) the date on which the property, with
respect to which such expenditures were made, is placed in service.
Section 3. The foregoing notwithstanding, no obligation will be issued
pursuant to this Statement more than three years after the date any
expenditure which is to be reimbursed is paid.
Adopted this 23,d day of June 2020. �
��® ..•.... ' . may,
ATTEST: :gip
By:
MatCP 't
'S
� .
Mary J. Kayser, City Secretary
;1z_XAS
• A • • , • , •
MISS
■
��_
®lpl� � . ■r ■Rr = LL - rp3.w 1 IImo,.
��d.� 1��'It = ,mar auiwvt �--,•
iii rrwr3 -+1 ��i� � ae ipill�lf�8�:�lll.rii€ _• •� �"► ��"" R �-`� ��+
■� +III® a Sfsi;t e
aiID33lei� [-
�'
�i������"���li:lS'aiSS�.R.ww�■■■r!!!r'' Iq. 1 � . , �� �..�, ,�� fill
BUFFALO SPRINGS.�
aWO
....,....,.'----------rCi31•r•la?ta3iffi
=.r•p�rsi�ey3a�.a3rparare"rr,l„r„� ��� �• .+� ,�l+.i•a••,nr�� t. .� .:'�.a a�
"".r3!•aza l[3lSSR3lelldl�.�leerR �` . � ""�► N►# �:�
F
er.�rr3lrrwrM rs3�r.ror�raa3rri , M.ee e��s ®a►Y��. m is
aseh�� .,'ortalkl7Wor,theae s :*� �i .�
1"eRNI ! Ills !! .�.,rr3rr.�.�
y i•a..�:A��� � �lrti a®�
r1 s sllupew eet
nA,el
.,r.«: '_'�� ,if'�i� eke i+15� rtIfMIDIDI►' � dl9!11.
- �.�..'°' • •. ,,, ' �1'1� At: �+!���" ..��sa.�e,ee�� � wrl<ww rri
a : .. -. • :;Yr�lSl ',� rk11 _ .Gi'rli : 6 p■l■l1._
%; ek�lp.■wiT'a. � � � �:IRe�Rw��aRr.,���s �'°N� a.in w'.N�
Y v } f 'St.
!a
� �: �,} - <��iN�grlay!(�.d�µ�■6 y� (Yle� ;t �:■,�rsisID�kss a.l�i'lEc���tl9i' ��
� ���.�� 1� ,1 apptr■ � �Y�a■py��l b�Glp/�'�~�a�i%������� � �����
1ID'rMS` iYt.t f
_ (■ �5liilekil 111 f
�• ucnliel.eY A, ! neY.tYYe■a. Y � !��
�a , ■ r, ■aerSYrkslu �i5e!!:Rr YEwK .• it+�,p;;4 ipil3r•'CiN�i
ZZ
���fi d■r�+�ra■ � - .clew rr.r'��V� "R�"'i'' � � �ID
e1/3f �
,,,��,�xst��R .9�ater,�kelee:,. -.�•�� �w b r.�--�� �rr■`aia����OI"r �F11��.
w.er B@$ai�4� �5311'�3�1�§I3dS/3 "11 9ie►a""-��t w ww.w R�'a a�fM3lprwl o..� r� Rtlit!I� IF�arreal..
i YrkM4ia*Aae:1°"� kM6L,. $.' �err+acp3Ytit, rrauRt+ .�aai; r..r
®. ® iiifl�pi��,le �rsl���au�a."w g .�aam wRa.■ �,i3will'
Peat a�ae.�xp�5s�;w ! - - • " • •� y - Mk A�' w3rkg
�� 5 {,,r 1.. vetekxpa yp��"�Q�tl`���"y►'C•�.s� �' � i
� lailsl l�{ Q. �tYIeKM/t wa" t'•a� tt�'
�''LuuSs• / r.PP■.w+�l:lxr•�k'Fv� `��wt ��CA y��
IYRooMY
T. raw le
$•�pJltwaw+"�t.�
Burleson
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 06/23/20 M&C FILE NUMBER: M&C 20-0461
LOG NAME: 60M257P2B-MOUNTAINC
SUBJECT
Authorize the Execution of a Contract with Mountain Cascade of Texas, LLC in the Amount of$7,142,003.00 for the Sanitary Sewer M257 Upper
and Middle Village Creek Parallel Relief Main,Part 2B Project and Provide for Project Costs for a Project Total in the Amount of$24,592,607.00,
Adopt Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt, and Adopt Appropriation Ordinance
(COUNCIL DISTRICTS 2 and 7)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the execution of a contract with Mountain Cascade of Texas, LLC, in the amount of$7,142,003.00,for the Sanitary Sewer M257
Upper and Middle Village Creek Parallel Relief Main, Part 213 project;
2. Adopt the attached Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds from Future Debt for the Sanitary Sewer
M257 Upper and Middle Village Creek Parallel Relief Main,Part 2B project; and
3. Adopt the attached Appropriation Ordinance adjusting appropriations in the Water and Sewer Commercial Paper Fund(W&S Commercial
Paper) by decreasing appropriations in the UNSPEC project(City Project No. UNSPEC)in the amount of$7,929,373.00 and increasing
appropriations in the Sanitary Sewer M257 Upper and Middle Village Creek Parallel Relief Main, Part 2B by the same amount(City Project
No. C01227)
DISCUSSION:
This Mayor and Council Communication provides for the construction of the Sanitary Sewer Main 257 Upper and Middle Village Creek Parallel
Relief Main("UMVCPRM") Part 2B project. In order to expedite construction of the total footage of UMVCPRM,the project was divided into Parts
2A and 2B.Construction of Part 2A is underway.
Construction of the project was advertised for bid on April 16,2020 and April 23,2020 in the Fort Worth Star-Telegram.On June 4,2020 the
following bids were received:
Bidder JAmount Calendar Days
Mountain Cascade of Texas, LLC F
540 7,142,003.00 Y
Da s Calendar
Belt Construction of Texas,LLC I $7,596,303.00
S.J.Louis Construction of Texas, $8,564,098.56
Ltd.
McKee Utility Contractors, Inc. ;8,650,336.0011
Thalle Construction Co.,Inc. $10,037,006.00
Jackson Construction,Ltd. ___jil$10,142,527.0011
In addition to the contract cost, $573,110.00 is required for project management, material testing and inspection, and$214,260.00 is provided for
project contingency.
Construction is anticipated to commence in September 2020 and be completed by February 2022.This project will have no impact on the Water
Department's operating budget when complete.This project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
Funding for the Sanitary Sewer Main 257 Upper and Middle Village Creek Parallel Relief Main, Part 2B project is as depicted below:
Fund Existing Additional Project Total*
Appropriations IAppropriations
W&S Capital
Projects-Fund $303,000.00 $0.00 $303,000.00
56002 _
Clean Water SRF- $969,090.00 $0.00
59602 $969,090.00
Fund
Sewer Capital
Legacy-Fund $3,283,000.00 $0.00 $3,283,000.00
59607
W&S Bond 2020A- $12,108,144.00 $0.00$12,108,144.00
Fund 56017
W&S Commercial 1 $0.00 $7,929,373.00 $7,929,373.00
Paper-Fund 56019
Project Total $16,663,234.00 $7,929,373.00$24,592,607.00
*Numbers rounded for presentation purposes.
This project is anticipated to be included in a future revenue bond issue for the Water&Sewer Fund.Available cash within the Water and Sewer
portfolio and the City's portfolio along with the appropriation authority authorized under the Callable Commercial Paper Program(CP)will be used
to provide interim financing for this project until debt is issued.To the extent resources other than the Water and Sewer portfolio are used to
provide interim financing,the Water and Sewer Fund will be charged interest that is equivalent to the overall rate of return being earned by the City
portfolio(currently approximately 2.3 percent annually).Should the City's portfolio not support the liquidity needed to provide an interim short-term
financing source,another funding source will be required,which could mean issuance of securities under the CP Program or earlier issuance of
Water and Sewer revenue bonds than is currently planned. Once debt associated with this project is sold,bond proceeds will be used to reimburse
the Water and Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution.
The City Council approved the Water Department's Fiscal Year 2020-2024 Five-Year Capital Improvement Plan on September 17,2019.This City
Council approved plan includes this specific project,with funding identified through the CP program to be reimbursed with future revenue bonds.
Fund 56019 is the current W&S Commercial Paper fund and the name will change to the bond issuance year(Water&Sewer Bond 20XX)once
the debt has be sold and a new fund will be created with the name W&S Commercial Paper fund. In accordance with the provisions of the
Financial Management Policy Statements,staff anticipates presenting revenue-supported debt issuances to the City Council for consideration
within the next three years.This debt must be issued within approximately three years to provide reimbursement for these expenses. If that does not
occur,the costs will no longer be reimbursable by issuing tax-exempt debt and the funding source will have to be made whole through other
budgetary methods.Adoption of this resolution does not obligate the City to sell bonds,but preserves the ability to reimburse the City from tax-
exempt bond proceeds.
M/WBE OFFICE:Mountain Cascade of Texas,LLC, is in compliance with City's BDE Ordinance by committing to 12 percent MBE participation
on this project.The City's MBE goal on this project is five percent.
The project is located in COUNCIL DISTRICTS 2 and 7.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified project within the W&S Commercial Paper fund and upon
approval of the above recommendations and adoption of the attached appropriation ordinance,funds will be available in the W&S Commercial
Paper Fund for the SS Main 257 Part 2 Upper and Middle Village Creek Parallel Relief Main,Part 2B project to support the approval of the above
recommendations and execution of the contract. Prior to any expenditure being incurred,the Water Department has the responsibility of verifying
the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: John Kasavich 8480