HomeMy WebLinkAboutOrdinance 24275-06-2020 Ordinance No. 24275-06-2020
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER AND SEWER BOND 2020A FUND (56017) IN THE AMOUNT OF $715,000.00,
FROM AVAILABLE FUNDS, FOR THE PURPOSE OF FUNDING THE VILLAGE CREEK
BIOSOLIDS MANAGEMENT AND BENEFICIAL REUSE FACILITY PROJECT;
PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE
OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2019-2020 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water
and Sewer Bond 2020A Fund (56017) in the amount of$715,000.00, from available funds,for the purpose of
funding the Village Creek Biosolids Management and Beneficial Reuse Facility Project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion orjudgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 23835-09-2019 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Denis C. McElroy Mary J. Kayser
Assistant City Attorney City Secretary
ADOPTED AND EFFECTIVE: June 23, 2020 �� ®I"6 J•s�
• A
• •
AND PROCESSING FACILITY
VILLAGE CREEK WATER
Nd
u
• :3
iJ
1 �,n
W"aiilYMdrM 10
r Ryk osinwim-
L
N6 g1dl .
&AJ
�'
to•+�1 ri RwAirw wre r�r>r
Nis
-
��-� ��as����.,` �� In+e;��Ixis��a !@ta'�����rs"'ie��-�.�.ellrrw tR ;.. • • , , �
D`i�'�i� • i�i��'h.�_c. *�;r'set sr � �"'�.cam �,,�
��,Rr'a'�' ts. t�i� '��'�!'.� �lia;��a"♦M s"�, '��'�!���!4�4"'�¢x�'A� rn re„�.•�r:`.�.
fl i yk+ is .1�tt, . +► #q°ri '� +. ♦_R �i1�nR % sn x
,�.,fj n. .Q ♦ . +M�ygyllYo yy �.drk�`y0'#f+ al.,rp bk q, a M/w•rwi'.���oR� a
41 ass:
y- iiiYiiii� A.alr EOil�ia�MlW,wc�ilP9Rrs f • r e L � q'jrr r
now
�wi�
s• � r'.' r Rilihiplik5ia yl'+t rl,,r Rr -.��±EiikMdRN�s!ffi!li&#liwil�r A!►"�ll���4ii�Ed '"?F",�r.€�aK„
si ti ymae w,nc�.ye erg' •se
•fl
• •.4 � �'�c���°�r�mr/ a�yr"G'n�:>. +� i irN'�'`p re�i fr""`
;#Mi'+Eve rru rt.t�1♦ :s
• •' .:y,�fr'�,+;'"�}�.ga`t��'i a,:�rr�raaF�, :MPi;11� •i��,SY c"��,s�« ,,,�
' ♦ ;inrr s trs 49,k447.��.!„'"rbM 1"�"'i y�`r�" ,r. dF� �t'kR`R. +b..� ,M�,�r,�,n'�'ydr��e:
kk • sa AQr1w� '.k +1•k ✓ rz v
� (�i.. �� ,''��` �;�� `� • • � r :s�+,�,►ar�;:,rr 1lW� �yR#R��s714pX�aN.'
i�� � � 44'i ♦ �4�Mtli#��YlfCrdl BRIE%s'�,o E� :#. �.�",�... '�`.11`#r �a� '4; a: .kla«;r�,lA �
FORTWORTH
r fi�4RllMMiYF�1116Mpi�t41r1
retr�unu w4LMa
slash YaNyiSr« i�ilea V4flti
■r((■■{,N Rain ilvF NY Rlw SP 1e: �F'9 1L'���" t M""fit
■P:i�#�i 4R ili'YIiR ISM 11d� "��r..a''�'��a� F'� ��� RT
- - ii I/r1V d111M s!R\i • r'' �.:yi,,y�� ��1 ,e' '15�. ���Sal.rd�ii
yr it MBV1'.�i M'ae*�w� 7i1 ,►I,}� a+1M -'�' O
r V 1I
� � I xi9► ,tlM' ns �� �Yrt�
_ ram- d� IrNlMlciatairtt�r'akFnu.anllP�....,.:t.. �,t��.,9'�: ►Ri:;rays
1 1
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/23/20 M&C FILE NUMBER: M&C 20-0463
LOG NAME: 60VCWRF MASTER PLAN UPDATE AMEND 3
SUBJECT
Authorize the Execution of Amendment No.3 in the Amount of$539,620.00 to an Engineering Agreement with CH2M Hill Engineers, Inc.,for the
Village Creek Biosolids Management and Beneficial Reuse Facility Project Owner On-site Representation,Adopt Resolution Expressing Official
Intent to Reimburse Expenditures with Proceeds of Future Debt and Adopt Appropriation Ordinance(COUNCIL DISTRICT 5)
RECOMMENDATION:
It is recommended that the City:
1. Authorize the execution of Amendment No.3 to City Secretary Contract No.50018,an Engineering Agreement with CH2M Hill Engineers,
Inc.in the Amount of$539,620.00,for a revised contract amount of$1,145,199.00,for the Village Creek Biosolids Management and
Beneficial Reuse Facility Project Owner On-site Representation (City Project No. 101961);
2. Adopt the attached Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt for the Village Creek
Biosolids Management and Beneficial Reuse Facility Project;and
3. Adopt the attached Appropriation Ordinance increasing estimated receipts and appropriations in the Water and Sewer Bond 2020A Fund,
from available funds,in the amount of$715,000.00 for the Village Creek Biosolids Management and Beneficial Reuse Facility Project.
DISCUSSION:
On November 14,2017(M&C C-28475),the City Council authorized an Engineering Agreement in the amount of$282,822.00 with CH2M Hill
Engineers, Inc.,for the Village Creek Biosolids Management and Beneficial Reuse Facility Project Update.Amendment No. 1, in the amount of
$77,296.00,was administratively authorized on September 4,2018,for additional wastewater solids process modeling work, long-term growth
projections and additional alternatives analysis,as well as the preparation of an engineering feasibility report submitted to the Texas Water
Development Board(TWDB)as part of a Clean Water State Revolving Fund (CWSRF) Loan application.Amendment No.2,in the amount of
$245,461.00,was approved on February 12,2019(M&C C-29039)to develop the Request for Qualifications(RFQ)and Request for Proposals
(RFP)as part of the procurement process for a design-build-operate contract for biosolids management project and responding to requests for
information(RFIs)during the procurement process,for providing technical analysis and recommendations during the evaluation of vendor
submittals and during the negotiation of the agreement.
On December 10,2019(M&C 19-0381),the City Council authorized Design-Build-Operate-Maintain Services with Synagro of Texas-CDR, Inc.,
for the Village Creek Water Reclamation Facility Biosolids Management and Beneficial Reuse Project including the Design-Build cost of
$58,001,558.00 for the construction of the new dryer facility.With construction to start in the near future,the City will require the use of
this engineering firm to provide inspection,construction materials and testing,equipment testing and construction administration.CH2M Hill
Engineers, Inc.,will provide these services as part of Amendment No.3 for a fee not to exceed$539,620.00.
In addition to the contract amount,$50,000.00 is required for contingency allowance and$125,380.00 is required for project management and
associated Water Department staff time.
Funding for the Village Creek Water Reclamation Facility Biosolids Management&Reuse project is as depicted in the table below:
Fund Existing Additional Project Total*
Appropriations JAI
propriations
WS Capital Project $245,461.00 $0.00 $245,461.00
2019 Fund 56016
WS Capital Project $60,000,000.00 $0.00 $60,000,000.00
2020 Fund 56018
W&S Commercial $0.00 $715,000.00 $715,000.00
Paper Fund 56017
Project Total $60,245,461.00$715,000.00 $60,960,461.00
*Numbers rounded for presentation purposes.
This project will have no impact on the Water Department's annual operating budget when completed.
This project is included in a pending revenue bond issue for the Water&Sewer Fund.The Water and Sewer System has a Council-authorized
system to allow it to initiate capital projects that will ultimately be bond funded, using available cash within the Water and Sewer portfolio and the
City's portfolio,along with the authority under the Callable Commercial Paper Program(CP)to provide interim financing for this project until the
debt is issued.To the extent resources other than the Water and Sewer portfolio are used to provide interim financing,the Water&Sewer Fund will
be charged interest that is equivalent to the overall rate of return being earned by the City portfolio(currently approximately 2.3 percent annually).
Should the City's portfolio not support the liquidity needed to provide an interim short-term financing source,another funding source will be
required,which could mean issuance of securities under the CP Program or earlier issuance of Water and Sewer revenue bonds than is currently
planned. Once debt associated with this project is sold,bond proceeds will be used to reimburse the Water and Sewer portfolio and the City's
portfolio in accordance with the attached Reimbursement Resolution.
The City Council approved the Water Department's Fiscal Year 2020-2024 Five-Year Capital Improvement Plan on September 17,2019.This City
Council approved plan includes this specific project,with funding identified through the CP program to be reimbursed with future revenue bonds.
Debt must be issued within approximately three years of an expense being incurred in order to provide reimbursement. If that does not occur,costs
are no longer reimbursable by issuing tax-exempt debt,and the funding source must be made whole through budgetary methods.Adoption of a
reimbursement resolution does not obligate the City to sell bonds but preserves the ability to reimburse the City from tax-exempt bond proceeds.
In this case, because the bonds that will provide the ultimate funding have already been authorized and sold(with a total interest cost(TIC)of
1.89%)but the closing has not yet occurred,what had been the Water&Sewer Commercial Paper Fund(56017)has already been renamed to
reflect the bond sale.
M/WBE OFFICE: CH2M Hill Engineers, Inc., is in compliance with the City's BDE Ordinance by committing to eight percent SBE participation on
amendment No.3 on this project.The City's SBE goal on Amendment No.3 on this project is eight percent.
This Project serves the entire City and is located in COUNCIL DISTRICT 5.
A Form 1295 is not required because:This contract will be with a publicly-traded business entity or a wholly-owned subsidiary of a publicly-traded
business entity: CH2M Hill Engineers, Inc.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds
will be available in the Water and Sewer Bond 2020A Fund for the engineering services for the future growth at the Village Creek Water
Reclamation Facility Biosolids Management&Reuse project. Prior to any expenditure being incurred,thg Water Department has the responsibility
to validate the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: David Townsend 8430