HomeMy WebLinkAboutOrdinance 24139-04-2020 Ordinance No. 24139-04-2020
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER AND SEWER CAPITAL PROJECTS FUND IN THE AMOUNT OF $1,370,915.00,
TRANSFERRED FROM AVAILABLE FUNDS IN THE WATER AND SEWER FUND, FOR
THE PURPOSE OF WATER AND SANITARY SEWER MAIN REPLACEMENTS 2018
BOND STREET RECONSTRUCTION CONTRACT 1; PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN
EFFECTIVE DATE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2019-2020 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of $1,370,915.00, transferred from available funds in the
Water and Sewer Fund, for the purpose of water and sewer main replacements 2018 Bond Street
Reconstruction Contract 1.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 23835-09-2019 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Bwft—
DBlack(Jun 26,202017:19 CDT)
Douglas W Black Mary J. Kayser
Sr Assistant City Attorney City Secretary
ADOPTED AND EFFECTIVE: April 7,2020
OF FO/�TGL
�)(AS
lam
; IMpo In*
New
VISO
"
•
rim WRI
' i'ii� fit =• ' ' fC` ? aw6w WWI.
w WWI,
RMk "P • Mrw*
Wo -
A' ��
:. ,
kWv
as Ow AxvM
}} ° •�
fix
•LM
Imlow tow
ISO am T - .....
� � ��� Ems►.Aim
" Mad
4 us ..
an MIM1►=dot e
r ���» �� ram'►
Ulu
.r •y kAw am
.macMd W,
IA1M
ia a;0 • '�t3wN rT
t�C�IMi i�itl
wAl r4g"
$ • �h � �
LIM
At,Y ,,
� fir ' � ► , .` �` �����*�
rt � 1
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 04/07/20 M&C FILE NUMBER: M&C 20-0227
LOG NAME: 202018CIPY1C1P2-MCCLENDON
SUBJECT
Authorize Execution of a Contract with McClendon Construction Company, Inc.,in the Amount of$2,488,458.13 for Combined Street Paving
Improvements and Water and Sanitary Sewer Main Replacements for 2018 Bond Street Reconstruction Contract 1,Part 2 Project,Located on
Kimbo Road, McComas Road and Alta View Street,Adopt Appropriation Ordinances,and Update the FY 2020-2024 CIP(COUNCIL DISTRICT
4)
RCV VmMr-MI.lA I IVN:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinance increasing appropriations in the Water and Sewer Capital Projects Fund in the amount of
$1,370,915.00 transferred from available funds within the Water&Sewer Fund;
2. Adopt the attached Appropriation Ordinance adjusting appropriations in the 2018 Bond Street Reconstruction Contract 1, Part 2 Project,in
the amount of$1,552,670.13 and reducing appropriations in the Street Construction/Reconstruction/Rehabilitation Programmable Project
(City Project No.P130001)by the same amount;and
3. Authorize execution of a contract with McClendon Construction Company,Inc.,in the amount of$2,488,458.13 for Combined Street Paving
Improvements and Water and Sanitary Sewer Main Replacements for 2018 Bond Street Reconstruction Contract 1,Part 2 project(City
Project No. 101119).
DISCUSSION:
This Mayor and Council Communication(M&C)is to authorize a construction contract for water and/or sanitary sewer and paving improvements
on approximately 1.24 lane miles for the 2018 Bond Street Reconstruction Contract 1,Part 2 on the following streets:
Street From To
Kimbo Road Mesquite Road NE Cul-De-Sac
McComas Road Kimbo Road N.Beach Street
Alta View Street Kimbo Road Premier Street
The Transportation and Public Works Department's share on this contract is$1,308,613.13.Funds for this project are included in the 2018 Bond
Program.Available resources within the General Fund will be used to provide interim financing until debt is issued.Once debt associated with the
project is sold,bond proceeds will reimburse the General Fund in accordance with the statement expressing official Intent to Reimburse that was
adopted as part of the ordinance canvassing the bond election(Ordinance No.23209-05-2018)and subsequent actions taken by the Mayor and
Council.
The Water Department's share on this contract of$1,179,845.00 will be available in the Water and Sewer Capital Projects Fund of the project
(City Project No. 101119).
The project was advertised for bid on December 12,2019 and December 19,2019 in the Fort Worth Star—Telegram.On January 30,2020,the
following bids were received:
Bidder Amount Time of Completion
McClendon Construction Company,Inc. $2,488,458.13 275 Calendar Days
Stabile&Winn,Inc. $2,527,094.00 T -1
i n n i
FNH Construction, LLC $3,359,867.35
In addition to the contract amount,$310,704.00(Water:$71,740.00,Sewer:$60,338.00,TPW:$178,626.00)is required for project management,
material testing and inspection and$124,423.00(Water:$32,081.00,Sewer:$26,911.00,TPW:$65,431.00)is provided for project
contingencies.
This project will have no impact on the Transportation&Public Works operating budget nor on the Water Department's operating budget when
completed.Construction is expected to start in June 2020 and be completed by March 2021.
The sanitary sewer component of this project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
Appropriations for the Water,Sanitary Sewer and Paving Improvements for 2018 Bond Street Reconstruction Contract 1,Part 2 project by Fund
will consist of the following:
FUND Existing Additional Project Total*
Appropriations Appropriations
2018 Bond Program—Fund 34018 $3,414,589.00 $1,552,670.13 $4,967,259.13
Tax Note 2017—Fund 34017 $350,000.00 $0.00 $350,000.00
Water&Sewer Capital Projects— $2,462,358.00 $1,370,915.00 $3,833,273.00
Fund 56002
Project Total $6,226,947.00 $2,923,585.13 $9,150,532.13
*Numbers rounded for presentation purposes.
MMIBE OFFICE—McClendon Construction Company,Inc.is in compliance with the City's BDE Ordinance by committing to 5 percent MBE
participation and documenting good faith effort.McClendon Construction Company,Inc.identified several subcontracting and supplier
opportunities.However,the firms contacted in the areas identified did not respond or did not submit the lowest bids.The City's MBE goal on this
project is 15 percent.
The 2018 Bond Program funding was included in the 2020-2024 Capital Improvement Plan for project PB0001.In order to administratively track
the spending of all funding sources in one project,appropriation ordinances are needed to move appropriations from the programmable project to
the jointly funded static project.This action will update the 2020-2024 Capital Improvement Plan.
rraGAL mtURMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current operating budget of the Water&Sewer Fund,and upon approval of the
above recommendations and adoption of the attached appropriation ordinances,funds will be available in the current capital budgets,as
appropriated,in the Water and Sewer Capital Projects Fund and 2018 Bond Program Fund.Prior to any expenditure being incurred,the
Transportation&Public Works and Water Department have the responsibility to validate the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: William Johnson 7801
Additional Information Contact: Monty Hall 8662